KYL_Lock_Excavation_July2018_PreBid_v2.pdf
PDF 15 MB Posted
- Attached to
- Downstream Lock Excavation Construction Contract
- Solicitation number
- W912P518B0005
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
.59
“The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”
Nashville District July 2018
KENTUCKY LOCK ADDITION
DOWNSTREAM LOCK EXCAVATION
File Name
2Downstream Lock Excavation Pre-bid Site Visit Agenda
• Contract Briefings
• Questions and Answers
• Safety Briefing
• Site Walk-thru
• Close-out session with Q&A’s and summary of action items
3Downstream Lock Excavation Pre-Bid Site Visit Briefing Agenda
• Opening, Purpose of Visit and Solicitation Overview – Jessica Baker, Contract Specialist
• Project and Contract Overview (including Cranes and Maintenance Building)– Don Getty, Project Manager
• Geology/Rock Excavation/Grouting, Geotechnical, and Instrumentation
– Mark Elson, KY Lock Lead Geologist
• Strand anchors, stoplog slots, gratings, bridge demolitions and modifications, maintenance building – Stephen Salaman, KY Lock Structural Engineer
• Contractor work areas, coordination with other contractors, and safety briefing – Jeremiah Manning, Resident Engineer
• Q&A’s
• Bid Schedule and Measurement & Payment
• Questions can be submitted until July 30, 2018
4Downstream Lock Excavation Solicitation Summary
• Please Sign-In (attendance roster will be posted to www.FBO.gov this week)
• Questions during today’s site visit- We will address any questions to the best of our ability, but anything said today is not official unless it is in writing in the issued amendment to this solicitation. All question must be written on index cards or they will not be addressed in the amendment.
• All amendments will be posted publicly on www.fbo.gov.
• Solicitation Walkthrough http://www.fbo.gov/ http://www.fbo.gov/
5Downstream Lock Excavation Major Contract Characteristics
• Award by September 30, 2018.
• Base with 12 Options
• Solely due to fiscal year funding constraints
• Scope of options is not on Plans – only in 01 00 00 and Bid
Schedule. Designed to easily change scope of Base & Options prior to advertising.
• Period of Performance – Approximately 3 years.
• Contract scope includes completion of Downstream Cofferdam and dewatering its pit.
6Downstream Lock Excavation Project and Contract Overview
• Key Points
• This powerpoint will be posted on FBO along with Q&A’s discussed today.
• Pls hold Questions until the bitter end of the presentations
• Our intent is to tell you some of the “Why” we are doing what we propose and describe key elements - in the hope this helps you to provide input to make this a better contract.
• We will describe the known Amendments.
BUILDING STRONG®
Lock Addition Alignment
New Hwy and RR Bridges New Transmission Towers
Upstream Cofferdam
Upstream Lock Monoliths
Kentucky Lock Addition Completed Features
Location of Ongoing Downstream Cofferdam
Kentucky Lock Addition
-$1.25B Total Project Cost -$450M Expended to Date -2024 Earliest Project Completion Date
Downstream Cofferdam
Downstream Cofferdam
-Contractor: Johnson Bros.
-$67.1M Award -Award: September 2016 -Complete: February 2020
Downstream Cofferdam
Modify Upstream Bridge
Demo Shop addition on Existing Ops Bldg
Site, Demolition, and Utilities (SDU) Contract $4.1M to Intec Completion Date: January 2019
Relocate Sanitary Sewer
Relocate Electrical and Control Lines
Existing Water and Sewer
Relocated Sewer Line
Catwalk on 3 sides of Ops Bldg
New Sewage Lift Station
Cantelevered Utility Systems
Note: All pipe support systems in SDU have been designed to accommodate the 8” water line relocation.
Top of brackets to be lowered 31” below top of lock wall
KY LOCK FUNDING HISTORY
$0
$10
$20
$30
$40
$50
$60
FY02 FY03 FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15 FY16 FY17 FY18
M illi on s
Annual Funding Allocations
Net Allocations
Last Year in Budget
ARRA $88.9M
CY 14 – 2 Major positive game changers to IWTF by Congress
$0 in
FY14
Near Efficient Funding
15Efficient Funding as Presented at Inland Waterways User Board on
1 March 2018 Goal: Exercise as many Options as possible with FY Funding and make full use of FY funding
Note: Above funding amounts for KY Lock are for many purposes, not just for this or other contracts.
LOCK EXCAVATION BASE
Downstream Cofferdam Contract
Maintenance Building Demolition
New Maintenance Building
Bridge Demolition
Land Wall Instrumentation and Vertical Anchors
Overburden Excavation
Landwall Grating and Crane Prepositioning
Schedule Constraints Prior to significant overburden excavation:
1) New Maint Bldg and demo existing
2) Fully functioning landwall instruments & vertical anchors
3) LW grating and crane prepositioning
4) Demo of land spans of 3 bridges
5) 8” water line relocation Bridge Demolition
1) No lock closures allowed except during 24 day closure in Aug 2019.
LOCK EXCAVATION OPTION 11
8” Water Main Relocation
Schedule Constraints
1) Corps exercises relocation contract with N. Marshall Utility District
2) Exercise Option by April 2019
LOCK EXCAVATION OPTION 1
Land Wall Vertical Anchors
Lower section may not be accessible until JB completes DS Cofferdam
Schedule Constraints
1) None except access noted below
LOCK EXCAVATION OPTION 2
Land Wall Angled Strand Anchors
Schedule Constraints
1) Overburden excavation down to elevation 330.
LOCK EXCAVATION OPTION 3
Land Wall Angled Strand Anchors
Schedule Constraints
1) Overburden excavation down to elevation 330.
2) Grouting must be completed prior to angled anchor drilling
LOCK EXCAVATION OPTION 4
Specialized Treatment Zone Grouting
Schedule Constraints
1) Access to Downstream
Cofferdam area.
LOCK EXCAVATION OPTION 5AA
Downstream Stoplog Slots Vertical cuts
Schedule Constraints
1) No lock closures allowed except during 24 day scheduled outage, currently scheduled from 6 to 30 August 2019.
LOCK EXCAVATION OPTION 5AB
Downstream Stoplog Slots Remainder of scope
Schedule Constraints
1) No lock closures allowed except during 24 day scheduled outage, currently scheduled from 6 to 30 August 2019.
LOCK EXCAVATION OPTION 6
Phase 2 Overburden Excavation
Schedule Constraints
1) JB Downstream Cofferdam activities could affect some of this area.
LOCK EXCAVATION OPTION 7
Phase 1 Rock Excavation
Schedule Constraints
1) Overburden excavation must be completed.
2) If this rock excavation is performed prior to dewatering DS Cofferdam, then tailwater elevations could impact limits of excavation. Existing toe drain pipe allows tailwater to enter this area.
LOCK EXCAVATION OPTION 8
Downstream Cofferdam Grouting, Instrumentation and Vertical Anchors
Schedule Constraints
1) JB Downstream Cofferdam activities must have progressed to allow access for all of these activities.
LOCK EXCAVATION OPTION 9
Phase 3 Overburden Excavation, Phase 2
Rock Excavation
Schedule Constraints
1) Dewatering cannot commence until completion of a) grouting,
b) fully functioning instrumentation system; and
c) vertical anchors in M22 and M23.
LOCK EXCAVATION OPTION 10
Phase 3 Rock Excavation
MAINTENANCE BUILDING
Slide 30
Rotated Maintenance Building (by Amendment)
Slide 31
Olmsted Project Terex Crane to be re-furbished and placed on Lock Wall. Available March 2019.
STRATIGRAPHY
TOP OF ROCK
Top of Rock at Upstream Cofferdam
Rock Excavation at Upstream Monolith Construction
ROCK EXCAVATION FOR UPSTREAM MONOLITHS 36
U/S LOCK EXCAVATION – AUGUST 2010 –
ROCK PINNACLES
Slide 37
LOCK EXCAVATION – MAY 2011
Slide 38
ROCK PINNACLE IN DOWNSTREAM EXCAVATION
EXCAVATION CROSS SECTION AT 6+00
EXCAVATION CROSS SECTION AT 10+00
DOWNSTREAM GROUT CURTAIN
GEOLOGIC PROFILE THROUGH
SPECIALIZED TREATMENT ZONE
KENTUCKY LOCK DISPOSAL AREAS 45
Area D (Primary)
Area A (Backfill Stockpile)
DISPOSAL AREA D
EXISTING INSTRUMENTATION
Existing system on US Cofferdam and existing land wall to Monolith EL13
NEW INSTRUMENTATION – EX. LOCK
Alignment Pins (2 per monolith) Inclinometers Tiltmeters Jointmeters Relative Block Movement Device (RBMD) Saw Cuts Load Cells (1 per monolith)
Typical installation pattern
INSTRUMENTATION – DS COFFERDAM
Alignment Pins (2 per monolith) Tiltmeters Jointmeters Relative Block Movement Device (RBMD) Saw Cuts Piezometers Inclinometers
Jointmeter
RBMD
Saw Cut
INSTRUMENTATION – DS COFFERDAM
Alignment Pins (2 per cell) Piezometers Inclinometers
DATALOGGING EQUIPMENT
Datalogger
Solar Panel to power dataloggers
EXISTING LOCK AND DOWNSTREAM COFFERDAM
ANCHORS
File Name
Anchor Locations
EXISTING LOCK ANCHORING– ANCHOR
INSTALLATION
UPSTREAM LOCK – ANCHOR INSTALLATION
UPSTREAM LOCK –
ANCHOR TENSIONING
UPSTREAM LOCK - ANGLED ANCHOR
DRILLING
Overhead obstruction at the existing lock operations building.
EXISTING LOCK ANCHORING
8 feet +/-
BRIDGE DEMOLITION
Bridge Demolition:
1. Former Powerhouse Access Bridge
2. Former P&L Railroad Bridge
3. Former US-62/641 HWY Bridge over
Lock
4. Abandoned US-62/641 HWY Bridge over RR
Plan of Former Access Bridge
X-Section
Support Floor Beam
Counter Weight
DOWNSTREAM STOPLOG SLOT INSTALLATION
Maintenance Building Demolition
Location of new Stoplog Slot
DOWNSTREAM STOPLOG SLOT INSTALLATION
Maintenance Building Demolition
1. Core holes have been pre-drilled
2. Slot will require wire saw cutting
DOWNSTREAM STOPLOG SLOTS
LANDWALL GRATING UPGRADES
Upgrade location
Grating as seen from top of lock wall.
Recent upgrades to river wall
69Downstream Lock Excavation Summary of Known Amendments
• Rotated Maintenance Building
• Changed pipe support bracket heights on lock wall by
SDU contractor
• Stoplog Slots
• Possible additional existing bridge demolition information
CONSTRUCTION LIMITS – CURRENT CONTRACTS
Maintenance Building Demolition
New Maintenance Building
Disposal Area D
Dual Access Corridor
DS Cofferdam Construction Limits
SDU Construction Limits
DS Cofferdam Construction Limits
CONSTRUCTION LIMITS – DOWNSTREAM LOCK
EXCAVATION
File Name
Maintenance Building Demolition
New Maintenance Building
Disposal Area D
DS Cofferdam Construction Limits And Future Lock Excavation Construction Limits
Dual Access Corridor
Initial DS Lock Excavation Construction Limits
DS Cofferdam Construction Limits
Shared Contractor Laydown Area
Disposal Area A
| Kentucky Lock Addition�Downstream Lock Excavation |
| Slide Number 2 |
| Slide Number 3 |
| Slide Number 4 |
| Slide Number 5 |
| Slide Number 6 |
| Slide Number 7 |
| Slide Number 8 |
| Slide Number 9 |
| Slide Number 10 |
| Slide Number 11 |
| Slide Number 12 |
| Slide Number 13 |
| KY Lock Funding history |
| Slide Number 15 |
| Lock Excavation Base |
| Lock Excavation Option 11 |
| Lock Excavation Option 1 |
| Lock Excavation Option 2 |
| Lock Excavation Option 3 |
| Lock Excavation Option 4 |
| Lock Excavation Option 5aa |
| Lock Excavation Option 5ab |
| Lock Excavation Option 6 |
| Lock Excavation Option 7 |
| Lock Excavation Option 8 |
| Lock Excavation Option 9 |
| Lock Excavation Option 10 |
| Maintenance building |
| Slide Number 30 |
| Slide Number 31 |
| Stratigraphy |
| Top of Rock |
| Slide Number 34 |
| Slide Number 35 |
| Rock Excavation for Upstream Monoliths |
| U/S Lock Excavation – August 2010 – Rock pinnacles |
| Lock Excavation – May 2011 |
| Rock Pinnacle in Downstream Excavation |
| Excavation Cross Section at 6+00 |
| Excavation Cross Section at 10+00 |
| Downstream Grout curtain |
| Slide Number 43 |
| Geologic Profile Through Specialized Treatment Zone |
| Kentucky Lock Disposal Areas |
| Disposal Area D |
| Existing Instrumentation |
| New Instrumentation – Ex. lock |
| Instrumentation – DS Cofferdam |
| Instrumentation – DS Cofferdam |
| Datalogging Equipment |
| Existing lock and downstream cofferdam anchors |
| Existing Lock Anchoring– Anchor Installation |
| Upstream Lock – Anchor Installation |
| Upstream Lock – Anchor Tensioning |
| Upstream Lock - Angled Anchor Drilling |
| Existing Lock Anchoring |
| Bridge Demolition |
| Bridge Demolition |
| Bridge Demolition |
| Bridge Demolition |
| Bridge Demolition |
| Downstream Stoplog Slot Installation |
| Downstream StoplOg Slot Installation |
| Downstream Stoplog Slots |
| Landwall Grating Upgrades |
| Landwall Grating Upgrades |
| Landwall Grating Upgrades |
| Slide Number 69 |
| Construction Limits – Current contracts |
| Construction Limits – Downstream Lock Excavation |
| Slide Number 72 |
File details come from the government source that posted it.