TrainingSupportRFIs.docx
DOCX document 14 KB Posted
- Solicitation number
- W912L8-16-R-0005
View the file
Other files
| File | Type | Posted |
|---|---|---|
| TrainingSupportRFIs.docx | DOCX document | |
| TrainingSupportRFIs.docx | DOCX document | |
| TrainingSupportRFIs.docx | DOCX document | |
| Bid_Schedule.xlsx | XLSX spreadsheet | |
| W912L8-16-R-0005-0002_Conformed.pdf | ||
| TrainingSupportRFIs.docx | DOCX document | |
| TrainingSupportRFIs.docx | DOCX document | |
| TrainingSupportRFIs.docx | DOCX document | |
| W912L8-16-R-0005-0001.pdf | ||
| TrainingSupportRFIs.docx | DOCX document | |
| Bid_Schedule.xlsx | XLSX spreadsheet | |
| W912L8-16-R-0005.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912L8-16-R-0005 Training Support Services West Virginia Army National Guard
Request for Proposal (Questions) and Answers
| RFI# |
| Date |
| Question |
| Answer |
| 1 |
| 2016/09/01 |
| Can you clarify the correct NAICS for this opportunity? FBO states 541990, however the solicitation SF1449 states 541618. |
| The solicitation was just updated to NAICS 541990. |
| 2 |
| 2016/09/01 |
| Can you also tell me if there is an incumbent or if this is a new requirement? |
| There is no incumbent. The requirement has been performed in the past with in-house manning. |
| 3 |
| 2016/09/02 |
| Is there a reason the due date moved up from Sep 16th to Sep 14th? |
We would like to ensure we have time to put together a solid proposal response and would like to request that date be extended to Sep 26th.
Is that possible?
The Government intends to award this contract prior to September 30, 2016. Therefore we need time to evaluate the offers and finish the acquisition process to successfully make the award by our target date. In order to meet our target, we cannot extend the due date.
| 4 |
| 2016/09/05 |
| Can you clarify number of days per exercise? |
| Please see the bid schedule. The bottom half of the schedule shows the estimated number of days per event in column E. |
| 5 |
| 2016/09/05 |
| Is there an estimate for the number of days for the CERF exercise? |
| Please see the bid schedule. The bottom half of the schedule shows the estimated number of days per event in column E. |
| 6 |
| 2016/09/05 |
| For CLIN 1001, Lead Planner / OM, is this a full time liaison position or strictly for exercise duration? |
| Please see the bid schedule. This is a full time position at Camp Dawson for the annual period. |
The Government anticipates awarding the first Task Order for this position immediately after contract award.
| 7 |
| 2016/09/05 |
| Should we include price of NACI in our bid? |
| Yes. Include the price for the NACIs in the loaded rates for the positions. |
| 8 |
| 2016/09/05 |
| Will billeting and meals be provided at Fort Dawson? |
| 9 |
| 2016/09/05 |
| Can you clarify CLIN 1002 |
“Role Players:10-6 events, 2 weeks each.”
Please see the bottom half of the bid schedule. The Government estimates 10 Role Players for 6 Events at 14 days each for each event.