UPDATED WITH PWS WITH PLYWOOD OR PLASTIC FLOORING

View the file

Other files

File Type Posted
XCTC_Performance_Work_Statement--03-30-2017.docx DOCX document
Military_Training_Excavation_SOP_4_NOV_15.pdf PDF
Copy_of_LSA_REQUIREMENTS_LATRINES_POTABLE_WATER_MEALS_30_MARCH_(002).xlsx XLSX spreadsheet
Combined_Synopsis_Solicitation_XCTC_03-30-2017.docx DOCX document
W912L7-17-R-0005_Questions.docx DOCX document
XCTC_Site_Attendance_Roster.pdf PDF
W912L7-17-R-0005_Additional_Questions.docx DOCX document
XCTC_Performance_Work_Statement--03-28-2017.docx DOCX document
LSA_REQUIREMENTS_LATRINES_POTABLE_WATER_MEALS_28_MARCH.xlsx XLSX spreadsheet
G8_XCTC_WHITE_CELL_Services_Timeline.xlsx XLSX spreadsheet
W912L7-17-R-0005_Additional_Questions.docx DOCX document
W912L7-17-R-0005_Questions.docx DOCX document
278th_FIELD_REQUIREMENTS-UPDATED_03-28-2017.xlsx XLSX spreadsheet
Combined_Synopsis_Solicitation_XCTC_03-28-2017.docx DOCX document
XCTC_Performance_Work_Statement--03-03-2017.docx DOCX document
Combined_Synopsis_Solicitation_XCTC_03-09-2017.docx DOCX document
278th_FIELD_REQUIREMENTS-UPDATED_03-09-2017.xlsx XLSX spreadsheet
LSA_REQUIREMENTS_LATRINES_POTABLE_WATER_MEALS_08_MARCH.xlsx XLSX spreadsheet
XCTC_Performance_Work_Statement--02-28-2017.docx DOCX document
278th_FIELD_REQUIREMENTS-UPDATED.xlsx XLSX spreadsheet
Combined_Synopsis_Solicitation_XCTC_02-28-2017.docx DOCX document
LSA_REQUIREMENTS_LATRINES_POTABLE_WATER_MEALS_22_FEB.xlsx XLSX spreadsheet
LSA_Space.PNG PNG image
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT (PWS)

FOR

Life Support Area (LSA) and Field Support Services for the eXportable Combat Training Capability (XCTC) of the Tennessee Army National Guard (TNARNG) 278th Armored Cavalry Regiment (ACR) and the 230th Sustainment Brigade (SBDE)

1.0 General:

1.1 Scope: The contractor shall provide all equipment, material, labor, supervision, supplies, and items necessary in support of the 278th ACR XCTC Mission. The specific requirements are outlined below. Services, as defined in this PWS

1.2 Background: The 278th ACR and the 230th SBDE have been tasked with a XCTC Mission located at Ft. Hood, TX. The 230th SBDE will be operating the LSA in support of the 278th ACR training mission that will take place at Ft. Hood, TX. This mission is in preparation of an upcoming mission at the National Training Center (NTC) located at Ft. Irwin, CA in 2018.

1.3 Period of Performance (PoP): The Period of Performance shall be May 8, 2017-July 2, 2017.

1.4 General Information:

1.4.1 Quality Control (QC): The contractor shall develop and maintain an effective QC Plan (QCP) to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s QCP is the means by which it assures itself that its work complies with the requirements of the contract. As a minimum, the contractor shall develop QC procedures that address the areas identified in Technical Exhibit 1, Performance Requirements Summary. After acceptance of the QCP, the contractor shall obtain the Contracting Officer’s (KO) acceptance in writing of any proposed changes to its QCP.

1.4.2 Quality Assurance (QA): The Government will evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s) (defect rate(s)).

1.4.3 Recognized Holidays: The following are recognized US holidays. The contractor shall perform services on these days:

1.4.3.1 New Year’s Day: January 1st

1.4.3.2 Martin Luther King, Jr.’s Birthday

1.4.3.3 President’s Day

1.4.3.4 Memorial Day

1.4.3.5 Independence Day: July 4th

1.4.3.6 Labor Day

1.4.3.7 Columbus Day

1.4.3.8 Veteran’s Day: November 11th

1.4.3.9 Thanksgiving Day

1.4.3.10 Christmas Day

1.4.4 Place and Performance of Services: The contractor is required to provide services between the hours of 5 AM- 7 PM Sunday-Saturday as well as being able to respond with two (2) hours if needed at anytime, or when the Government facility/installation is closed due to local or national emergencies, administrative closings, or similar Government-directed facility/installation closings. Performance shall be at Designated LSA area located on South Ft. Hood, TX, as well as designated locations for field exercise outside the LSA. The contractor shall at all times maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS when the Government facility/installation is not closed for the above reasons. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential. Telecommuting is not authorized.

1.4.4.1 Unscheduled gate closures by the Security Police may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented. Contractors are not compensated for unexpected closures or delays. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.

1.4.4.2 The contractor’s employees shall become familiar with and obey the regulations of the installation; including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall carry proper identification with them at all times. The contractor shall ensure compliance with all regulations and orders of the installation which may affect performance.

1.4.5 Security Requirements. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

1.4.5.1 COMSEC/IT Security. All communications with DOD organizations are subject to communications security (COMSEC) review. All telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. DOD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DOD organizations. Therefore, the contractor is advised that any time contractor place or receive a call they are subject to COMSEC procedures. The contractor shall ensure wide and frequent dissemination of the above information to all employees dealing with DOD information. The contractor shall abide by all Government regulations concerning the authorized use of the Government's computer network, including the restriction against using the network to recruit Government personnel or advertise job openings.

1.4.5.2 Protection of Personally Identifiable Information (PII). The contractor shall protect all Personally Identifiable Information (PII) encountered in the performance of services in accordance with DFARS 224.103 and DoD 5400.11, Department of Defense Privacy Program, and DoD 5400.11-R. If a PII breach results from the contractor’s violation of the aforementioned policies, the contractor shall bear all notification costs, call-center support costs, and credit monitoring service costs for all individuals who’s PII has been compromised.

1.4.5.3 For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies by complying with Ft. Hood access policies and procedures which include a background check, valid driver’s license or ID, and coordination with the Ft. Hood Visitor Center at (254) 287-9909, or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

1.4.5.4 AT Level 1 Awareness Training (AT): All contractor employees requiring access to Army Installations, facilities, and controlled access areas shall complete Level 1 AT within ten (10) calendar days after contract start date and within 10 calendar days of new employees commencing performance. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee, to the COR, or to the KO if a COR is not assigned, within five (5) calendar days after completion of training. Level 1 AT is available at https://atlevel1.dtic.mil/at/.

1.4.5.5 iWATCH Training. The contractor with an area of performance within an Army-controlled installation, facilities or area shall brief all employees on the local iWATCH program. This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR or the KO. This training shall be completed within 10 calendar days of contract award and within 10 calendar days of new employees commencing performance. The contractor shall report completion for each affected contractor employee and subcontractor employee, to the COR, or to the KO if a COR is not assigned, within five (5) calendar days after completion of training.

1.4.5.6 OPSEC Training. In accordance with AR 530-1, Operations Security, new contractor employees shall complete Level I OPSEC training within ten (10) calendar days of their reporting for duty and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee, to the COR, or to the KO if a COR is not assigned, within five (5) calendar days after completion of training. Level 1 OPSEC training is available at http://cdsetrain.dtic.mil/opsec/.

1.4.5.7 OPSEC SOP/Plan. The contractor shall develop an OPSEC Standing Operating Procedure (SOP)/Plan and provide it to the COR or the Contracting Officer within ten (10) calendar days of contract award), to be reviewed and approved by the responsible Government OPSEC officer, per AR 530-1, Operations Security. This SOP/Plan shall include the government's critical information, why it needs to be protected, where it is located, who is responsible for it, and how to protect it. In addition, the contractor shall identify an individual who will be an OPSEC Coordinator. The contractor shall ensure this individual becomes OPSEC Level II certified in accordance with AR 530-1.

1.4.6 Physical Security. The contractor shall safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured.

1.4.6.1.1 In the event keys, other than master keys, are lost or duplicated the contractor shall, upon direction by the KO, re-key or replace the affected lock or locks; however, the Government, at its option, may replace the affected lock or locks or perform re-keying. When the replacement of locks or re-keying is performed by the Government, the total cost of re-keying or the replacement of the lock or locks shall be deducted from the monthly payment due the contractor. In the event a master key is lost or duplicated, all locks and keys for that system shall be replaced by the Government and the total cost deducted from the monthly payment due the contractor.

1.4.7 Contract Manager (CM): The contactor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO. The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the COR, (or the KO if a COR is not assigned), to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.

1.4.8 Identification of Contractor Employees: All contractor personnel attending meetings, answering Government telephones and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. All contract employees will wear a badge identifying themselves and what company they are with. The contractor shall ensure that all documents or reports produced by contractor personnel are suitably marked as contractor products or that contractor participation is appropriately disclosed. The contractor’s status as a “contractor” shall be predominantly displayed in all correspondence types (to include signature blocks on e-mail) and dealings with Government or non-Government entities/ Contractor personnel shall wear identification badges distinguishing themselves as such. The badges shall have the company name, employee name and the word “contractor” displayed. The contractor shall retrieve all identification media (including vehicle passes) from their employees who depart employment for any reason. All identification media (i.e., badges and vehicles passes) shall be returned to the KO within 14 days of an employee’s departure.

1.4.9 Combating Trafficking in Persons: The United States Government has adopted a zero tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in severe forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. Such actions may include, but are not limited to, removal from the contract, reduction in benefits, or termination of employment. The contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at FAR 22.17.2.0 Definitions and Acronyms:

2.0 DEFINITIONS

2.1.1 CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.

2.1.2 CONTRACTING OFFICER (KO). A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.

2.1.3 CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the U.S. Government designated by the KO to monitor contractor performance. Such appointment will be in writing and will state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

2.1.4 DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.

2.1.5 DELIVERABLE. Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.

2.1.6 KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.7 PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.

2.1.8 QUALITY ASSURANCE. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.9 QUALITY ASSURANCE SURVEILLANCE PLAN (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.10 QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

2.1.11 SUBCONTRACTOR. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

2.1.12 WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.

2.1.13 WORK WEEK. Sunday through Saturday, unless specified otherwise.

2.2 ACRONYMS:

AFARS Army Federal Acquisition Regulation Supplement AR Army Regulation AT/OPSEC Antiterrorism/Operational Security CFR Code of Federal Regulations CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer Representative COTS Commercial-Off-the-Shelf DA Department of the Army DD250 Department of Defense Form 250 (Receiving Report) DD254 Department of Defense Contract Security Requirement List DFARS Defense Federal Acquisition Regulation Supplement DOD Department of Defense FAR Federal Acquisition Regulation GFP/M/E/S Government Furnished Property/Material/Equipment/Services IA Information Assurance IS Information System(s) KO Contracting Officer OCI Organizational Conflict of Interest ODC Other Direct Costs PII Personally Identifiable Information PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program TE Technical Exhibit

3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S): The Government will provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract: None provided.

4.0 Contractor Furnished Property, Materials, and Equipment (CFP/M/E):

4.1 General: Except for those items specifically stated to be Government-Furnished in Paragraph 3.0, the contractor shall furnish everything required to perform these services as indicated in Paragraph 1.1.

5.0 Requirements: The contractor shall:

5.1 Grey Water Removal (LSA) Contractor shall provide removal of grey water collection tanks in life support area for contracted facilities and Army Organic facilities. Contractor shall dispose of gray water off site. Grey water shall be collected daily. Grey water removal will be based off the fresh water coming in. Please see potable water for those estimates. Contractor will not be required to provide any grey water blivets for any Government equipment. The 542nd Force Providers will be bringing five (5), 3,000 gallon grey water blivets with 2” couplings.

Period of Performance will be: 17 May- 2 July 2017.

5.1.1 Grey Water Removal (Field) Contractor shall provide removal of grey water collection tanks in life support area for contracted facilities and Army Organic facilities. Contractor shall provide capability to remove up to 7,000-10,000 gallons of grey water per day. Contractor shall provide off site removal of gray water. Grey water shall be collected daily and shall dispose of offsite. Contractor shall establish several different sites for gray water collection. Spreadsheet providing locations and dates needed will be attached titled 278th ACR Field Requirements is attached.

Period of Performance will be: 6-20 June 2017

5.2 Portable Sink Units (LSA) - Contractor shall provide portable sink units with a ratio of 1 sink per 25 soldiers. Sink units shall provide hot and cold water. Contractor shall provide enough sink units to support the LSA population. Contractor shall maintain sinks to a clean and sanitary condition daily per the period of performance below. Contractor shall provide propane and grey water removal on site. Contractor must provide hand soap and paper towels as part of service. Must be able to support up to 4,600 soldiers at any time.

Electrical cords used in sink trailers shall have water proof boxes covering the inlet and outlet plugs of the extension cord IAW DA PAM 385-26, chapters 2-5; 5-5; 5- 6; and 6-1.

Contractor shall provide backflow and check valves which shall have current inspection tags. Contractor shall be responsible for plumbing/wiring all connections to existing infrastructure and restoration to their original state upon completion of the contract.

Period of Performance will be: 30 May thru 07 June 2017; 18 June thru 25 June 2017

5.3 Trash Removal and Dumpsters (LSA) Fort Hood will not be providing dumpsters or trash removal, therefore, responsive contractors will be required to provide for dumpsters and trash removal in support of and from LSA site.

Period of Performance will be: 17 May Thru 02 July 2017. Number of dumpsters will be 3 each dumped daily. Size of dumpster will need to be 8 Yards.

5.3.1 Trash Removal and Dumpsters (Field) Fort Hood will not be providing dumpsters or trash removal, therefore, responsive contractors will be required to provide for dumpsters and trash removal in support of and from various RSA sites. Contractor shall be expected to empty dumpster(s) daily. Spreadsheet providing locations and dates needed will be attached titled 278th ACR Field Requirements. A 20 yard, roll-on, roll-off type. Measurements would be 7’9” high by 8’ wide, by 22’ long

Period of Performance will be: 6-10 June 2017 (Location 1), 10-17 June 2017 (Location 2)

5.4 Hand Sanitation Stations (LSA) The contractor shall provide and service hand sanitation stations. Hand sanitation stations will require service to refill hand antiseptics when servicing chemical latrines. Placement shall be at a minimum of 1 station per 6 chemical toilets serviced by this contract.

Period of Performance will be: 11 May 2017 through 02 July 2017.

Headcount will be per the attached spreadsheet titled LSA requirements.

5.5 Hand Washing Stations (LSA) The contractor shall provide and service hand washing stations. Hand washing stations shall be cleaned and serviced daily. Service will include paper towels, soap, and refill/refresh potable water and removal of grey water. Placement shall be outside and inside the entrance of the feeding tents. 15 Handwashing stations required. Hand wash stations shall be in accordance to OSHA 29 CFR 1910.142(f) (1) (i).

Period of Performance is 30 May 2017- 2 July 2017

5.5.1 Hand Washing Stations (Field) The contractor shall provide and service hand washing stations. Hand washing stations shall be cleaned and serviced every other day. Paper towels, soap, and grey water removal need to be part of the service included. Placement shall be shall be in accordance with spreadsheet titled 278th Field requirements. Hand wash stations shall be in accordance with OSHA 29 CFR 1910.142(f) (1) (i).

Spreadsheet named 278th ACR Requirements providing locations and dates needed will be attached. Locations will be at each grey water removal point besides SLCR unit locations.

5.6 Power Generation (LSA) Contractor shall provide power generation. Power requirements are for all sleeping tents, dining facility, and all other facilities that require power. Contractor shall deliver, setup, maintain (to include maintenance and wiring), and remove all power generation equipment once contract is complete. Government will either provide contractor with fuel card to access Ft. Hood fuel point, or government will provide escort to the Ft. Hood fuel point to get fuel. The fuel will be at no cost to the contractor. The service requested will be to refuel generators on the LSA. (Generators will need to be diesel, F24 Capability. F24 same as JP8 but additives added to prevent freezing in cooler temperatures).

Contractor shall be available to respond to service calls for maintenance within two (2) hours once notified. Contractor shall place generators at a minimum of 30 – 50 feet away from all tents.

Contractor shall establish power generation by 17 May 2017 and be operational through 02 July 2017.

Emplacement of any grounding rods, anchors, or other accessories into the ground on Fort Hood requires an approved dig permit and confirmation of non-interference with existing underground utilities. POC for dig permits at Ft. Hood will be provided at contract award. Dig permits take approximately 14 business days to obtain.

5.7 Setup and Breakdown (LSA) Contractor shall be responsible for the erection, maintenance, and clearance of all facilities, to include wiring and hookup. Contractor shall be responsible for removal of all debris, trash, and materials from the site. Upon completion of the exercise, contractor shall be responsible for the return of sites to their original state. Set up must be completed between completed with schedule of spreadsheet for dates of services that is attached to solicitation. Breakdown should be completed within 10 days after period of performance of contract is complete.

5.7.1 Setup and Breakdown (Field) Contractor shall be responsible for the erection, maintenance, and clearance of all facilities, to include wiring and hookup. Contractor shall be responsible for removal of all debris, trash, and materials from the site. Upon completion of the exercise, contractor shall be responsible for the return of sites to their original state. Please see attached spreadsheet titled 278th ACR Field Requirements for start dates.

5.8 Portable Chemical Latrines (LSA) The contractor shall service and provide at a minimum one (1) chemical latrines per 25 Soldiers based off of provided schedule to support LSA population. ALL chemical Latrines shall be cleaned and serviced daily. Toilet paper needs to be included as part of the service. Government shall provide guidance for placement following the completion of the site survey at Fort Hood, TX. Placement shall be coordinated with the COR. IAW FM 21-10 (Field Hygiene and Sanitation) we will need the Chemical Latrines to be at least 300 feet from Dining Facility.

Contractor shall have chemical latrines available for use on 11 May 2017 and be operational through 02 July 2017.

5.8.1 Portable Chemical Latrines (Field) The contractor shall provide one (1) chemical latrine per 25 soldiers and service based off provided spreadsheet throughout training area populations throughout Fort Hood, TX. ALL chemical Latrines shall be cleaned and serviced every other day. Toilet paper needs to be include as part of service. Government shall provide guidance for placement following the completion of the site survey at Fort Hood, TX. Placement shall be coordinated with the COR.

Contractor shall have chemical latrines available for use at various locations on various dates. Spreadsheet titled 278th ACR Field Requirements providing locations and dates needed are attached.

5.9 Reefer (Freezer & Refrigeration)(LSA) Contractor shall provide two (2) 20-foot reefer vans (one (1) freezer & one (1) Refrigeration) to include power generation if not self-sustaining. Contractor shall provide their own fuel and fueling operations. Contractor shall deliver, setup, maintain (to include maintenance and wiring), and remove all reefer equipment. Contractor shall be available to respond to service calls for maintenance within two (2) hours notice. These reefers will not be moved once placed, therefore do not have to be drivable or on a chassis.

Contractor shall place vans at a minimum of 30 – 50 feet away from all tents.

Contractor shall establish placement and operations by 11 May 2017 and be operational through 02 July 2017.

Emplacement of any grounding rods, anchors, or other accessories into the ground on Fort Hood requires an approved dig permit and confirmation of non-interference with existing underground utilities. POC for dig permits will be provided at contract award. Dig permits take approximately 14 business days to obtain.

5.9.1 Freezer (Field) Contractor shall provide eight (8) 20-foot freezer vans to include power generation if not self-sustaining. Refueling of Freezer vans will be provided by the government. Contractor shall deliver, setup, maintain (to include maintenance and wiring), and remove all freezer equipment. Contractor shall be available to respond to service calls for maintenance within two (2) hours notice.. Each 20-foot Freezer van must have driving capability for the 278th to move out to the field. Freezer vans need to be staged at LSA ready for 278th to jump to field.

Contractor shall place vans at a minimum of 30 – 50 feet away from all tents.

Contractor shall establish placement and operations by 2 June 2017 and be operational through 30 June 2017.

Emplacement of any grounding rods, anchors, or other accessories into the ground on Fort Hood requires an approved dig permit and confirmation of non-interference with existing underground utilities. POC for dig permits will be provided at contract award. Dig permits take approximately 14 business days to obtain.

5.10 Potable Water Supply (LSA) Contractor shall provide supply of potable water in life support area. Potable water shall be refreshed daily in coordination with LSA. Required to be able to support eight (8) gallons of potable water per service member per day as provided in attached spreadsheet titled LSA Requirements, LATRINES, SINKS, MEALS. NOT TO EXCEED 30,000 gallons a day. Potable water on Ft. Hood is provided to the contractor at no charge at their water point. Must obtain access code from Range Control to access the water point. Ft. Hood water points are located: FT Hood has 4 x Bulk Water Points. One is located on North Fort Hood on Park Street between 20th and 21st Street at Building 56560 (Grid PV23807090). A second Bulk Water Point is located on Turkey Run west of Clear Creek Rd in Building 44017 (Grid PV13404780). The third and fourth Bulk Water Points are located at Range Control on Black Gap Road at Buildings 56008 and 56099 (Grid PV21604685). Pins are required for access to the Bulk Water Points. Pins can be acquired by Ft. Hood Range Control. POC for Range Control will be provided at award.

Period of Performance will be: 17 May Thru 02 July 2017

5.10.1 Potable Water Supply (Field) Contractor shall provide supply of potable water in the field in support of the SLCR unit. Spreadsheet titled 278th Requirements has exact locations of SLCR Unit. Potable Water will be provided by government located at the Ft. Hood Water points located at: T Hood has 4 x Bulk Water Points. One is located on North Fort Hood on Park Street between 20th and 21st Street at Building 56560 (Grid PV23807090). A second Bulk Water Point is located on Turkey Run west of Clear Creek Rd in Building 44017 (Grid PV13404780). The third and fourth Bulk Water Points are located at Range Control on Black Gap Road at Buildings 56008 and 56099 (Grid PV21604685). Pins are required for access to the Bulk Water Points. Pins can be acquired by Ft. Hood Range Control. POC for Range Control will be provided at award.

Potable water NOT TO EXCEED 19,500 gallons per day. Locations, dates, and specifications of the SLCR unit are provided in the spreadsheet titled 278th Field Requirements.

5.11 Sleep Tents (LSA) - Each tent shall provide 50 square foot of space per soldier. The site shall sustain both male and female Soldiers in order to support the LSA population. All tents shall include fire extinguishers (TYPE C) in each tent IAW AR 385-10. The sleeping tent shall include lights (a minimum illumination of 30 foot candle at table height), minimum of one (1) (2-receptacle) outlet per four (4) cots evenly spaced on the wall, and HVAC to sustain 68-72 degrees. The Contractor shall be responsible for erecting and dismantling of the sleeping tents as well as maintaining the operation of lights, HVAC, and power generation. Sleeping tents shall be able to withstand wind gusts of 75mph. Sleeping tents shall have 3/4” plywood floor placed on 4”x 4”stringers or 1” plastic/composite flooring. Please state in your proposal the type of flooring that will be used. Bare floors shall not be accepted.

All sleeping tents shall be clear span, pole or other technically acceptable alternative and must be separated by gender. Contractor shall provide tent space to sleep 4,600 soldiers of tented billeting with Cots. Out of the 4,600 soldiers, approximately 443 will be female and require a separate sleeping tent.

Contractor shall have sleeping tents ready for occupancy on 30 May 2017 through 25 June 2017.

5.12 Feeding Tents (LSA) Contractor shall provide tented dining facility with minimum of 15 square feet person soldier, with lights (minimum illumination of 50 foot candle at table height), HVAC to sustain 68-72 degrees, and fire extinguishers (Type C) in order to support LSA population. Contractor shall be prepared to adjust feeding schedule based off of changes to the training schedule and other events. COR shall provide 24-hour notice to any changes to the feeding schedule. Feeding tents shall be able to withstand wind gusts of 75mph. All feeding tents shall have 3/4” plywood floor placed on 4”x 4”stringers or 1” plastic/composite flooring. Please state in your proposal the type of flooring that will be used. Bare floors shall not be accepted. Please state in your proposal the type of flooring that will be used. Tables and chairs shall be provided by the contractor so the soldiers can eat while sitting down. Contractor shall provide cleaning services for feeding tent to ensure a clean environment in including trash receptacles. Contractor shall be responsible for erecting and dismantling of feeding tents as well as maintain operation of lights, HVAC, and power generation.

Contractor shall have feeding tents ready for service and occupancy on 30 May 2017 through 02 July 2017. Expected feeding schedule with have 1,000 soldiers sitting down to eat at one time. Actually feeding schedule will be provided upon award.

5.13 Meals (LSA) Breakfast meals shall consist of at least three (3) menus offering a selection of one (1) meat, two (2) eggs, biscuits with gravy or pancakes with syrup, one (1) serving of orange or grape juice, one half (1/2) pint of milk and one (1) serving of coffee. Each serving of meat shall be a minimum of eight (8) ounces, each serving of drinks shall be a minimum of one (1) ounces, and all other servings shall be a minimum of four (4) ounces. Dinner meals will consist of at least five (5) menus offering a selection of one (1) serving of meat, two (2) servings of vegetables, one (1) serving of bread, one (1) serving of desert and one (1) serving of tea, coffee or soda as a beverage. Each serving of meat shall be a minimum of four (4) ounces, each serving of drinks shall be a minimum of 12 ounces, and all other servings shall be a minimum of four (4) ounces. Contractor must submit five (5) menu options for both breakfast and dinner. These menus must be approved by the COR who will coordinate with the TNARNG G4.

Number of meals and dates are attached in spreadsheet titled LSA Requirements. Feeding schedule will be provided at time of award.

5.14 Briefing Tents (LSA) Contractor shall provide 2 tents with to accommodate 300 soldiers in each. Required space will need to be 12 sq ft per person in each tent. Tents to be used for briefings, with lights (minimum illumination of 50 foot candle at table height). Placement begins 11-May 2017 until 2 July 2017 Government shall provide guidance for placement of tent following the completion of the site survey at Fort Hood, TX. Placement shall be coordinated with the COR. Require folding chairs for 300 personnel in each tent. Require 40, 6 foot folding tables for admin use in one tent. All tents shall include fire extinguishers (TYPE C) in each tent IAW AR 385-10. A minimum of one (1) (2-receptacle) outlets per 15 feet evenly spaced on the wall, and HVAC to sustain 68-72 degrees. The Contractor shall be responsible for erecting and dismantling of the tents as well as maintaining the operation of lights, HVAC, and power generation. Tents shall be able to withstand wind gusts of 75mph. Briefing tents shall have 3/4” plywood floor placed on 4”x 4”stringers or 1” plastic/composite flooring. Please state in your proposal the type of flooring that will be used. Bare floors shall not be accepted.

5.15 Light Towers (LSA) Contractor shall provide 40 light towers located in the life support area from 11 May 2017 to 2 July 2017. Government shall provide guidance for placement of light towers following the completion of the site survey at Fort Hood, TX. Placement shall be coordinated with the COR. DIESEL FUEL CAPABILITY REQUIRED. (F24 Fuel will be provided to contractor at no cost to Contractor, but will need to be refueled by the contractor)

5.15.1 Light Towers (Field) Contractor shall provide 58 light towers from 18 May 2017 to 08 June 2017 and 18 light towers from 19-30 June 2017. Government shall provide guidance for placement of light towers following the completion of the site survey at Fort Hood, TX. Placement shall be coordinated with the COR. If light sets needs to be restaged during movement, restaging will be coordinated with COR. DIESEL FUEL CAPABILITY REQUIRED. (Government will do the refueling of the light sets. Light sets will need have F24 fuel capability)

5.16 Site Improvements (LSA) Contractor shall use wood, stone or clay ONLY for improvements. ALL improvements provided by contractor shall be removed at completion of exercise ensuring the area is returned to its original state. There may not be any site improvements needed. This will be determined at the scheduled site visit as the LSA area in South Ft. Hood, TX per the solicitation. Due to the unexpected training scheduled at the LSA at Ft. Hood, there may be no time for site improvements. Will include as an option on solicitation.

5.17 Contractor Manpower Reporting Application (CMRA):

5.17.1 The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the Tennessee Army National Guard via a secure data collection site.

5.17.2 The contractor shall completely fill in all required data fields using the following web address: http://www.ecmra.mil/. Reporting inputs shall be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year, beginning with 2013. Contractors may direct questions to the help desk at http://www.ecmra.mil.

6.0 Applicable Publications: Publications applicable to this PWS are listed below:

Publication (Chapter/Page)

Date of Publication
Mandatory or Advisory
Website
DA Pam 385-26
02/01/2013
Mandatory
http://www.apd.army.mil/pdffiles/p385_26.pdf
AR 385-10
11/27/2013
Mandatory
http://www.apd.army.mil/pdffiles/r385_10.pdf
FM 21-10
06/21/2000
Mandatory
http://www.globalsecurity.org/military/library/policy/army/fm/21-10/fm21-10.pdf

TECHNICAL EXHIBIT 1

Performance Requirements Summary

This Performance Requirements Summary includes performance standards. The Government will use these standards to determine contractor performance and will compare contractor performance to the Acceptable Quality Level (AQL).

PWS Paragraph
Task
Performance Standard
Acceptable Quality Levels (AQL)
Surveillance Method / By Whom
5.1
Grey Water Removal (LSA) Daily.
The contractor shall remove grey water from the LSA once a day
98% must be completed. 2% failure rate
Daily Inspection - COR
5.1.1
Grey Water Removal (Field) once every 3 Days
The contractor shall remove grey water from the field operations once every 3 days
98% must be completed. 2% failure rate
Daily Inspection - COR
5.3
Trash Removal and Dumpster (LSA)
Contractor will provide trash removal daily
98% must be completed. 2% failure rate
Daily Inspection - COR
5.3.1
Trash Removal and Dumpster (field)
Contractor will provide trash removal daily
98% must be completed. 2% failure rate
Daily Inspection - COR
5.4
Hand Sanitation Stations (LSA)
Contractor will service and Clean Daily
98% must be completed with 2% failure rate
Daily Inspection-COR
5.5
Hand Washing Stations (LSA)
Contractor will service and Clean Daily
98% must be completed with 2% failure rate
Daily Inspection-COR
5.5.1
Hand Washing Stations (Field)
Contractor will service and clean every other Day
98% must be completed. 2% failure rate
Daily Inspection -COR
5.6
Power Generation
Contracting will provide Power Generation to the LSA
Power is available and response to response to service calls within 2 hours 98% of the time
Daily Inspection-COR
5.8
Chemical Latrines (LSA)
Contractor will provide Chemical Latrines and Service and Clean Daily
98% must be completed with 2% failure rate
Daily Inspection-COR
5.8.1
Chemical Latrines (Field)
Contractor will provide Chemical Latrines and Service and Cleaned every other day
98% must be completed-2% failure rate
Daily Inspection-COR
5.9
Reefer Van (Freezer and Refrigeration) LSA
Contractor will provide power and fuel to ensure functionality
Power is available and response to response to service calls within 2 hours 98% of the time
Daily Inspection-COR
5.9.1
Freezer Van (Field)
Contractor will provide power to ensure functionality
Power is available and response to response to service calls within 2 hours 98% of the time
Daily Inspection-COR
5.10, 5.10.1
Potable Water Supply (LSA and Field)
Contractor will provide potable water on a daily basis to the LSA and Field
98% must be completed. 2% failure rate
Daily Inspection-COR
5.12, 5.13
Feeding Tents
Contractor shall provide food services and meals per attached schedule. Cleaning must be performed after every meal
98% must be completed. 2% failure rate
Daily Inspection-COR (on days meals are being served)
1.4.8
Identification of Contractor Employees
Contractor Employees wear identification as Contractor
98% must be completed. 2% failure rate
Daily Inspection-COR

TECHNICAL EXHIBIT 2

Deliverables Schedule

PWS Reference / Deliverable Title
Frequency
Number of Copies
Medium/Format
Submit To
1.4.5.4 AT Level 1 Awareness Training Certificates
Provide within 10 calendar days after contract start date and contractor submits to COR five (5) days after training completion
1
Electronic Submission
COR
1.4.5.5 iWatch Training
Training Completed within 10 days of contract award and contractor submits to COR five (5) days after training completion
1
Electronic Submission
COR
1.4.5.6 OPSEC Training
Provide within 10 of contract award contractor submits to COR five (5) days after training completion
1
Electronic Submission
COR

1.4.5.7 OPSEC

SOP/PLAN

Provide within 10 calendar days of Award
1
Electronic Submission
COR/KO
1.4.8 Return of Vehicle Passes and Badges
Return within 14 days of departure
Originals
Originals
COR

File details come from the government source that posted it. Updated .