Lock Excavation Chickamauga Lock Replacement W912P5-16-B-0005 Amendment No. 0002 Hamilton County, Tennessee
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 SCOPE
This section of the Specifications provides general information and requirements; work and access restrictions; and required coordination with others. The work covered by these Specifications consists of furnishing all equipment, labor, and materials required for the staging and construction of Chickamauga Lock Excavation features and associated facilities as shown on the drawings and as described herein
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
EP 310-1-6a (2006) Sign Standards Manual, VOL 1
1.3 COORDINATION WITH OTHERS
Construction of features in this contract will impact or be impacted by other organizations. The Contractor has primary responsibility to initiate the coordination and communication in a timely manner with the Contracting Officer to schedule activities of others and minimize or eliminate conflicts with others. The Contracting Officer will then determine the appropriate course of communicating with the others involved. In many cases, the Contracting Officer may determine that the Contractor should communicate directly with others while ensuring the Contracting Officer is timely informed of the decisions of the communications or actively involved in the communications.
1.3.1 Coordination with Other Contractors Within the Same General Area
In addition to the provisions of Contract Clause 52.236-8 titled "OTHER CONTRACTS", the following information is provided:
1.3.1.1 Coordination with TVA or Corps of Engineers' Dewatering & Maintenance
The contractor is advised that Tennessee Valley Authority (TVA) or Corps of Engineers' construction crews may be operating in and near the work limits of this contract while performing dewatering and maintenance repairs to the existing lock, typically in spring / summer months and typically only once every three years.
SECTION 01 00 00 Page 3
Most of the work will be performed from barges in the downstream approach of the existing lock and typically is completed within 30 days. Typically, the work will require that the Government position a crane and other support equipment in the downstream approach channel. Corps maintenance activities will have priority over the Contractor's forces during such periods, but such work should not impact work outside of the downstream approach to the existing lock. There are no scheduled dewatering and maintenance activities that would impact the Contractor's activities at this time.
The Corps will inform the contractor in advance of obstructions to lock contract activities. The Contractor shall coordinate all activities through the Resident Engineer. The primary point of contact for this activity is:
Mr. John Tribble, Navigation Branch Phone: (615) 736-7809
The secondary point of contact is:
Mr. Matt Emmons, Chickamauga Lockmaster Phone: (423) 875-6230
1.3.2 Coordination with Land Owners and Utilities
1.3.2.1 General
The primary lay down / staging areas for this contract shall be LAYDOWN AREA #1 landward of the existing lock and LAYDOWN AREA #2 adjacent to and North of Trailhead Drive. LAYDOWN AREA #2 shall be available to the Contractor from Notice to Proceed until 30 September 2017; on this date LAYDOWN AREA #2 will be made available to other future contracts scheduled for award. These areas are clearly identified on Drawing 61W510-02a-LE.
These areas belongs to TVA, owner of the Chickamauga Lock and Dam. Any supplemental lands needed for contract staging shall be the responsibility of the contractor. Supplemental lands should be active commercial facilities that are currently used for construction operations.
Supplemental lands which are not in active commercial use shall require additional environmental assessments which could require up to 6 months for approval, depending on the environmental quality and previous disturbance of the site. The Contractor shall submit a Contractor Lay Down and Staging Area Plan showing development, utilization and restoration to the Contracting Officer for approval prior to initiation of work. All staging areas shall be returned to initial conditions to the extent possible, unless so directed by the Contracting Officer. The Contracting Officer reserves the right to disapprove the proposed site if it is determined to have an adverse environmental impact.
Where known, the locations of utilities are shown on the Contract Drawings. No utility relocations are anticipated for the work activities in this Contract. If during the course of this Contract, it is determined that utility relocations are necessary, they shall be performed by the respective owners, except as noted below. The Contractor is (a) responsible for field verification of exact locations with the utility owner; (b) responsible for coordination and cooperation with utility owners and scheduling access to required work areas; (c) should not assume that this list is all inclusive, and should anticipate that other utilities may be encountered. If this should occur, it is the Contractor's responsibility to notify the Contracting Officer and to coordinate the relocation of the utility appurtenance with the utility owner.
SECTION 01 00 00 Page 4
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 PAYMENT ITEMS
1.2 BASE
1.2.1 CLIN 0001 Mobilization and Demobilization
1.2.1.1 Payment
1.2.1.2 Unit of Measure
1.2.2 CLIN 0002 Initial Unwatering and Design of Dewatering System
1.2.2.1 Payment
1.2.2.2 Unit of Measure
1.2.3 CLIN 0003 Diversion and Care of Water - Base
1.2.3.1 Payment
1.2.3.2 Measurement
1.2.3.3 Unit of Measure
1.2.4 CLIN 0004 Instrumentation Program O&M - Base
1.2.4.1 Payment
1.2.4.2 Measurement
1.2.4.3 Unit of Measure
1.2.5 CLIN 0005 USACE Office Cleaning Services - Base
1.2.5.1 Payment
1.2.5.2 Measurement
1.2.5.3 Unit of Measure
1.2.6 CLIN 0006 USACE Office Carpet Cleaning Services - Base
1.2.6.1 Payment
1.2.6.2 Measurement
1.2.6.3 Unit of Measure
1.2.7 CLIN 0007 Core Drilling, Vertical Holes
1.2.7.1 Payment
1.2.7.2 Measurement
1.2.7.3 Unit of Measure
1.2.8 CLIN 0008 Secant Wall; Primary Piles In-Place
1.2.8.1 Payment
1.2.8.2 Measurement
1.2.8.3 Unit of Measure
1.2.9 CLIN 0009 Secant Wall; Secondary Piles In-Place
1.2.9.1 Payment
1.2.9.2 Measurement
1.2.9.3 Unit of Measure
1.2.10 CLIN 0010 Secant Wall; Cap Beam
1.2.10.1 Payment
1.2.10.2 Unit of Measure
1.2.11 CLIN 0011 Furnish and Install Inclined Anchors
1.2.11.1 Payment
1.2.11.2 Measurement
1.2.11.3 Unit of Measure
1.2.12 CLIN 0012 Performance Tests
SECTION 01 22 00 Page 1
1.2.12.1 Payment
1.2.12.2 Measurement
1.2.12.3 Unit of Measure
1.2.13 CLIN 0013 Proof Tests
1.2.13.1 Payment
1.2.13.2 Measurement
1.2.13.3 Unit of Measure
1.2.14 CLIN 0014 Watertightness Testing
1.2.14.1 Payment
1.2.14.2 Measurement
1.2.14.3 Unit of Measure
1.2.15 CLIN 0015 Grouting Holes & Redrilling
1.2.15.1 Payment
1.2.15.2 Measurement
1.2.15.3 Unit of Measure
1.2.16 CLIN 0016 Anchor Support Blocks
1.2.16.1 Payment
1.2.16.2 Measurement
1.2.16.3 Unit of Measure
1.2.17 CLIN 0017 Probe Hole
1.2.17.1 Payment
1.2.17.2 Measurement
1.2.17.3 Unit of Measure
1.2.18 CLIN 0018 Cofferdam Stability Berm
1.2.18.1 Payment
1.2.18.2 Measurement
1.2.18.3 Unit of Measure
1.2.19 CLIN 0019 Lock Overburden Removal
1.2.19.1 Payment
1.2.19.2 Measurement
1.2.19.3 Unit of Measure
1.2.20 CLIN 0020 Flood Facility Concrete Splash Pad
1.2.20.1 Payment
1.2.20.2 Unit of Measure
1.2.21 CLIN 0021 Shotcrete Placement (4")
1.2.21.1 Payment
1.2.21.2 Measurement
1.2.21.3 Unit of Measure
1.2.22 CLIN 0022 Rock Excavation
1.2.22.1 Payment
1.2.22.2 Measurement
1.2.22.3 Unit of Measure
1.2.23 CLIN 0023 Pre-Splitting
1.2.23.1 Payment
1.2.23.2 Measurement
1.2.23.3 Unit of Measure
1.2.24 CLIN 0024 Line Drilling (6" Spacing)
1.2.24.1 Payment
1.2.24.2 Measurement
1.2.24.3 Unit of Measure
1.2.25 CLIN 0025 Rock Bolts
1.2.25.1 Payment
1.2.25.2 Measurement
1.2.25.3 Unit of Measure
1.2.26 CLIN 0026 Grubbing Only
1.2.26.1 Payment
1.2.26.2 Measurement
1.2.26.3 Unit of Measure
1.2.27 CLIN 0027 Clearing and Grubbing
SECTION 01 22 00 Page 2
1.2.27.1 Payment
1.2.27.2 Measurement
1.2.27.3 Unit of Measure
1.2.28 CLIN 0028 Drainage Ditch Construction
1.2.28.1 Payment
1.2.28.2 Measurement
1.2.28.3 Unit of Measure
1.2.29 CLIN 0029 Manage, and Place Disposal Area Fill
1.2.29.1 Payment
1.2.29.2 Measurement
1.2.29.3 Unit of Measure
1.2.30 CLIN 0030 Geotextile Installations
1.2.30.1 Payment
1.2.30.2 Measurement
1.2.30.3 Unit of Measure
1.2.31 CLIN 0031 Manhole Extensions
1.2.31.1 Payment
1.2.31.2 Measurement
1.2.31.3 Unit of Measure
1.2.32 CLIN 0032 Strip, Manage, and Place On-Site Vegetative Soil
1.2.32.1 Payment
1.2.32.2 Measurement
1.2.32.3 Unit of Measure
1.2.33 CLIN 0033 Furnish, Manage, and Place Off-Site Vegetative Soil
1.2.33.1 Payment
1.2.33.2 Measurement
1.2.33.3 Unit of Measure
1.2.34 CLIN 0034 Seeding
1.2.34.1 Payment
1.2.34.2 Measurement
1.2.34.3 Unit of Measure
1.2.35 CLIN 0035 Control Monuments
1.2.35.1 Payment
1.2.35.2 Measurement
1.2.35.3 Unit of Measure
1.2.36 CLIN 0036 Toe Drain Discharge Pipe Replacement
1.2.36.1 Payment
1.2.36.2 Unit of Measure
1.3 OPTION 1 - STAGE 2 ROCK EXCAVATION
1.3.1 CLIN 0038 Diversion and Care of Water - Option 1
1.3.1.1 Payment
1.3.1.2 Measurement
1.3.1.3 Unit of Measure
1.3.2 CLIN 0039 Instrumentation Program O&M - Option 1
1.3.2.1 Payment
1.3.2.2 Measurement
1.3.2.3 Unit of Measure
1.3.3 CLIN 0040 USACE Office Cleaning Services - Option 1
1.3.3.1 Payment
1.3.3.2 Measurement
1.3.3.3 Unit of Measure
1.3.4 CLIN 0041 USACE Office Carpet Cleaning Services - Option 1
1.3.4.1 Payment
1.3.4.2 Measurement
1.3.4.3 Unit of Measure
1.3.5 CLIN 0042 Shotcrete Placement (4") - Option 1
1.3.5.1 Payment
1.3.5.2 Measurement
1.3.5.3 Unit of Measure
SECTION 01 22 00 Page 3
1.3.6 CLIN 0043 Rock Excavation - Option 1
1.3.6.1 Payment
1.3.6.2 Measurement
1.3.6.3 Unit of Measure
1.3.7 CLIN 0044 Pre-Splitting - Option 1
1.3.7.1 Payment
1.3.7.2 Measurement
1.3.7.3 Unit of Measure
1.3.8 CLIN 0045 Line Drilling (6" Spacing) - Option 1
1.3.8.1 Payment
1.3.8.2 Measurement
1.3.8.3 Unit of Measure
1.3.9 CLIN 0046 Rock Bolts - Option 1
1.3.9.1 Payment
1.3.9.2 Measurement
1.3.9.3 Unit of Measure
1.3.10 CLIN 0047 Manage, and Place Disposal Area Fill - Option 1
1.3.10.1 Payment
1.3.10.2 Measurement
1.3.10.3 Unit of Measure
1.4 OPTION 2 - STAGE 3 ROCK EXCAVATION
1.4.1 CLIN 0048 Diversion and Care of Water - Option 2
1.4.1.1 Payment
1.4.1.2 Measurement
1.4.1.3 Unit of Measure
1.4.2 CLIN 0049 Instrumentation Program O&M - Option 2
1.4.2.1 Payment
1.4.2.2 Measurement
1.4.2.3 Unit of Measure
1.4.3 CLIN 0050 USACE Office Cleaning Services - Option 2
1.4.3.1 Payment
1.4.3.2 Measurement
1.4.3.3 Unit of Measure
1.4.4 CLIN 0051 USACE Office Carpet Cleaning Services - Option 2
1.4.4.1 Payment
1.4.4.2 Measurement
1.4.4.3 Unit of Measure
1.4.5 CLIN 0052 Shotcrete Placement (4") - Option 2
1.4.5.1 Payment
1.4.5.2 Measurement
1.4.5.3 Unit of Measure
1.4.6 CLIN 0053 Rock Excavation - Option 2
1.4.6.1 Payment
1.4.6.2 Measurement
1.4.6.3 Unit of Measure
1.4.7 CLIN 0054 Pre-Splitting - Option 2
1.4.7.1 Payment
1.4.7.2 Measurement
1.4.7.3 Unit of Measure
1.4.8 CLIN 0055 Line Drilling (6" Spacing) - Option 2
1.4.8.1 Payment
1.4.8.2 Measurement
1.4.8.3 Unit of Measure
1.4.9 CLIN 0056 Rock Bolts - Option 2
1.4.9.1 Payment
1.4.9.2 Measurement
1.4.9.3 Unit of Measure
1.4.10 CLIN 0057 Manage, and Place Disposal Area Fill - Option 2
1.4.10.1 Payment
SECTION 01 22 00 Page 4
1.4.10.2 Measurement
1.4.10.3 Unit of Measure
1.5 OPTION 3 - LOCK FLOOR TREATMENT
1.5.1 CLIN 0058 Diversion and Care of Water - Option 3
1.5.1.1 Payment
1.5.1.2 Measurement
1.5.1.3 Unit of Measure
1.5.2 CLIN 0059 Instrumentation Program O&M - Option 3
1.5.2.1 Payment
1.5.2.2 Measurement
1.5.2.3 Unit of Measure
1.5.3 CLIN 0060 USACE Office Cleaning Services - Option 3
1.5.3.1 Payment
1.5.3.2 Measurement
1.5.3.3 Unit of Measure
1.5.4 CLIN 0061 USACE Office Carpet Cleaning Services - Option 3
1.5.4.1 Payment
1.5.4.2 Measurement
1.5.4.3 Unit of Measure
1.5.5 CLIN 0062 Lock Floor Excavation & Concrete - Option 3
1.5.5.1 Payment
1.5.5.2 Measurement
1.5.5.3 Unit of Measure
1.5.6 CLIN 0063 Manage, and Place Disposal Area Fill - Option 3
1.5.6.1 Payment
1.5.6.2 Measurement
1.5.6.3 Unit of Measure
1.6 OPTION 4 - STAGE 4 ROCK EXCAVATION
1.6.1 CLIN 0064 Diversion and Care of Water - Option 4
1.6.1.1 Payment
1.6.1.2 Measurement
1.6.1.3 Unit of Measure
1.6.2 CLIN 0065 Instrumentation Program O&M - Option 4
1.6.2.1 Payment
1.6.2.2 Measurement
1.6.2.3 Unit of Measure
1.6.3 CLIN 0066 USACE Office Cleaning Services - Option 4
1.6.3.1 Payment
1.6.3.2 Measurement
1.6.3.3 Unit of Measure
1.6.4 CLIN 0067 USACE Office Carpet Cleaning Services - Option 4
1.6.4.1 Payment
1.6.4.2 Measurement
1.6.4.3 Unit of Measure
1.6.5 CLIN 0068 Shotcrete Placement (4") - Option 4
1.6.5.1 Payment
1.6.5.2 Measurement
1.6.5.3 Unit of Measure
1.6.6 CLIN 0069 Rock Excavation - Option 4
1.6.6.1 Payment
1.6.6.2 Measurement
1.6.6.3 Unit of Measure
1.6.7 CLIN 0070 Pre-Splitting - Option 4
1.6.7.1 Payment
1.6.7.2 Measurement
1.6.7.3 Unit of Measure
1.6.8 CLIN 0071 Line Drilling (6" Spacing) - Option 4
1.6.8.1 Payment
1.6.8.2 Measurement
SECTION 01 22 00 Page 5
1.6.8.3 Unit of Measure
1.6.9 CLIN 0072 Rock Bolts - Option 4
1.6.9.1 Payment
1.6.9.2 Measurement
1.6.9.3 Unit of Measure
1.6.10 CLIN 0073 Manage, and Place Disposal Area Fill - Option 4
1.6.10.1 Payment
1.6.10.2 Measurement
1.6.10.3 Unit of Measure
1.7 OPTION 5 - STAGE 5 ROCK EXCAVATION
1.7.1 CLIN 0074 Diversion and Care of Water - Option 5
1.7.1.1 Payment
1.7.1.2 Measurement
1.7.1.3 Unit of Measure
1.7.2 CLIN 0075 Instrumentation Program O&M - Option 5
1.7.2.1 Payment
1.7.2.2 Measurement
1.7.2.3 Unit of Measure
1.7.3 CLIN 0076 USACE Office Cleaning Services - Option 5
1.7.3.1 Payment
1.7.3.2 Measurement
1.7.3.3 Unit of Measure
1.7.4 CLIN 0077 USACE Office Carpet Cleaning Services - Option 5
1.7.4.1 Payment
1.7.4.2 Measurement
1.7.4.3 Unit of Measure
1.7.5 CLIN 0078 Shotcrete Placement (4") - Option 5
1.7.5.1 Payment
1.7.5.2 Measurement
1.7.5.3 Unit of Measure
1.7.6 CLIN 0079 Rock Excavation - Option 5
1.7.6.1 Payment
1.7.6.2 Measurement
1.7.6.3 Unit of Measure
1.7.7 CLIN 0080 Pre-Splitting - Option 5
1.7.7.1 Payment
1.7.7.2 Measurement
1.7.7.3 Unit of Measure
1.7.8 CLIN 0081 Line Drilling (6" Spacing) - Option 5
1.7.8.1 Payment
1.7.8.2 Measurement
1.7.8.3 Unit of Measure
1.7.9 CLIN 0082 Rock Bolts - Option 5
1.7.9.1 Payment
1.7.9.2 Measurement
1.7.9.3 Unit of Measure
1.7.10 CLIN 0083 Manage, and Place Disposal Area Fill - Option 5
1.7.10.1 Payment
1.7.10.2 Measurement
1.7.10.3 Unit of Measure
1.8 OPTION 6 - STAGE 6 ROCK EXCAVATION
1.8.1 CLIN 0084 Diversion and Care of Water - Option 6
1.8.1.1 Payment
1.8.1.2 Measurement
1.8.1.3 Unit of Measure
1.8.2 CLIN 0085 Instrumentation Program O&M - Option 6
1.8.2.1 Payment
1.8.2.2 Measurement
1.8.2.3 Unit of Measure
SECTION 01 22 00 Page 6
1.8.3 CLIN 0086 USACE Office Cleaning Services - Option 6
1.8.3.1 Payment
1.8.3.2 Measurement
1.8.3.3 Unit of Measure
1.8.4 CLIN 0087 USACE Office Carpet Cleaning Services - Option 6
1.8.4.1 Payment
1.8.4.2 Measurement
1.8.4.3 Unit of Measure
1.8.5 CLIN 0088 Shotcrete Placement (4") - Option 6
1.8.5.1 Payment
1.8.5.2 Measurement
1.8.5.3 Unit of Measure
1.8.6 CLIN 0089 Rock Excavation - Option 6
1.8.6.1 Payment
1.8.6.2 Measurement
1.8.6.3 Unit of Measure
1.8.7 CLIN 0090 Pre-Splitting - Option 6
1.8.7.1 Payment
1.8.7.2 Measurement
1.8.7.3 Unit of Measure
1.8.8 CLIN 0091 Line Drilling (6" Spacing) - Option 6
1.8.8.1 Payment
1.8.8.2 Measurement
1.8.8.3 Unit of Measure
1.8.9 CLIN 0092 Rock Bolts - Option 6
1.8.9.1 Payment
1.8.9.2 Measurement
1.8.9.3 Unit of Measure
1.8.10 CLIN 0093 Manage, and Place Disposal Area Fill - Option 6
1.8.10.1 Payment
1.8.10.2 Measurement
1.8.10.3 Unit of Measure
1.9 OPTION 7 - STAGE 7 ROCK EXCAVATION
1.9.1 CLIN 0094 Diversion and Care of Water - Option 7
1.9.1.1 Payment
1.9.1.2 Measurement
1.9.1.3 Unit of Measure
1.9.2 CLIN 0095 Instrumentation Program O&M - Option 7
1.9.2.1 Payment
1.9.2.2 Measurement
1.9.2.3 Unit of Measure
1.9.3 CLIN 0096 USACE Office Cleaning Services - Option 7
1.9.3.1 Payment
1.9.3.2 Measurement
1.9.3.3 Unit of Measure
1.9.4 CLIN 0097 USACE Office Carpet Cleaning Services - Option 7
1.9.4.1 Payment
1.9.4.2 Measurement
1.9.4.3 Unit of Measure
1.9.5 CLIN 0098 Shotcrete Placement (4") - Option 7
1.9.5.1 Payment
1.9.5.2 Measurement
1.9.5.3 Unit of Measure
1.9.6 CLIN 0099 Rock Excavation - Option 7
1.9.6.1 Payment
1.9.6.2 Measurement
1.9.6.3 Unit of Measure
1.9.7 CLIN 0100 Mechanical Excavation - L13 - Option 7
1.9.7.1 Payment
SECTION 01 22 00 Page 7
1.9.7.2 Measurement
1.9.7.3 Unit of Measure
1.9.8 CLIN 0101 Pre-Splitting - Option 7
1.9.8.1 Payment
1.9.8.2 Measurement
1.9.8.3 Unit of Measure
1.9.9 CLIN 0102 Line Drilling (6" Spacing) - Option 7
1.9.9.1 Payment
1.9.9.2 Measurement
1.9.9.3 Unit of Measure
1.9.10 CLIN 0103 Rock Bolts - Option 7
1.9.10.1 Payment
1.9.10.2 Measurement
1.9.10.3 Unit of Measure
1.9.11 CLIN 0104 Manage, and Place Disposal Area Fill - Option 7
1.9.11.1 Payment
1.9.11.2 Measurement
1.9.11.3 Unit of Measure
1.10 OPTION 8 - STAGE 8 ROCK EXCAVATION
1.10.1 CLIN 0105 Diversion and Care of Water - Option 8
1.10.1.1 Payment
1.10.1.2 Measurement
1.10.1.3 Unit of Measure
1.10.2 CLIN 0106 Instrumentation Program O&M - Option 8
1.10.2.1 Payment
1.10.2.2 Measurement
1.10.2.3 Unit of Measure
1.10.3 CLIN 0107 USACE Office Cleaning Services - Option 8
1.10.3.1 Payment
1.10.3.2 Measurement
1.10.3.3 Unit of Measure
1.10.4 CLIN 0108 USACE Office Carpet Cleaning Services - Option 8
1.10.4.1 Payment
1.10.4.2 Measurement
1.10.4.3 Unit of Measure
1.10.5 CLIN 0109 Shotcrete Placement (4") - Option 8
1.10.5.1 Payment
1.10.5.2 Measurement
1.10.5.3 Unit of Measure
1.10.6 CLIN 0110 Rock Excavation - Option 8
1.10.6.1 Payment
1.10.6.2 Measurement
1.10.6.3 Unit of Measure
1.10.7 CLIN 0111 Pre-Splitting - Option 8
1.10.7.1 Payment
1.10.7.2 Measurement
1.10.7.3 Unit of Measure
1.10.8 CLIN 0112 Line Drilling (6" Spacing) - Option 8
1.10.8.1 Payment
1.10.8.2 Measurement
1.10.8.3 Unit of Measure
1.10.9 CLIN 0113 Rock Bolts - Option 8
1.10.9.1 Payment
1.10.9.2 Measurement
1.10.9.3 Unit of Measure
1.10.10 CLIN 0114 Manage, and Place Disposal Area Fill - Option 8
1.10.10.1 Payment
1.10.10.2 Measurement
1.10.10.3 Unit of Measure
SECTION 01 22 00 Page 8
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 CONTRACT COST BREAKDOWN
-- End of Section Table of Contents --
SECTION 01 22 00 Page 9
SECTION 01 22 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 PAYMENT ITEMS
Payment items for the work of this contract are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular payment item, shall be included in the listed payment item most closely associated with the work involved. The payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.2 BASE
1.2.1 CLIN 0001 Mobilization and Demobilization
1.2.1.1 Payment
Payment will be made for costs associated with mobilization and demobilization for the base contract, as defined in Contract Clause
252.236-7004 PAYMENT FOR MOBILIZATION AND DEMOBILIZATION.
60 percent of the price for this payment item will be paid upon completion of the Contractor's mobilization at the work site.
The remaining 40 percent will be paid upon completion of demobilization.
1.2.1.2 Unit of Measure
Unit of measure: Job.
1.2.2 CLIN 0002 Initial Unwatering and Design of Dewatering System
1.2.2.1 Payment
Payment will be made for costs associated with initial unwatering and design of dewatering system as specified in Section 01 57 24 DIVERSION AND CARE OF WATER. Payment for initial unwatering will be made at the contract price per Job for "Initial Unwatering and Design of Dewatering System".
Payment for initial unwatering shall include all costs associated with dewatering the cofferdam area for the first time. Initial unwatering is defined as complete when entire spillway flip bucket and 75% of the area within the cofferdam (outside the spillway flip bucket)is either dry or has standing water less than 1/2 inch in depth. Costs shall include but not limited to equipment, fuel, electricity, personnel, and maintenance.
All costs associated with design and installation of the pumping system for
SECTION 01 22 00 Page 10 the Diversion and Care of Water CLINS are incidental to this bid item.
1.2.2.2 Unit of Measure
Unit of measure: Job.
1.2.3 CLIN 0003 Diversion and Care of Water - Base
1.2.3.1 Payment
Payment will be made for costs associated with diversion and care of Water as specified in Section 01 57 24 DIVERSION AND CARE OF WATER. Payment for diversion and care of water for the base contract, including the construction, maintenance, operation (including pumping), regulation of flow; diversion and care of water during construction; and all other work necessary to perform the construction work in areas free from water, will be made at the contract unit price per month for "Diversion and Care of Water - Base".
Costs shall include but not be limited to equipment, fuel, electricity, personnel, and maintenance.
1.2.3.2 Measurement
The monthly average flowrate will be the calculated as follows:
A daily measurement of the flow will be taken by flow meter by the Contractor and witnessed by the Government. The use of Manufacturer's charts and RPM shall not be used for official computations. A monthly average will be computed using flow meter data.
1.2.3.3 Unit of Measure
Unit of measure: Month.
1.2.4 CLIN 0004 Instrumentation Program O&M - Base
1.2.4.1 Payment
Payment will be made for costs associated with installation, operation, and maintenance of the instrumentation program as specified in Section 13 50 00
INSTRUMENTATION PROGRAM.
Monitoring and maintaining cofferdam instrumentation components (and related data acquisition components required to collect, store and relay data), reporting this data, and development and maintenance of the Emergency Action Plan will be measured and paid on a monthly basis under the pay item "Instrumentation Program O&M - Base".
1.2.4.2 Measurement
This payment item applies during the operation and maintenance period of the instrumentation program.
1.2.4.3 Unit of Measure
Unit of measure: Month.
SECTION 01 22 00 Page 11
1.2.5 CLIN 0005 USACE Office Cleaning Services - Base
1.2.5.1 Payment
Payment will be made for costs associated with providing cleaning services to the USACE office as specified in Section 01 50 00 TEMPORARY AND PERMANENT CONSTRUCTION FACILITIES AND CONTROLS. Payment will be made at the contract unit price per month for "USACE Office Cleaning Services - Base".
1.2.5.2 Measurement
Measurement for payment will be made by the quantity of months of satisfactorily performed cleaning services.
1.2.5.3 Unit of Measure
Unit of measure: Month.
1.2.6 CLIN 0006 USACE Office Carpet Cleaning Services - Base
1.2.6.1 Payment
Payment will be made for costs associated with providing carpet cleaning services to the USACE office as specified in Section 01 50 00 TEMPORARY AND PERMANENT CONSTRUCTION FACILITIES AND CONTROLS. Payment will be made at the contract unit price per each for "USACE Office Carpet Cleaning Services
- Base".
1.2.6.2 Measurement
Measurement for payment will be made for each time of satisfactorily performed cleaning service.
1.2.6.3 Unit of Measure
Unit of measure: Each (EA).
1.2.7 CLIN 0007 Core Drilling, Vertical Holes
1.2.7.1 Payment
Payment will be made for costs including equipment, labor, materials and incidentals associated with Core Drilling, Vertical Holes, as specified in Section 02 32 00 SUBSURFACE DRILLING, SAMPLING, AND TESTING. Payment for Core Drilling, Vertical Holes will be made at the contract unit price per linear feet (LF) for "Core Drilling, Vertical Holes".
1.2.7.2 Measurement
Core Drilling, Vertical Holes will be measured for payment to the nearest foot, based upon the linear feet of hole actually drilled in accordance with the specifications or as directed by the Contracting Officer.
Measurements less than 0.5 of a foot shall be rounded down, and measurements of 0.5 of a foot or greater shall be rounded up.
1.2.7.3 Unit of Measure
Unit of measure: Linear Feet (LF).
SECTION 01 22 00 Page 12
1.2.8 CLIN 0008 Secant Wall; Primary Piles In-Place
1.2.8.1 Payment
Payment will be made for costs associated with Secant Wall; Primary Piles In-Place as specified in Section 31 66 17 SECANT PILE WALLS. Payment for Secant Wall; Primary Piles In-Place will be made at the contract price per Linear Feet (LF) for "Secant Pile Wall; Primary Piles In-Place".
a. Primary piles of the secant pile wall shall be measured and paid for by the linear foot of piles actually installed, tested, and accepted. No separate measurement or payment will be made for related work considered incidental to the pile construction, including but not limited to environmental protection; drilling; material disposal;
inspection; temporary casings; taxes and delivery costs of Portland cement and fly ash; furnishing Portland cement, fly ash; concrete or tremie concrete; advance planning and engineering; report preparation;
re-testing; and/or all other labor, materials, equipment, and supplies associated with the piles construction; and all such work associated therewith shall be incidental to and included in the Secant Piles and Testing item.
b. The unit price paid for installation of primary piles shall be different from the unit price for installation of secondary piles. The unit price paid for installation of the piles includes full compensation for all labor, materials, equipment, and supplies to complete the piles as shown on the Contract Drawings and as specified herein, including all incidental items of work. Pile length actually provided, as directed and approved by the Contracting Officer, shall be the cumulative total of pile length constructed tabulated as both additive and deductive to the lengths indicated on the Contract Drawings, shall be paid for by the unit price per linear foot.
1.2.8.2 Measurement
Primary piles of the secant pile wall will be measured by the linear foot of piles actually installed, tested, and accepted, measured from the tip elevation to top of pile extension as indicated on the Contract Drawings.
The final tip elevation of primary piles and secondary piles may be lower or higher than the nominal design tip elevation as shown in the Contract Drawings. Pile length actually provided, as directed and approved by the Contracting Officer, shall be measured and shall be the cumulative total of pile length constructed tabulated as both additive and deductive to the lengths indicated on the Contract Drawings, shall be measured by the per linear foot basis.
1.2.8.3 Unit of Measure
Unit of measure: Linear Feet (LF).
1.2.9 CLIN 0009 Secant Wall; Secondary Piles In-Place
1.2.9.1 Payment
Payment will be made for costs associated with Secant Wall; Secondary Piles In-Place as specified in Section 31 66 17 SECANT PILE WALLS. Payment for Secant Wall; Secondary Piles In-Place will be made at the contract price per Linear Feet (LF) for "Secant Wall; Secondary Piles In-Place".
SECTION 01 22 00 Page 13
a. Secondary piles of the secant pile wall shall be measured and paid for by the linear foot of piles actually installed, tested, and accepted.
No separate measurement or payment will be made for related work considered incidental to the pile construction, including but not limited to environmental protection; drilling; material disposal;
inspection; taxes and delivery costs of mill reinforcement steel;
furnishing reinforcement steel; fabrication, transportation and placement of steel reinforcing bars; mechanical couplers; steel fabrications embedded in and projecting from piles; temporary casings;
taxes and delivery costs of Portland cement and fly ash; furnishing Portland cement, fly ash; concrete or tremie concrete; Crosshole Sonic Logging testing; advance planning and engineering; report preparation;
re-testing; and/or all other labor, materials, equipment, and supplies associated with the piles construction; and all such work associated therewith shall be incidental to and included in the Secant Piles and Testing item.
b. The unit price paid for installation of primary piles shall be different from the unit price for installation of secondary piles. The unit price paid for installation of the piles and Crosshole Sonic Logging testing includes full compensation for all labor, materials, equipment, and supplies to complete the piles as shown on the Contract Drawings and as specified herein, including all incidental items of work. Pile length actually provided, as directed and approved by the Contracting Officer, shall be the cumulative total of pile length constructed tabulated as both additive and deductive to the lengths indicated on the Contract Drawings, shall be paid for by the unit price per linear foot.
1.2.9.2 Measurement
Secondary piles of the secant pile wall will be measured by the linear foot of piles actually installed, tested, and accepted, measured from the tip elevation to top of pile extension as indicated on the Contract Drawings.
The final tip elevation of primary piles and secondary piles may be lower or higher than the nominal design tip elevation as shown in the Contract Drawings. Pile length actually provided, as directed and approved by the Contracting Officer, shall be measured and shall be the cumulative total of pile length constructed tabulated as both additive and deductive to the lengths indicated on the Contract Drawings, shall be measured by the per linear foot basis.
1.2.9.3 Unit of Measure
Unit of measure: Linear Feet (LF).
1.2.10 CLIN 0010 Secant Wall; Cap Beam
1.2.10.1 Payment
Payment will be made for costs associated with Secant Wall; Cap Beam as specified in Section 31 66 17 SECANT PILE WALLS. Payment for Secant Wall;
Cap Beam will be made at the contract price per Job for "Secant Wall; Cap Beam".
No separate measurement or payment will be made for related work considered incidental to the capbeam construction, including but not limited to environmental protection; rock excavation; installation of the drilled and
SECTION 01 22 00 Page 14 grouted dowels from the capbeam into the L13 cofferdam monolith;
inspection; taxes and delivery costs of mill reinforcement steel;
furnishing reinforcement steel; fabrication, transportation and placement of steel reinforcing bars; mechanical couplers; steel fabrications embedded in and projecting from piles; temporary casings; taxes and delivery costs of Portland cement and fly ash; furnishing Portland cement, fly ash;
concrete and testings; advance planning and engineering; report preparation; re-testing; and/or all other labor, materials, equipment, and supplies associated with the capbeam construction; and all such work associated therewith shall be incidental to and included in the Secant Pile Capbeam item.
1.2.10.2 Unit of Measure
Unit of measure: Job.
1.2.11 CLIN 0011 Furnish and Install Inclined Anchors
1.2.11.1 Payment
Payment will be made for costs associated with furnishing and installing inclined anchors as specified in Section 31 68 14 ROCK STABILITY ANCHORS.
The anchor tendon sizes and lengths are shown on the drawings. Payment shall include all hardware required for proper installation and lock off including the bearing plate, anchor head, etc. Payment will include all labor, equipment, and materials required for successful installation of the anchors. Payment will include drilling of anchor hole. No payment will be made for anchors which do not meet the acceptance criteria. Payment for furnishing and installing inclined anchors will be made at the contract unit price per linear feet (LF) for "Furnish and Install Inclined Anchors".
1.2.11.2 Measurement
Inclined anchors will be measured for payment to the nearest foot, based upon the linear feet of anchor actually installed below the bearing plate in accordance with the specifications.
1.2.11.3 Unit of Measure
Unit of measure: Linear Feet (LF).
1.2.12 CLIN 0012 Performance Tests
1.2.12.1 Payment
Payment will be made for costs associated with performing Option 1 Performance Tests on accepted anchors as specified in Section 31 68 14 ROCK STABILITY ANCHORS. Payment for Performance Tests on anchors will be made at the contract price per Each (EA) for "Performance Tests".
1.2.12.2 Measurement
Performance Tests will be measured based upon the number of tests performed.
1.2.12.3 Unit of Measure
Unit of measure: Each (EA).
SECTION 01 22 00 Page 15
1.2.13 CLIN 0013 Proof Tests
1.2.13.1 Payment
Payment will be made for costs associated with performing Proof Tests on all anchors which are not performance tested as specified in Section 31 68 14 ROCK STABILITY ANCHORS. Payment for Proof Tests will be made at the contract price per Each (EA) for "Proof Tests".
1.2.13.2 Measurement
Proof Tests will be measured based upon the number of tests performed on anchors which are accepted in accordance with the specifications.
1.2.13.3 Unit of Measure
Unit of measure: Each (EA).
1.2.14 CLIN 0014 Watertightness Testing
1.2.14.1 Payment
Payment will be made for costs associated Watertightness Testing as specified in Section 31 68 14 ROCK STABILITY ANCHORS. Payment for Watertightness Testing will be made at the contract price per Each (EA) for "Watertightness Testing".
1.2.14.2 Measurement
Watertightness Testing will be measured for payment based upon the number of watertightness tests actually performed in accordance with the specifications or as otherwise required.
1.2.14.3 Unit of Measure
Unit of measure: Each (EA).
1.2.15 CLIN 0015 Grouting Holes & Redrilling
1.2.15.1 Payment
Payment will be made for costs associated with Grouting Holes and Redrilling as specified in Section 31 68 14 ROCK STABILITY ANCHORS.
Payment for Grouting Holes and Redrilling will be made at the contract price per Linear Feet (LF) for "Grouting Holes & Redrilling".
1.2.15.2 Measurement
Grouting Holes and Redrilling will be measured for payment to the nearest foot, based upon the linear feet of hole actually grouted and redrilled in accordance with the specifications.
1.2.15.3 Unit of Measure
Unit of measure: Linear Feet (LF).
SECTION 01 22 00 Page 16
1.2.16 CLIN 0016 Anchor Support Blocks
1.2.16.1 Payment
Payment will be made for costs associated with Anchor Support Blocks as specified in Section 31 68 14 ROCK STABILITY ANCHORS. Payment will consider all costs associated with material supply, placement, and finishing including: concrete, rebar, embedments and formwork. Payment for Anchor Support Blocks will be made at the contract price per Linear Feet (LF) for "Anchor Support Blocks".
1.2.16.2 Measurement
Anchor Support Blocks will be measured for payment to the nearest foot, based upon the linear feet of support block actually placed in accordance with the specifications.
1.2.16.3 Unit of Measure
Unit of measure: Linear Feet (LF).
1.2.17 CLIN 0017 Probe Hole
1.2.17.1 Payment
Payment will be made for costs associated with drilling a vertical probe hole through the rock and bentonite beds prior to installation of the anchor support as specified in Section 31 68 14 ROCK STABILITY ANCHORS.
Payment for Probe Hole will be made at the contract price per Linear Feet (LF) for "Probe Hole".
1.2.17.2 Measurement
Pilot holes drilled through the rock and bentonite bed will be measured for payment to the nearest linear foot.
1.2.17.3 Unit of Measure
Unit of measure: Linear Feet (LF).
1.2.18 CLIN 0018 Cofferdam Stability Berm
1.2.18.1 Payment
Payment for the cofferdam stability berm will be made at the unit price for "Cofferdam Stability Berm", which price shall include the cost of all items connected with the work in full compliance with the Specifications and the drawings.
1.2.18.2 Measurement
Measurement for payment for COFFERDAM STABILITY BERM will be based on the number of cubic yards furnished, placed, compacted, and maintained as specified in with Section 31 00 00 EARTH EXCAVATION AND FILL PLACEMENT and within the lines and grades shown on the drawings, or as directed or by the Contracting Officer. Quantities will be determined on the basis of surveys made prior to placement of the fill and the lines and grades shown on the drawings.
SECTION 01 22 00 Page 17
1.2.18.3 Unit of Measure
Unit of measure: Cubic Yard (CY).
1.2.19 CLIN 0019 Lock Overburden Removal
1.2.19.1 Payment
The contract unit prices for the various items under Section 31 23 05 LOCK EXCAVATION shall constitute full compensation for furnishing all materials, labor, tools, equipment, and incidentals necessary to accomplish the work herein, including environmental protection, cleanup of the work area, dewatering and disposal of any waste. Removal of construction debris (i.e., reinforced concrete, timbers, etc.) remaining from the original lock construction shall be included in the payment for Lock Overburden Excavation.
Lock Overburden Removal will be paid for at the contract unit price per cubic yard. This payment will constitute full compensation for all labor, equipment, tools supplies, and incidentals necessary to complete the work.
Payment will be made under payment item "Lock Overburden Removal".
1.2.19.2 Measurement
A survey of the site shall be made prior to the commencement of any overburden excavation. Any material excavated prior to survey cross sections will not be paid for by the Government. A second survey shall be completed after completion of the overburden excavation. The Contracting Officer shall verify that all overburden material has been removed prior to the survey of top of rock. All measurements for payment for overburden removal will be based on these surveys and additional surveys as specified hereinafter without regard to any changes that may occur during the execution of the work. Quantities for payment for overburden removal will be determined in cubic yards based on cross-section measurements. All quantity computations for overburden removal payment will be made using the average end area method from cross-sections taken at 50 foot intervals.
The Contracting Officer will make all decisions concerning classification of the excavated materials. Quantities will be measured to the nearest cubic yard based on the surveys.
1.2.19.3 Unit of Measure
Unit of measure: Cubic Yard (CY).
1.2.20 CLIN 0020 Flood Facility Concrete Splash Pad
1.2.20.1 Payment
Payment will be made for costs associated with Flood Facility Concrete Splash Pad as specified in Section 31 23 05 LOCK EXCAVATION. Payment for Flood Facility Concrete Splash Pad will be made at the contract price per Job for "Flood Facility Concrete Splash Pad".
No separate measurement or payment will be made for related work considered incidental to the splash construction, including but not limited to environmental protection; inspection; taxes and delivery costs of mill reinforcement steel; furnishing reinforcement steel; fabrication, transportation and placement of steel reinforcing bars; mechanical couplers; steel fabrications embedded in and projecting from piles;
SECTION 01 22 00 Page 18 temporary casings; taxes and delivery costs of Portland cement and fly ash;
furnishing Portland cement, fly ash; concrete and testings; advance planning and engineering; report preparation; re-testing; and/or all other labor, materials, equipment, and supplies associated with the splash construction; and all such work associated therewith shall be incidental to and included in the Flood Facility Concrete Splash Pad item.
1.2.20.2 Unit of Measure
Unit of measure: Job.
1.2.21 CLIN 0021 Shotcrete Placement (4")
1.2.21.1 Payment
a. The contract price shall constitute full compensation for furnishing all plant, labor, equipment, materials, and supplies, except as otherwise specified, and for performing all operations required for the completion of all work included under the item as specified in Section 03 37 13, shown on the contract Drawings, or directed by the Contracting Officer. All measurements for payment shall be made in the presence of the Contracting Officer.
b. Payment will be made for costs associated with shotcrete placement.
All costs associated with satisfactory placement and curing of shotcrete, as specified in Section 03 37 13 SHOTCRETE, shall be included and shall not be paid as separate items. Areas to be treated with shotcrete will be determined or approved by the Contracting Officer. Shotcrete placement for test panels shall be as indicated in Section 03 37 13, paragraph 3.7.1 STRENGTH TESTING.
c. Costs associated with laboratory strength testing of cores and sawed beams of shotcrete test panels shall be included in this payment and shall not be paid as separate items. Costs associated with materials and placement of drains shall be included in this payment and shall not be paid as separate items. Payment will be made under payment item "Shotcrete Placement (4")".
1.2.21.2 Measurement
Shotcrete placed will be measured for payment on the basis of shotcrete material sprayed through the nozzle onto the rock surface designated for treatment by the Contracting Officer. Measurement of shotcrete satisfactorily placed will be determined by the area sprayed to/or above the gauge pins. Thickness will be determined in accordance with Section 03 37 13, paragraph 3.3.2.1 Placement Control.
1.2.21.3 Unit of Measure
Unit of measure: Square Yard (SY).
1.2.22 CLIN 0022 Rock Excavation
1.2.22.1 Payment
a. Rock excavation will be paid for at the contract unit price per cubic yard. This payment will constitute full compensation for furnishing all materials, labor, equipment, materials, tools, supplies, and incidentals necessary to complete the work including environmental
SECTION 01 22 00 Page 19 protection, dewatering and disposal of any material. Payment for rock excavation will be made only for the volume of rock as defined in Section 31 23 05 LOCK EXCAVATION actually removed by the Contractor, and only for the material excavated within the limits shown on the contract Drawings or established in the field by the Contracting Officer.
b. Payment for rock excavation shall be at the contract unit price for "Rock Excavation". Over-excavation and subsequent backfilling of excavations necessary through the fault or negligence of the Contractor shall be at no additional cost to the Government. No separate payment shall be made for surveying, blasting, hoe-ramming, ripping, mucking, scaling, sandbagging, excavation of rock used as temporary fill for the convenience of the Contractor, surveying for determination of excavation quantities and maintaining the excavation in a dewatered state.
c. No payment will be made for test blasting or production blasting.
Except for presplitting and line drilling, blasting shall be incidental to rock excavation.
1.2.22.2 Measurement
a. Measurement for required rock excavation. A survey of the site shall be made prior to the commencement of any rock excavation. The Contracting Officer shall verify that all overburden material has been excavated prior to the survey of the top of rock surface. All measurements for payment for rock excavation will be based on that survey and additional surveys as specified hereinafter without regard to any changes that may occur during the execution of the work. All quantity computations for rock excavation payment will be made using the average end area method from cross-sections taken at intervals not to exceed 50 feet. The Contracting Officer will make all decisions concerning classification of the excavated materials. Quantities will be measured to the nearest cubic yard based on the survey. Excavation will be paid for up to 1 foot below the assigned founding grades and to the neat lines as ROCK EXCAVATION.
b. Rock excavation, excluding pre-splitting, shall include full compensation for materials excavated as shown on the drawings.
Pre-splitting shall be measured for payment as outlined in Section 31 23 05 LOCK EXCAVATION, paragraph PRE-SPLITTING. Line drilling shall be measured for payment as outlined in Section 31 23 05, paragraph LINE
DRILLING.
1.2.22.3 Unit of Measure
Unit of measure: Cubic Yard (CY).
1.2.23 CLIN 0023 Pre-Splitting
1.2.23.1 Payment
Pre-splitting will be measured for payment based on the linear foot of pre-split blasthole drilling. Payment for pre-splitting will be made at the contract price per linear foot for "Pre-Splitting" which price shall constitute full compensation for all costs for materials, explosives, labor, equipment, and miscellaneous items which are necessary to complete the pre-splitting as specified in Section 31 23 06 BLASTING.
SECTION 01 22 00 Page 20
1.2.23.2 Measurement
Pre-split drilling will be measured on the pre-split finish face at the rock excavation limit and tolerance. Measurement shall be made by survey provided by the Contractor.
1.2.23.3 Unit of Measure
Unit of measure: Linear Foot.
1.2.24 CLIN 0024 Line Drilling (6" Spacing)
1.2.24.1 Payment
a. Payment for line drilling will be made at the contract price per square yard for "Line Drilling (6" Spacing)" which price shall constitute full compensation for all costs for materials, explosives, labor, equipment, and miscellaneous items which are necessary to complete the line drilling as specified in Section 31 23 06 BLASTING.
b. Payment will be made for costs associated with line drilling including supplies, equipment, and surveying are incidental to line drilling.
Payment for line drilling will be made at the contract price per square yard of approved excavation face for "Line Drilling (6" Spacing)" which price shall constitute full compensation for all costs for materials, labor, equipment, survey and miscellaneous items which are necessary to complete the line drilling as specified in Section 31 23 06.
1.2.24.2 Measurement
Line Drilling will be measured for payment based on the square yard of approved excavation face. Line drilling will be measured on the square yard of line drilled face within the rock excavation tolerance.
Measurement shall be made by survey provided by the Contractor.
1.2.24.3 Unit of Measure
Unit of measure: Square Yards (SY).
1.2.25 CLIN 0025 Rock Bolts
1.2.25.1 Payment
a. Payment for installed rock bolts as specified in Section 31 68 13 ROCK BOLTS FOR SLOPE PROTECTION, will be made under contract bid schedule "Rock Bolts". No payment will be made for rock bolts or other materials wasted due to improper installations, nor for grout due to improper use, or which is wasted due to negligence on the part of the Contractor, or which is rejected by the Contracting Officer because of improper mixing. No payment will be made for replacement of rock bolt holes and installed rock bolts that are not in accordance with these specifications. Cement grout and/or rock bolt manufacturer's representative site visit and supervision of rock bolt test installation, surveying of rock bolt top of hole location and elevation, rock bolt plates, nuts, washers, couplings, and other materials used or necessary for the installation are incidental to rock bolt installation. Payment will be made under Payment item "Rock Bolts."
SECTION 01 22 00 Page 21
b. The contract price shall constitute full compensation for mobilization, demobilization; drilling rock bolt holes; rock bolt fabrication, installation and grouting including grout constituents; care and disposal of waste grout, cleanup of the site; furnishing, handling, transporting, and storing of materials; and furnishing all labor and supplies incidental to the work.
1.2.25.2 Measurement
Payment will be made for rock bolts accepted and installed at the direction of the Contracting Officer. Payment will be made for the length of rock bolt installed. Length of rock bolt installed will be rounded to the nearest foot. Lengths of less than five-tenths of a foot will be rounded down, and lengths of five-tenths of a foot or greater will be rounded up.
1.2.25.3 Unit of Measure
Unit of measure: Linear Feet (LF).
1.2.26 CLIN 0026 Grubbing Only
1.2.26.1 Payment
Payment will be made for costs associated with or incidental to all areas in which only grubbing is to be performed under this contract, as specified in Section 31 11 00 CLEARING AND GRUBBING, at the Hixson-Greenway Disposal Area and any other project area designated on the drawings and as specified herein. The Contractor shall keep grubbing of vegetation to the minimum necessary for site development and protect existing vegetation as stated in Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS.
1.2.26.2 Measurement
Measurement of grubbing only for payment shall be the actual total measured area of vegetation removal performed during grubbing only operations.
1.2.26.3 Unit of Measure
Unit of measure: Acre.
1.2.27 CLIN 0027 Clearing and Grubbing
1.2.27.1 Payment
Payment will be made for all costs associated with or incidental to all areas in which both clearing and grubbing are to be performed under this contract, as specified in Section 31 11 00 CLEARING AND GRUBBING, at the Hixson-Greenway Disposal Area and any other project areas designated on the drawings and as specified herein. The Contractor shall keep clearing and grubbing of vegetation to the minimum necessary for site development and protect existing vegetation as stated in Section 01 57 19 TEMPORARY
ENVIRONMENTAL CONTROLS.
1.2.27.2 Measurement
Measurement of clearing and grubbing for payment shall be the actual total measured area of vegetation removal performed during clearing and grubbing operations.
SECTION 01 22 00 Page 22
1.2.27.3 Unit of Measure
Unit of measure: Acre.
1.2.28 CLIN 0028 Drainage Ditch Construction
1.2.28.1 Payment
Payment will be made for all costs associated with or incidental to constructing drainage ditches at the disposal at the locations shown on the drawings and as specified in Section 31 00 00 EARTH EXCAVATION AND FILL PLACEMENT, including, but not limited to, excavation of the ditches to promote positive drainage; transporting and disposal of excavated material;
providing vegetative cover on the slopes of the ditches to prevent erosion;
installation of jute mesh…