PWS_Repair_Generator.pdf
PDF 90 KB Posted
- Solicitation number
- W912L7-15-Q-1112
About this file
PWS Generator Repair Amendment 1
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PWS_Repair_Generator_Amendment_II.pdf | ||
| Q A_1.pdf | ||
| PWS_Snorkel_Repair.pdf | ||
| PWS_Install_130_ton_chiller_3.pdf | ||
| PWS_Repair_Generator.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
th
Wing SECTION 01000
Nashville, Tennessee Performance Work Statement
BKTZ152015 Amendment 1
PERFORMANCE WORK STATEMENT
GENERATOR REPAIR BLDG 757
PROJECT # BKTZ 152015
BERRY FIELD, NASHVILLE, TENNESSEE
GENERAL
The work covered by this Performance Work Statement (PWS) consists of furnishing all labor, equipment, and materials to repair generator at bldg. 757. The work location is the 118th Wing, Nashville, Tennessee. Contractor shall be fully responsible for compliance with all base, local, state, and federal environmental/occupational safety laws, rules and regulations that apply. The contractor shall follow life and safety codes, and take necessary actions to avoid conditions which may be hazardous to the health and safety of base personnel. The Contractor is responsible for all permits associated with the project.
1.1 PERFORMANCE PERIOD
The performance period for this project is 2 calendar days.
1.2 PROJECT DESCRIPTION
1. Repair Katolight 500kw generator model 500FRV4 at bldg. 757, See attached
GENERATOR OPERATING LOG
A. Scope of Work: Contractor shall perform all work as described herein. Work includes but is not limited to:
i. The contractor will install in accordance with manufactures specifications
(1) control board DGC500. Board specifications shall be approved by the
COR. (Contracting Officer Representative).
ii. The contractor will install in accordance with manufactures specifications
(1) fan belt set 96263. Fan belt set shall be approved by the COR.
iii. The contractor will install in accordance with manufactures specifications
(1) alternator belt set 96314. Alternator belt set shall be approved by the
COR.
iv. The contractor will install in accordance with manufactures specifications
(1) tensioner pulley. Tensioner pulley shall be approved by the COR.
Wing SECTION 01000
BKTZ152015 Amendment 1
v. The contractor will install in accordance with manufactures specifications
(1) fan hub assembly. Fan hub assembly shall be approved by the COR.
vi. The contractor will The contractor will remove and dispose of the contaminated fuel. The contactor will clean the fuel tank. The government will replace the fuel.
vii. The contractor will test in accordance with manufactures specifications the generator after repairs are complete to ensure proper operation. Testing procedures shall be approved by the COR.
viii. The contractor will remove all work related debris and dispose of it off the property. The grounds shall be repaired, as required, to the condition prior to construction.
ix. All materials and testing procedures will be approved by the COR.
x. All work will be performed in accordance with all Local, State and
Federal codes.
1.3 REFERENCES
1.3.1 In general, all technical specifications are provided within the Construction Documents however, in the event any project element is not covered in the specifications provided, the contractor should refer to the Specification Hierarchy for direction related to the element.
1.4 SPECIFICATION HIERARCHY
1.4.1 The specification hierarchy is the collection of technical specification to be used for all projects. The contractor should refer to the specifications provided in the Construction
Documents first before moving to the next technical specification listed in the specification hierarchy. The hierarchy is listed in the order of precedence (i.e. “A” supersedes “B”, “B” supersedes “C”, etc.). The hierarchy is as follows:
1. Specifications provided with Construction Documents.
2. Base Standard Specifications.
3. MATOC Default Specifications.
4. AIA Master Spec Specifications.
Wing SECTION 01000
BKTZ152015 Amendment 1
PART 2
Deliverable Schedule
The contractor deliverable has one time period with one acceptable threshold for that deliverable.
Deliverable Time Period Deliverable Threshold
50% End of 1 days COMPLETE
100% End of 2 days COMPLETE
All parts installation and testing will be in according with manufactures specifications.
'End of Performance Work Statement’