BEST VALUE IDIQ
CONSTRUCTION SERVICES
TASK ORDER CONTRACT
PRE-PROPOSAL CONFERENCE
July 14 & 17, 2017
Iowa National Guard
Introduction
Daniel Collins - Contract Specialist
Mark Thompson - Contracting Officer
WHAT IS A MULTIPLE AWARD
TASK ORDER CONTRACT???
“MATOC ”
COMPETITIVE
MULTIPLE AWARD
IDIQ CONTRACT
WHAT TYPE(S) OF MATOC WILL BE
AWARDED???
• GENERAL CONTRACTOR
WHAT WORK IS
INCLUDED IN A
MATOC???
• Construction, repair and alteration of various facilities
• Construction, repair and alteration of Electrical
Systems (ES)
• Construction, repair and alteration of Mechanical
Systems (e.g. HVAC systems and controls)
• Concrete and/or Asphalt Paving
• Demolition of facilities when required
Section 00100, Paragraph 1.2
CONTRACT DURATION,
LIMITS AND AMOUNTS
• Two-year base period and three one-year option periods
• Maximum value of each base contract will not exceed $10 million
• Minimum value for a single Task Order is $2,000.00
• Maximum value for a single Task Order is $5,000,000
• Minimum guaranteed order for each contract is one
(1) task order valued at $2,000
• Typical MATOC projects are under $1,000,000.00
Section 00100, paragraph 1.3
DO I HAVE A CHOICE OF
LOCATIONS?
YES!!!
• Des Moines International Airport
• Sioux City Gateway Airport
• Fort Dodge Air Station
• Other locations within the State of Iowa
Areas of consideration – Offerors must return page 13 of 70 Section 00010, paragraph 1
DO I HAVE A CHOICE OF
THE $$ RANGE OF PROJECT
I WILL COMPETE FOR?
YES!!!
• $2,000.00 - $250,000.00
• $2,000.00 - $500,000.00
• $2,000.00 - $1,000,000.00
• $2,000.00 - $2,000,000.00
• $2,000.00 - $3,000,000.00
• $2,000.00 - $5,000,000.00
Section 00010, paragraph 2
WHAT IF I DON’T HAVE THE CAPABILITY
NOW BUT WOULD LIKE TO BE
CONSIDERED FOR LARGER PROJECT IN
THE FUTURE, IS THERE AN OPTION?
YES!!!
• Base $2K – $500K, Opt #1 up to $1M, Opt #2 up to $2M, and Opt #3 up to $3M
• Base $2K – $1M, Opt #1 up to $2M, Opt #2 up to $3M, and Opt #3 up to $4M
• Base $2K – $2M, Opt #1 up to $3M, Opt #2 up to $4M, and Opt #3 up to $5M
• Increases in option years may be granted based on Satisfactory performance & bonding capability at the sole discretion of the Contracting Officer.
Section 00010, paragraph 2
What is a Task Order (T.O.)
“Task order” means an order for services placed against an established contract or with Government sources.
T.O. PROCEDURES
• Engineer provides a SOW to the KO.
• Contracting officer emails a notice of proposed task order project Request For Proposal (RFP) to all applicable MATOC contractors.
• Government conducts an onsite conference with all TOC Contractors.
• Government validates proposal due date with Contractors.
T.O. PROCEDURES
CONTINUED
• If necessary, the Government will make changes to SOW and the Contracting Office will issue an amendment.
• Contractor submits price or best value proposal by fax/E- Mail.
• KO makes awards upon receipt of funds.
RESPONSE TIME
NORMAL
• Two day (min.) response time for on-site conference from receipt of RFP
EMERGENCY
• 120 Minute response time from receipt of RFP
Technical Subfactor #1 and Attachment 5 , paragraph SC4
WHO MAY AWARD TASK
ORDERS???
FEDERAL CONTRACTING OFFICERS AT:
185TH ARW
132ND W
USPFO-P&C
DAVIS BACON WAGES
MOST CURRENT
CONSTRUCTION WAGE
DETERMINATION WILL BE
PROVIDED WITH EACH
PROJECT REQUEST FOR
PROPOSAL (RFP)
WHAT DOES A FAIR
OPPORTUNITY TO COMPETE
MEAN???
All eligible MATOC contractors, unless a task order is set-aside for a socio-economic group, within their awarded Areas of Consideration, will be provided a fair opportunity to compete for each project offered under this contract unless an exception applies (exceptions are listed in Attachment #5, paragraph 4.3.3.)
CAN I PROTEST A CONTRACTING
OFFICERS AWARD DECISION????
NO??
OMBUDSMAN -- DETERMINES
IF CONTRACTORS WERE
PROVIDED A FAIR
OPPORTUNITY TO COMPETE.
Reference Attachment #5, paragraph 6.5
CONTRACTORS MAY
PROTEST TO GAO BASED
ON :
• Order increases the scope, period, or maximum value of the contract
• Order issued above the maximum contract amounts $10 mil
Reference Attachment #5, paragraph 6.4
Solicitation, Plans & Specifications
• On the web:
– www.fbo.gov
– Solicitation
– Exhibits
– Plans & Specifications (Fed Biz Ops)
– Questions & Answers Document
– Pre-proposal presentation
– Amendments
• Check regularly and refresh http://www.fbo.gov/
Disclaimer
OFFERORS ARE STRONGLY
CAUTIONED TO
CAREFULLY READ THE
REQUIREMENTS OF THE
SOLICIATION AND
COMPLY ACCORDINGLY
WHAT DO I NEED TO
SUBMIT??
• VOLUME 1, PRICE/COST INFORMATION:
(Reference Section 00110, Paragraph 3.1 for detailed information)
– Introductory Page as outlined in section 00110, paragraph
3.1.2.
– Standard Form 1442, Signed with Amendments noted
– Section 00010 Areas of Consideration
– Section 000600 Representations and Certifications
– Completion of Electronic Representations and Certifications in
System for Award Management (SAM)
– Prices for BOTH seed projects regardless of Areas of
Consideration (Exhibit D-1 and D-2)
– Adequate financial resources (bonding)
WHAT IS A SEED PROJECT??
• Represents the type of project that will be awarded under this contract
– Exhibit D-1, Remodel Restrooms in Hangar, Building 261 at the Sioux
City Air Base
– Exhibit D-2, Renovate Building 270 for Contracting and MSG at the Des
Moines Air Base
• Measures accuracy of Contractors estimating system
• Seed Projects will be awarded to contractors within areas of consideration!!!!
All offerors, regardless of the areas of consideration on location and price, shall price the both seed projects for evaluation purposes. Failure to provide a price is considered non-compliant with the solicitation requirements and grounds for elimination from consideration/evaluation
• VOLUME 2, TECHNICAL INFORMATION-
(Reference Section 00110, Paragraph 3.2 for detailed information)
– Subfactor 1 – Experience & Capability (paragraph 3.2.4.)
– Subfactor 2 – Organization (paragraph 3.2.5.)
– Subfactor 3 – Specific Personnel (paragraph 3.2.6.)
• Includes Resumes for Project Manager, Site Superintendents, QC Manager, and Safety Manager
– Subfactor 4 – Quality Control (paragraph 3.2.7.)
– Subfactor 5 – Scheduling Methodology (paragraph 3.2.8.)
• Gantt chart for both Exhibit D projects
– Subfactor 6 – Experience with building to United States Green Building
Council (USGBC) LEED® standards (paragraph 3.2.9.)
• VOLUME 2, PAST PERFORMANCE INFORMATION:
(Reference Section 00110, Paragraph 3.3. for detailed information)
– Exhibit A Part 1- Prepare a minimum of three (3) but not more than five
(5) “Performance Relevancy Questionnaires” for relevant contracts substantially completed (70%) or completed within the last five years (completed after July 2012)
– Exhibit A Part 2- Complete one time
– Send out questionnaires, Exhibit C, to your references for the Exhibit A projects (Responses are sent directly to the USPFO from the reference):
• Do this early and follow-up with references and USPFO to confirm receipt –
Exhibit C can be submitted to the USPFO via mail, fax or e-mail
• DUE 8 August 2017 by 1:00 P.M.
WHEN IS MY SUBMITTAL
DUE??
• All volumes are due at 1:00 P.M. CST on 8 August 2017
– Proposals must be signed by an officer of your company
– No facsimile or electronic offers will be accepted
– Reference Questionnaires are also due by this time and date!
QUESTIONS CONCERNING
MATOC
• Questions must be submitted in writing via Email to:
daniel.w.collins.mil@mail.mil and mark.l.thompson10.mil@mail.mil
• Questions must be received 5 days prior to closing
• Submit questions NLT 3 August 2017
• Submit questions to Contracting Officer or Contract
Specialists only. Do not call other Government Personnel.
• Questions and answers will be posted as an amendment to the
FedBizOps website only.
mailto:daniel.w.collins.mil@mail.mil mailto:mark.l.thompson10.mil@mail.mil
IMPORTANT REMINDER
THE GOVERNMENT INTENDS
TO AWARD WITHOUT
DISCUSSIONS AND THERE
MAY NOT BE A CHANCE FOR
DISCUSSIONS, CORRECTIONS,
OR REVISED PROPOSALS!
•QUALITY
“QUALITY IS NEVER AN ACCIDENT; IT
IS ALWAYS THE RESULT OF HIGH
INTENTION, SINCERE EFFORT,
INTELLIGENT DIRECTION AND
SKILLFUL EXECUTION; IT
REPRESENTS THE WISE CHOICE OF
MANY ALTERNATIVES” RESULT IS
“BEST VALUE”
TECHNICAL PROPOSAL
WILL BE EVALUATED ON:
Subfactor 1 - Experience and Capability Subfactor 2 - Organization Subfactor 3 - Specific Personnel Subfactor 4 - Quality Control Subfactor 5 - Scheduling Methodology Subfactor 6 - LEED (Applies only to offerors requesting projects > $1M)
Subfactors 1-6 will be rated in descending order of importance with Subfactor 1, Experience and Capability being the most important.
PAST PERFORMANCE PROPOSAL
WILL BE EVALUATED ON:
Subfactor 1 - Quality Control Subfactor 2 - Timely Performance Subfactor 3 - Compliance with Safety Standards Subfactor 4 - Management Effectiveness Subfactor 5 - Compliance with Federal laws and regulations Subfactor 6 - Compliance with utilization of small business concerns requirements (applicable to all offerors); including small business concerns. Reference FAR 19.702
All six (6) subfactors will be rated equally. An overall evaluation for Past Performance will be at the factor level.
EVALUATION FACTORS
Technical factor is somewhat more important than Present/ Past Performance and when combined, however, the non-cost factors are approximately equal to the Price Factor
BEST VALUE AWARD
DECISION
Proposals that are determined to be the most beneficial to the Government, with appropriate consideration given to the three (3) evaluation factors: Technical, Price, and Past Performance
CIRAS-PTAC
Pam Russenberger, Program Director CIRAS – Procurement Assistance 2829 Westown Parkway, Suite 220
West Des Moines, Iowa 50021 Tel. 515-509-1814 Fax 515-598-7781
E-mail – plrussen@iastate.edu Web Address – www.ciras.iastate.edu mailto:plrussen@iastate.edu
QUESTIONS ???
| 2017 MATOC Preproposal Conference Slides |
| BEST VALUE IDIQ�CONSTRUCTION SERVICES�TASK ORDER CONTRACT |
| Introduction |
| WHAT IS A MULTIPLE AWARD TASK ORDER CONTRACT???�“MATOC ” |
| WHAT TYPE(S) OF MATOC WILL BE AWARDED??? |
| WHAT WORK IS INCLUDED IN A MATOC??? |
| CONTRACT DURATION, LIMITS AND AMOUNTS |
| DO I HAVE A CHOICE OF LOCATIONS? |
| DO I HAVE A CHOICE OF THE $$ RANGE OF PROJECT I WILL COMPETE FOR? |
| WHAT IF I DON’T HAVE THE CAPABILITY NOW BUT WOULD LIKE TO BE CONSIDERED FOR LARGER PROJECT IN THE FUTURE, IS THERE AN OPTION? |
| What is a Task Order (T.O.) |
| T.O. PROCEDURES |
| T.O. PROCEDURES�CONTINUED |
| RESPONSE TIME |
| WHO MAY AWARD TASK ORDERS??? |
| DAVIS BACON WAGES |
| WHAT DOES A FAIR OPPORTUNITY TO COMPETE MEAN??? |
| CAN I PROTEST A CONTRACTING OFFICERS AWARD DECISION????��NO?? |
| CONTRACTORS MAY PROTEST TO GAO BASED ON : |
| Solicitation, Plans & Specifications |
| Disclaimer |
| WHAT DO I NEED TO SUBMIT?? |
| WHAT IS A SEED PROJECT?? |
| WHAT DO I NEED TO SUBMIT?? |
| WHAT DO I NEED TO SUBMIT?? |
| WHEN IS MY SUBMITTAL DUE?? |
| QUESTIONS CONCERNING MATOC |
| IMPORTANT REMINDER |
| QUALITY |
| TECHNICAL PROPOSAL WILL BE EVALUATED ON: |
| PAST PERFORMANCE PROPOSAL WILL BE EVALUATED ON: |
| EVALUATION FACTORS |
| BEST VALUE AWARD DECISION |
| CIRAS-PTAC |
| QUESTIONS ??? |