Chick_Lock_-_Lock_Excavation_PreBid_Slides.pdf

PDF 8 MB Posted

Attached to
Lock Excavation, Chickamauga Lock Federal contract opportunity
Solicitation number
W912P5-16-B-0005
Issued by
Department of the Army Corps of Engineers Engineering District Nashville

About this file

Pre-Bid Slide Presentation

View the file

Other files for this federal contract opportunity

Other files attached to Lock Excavation, Chickamauga Lock, newest first.
File Type Posted
Bid_Abstract_(OF_1419).pdf PDF
W912P5-16-B-0005-0003.pdf PDF
W912P5-16-B-0005_Bid_Schedule.xlsx XLSX spreadsheet
W912P5-16-B-0005_AppA-02.pdf PDF
W912P5-16-B-0005_AppA-06.pdf PDF
W912P5-16-B-0005_TSpecs_Am2pages.pdf PDF
W912P5-16-B-0005_Plans_Am2sheets.pdf PDF
W912P5-16-B-0005_AppA-11.pdf PDF
CHH_Tail_Water.xlsx XLSX spreadsheet
W912P5-16-B-0005-0002.pdf PDF
W912P5-16-B-0005_AppA-15.pdf PDF
W912P5-16-B-0005_AppA-12.pdf PDF
W912P5-16-B-0005_AppA-07.pdf PDF
W912P5-16-B-0005_AppA-08.pdf PDF
W912P5-16-B-0005_AppA-04.pdf PDF
W912P5-16-B-0005_AppA-01.pdf PDF
W912P5-16-B-0005_AppA-03.pdf PDF
W912P5-16-B-0005_AppA-13.pdf PDF
W912P5-16-B-0005_AppA-16.pdf PDF
W912P5-16-B-0005_AppA-05.pdf PDF
W912P5-16-B-0005_AppA-09.pdf PDF
W912P5-16-B-0005_AppA-10.pdf PDF
W912P5-16-B-0005_AppA-14.pdf PDF
Site_Visit_Sign_In_Sheet.pdf PDF
W912P5-16-B-0005-0001.pdf PDF
Pre-Bid_Site_Visit_Form.pdf PDF
W912P5-16-B-0005_TSpecs.pdf PDF
W912P5-16-B-0005.pdf PDF
W912P5-16-B-0005_Plans.pdf PDF
Foreign_National_Security_Form.pdf PDF
Site_Visit_Map.jpg JPG image
Show all 31

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Army Corps of Engineers

BUILDING STRONG®

Chickamauga Lock Replacement Lock Excavation Contract Pre-Bid Conference

Project Delivery Team Chickamauga Lock Nashville District 7 July 2016

Pre-Bid Conference Agenda Purpose: Highlight specific items in the Contract and Plans & Specifications that may impact bids/schedules

Adam Walker - Project Manager Project Background and Funding Contract Scope – Base w/ Options and Alternatives Work Limits & Environmental constraints

Lether Robinson – Contract Specialist Contract Information Potential Future Amendment Items

Cory Morgan & Mike Arles – Technical Leads Existing Conditions Rock Excavation Base/Options, Toe Drain Alternative

(Disposal Area), Secant Wall, Anchors Tommy Long – Resident Engineer

Tour – Cofferdam, Disposal Area, Laydown Area, Etc.

Nashville District Area of Responsibility Tennessee and Cumberland River Navigation Systems

Chickamauga Lock Replacement Construction Contracts

Miter Gates, Culvert Valves, Bulkheads

Approach Wall Beams

Temporary Cofferdam

Project Funding 4th highest priority construction project for funding from the Inland Waterways Trust Fund (IWTF).

Like many inland navigation projects, Chickamauga is not currently eligible for the President’s Budget due to BCR requirements.

Project received no funding in FY12-FY14, due to funding limitations of IWTF.

Changes occurred in 2014 that strengthened the IWTF.

WRDA 2014 – Increased diesel fuel fee from $0.20 to

$0.29/gallon Olmsted cost share changed from 50/50 to 85/15

Project Funding

Project has received funding through Corps Work Plans or “Funding Pots” in FY15 and FY16.

Project will not know FY17 funding until approximately February 2017 and should receive any funds in the March/April timeframe.

If sufficient funding is received in FY17, it is the Government’s intent to exercised all remaining options by 28 April 2017.

Chickamauga Lock Lock Excavation Contract

44 Inclined Rock Strand Anchors

51’ Long Secant Pile Ret. Wall

Exploratory Drilling & Rock Excavation

- Contract Award: Sep 2016

- Contract Duration: 2 years

Toe Drain Alternative

Lock Concrete FY 17 Capability

Future Construction Contract – Lock Concrete

- Contract Award ~Sep 2017

- Base with options (using FY17 funding)

- Contract complete by ~Jan 2021

Approximate Work Area

Disposal Area

Wetland Area (to be avoided)

Contract Information

This acquisition is Full & Open with a 10% HUBZone price evaluation

Firm Fixed Construction Contract

Award made to: Lowest Price Bid who is found to be responsive and responsible

Contract includes: Base with Eight Options Options to be awarded no later than 28 April 2017.

Alternatives: Toe Drain (Replace or New Alignment)

Subcontracting Plan required if contract awarded to a Large business

Contract Information, Cont.

Questions Due 13 July 2016 at 12:00 PM central time

Bid Opening - 5 Aug 2016 at 1:00 PM central time

Payment & Performance Bonds required

Clauses

Wage Determination Rates

Notice to Proceed:

May be delayed until the State of Tennessee 401 permit is received Application submitted 10 June 2016.

Approx. 120 day process

Partial NTP may be issued to allow submittals to be developed.

Potential Future Amendments

1) Laydown Area #2 will be available until 30 Sept 2017 to make room for follow-on contractor. COR will provide advance notice of timeframe to release Laydown Area #2.

2) Toe drain alternative decision will be made within 60 days of NTP. Further evaluation is underway to potentially remove one of the alternatives prior to bid opening.

4) Redesign of stability anchors: Updated requirements will likely include 15” diameter hole, Class I Protection, anchors will consist of 61 strands (maximum), anchors will not be re-stressable.

5) Cut 3 trees that provide potential bat habitat (15 Nov – 31 Mar), payment will be incidental to disposal area clearing.

6) Update with detailed information/data from recent cofferdam unwatering.

7) Options to be awarded no later than 31 May 2017.

8) Answers to Bidder questions.

Unwatered Cofferdam

Core Storage Building

Toe Drain Alternatives

Exploratory Drilling

Secant Wall

Rock Anchors

Rock Anchors

Rock Excavation - Base Contract

Rock Excavation – Options 1 & 2

Rock Excavation – Option 3

Rock Excavation – Option 4

Rock Excavation – Options 5-8

Questions

Site Visit Parking

File details come from the government source that posted it. Updated .