W912LC-19-B-5000_Amendment_3.pdf

PDF 376 KB Posted

Attached to
ASE Maintenance and Storage Facility Federal contract opportunity
Solicitation number
W912LC-19-B-5000
Issued by
Department of the Army Colorado Army National Guard

View the file

Other files for this federal contract opportunity

Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Project Title: ASE MAINTENANCE & STORAGE FACILITY, BUILDING 808 Project Number: CRWU 06-9125

Amendment 3 is issued as follow s:

1) Revise specif ication sections: 01000, 01010, 01230, 024116, 321215 as described on block 14 continuation page.

2) Revise/Replace draw ings: C104, A251, A301, A411, A412, A502, A701, E602 as described on block 14 continuation page.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 08-May-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912LC19B5000

X 9B. DATED (SEE ITEM 11)

12-Apr-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

08-May-2019

CODE

USPFO-PNC-CO

660 S. ASPEN ST., MS #66,

BLDG 1005

BUCKLEY AIR FORCE BASE

AURORA CO 80011-9551

W912LC 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912LC19B5000

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 3

CHANGES TO TECHNICAL SPECIFICATIONS:

1. Specification Section 01000, paragraph 1.28 B.: Delete paragraph 1.28 B. The Contractor shall not be required to provide temporary office space for Government use.

2. Specification Section 01010, paragraph 1.2 A.: Change paragraph to read “The Contractor shall achieve Substantial Completion between 270 days and 335 days, depending on options selected, from the date of receiving Notice to Proceed (NTP) unless approved otherwise by the Contracting Officer.”

3. Specification Section 01010, paragraph 1.3 B. 6.: Options 6, change Conduit” to “Cable”.

4. Specification Section 01230, paragraph 3.1 F.: Options 6, change “Conduit” to “Cable”.

5. Specification Section 024116, paragraph 3.7 A.: Add the following sentences to paragraph 3.7 A.: “Clean fill dirt (Borrow Soil) is available on Buckley AFB at the South Fill site for the Contractors use. Soil may be used for the purpose of backfilling the below grade areas during the demolition of Building 1606.

Coordinate with the COR.”

6. Specification Section 321215, Hot-Mix Asphalt Airfield Paving: Delete Specification Section 321215.

There is no longer a requirement to install hot-mix asphalt airfield pavement under this project.

CHANGES TO CONTRACT DRAWINGS:

1. Drawing C104: Replace drawing C104 with revised drawing dated 7 May 2019. Water fire line and domestic water tap and connections at the flightline have changed.

2. Drawing A251, Detail 1: Delete portion of note on the top left part of the detail that reads “W/HEAT TRACE”. No heat trace is required on the roof or gutters of this building.

3. Drawing A301: Replace drawing A301 with revised drawing (pdf file dated R20190429). This is to clarify Bid Option 11 windows.

4. Drawing A411, Detail 4: Change “ABI #11” to “Bid Option #11” (window).

5. Drawing A412, Detail 4: Change “ABI #11” to “Bid Option #11” (window).

6. Drawing A502: Replace drawing A502 with revised drawing (pdf file dated R20190429). This is to correct windows incorrectly identified as base bid versus bid option 11 in details 4 and 6.

7. Drawing A701: Replace drawing A701 with revised drawing dated 8 May 2019. Corrected Door and Frame Schedule. Door number 200B and 201C are in Option #9. “ABI #9” for Door 201B shall be deleted from the remarks.

8. Drawing E602: Add missing breaker size to circuits 37, 39, 41 (MJ-1B/C Bomb Lift) and 43, 45, 47 (MJ-1B/C Bomb Lift) in electrical panel LP2. The panel schedule needs to indicate that the breaker size shall be a 3 pole, 20 amp breaker for these circuits.

(End of Summary of Changes)