Vendor_questions_1.docx

DOCX document 14 KB Posted

Attached to
Wyoming National Guard MATOC
Solicitation number
W912L3-13-R-0001
Issued by

View the file

Other files

File Type Posted
Vendor_questions_4.docx DOCX document
13-R-0001-0003.pdf PDF
Vendor_questions_3.docx DOCX document
13-R-0001-0002.pdf PDF
Vendor_questions_2.docx DOCX document
MATOC_Pre-Proposal_Sign_in_sheet.pdf PDF
MATOC_Preproposal_Conference_FY_13.pptx PPTX presentation
Vendor_questions_1.docx DOCX document
Amendment_1.pdf PDF
A-11_MATOC_Exhibits_A_D_F_G__Feb_2013_R_1.docx DOCX document
A-10_Synopsis__MATOC_Oct_12_WY.docx DOCX document
A-11_MATOC_Exhibits_A_D_F_G__Feb_2013_R_1.docx DOCX document
MATOC__EXHIBIT_E__Oct__2012_WY_New.docx DOCX document
A-11_MATOC_Exhibits_A_D_F_G__Feb_2013_R_1.docx DOCX document
Prototypical_Proj-B55_100__Specs.pdf PDF
Prototypical_Proj_-B55_100__Half_Size_Dwgs.pdf PDF
W912L3-13-R-0001_WY_MATOC.pdf PDF
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. In the Synopsis a 2hr response time is mentioned, where do we have to respond to in 2hrs?

2 hours from the location that you check on page 12 of the Solicitation.

2. Do you know if fitness equipment (cardio, strength, selectorized, weights, training accessories) will be included in this requirement as sometimes is under a construction contract?

Fitness equipment would have to be purchased after construction and with different money. So fitness equipment wouldn’t apply to this solicitation.

3. Section 00110 Submission Requirements and Instructions paragraph 2.2.4. states that “offerors lacking Past Performance experience may submit information regarding predecessor companies, key personnel who have relevant experience or subcontractors that will perform major or critical aspects of the requirement if such information is relevant to this acquisition.” In the case of our company being a newer company and lacking the 6 projects, it is our understanding that we could list projects that the owner performed with his previous employer to make up for the lack of experience as the new company. Is this a correct understanding?

Yes as long as they are key personnel and the experience is relevant.

4. It appears that as of 1050 MDT on 16 APR 13 there were no exhibits posted on FBO for us to fill out. Can the WYNG please provide all the exhibits referenced in the RFP?

Exhibits are now attached.

5. I had noticed that there is a walk through at your Wyoming National Guard project on May 1, 2013 but I did not notice a time for that. We are a boiler rep for Wyoming and we would like to attend, can you please let me know time frames so we can be sure to get out there and attend the walk through?

Please see Section 00100 1.5.1 (Page 14).

6. I just wanted to confirm whether this MATOC includes Design-Build opportunities.

Please see Section 00100 1.1 (Page 13).

7. Is this project being handled out of Wyoming or out of Louisville?

Please see page 12 of the solicitation for locations.

8. Reference SF 1442, Block 13A – The proposal due date and time are blank on the SF 1442. Please confirm the that the proposal is due on May 17th at 7:00 AM Mountain as listed on the FBO advertisement.

Yes, proposals are due the date and time stated on the FBO advertisement.