Solicitation Amendment 1 W912L9-20-B-0005.pdf
PDF 155 KB Posted
- Attached to
- Barracks Restoration Project #12 - Bid Abstract Added Federal contract opportunity
- Solicitation number
- W912L9-20-B-0005
- Issued by
- Department of the Army National Guard
About this file
This solicitation notice is for a firm fixed-price construction contract to renovate two barracks buildings at Camp Atterbury in Edinburgh, Indiana. The contract value is between $1 million and $5 million. Work includes interior and exterior renovations, installing a geo-thermal well system, mechanical and electrical upgrades, fire suppression, and site work. The North American Industry Classification System code is 236220 and the small business size standard is $39.5 million. The solicitation is 100% set aside for small businesses. The contractor cannot subcontract more than 85% of the work to non-similarly situated entities. The pre-bid conference is at Camp Atterbury and the bid opening is September 9, 2020. Interested contractors must register in the System for Award Management to access solicitation documents on beta.SAM.gov. The solicitation is issued by the USPFO for Indiana on behalf of the Department of the Army National Guard.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| BID OPENING ABSTRACT.pdf | ||
| Questions and Answers UPDATED 9-2-2020.pdf | ||
| Solicitation Amendment 3 W912L920B00050003.pdf | ||
| Questions and Answers.pdf | ||
| Solicitation Amendment 2 W912L920B00050002.pdf | ||
| CAMP ATTERBURY BARRACKS AND BOQ RENOVATION -BP12 - 2020.0820.pdf | ||
| Sign In Sheet Site Visit.pdf | ||
| Phase 2 Addendum No 01 BP12.pdf | ||
| 20200819 SITE VISIT PREPROPOSAL CONFERENCE MEETING MINUTES COMBINED.pdf | ||
| 102113.19 FL - Plastic Toilet Compartments.pdf | ||
| eCMRAMemo.pdf | ||
| 003_Phase 2_Project Manual Vol 1of 2_19May20.pdf | ||
| DRAWINGS BP12 20200519.pdf | ||
| W912L9-20-B-0005 PROJECT 12.pdf | ||
| Barracks Statement of Work 05-21-2020 BP-12.pdf | ||
| 007_APNDX-B_CD-REPORT_Pkg 12_216-217.pdf | ||
| 004_Phase 2_Project Manual Vol 2 of 2_19May20.pdf | ||
| AF-66 Submittals_BP12.pdf |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
0011466882
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to 1) post site visit/pre-proposal conference minutes w ith questions and answ ers to FBO; 2) post list of attendees to site visit/pre-proposal conference to FBO; 3) replace original draw ings to incorporate bathroom fixtures; 4 ;) correct liquidated damages charges per day. Corrected charges are $606.95 per day. 5) Replace AF66 and Statement of Work w ith correctly named files for posting on FBO.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 24-Aug-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912L920B0005
X 9B. DATED (SEE ITEM 11)
19-Aug-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
24-Aug-2020
CODE
USPFO FOR INDIANA-CAMP ATTERBURY
BLDG 244 EGGLESTON RD
EDINBURGH IN 46124
W912L9 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912L920B0005
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00700 - CONTRACT CLAUSES
The following have been modified:
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $606.95 for each calendar day of delay until the work is completed or accepted. There is also a one-time charge of $153.00 for legal services that will apply.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.