MEAD & HUNT, INC.

Engineers - Architects - Scientists - Planners 6501 Watts Road, Suite 101 Madison, Wisconsin 53719-2700

(608) 273-6380 www.meadhunt.com

MICHIGAN

AIR

NATIONAL

GUARD

ALPENA - CRTC

REPAIR PARKING APRON A01B and A08B Alpena - CRTC Alpena, Michigan

September 13, 2013

PROJECT MANUAL

TYPE B-3 FINAL SUBMITTAL

Project No. TDVG 122778 Mead & Hunt Project No. 31418-00-120876.01

TC-1

TECHNICAL SPECIFICATIONS

Repair Parking Apron A01B and A08B

Alpena - CRTC Alpena, Michigan

C COVER

TC TABLE OF CONTENTS

00 31 10 METRIC MEASUREMENTS

00 41 00 BID SCHEDULES

DIVISION 01 – GENERAL REQUIREMENTS

01 00 00 GENERAL REQUIREMENTS

01 10 00 SUMMARY

01 16 20 HAZARDOUS MATERIAL USAGE REQUIREMENTS

01 31 00 PROJECT MANAGEMENT AND COORDINATION

01 32 16 CONSTRUCTION PROGRESS DOCUMENTATION

01 33 00 SUBMITTAL PROCEDURES

01 35 13 SPECIAL PROJECT PROCEDURES

01 35 26 GOVERNMENT SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00 (1) QUALITY CONTROL (CONTRACTOR QUALITY CONTROL)

01 45 00 (2) QUALITY CONTROL (CONTRACTOR QUALITY ASSURANCE)

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROL

01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL

01 60 00 PRODUCT REQUIREMENTS

01 62 35 RECYCLED/RECOVERED MATERIALS

01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

01 78 00 CLOSEOUT SUBMITTALS

DIVISION 02 – EXISTING CONDITIONS

02 41 10 DEMOLITION

DIVISION 03 – CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE

DIVISION 31 – EARTHWORK

31 00 00 EARTHWORK

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID PAVEMENTS

32 05 33 LANDSCAPE ESTABLISHMENT

32 11 16 BASE COURSE FOR RIGID AND SUBBASES FOR FLEXIBLE PAVING

32 11 23 AGGREGATE AND/OR GRADED-CRUSHED AGGREGATE BASE COURSE

32 12 10 BITUMINOUS TACK AND PRIME COATS

32 12 15 HOT-MIX ASPHALT AIRFIELD PAVING

TC-2

32 13 11 CONCRETE PAVEMENT FOR AIRFIELDS AND OTHER HEAVY-DUTY

PAVEMENTS

32 13 73 COMPRESSION JOINT SEALS FOR CONCRETE PAVEMENTS

32 17 24 PAVEMENT MARKINGS

32 92 19 SEEDING

DIVISION 33 – UTILITIES

33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION

33 73 13 GROUNDING/MOORING POINTS FOR AIRCRAFT

00 31 10 - 1 METRIC MEASUREMENTS

DOCUMENT 00 31 10 - METRIC MEASUREMENTS

04/06

PART 1 - GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM SI10 (2010) American National Standard for Use of the International

System of Units (SI): The Modern Metric System

1.2 GENERAL

This project includes metric units of measurements. The metric units used are the International System of Units (SI) developed and maintained by the General Conference on Weights and Measures (CGPM); the name International System of Units and the international abbreviation SI were adopted by the 11th CGPM in 1960. A number of circumstances require that both metric SI units and English inch-pound (I-P) units be included in a section of the specifications. When both metric and I-P measurements are included, the section may contain measurements for products that are manufactured to I-P dimensions and then expressed in mathematically converted metric value (soft metric) or, it may contain measurements for products that are manufactured to an industry recognized rounded metric (hard metric) dimensions but are allowed to be substituted by I-P products to comply with the law. Dual measurements are also included to indicate industry and/or Government standards, test values or other controlling factors, such as the code requirements where I-P values are needed for clarity or to trace back to the referenced standards, test values or codes.

1.3 USE OF MEASUREMENTS IN SPECIFICATIONS

Measurements in specifications shall be either in SI or I-P units as indicated, except for soft metric measurements or as otherwise authorized. When only SI or I-P measurements are specified for a product, the product shall be procured in the specified units (SI or I-P) unless otherwise authorized by the Contracting Officer. The Contractor is responsible for all associated labor and materials when authorized to substitute one system of units for another and for the final assembly and performance of the specified work and/or products.

1.3.1 Hard Metric (NOT USED)

A hard metric measurement is indicated by an SI value with no expressed correlation to an I-P value. Hard metric measurements are often used for field data such as distance from one point to another or distance above the floor. Products are considered to be hard metric when they are manufactured to metric dimensions or have an industry recognized metric designation.

1.3.2 Soft Metric

a. A soft metric measurement is indicated by an SI value which is a mathematical conversion of the I-P value shown in parentheses (e.g. 38.1 mm (1-1/2 inches)).

00 31 10 - 2 METRIC MEASUREMENTS

Soft metric measurements are used for measurements pertaining to products, test values, and other situations where the I-P units are the standard for manufacture, verification, or other controlling factor. The I-P value shall govern while the metric measurement is provided for information.

b. A soft metric measurement is also indicated for products that are manufactured in industry designated metric dimensions but are required by law to allow substitute I-P products. These measurements are indicated by a manufacturing hard metric product dimension followed by the substitute I-P equivalent value in parentheses (e.g., 190 x 190 x 390 mm (7-5/8 x 7-5/8 x 15-5/8 inches)).

1.3.3 Neutral

A neutral measurement is indicated by an identifier which has no expressed relation to either an SI or an I-P value (e.g., American Wire Gage (AWG) which indicates thickness but in itself is neither SI nor I-P).

1.4 COORDINATION

Discrepancies, such as mismatches or product unavailability, arising from use of both metric and non-metric measurements and discrepancies between the measurements in the specifications and the measurements in the drawings shall be brought to the attention of the Contracting Officer for resolution.

1.5 RELATIONSHIP TO SUBMITTALS

Submittals for Government approval or for information only shall cover the SI or I-P products actually being furnished for the project. Submit the required drawings and calculations in the same units used in the contract documents describing the product or requirement unless otherwise instructed or approved. Use ASTM SI10 as the basis for establishing metric measurements required to be used in submittals.

END OF SECTION

00 41 00 - 1 BID SCHEDULES

SECTION 00 41 00 – BID SCHEDULES

PART 1 GENERAL

1.1 BASIS OF BIDS

1.1.1 Unit Price Schedule

This contract will be solicited with bid items and unit prices required for each item of work. The following “Schedule of the Unit Price Work” is to be attached to the Standard Form SF 1442, "Solicitation, Offer and Award." See Contract Clauses, "FAR 52.212-11, Variation in Estimated Quantity" and "FAR 52.236-16, Quantity Surveys."

In the event there is a difference between a unit price and the extended total, the unit price will be held to be the intended bid. If the bidder shows only the total price but fails to enter a unit price, the total divided by the estimated quantity will be held to be the intended unit price.

Any bid price for items which are unbalanced as to price may be rejected as non-responsive. An unbalanced bid is one which is based on price significantly less than cost for some work and price which is significantly overstated for other work.

The unit price, or lump sum price, for each item listed shall constitute the full compensation for furnishing all plants, labor, materials, equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, incidental items, and for performing all work required for each item listed as shown in the plans and according to the specifications, complete and accepted. Each item shall include the costs of all items required, along with any item the contractor may deem required which may not be specifically mentioned or included in a particular lump sum or unit price item mentioned.

No claims for anticipated profits, loss of profits, or damage of any sort due to differences between the estimated and actual quantities of any item included in the original work will be allowed.

Quantities listed are estimated quantities and to be considered "not to exceed".

The Contractor is cautioned that express written approval prior to performing any work in excess of the estimated quantities shown must be received from the Contracting Officer.

DIVISION 01 – GENERAL REQUIREMENTS

01 00 00 - 1 GENERAL REQUIREMENTS

SECTION 01 00 00 – GENERAL REQUIREMENTS

PART 1 - GENERAL

1.1 SCOPE

A. This project provides for furnishing all plant, labor, materials and equipment to Repair the Parking Apron A01B and A08B, the construction of an asphalt shoulder, and associated work at Alpena CRTC, Alpena, MI, as described herein and shown on the construction drawings. This project will consist of a Base Bid with no Additive Bid Items (ABI’s) or Options.

B. The Base Bid portion shall consist of three Contract Line Item Numbers (CLIN’s), when added together will include all the work shown in the plan set and included in these specifications.

CLIN 1 = Minor Construction This portion of the project shall consist of all construction, along with miscellaneous items required to construct the new 15.24m (50-foot) wide asphalt shoulder along the western edge of the concrete apron included under CLIN 2 below. Not included in this CLIN is the replacement of all existing asphalt and concrete pavement areas west of the western edge of the concrete apron. These areas to be included in CLIN 2 below.

CLIN 2 = Repair This portion of the project shall consist of all construction, along with miscellaneous items required to repair the 83.82m (275-foot) by 731.52m (2,400-foot) area of the Main Aircraft Parking Apron A01B, along with the replacement of all existing asphalt and concrete pavement areas north, south and west of the eastern edge of the concrete apron.

CLIN 3 = Repair This portion of the project shall consist of all construction, along with misc. items required to repair the 22.86m (75-foot) by 731.52m (2,400-foot) area of the Main Aircraft Parking Apron A08B located east of CLIN 2.

C. The Contractor will be held responsible for all requirements described in the contract documents and all work including that of his Subcontractors, if any, shall be done in accordance with the contract documents. Failure to familiarize himself with their requirements will not relieve the Contractor of his responsibility to comply.

D. The organization of the specifications into divisions, sections, and articles, and the arrangement of the drawings shall not control the Contractor in dividing the work among Subcontractors or in establishing the extent of the work to be performed by any trade.

1.2 PROJECT SCHEDULE

A. The estimated time of award is in the Winter 2014. The award date will start the Stage I portion of the project (see below), which will run to approximately Spring 2014, which is the estimated time of the start of construction (Stage II).

01 00 00 - 2 GENERAL REQUIREMENTS

See plan set for information on construction phasing required under this project during Stage II.

The Contractor shall start the Stage I portion immediately after the award of the contract.

The Stage I portion of the project shall consist of the time for submitting all required contractual items, providing of all pre-construction submittals, perform and submit required testing and mix designs of all proposed materials to be used in the project, obtain required permits, and at the option of the contractor, start to produce materials for use in the project. Upon completion of Stage I, all pre-construction submittals, permits, material submittals, mix designs, pre-construction submittals, and all required documentation shall be completed, submitted, and approved. The contractor will not be entitled to any extension of time or additional payment due to any delays raised by not completing the Stage 1 portion of work.

Stage I will also include attending the Pavement Workshop as described in 1.3

Pavement Workshop.

B. The Government will issue a Notice to Proceed (NTP) with a start date to the contractor for initiation of work after the bonds have been submitted to the KO and approved by the JAG. The contractor shall give 72-hour notice to the Contracting Officer before he/she plans to start the work if the start date is after the date listed on the NTP. Written permission from the Contracting Officer shall be obtained for any deviation from the approved schedule.

C. The estimated start of construction is Spring 2014, or the date as stated on the Notice to

Proceed. This date will start the beginning of the Stage II portion of the project, at which time all required items shall be submitted and approved. No item shall still be in the process of approval which may delay construction.

D. The completion date for the project is October 31, 2014. Contract time begins on the date stated in the Notice to Proceed.

E. Normal base work hours for the Contractor will be between the hours of 7:00 AM thru

5:00 PM, excluding Saturdays, Sundays, and Federal Holidays. If the Contractor desires to work during periods other than above, he must notify the Contracting Officer five (5) working days in advance of his intention to work during other periods to allow assignment of additional inspection forces and for notification of fire, security and safety.

When the Contracting Officer determines that they are reasonably available, he may authorize the Contractor to perform work during periods other than normal duty hours/days. However, if inspectors are required to perform in excess of their normal duty hours/days solely for the benefit of the Contractor, the actual cost of the inspection, at overtime rates, will be charged to the Contractor and will be deducted from the final payment of the Contract amount.

F. The following Federal legal Holidays are observed by this Base:

New Year's Day 1 January Martin Luther's King's Birthday Third Monday of January President's Day Third Monday of February Memorial Day Last Monday of May Independence Day 4 July Labor Day First Monday in September

01 00 00 - 3 GENERAL REQUIREMENTS

Columbus Day Second Monday in October Veteran's Day 11 November Thanksgiving Day Fourth Thursday in November Christmas Day 25 December

NOTE: Any of the above holidays falling on a Saturday will be observed the preceding

Friday, holidays falling on a Sunday will be observed on the following Monday.

G. Prior to commencing work on the job initially, resumption of work after prolonged interruption (7 calendar days or more), commencement of any warranty work, and upon completion of warranty work, the Contractor must notify the Contracting Officer (or his/her Contracting Officer Representative (COR)). When relocating to new sites, returning to sites for follow-up work on a phased work plan, notification to the Contracting Officer’s Representative is sufficient. Notification should be by personal contact; however, advance notification may be by telephone, or in writing, and should be accomplished sufficiently in advance to allow scheduling of inspection forces. The above precautions are to ensure construction inspection and recording of work proceedings.

H. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by the

Government, Airport, and others unless permitted and then only after arranging to provide temporary utility services according to requirements stated in “Utility Interruptions/Protection of Utilities” to follow. Do not proceed with utility interruption without COR written permission.

1.3 PAVEMENT WORKSHOP

The Corps of Engineers will conduct a three day pavement workshop to be held at

Alpena CRTC. The workshop will consist of one day (8 hours) for the Hot Mix Asphalt (HMA) and two days (16 hours) for the Portland Cement Concrete (PCC). It is mandatory that the Contractor and his representatives, subcontractors, materials testing laboratory(s) personnel attend the workshop for the minimum amount of time as listed above. Additionally, personnel may attend any non-mandatory sessions on a space-available basis. The dates for the workshop will be scheduled by the COR after the project is awarded and prior to the start of construction, and will be as directed by the Contracting Officer. The costs associated with the contractors personnel attending this workshop shall be paid by the contractor and considered incidental to the project.

1.4 METHOD OF CARRYING ON THE WORK

A. All work under the Contract shall be arranged and carried on in such a manner as to complete work in the least possible time. The Contractor shall consult with the Contracting Officer as to methods or sequence of carrying on the work. A definite program of work shall be arranged before starting. Reference Contract Clause FAR 52.236-15, “Schedules for Construction Contracts”.

B. Activities in the vicinity of this project will be kept in full or partial operation during construction. The Contractor shall coordinate with the Contracting Officer and schedule construction activities. Reference Contract Clause FAR 52.236-8, “Other Contracts”.

01 00 00 - 4 GENERAL REQUIREMENTS

1.5 ENTRY TO BASE/ACCESS TO SITE

A. CONTROLLED ACCESS: The Alpena Combat Readiness Training Center is a closed facility and has controlled access. The General Contractor and all other personnel under their supervision will need a Contractor pass for approved access. The General Contractor shall submit a request for base access. The request shall have the contract number, job location, duration of the contract, the individual’s full name, date of birth and social security number. Typed Entry Authorization Lists (EAL) must include a list of all employees, subcontractors, and vendors requiring access to the base. This request is to be submitted to the COR (Contracting Officer’s Representative) 48 hours prior to contractor arrival and will be forwarded to security operations. Contractors requiring access may be issued a photo identification card for the length of the contract.

Individuals will be required to show a current photo identification and proof of their social security number to obtain their Contractor pass. All individuals will be required to take an antiterrorism interactive awareness course before obtaining their pass. This may be done on station or may be accessed on the internet at http:/atlevel1.dtic.mil/at/, access code-aware. Training takes approximately 60 minutes. When completed, click on e-mail and send to loretta.smith.ctr@ang.af.mil (this logs your training in the data base as complete.) Individuals are required to show their contractor pass at the point of entry and visible while on base, and must show identification when requested by security personnel. The Contractor pass remains the property of the base and shall be surrendered at the termination of employment, duration of the contract and as requested by security personnel. The General Contractor shall be held accountable for all Contractor passes. Any contractor personnel may be denied access or removed from the base at any time and/or for any reason by base security or the C.O.R.

B. During construction, the Contractor shall permit base personnel access to the facilities within the work area. The Contractor shall provide protection to persons and property throughout the progress of the work.

C. In the event of a declared National Emergency the Contracting Officer may be required to stop work on this contract for security reasons. Contractor shall ensure the Contracting Officer has a current “Off Duty” contact name and telephone number at all times to facilitate notification.

D. During construction, Security Forces (Alpena County Sheriff Deputies) will be required to perform gate guard duties where the haul route enters the airfields perimeter fence. A gate guard is required any time a contractor or subcontractor is present or performing work on this project within the airport perimeter fence. Gate guard use requires no less than 24 hour notice and shall be coordinated at the progress and coordination meetings and scheduled through the COR. The hourly rates for gate guards are as follows:

$30.60 regular rate $45.90 overtime and less than 24 hour prior notice per contract

Payment for this item shall be included under the item “Security Force/Gate Guard”.

1.6 SECURITY REQUIREMENTS / UNAUTHORIZED PERSONNEL

01 00 00 - 5 GENERAL REQUIREMENTS

A. The Contractor shall inform all personnel working under his/her jurisdiction (including subcontractor and visiting supplier personnel) that access to areas outside of the immediate work area excluding, direct haul and access routes, contracting and Civil Engineering offices and point of supply and storage is prohibited. Circulation of said personnel will be limited to official business only. Persons in violation of the above will be apprehended and appropriately disciplined.

B. The Contractor shall comply with all security regulations imposed by the base commander and/or agency occupying the space where work is to be performed. Any necessary security clearances shall be obtained prior to commencement of work.

C. The Contractor shall ensure that all parts of the facility where work is being performed are adequately protected against vandalism and theft.

1.7 SUPERINTENDENCE BY THE CONTRACTOR

A. At all times during performance of this contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the Contractor. See Section 01 45 00 “Quality Control” for additional information.

1.8 PERMITS AND TAXES

A. The Contractor shall procure all permits (unless otherwise noted below), licenses and approvals necessary for the execution of this Contract and performance of the Work, and shall provide evidence of such permits, licenses and approvals at the Pre- Construction meeting or before commencement of the Work.

1. The erosion control is the responsibility of the Contractor as described in the specifications and identified on the plans. Permits required are:

a. NPDES permit through MDNRE

b. County SESC permit

c. Erosion and sediment control form and inspection reports.

d. See Section 01 57 23 “Temporary Storm Water Pollution Control” for information.

e. AF Form 103 “ Locate Permit” minimum 10 days prior to the start of work.

2. The Contractor shall pay all Sales, Consumer, Use and other similar taxes required by the law assessed to or arising out of the construction of the Project.

1.9 EXCAVATING PERMIT

A. The contractor is required to fill out and return to the COR (BCE Building 2), AF Form

103 digging permit a minimum of 10 working days prior to the start of any excavation.

The Government will only locate utilities one time. Once the area is flagged it is the contractor’s responsibility to maintain the flags or markings.

B. The BCE office has seven calendar days to complete the form after being submitted by the contractor.

01 00 00 - 6 GENERAL REQUIREMENTS

C. The contractor shall call the MISS DIG System at 811 or 1-800-482-7171 and allow 3 full working days to complete locate prior to the start of any excavation.

1.10 DIVISION OF WORK

A. The various divisions of the Specifications shall not be considered as negotiations of the material and labor involved. The arrangement and order of these divisions have been made for convenience only, and it is not the intent, nor shall it be so construed, a particular trade or subcontractor must perform that work included in any one division.

B. Any item mentioned under any division heading must be supplied even though it is not specified under the heading for the respective work, but is shown on the Drawings. No claims for extras arising out of real or alleged error in such arrangement or order of the various divisions will be given consideration.

C. The organization of the specifications into divisions, sections, and articles, and the

Subcontractor or in establishing the extent of the work to be performed by any trade.

D. Reference Contract Clause FAR 52.236-21, “Specifications and Drawings for

Construction”.

1.11 CORRELATION OF DRAWINGS, SPECIFICATIONS AND CONTRACTS

A. The specifications, Contract, and the accompanying Drawings are intended to describe and provide for a complete, new, and usable facility. They are intended to be cooperative and what is called for by one shall be as binding as if called for by all. The Contractor will understand that the work herein described shall be complete in every detail, notwithstanding every item necessarily involved is not particularly mentioned, and the Contractor shall be held to provide all labor and material for the entire completion of the work intended to be described and shall not avail himself of any manifestly unintentional error or omission, should any exist. Should any error or inconsistency appear in the Drawings or Specifications, the Contractor, before proceeding with the work, shall make mention of same to the Contracting Officer for proper adjustment, and in no case shall he proceed with the work in uncertainty. Reference Contract Clause DFARS 252.236-7001, “Contract Drawings, Maps and Specifications”.

1.12 REPORT OF ERROR AND DISCREPANCIES

A. The Contractor shall be responsible for any and all discrepancies in work due to failure to obtain dimensions and investigate conditions before start of construction.

B. The Contractor shall bear all costs in replacing all materials and labor due to not observing the above paragraph and such replaced materials shall meet the approval of the Contracting Officer.

C. The Contractor shall promptly notify the Contracting Officer in writing of any discrepancies.

01 00 00 - 7 GENERAL REQUIREMENTS

D. Reference Contract Clauses FAR 52.236-21, “Specifications and Drawings for Construction”, FAR 52.246-12 “Inspection of Construction”, and DFARS 252.236- 7001, “Contract Drawings, Maps and Specifications”.

E. Any proposed changes to the specifications or plan set by the Contractor must be submitted in writing to the Contracting Officer for approval and approved prior to implementation.

1.13 STANDARDS OF MANUFACTURE, MATERIALS & WORKMANSHIP

A. All recognized regulatory/code standards shall be the latest published edition prior to the date of release for bid/proposal of the contract documents.

B. For purpose of establishing the standard of construction and the requirements to be met in the work of all divisions, the drawings and these specifications are based on the use of products hereinafter specified, adapted to the installation as required to meet the condition.

C. Where brand names are shown, these names are intended to describe a quality of product, and in no way are intended to limit products of equal quality. Therefore, products of other manufacturers may be employed for this work provided they are equivalent materials and construction, meet all specification requirements, and are equally adaptable to the conditions as approved by the Contracting Officer.

Reference Contract Clause FAR 52.236-5, “Materials and Workmanship”. The

Contracting Officer or his/her designated COR will consider un-named products when the following are provided: (See Section 01 60 00 for additional information)

1. Evidence that the proposed product does not require revisions to the Contract

Documents; that it is consistent with the Contract Documents and will produce the indicated results; and that it is compatible with other portions of the Work.

2. A detailed comparison of the significant qualities of proposed product with those of the named product and those named in the Specifications. Significant qualities include attributes such as performance, weight, size, durability, visual effect, and specific features and requirements indicated.

3. Evidence that proposed product provides specified warranty.

4. Samples, if requested.

D. Where, named products are followed by language such as “no substitutions”, “no comparable products” or similar language, the product has been approved to be sole sourced and the Contractor shall provide the named product.

E. All equipment, materials, and articles incorporated into the work covered by this contract shall be new and of the most suitable grade for the purpose intended, unless otherwise specifically provided in this contract. References in the specifications to equipment, material, articles, or patented processes by trade name, make, or catalog number, shall be regarded as establishing a standard of quality and shall not be construed as limiting competition. The Contractor may, at its option, use any equipment, materials, articles, or process that, in the judgment of the Contracting Officer, is equal to that named in the specifications, unless otherwise specifically provided in this contract.

01 00 00 - 8 GENERAL REQUIREMENTS

F. The Contractor shall obtain the Contracting Officer’s approval of the machinery, mechanical, and other equipment to be incorporated into the work. When requesting approval, the Contractor shall furnish to the Contracting Officer the name of the manufacturer, the model number, and other information concerning the performance, capacity, nature, and rating of the machinery, mechanical, and other equipment. When required by this contract or by the Contracting Officer, the Contractor shall also obtain the Contracting Officer’s approval of the material or articles which the Contractor contemplates incorporating into the work. When requesting approval, the Contractor shall provide full information concerning the material or articles. When directed to do so, the Contractor shall submit samples for approval at the Contractor’s expense, with all shipping charges prepaid. Machinery, equipment, material, and articles that do not have the required approval shall not be installed or used at the risk of subsequent rejection and removal.

G. All work under this contract shall be performed in a skillful and workmen like manner.

The Contracting Officer may require, in writing, that the Contractor remove from the Project any employee the Contracting Officer deems incompetent, careless, or otherwise objectionable.

1.14 BLOCKING OFF BASE STREETS (IF REQUIRED)

A. See Section 01 50 00 - “Temporary Construction Facilities and Controls” par. 3.3.1

1.15 MAINTENANCE OF TRAFFIC AND SAFETY

A. The contractor shall comply with all applicable Federal, State, Local, DOD, National

Guard Bureau, and Air Force regulations pertaining to safety, traffic control, and fire prevention.

B. The Contractor, his employees, and Subcontractors shall become familiar with and obey the regulations of the installation including fire, traffic, safety and security regulations while on the military installation. Those driving motor vehicles shall observe and obey all speed limits posted throughout the installation. Personnel should not enter restricted areas unless required to do so and only upon prior approval. All contractor employees and Subcontractors shall carry proper personal identification with them at all times.

C. See Section 01 50 00 - “Temporary Construction Facilities and Controls” for additional

D. Where possible, the Contractor and his work shall not interfere with the normal operations of traffic, particularly emergency vehicles and equipment. Contractor is responsible for safety on the Project Site.

E. Barricades and signage shall be in accordance with the Construction Operations Plan, General Notes, Phasing Plan and Haul Route Signage Plan contained in the plan set.

F. The Contractor shall construct and use only established haul routes. When materials are transported in prosecution of the work, vehicles shall not be loaded beyond the loading limit established by Federal, State, or Local Law or regulation. When it is necessary to cross curbing, sidewalks, or existing roadways protection against damage shall be provided by the Contractor. The Contractor shall observe all Frost Laws.

01 00 00 - 9 GENERAL REQUIREMENTS

G. The Contractor shall provide for the free and unobstructed movement of vehicles entering and leaving areas of the Base with respect to his own operations and the operations of all his Subcontractors.

H. With respect to his own operations, and those of all his Subcontractor, the Contractor shall provide marking, lighting, and other acceptable means of identifying personnel, equipment, vehicles, storage areas, and any work or condition that may be hazardous to vehicles, fire-rescue equipment, or maintenance vehicles at the Base.

I. Contractor’s equipment shall be conspicuously marked for identification and parked or placed within approved areas only, out of the way of driveways, emergency access roads, and traffic. The contractor shall ensure that all parts of the facility where work is being performed are adequately protected. The contractor shall comply with all security regulations imposed by the base commander against vandalism and theft.

J. The Contractor shall furnish, erect, and maintain weighted barricades, warning signs, and other traffic control devices, as required, to maintain traffic and insure the safety of the public and the Contractor’s equipment. The Contractor shall make his own estimate of all labor, materials, equipment, and coincidental necessary for providing the maintenance of public and military vehicular traffic.

See “Construction Operations Plan”, “Construction Operations Plan General Notes”, “Phasing Plan”, and “Haul Route Signage Plan” contained in the plan set for additional

K. The Contractor shall furnish, erect, and maintain artificial lighting when night work is required. Artificial lighting shall be sufficient quantity to illuminate the entire area when the work is occurring and not adversely impact the operations of the airport/base. The Contractor shall submit an artificial lighting plan to the COR minimum 7 calendar days prior to anticipated implementation. Artificial lighting, if required, shall be erected and functioning a minimum of 2 hours prior to dusk and shall remain a minimum 2 hours after dawn. Artificial lighting shall be lowered when not in use.

1.16 REGULATIONS

A. The Contractor, his employees, and his Subcontractors are subject to, and shall abide by and comply with, all relevant statutes, ordinances, laws and regulations of the United States (including Executive Orders of the President) and any State (or other public authority now or hereafter in force). The Contractor agrees to observe and comply with all applicable state and federal requirements regarding social security, workman’s compensation, unemployment insurance, and any other matters concerning employment applicable to the performance of this contract or rules, regulations, directions, and orders not consistent herewith as may from time to time be issued by the Government. The unilateral act of any governmental body against any employee of the Contractor for the violation of a state or federal law or regulation shall not excuse the Contractor from full compliance with the terms and conditions of this contract.

B. The Contractor may use the Civil Engineering library which contains most applicable

Army and Air Force publications as well as some commercial project data information or the following Contracting Resources on the Internet, 01 00 00 - 10 GENERAL REQUIREMENTS http://users.interline.net:80/jc/contract.htm or DOD Acquisition Reform Home Page which links for several other sites with available publications, forms and project data information, http://www.acq.osd.mil/dpap/. These may also be acquired from the Government Printing Office website, http://www.gpoaccess.gov/index.html.

1.18 ENVIRONMENTAL IMPACT

A. All waste materials generated by any work under the contract performed on a government installation shall be handled, transported, stored, and disposed of by the Contractor and by his Subcontractors at any time in accordance with all applicable Federal, State, or Local laws, ordinances, regulations, court orders, or other types of rulings having the effect of the law, including, but not limited to Executive Order 12088, 13 October 1978; the Federal Water Pollution Control Act, as amended (33 U.S.C. 1251 ET SEQ); the Clean Air Act as amended (42 U.S.C. Sec 1857 ET SEQ); the Endangered Species Act, as amended (16 U.S.C. Sec 1531, ET SEQ); the Toxic Substances Control Act, as amended (15 U.S.C. Sec 2601, ET SEQ); the National Historic Preservation Act, as amended (16 U.S.C. Sec 470, ET SEQ); the Solid Waste Disposal Act, Resource Conservation and Recovery Act (RCRA), as amended (42 U.S.C. 6901 ET SEQ); and the Archaeological and Historic Preservation Act, as amended (16 U.S.C. Sec 469, ET SEQ). Should the United States Government be held liable for any neglect or improper actions by the Contractor or any subcontractor regarding removal or disposal of any hazardous waste, the contractor shall reimburse the government for all such liability.

Also see Section 01 57 19 – “Temporary Environmental Controls” for additional

1.19 ARCHEOLOGICAL, PALEONTOLOGICAL AND ENDANGERED SPECIES FINDS

A. Any archeological finds (evidence of human occupation) or paleontological finds

(evidence of prehistoric plant or animal life) are to be reported to the Contracting Officer immediately and continue work in other areas without interruption. Protect native endangered flora and fauna and notify Contracting Officer of any construction activities that might threaten endangered species or their habitats.

1.20 POLLUTION ABATEMENT

A. All work shall be performed in a manner minimizing pollution of air, water and land as required. See section 01 57 23 “Temporary Storm Water Pollution Control” for additional

B. Transporting materials to or from the site shall be accomplished in a manner preventing materials or particles from becoming airborne. Earth materials shall be wetted or otherwise protected. Crushed aggregate, sand, asphalt, and concrete shall be contained within vehicles to prevent spillage. Tarpaulins must be fastened over load before entering surrounding streets. Removal of any materials dropped or blown off vehicles shall be the responsibility of the Contractor.

C. Burning of any material is strictly prohibited.

D. Stream beds, lakes, drainage ways, sanitary and storm sewers, etc., shall not be polluted by fuels, oils, bitumen, acids or other harmful materials. Grading shall be http://users.interline.net/jc/contract.htm http://www.acq.osd.mil/dpap/ http://www.gpoaccess.gov/index.html

01 00 00 - 11 GENERAL REQUIREMENTS

accomplished to prevent surface drainage from the construction site containing harmful amounts of sediment from draining onto adjacent areas.

E. Flushing of concrete trucks will be restricted to the location specifically constructed and designed by the Contractor for this purpose. The wash out area shall be either an above or below ground self-installed area or a pre-fabricated container. The area shall be sized sufficiently and according to EPA NPDES “Concrete Wash out Area – Best Management Practice” and Ecology BMPC154 and BMPC105. Design Standards used to be supplied to the COR for Approval.

The construction/payment of the concrete washout structure, maintenance, removal and clean-up of area to be included under the Item 01 00 00 “Mobilization”.

1.21 ENERGY AND WATER EFFICIENCY AND RENEWABLE ENERGY

A. The Government’s policy is to acquire supplies and services that promote energy and water efficiency, advance the use of renewable energy products, and help foster markets for emerging technologies.

B. The Contractor shall include the provisions of energy-using products for construction, renovation, or maintenance of a public building by acquiring energy-using products designated by the Department of Energy’s Federal Energy Management Program

(FEMP).

1.22 REFUSE, SALVAGE, WASTE DISPOSAL AND DIVERSION TRACKING

A. Also see Section 01 57 19 and 01 16 20 for additional information.

B. All work shall be done in accordance with the applicable codes and/or ordinances in force at the time of construction. It is the Contractor’s responsibility to insure that where EPA, DEQ or other such regulations control the removal, handling, installation or disposal of materials, they shall be strictly adhered to whether or not specifically referenced in the construction documents.

C. Contractor shall have data sheets available at the site on any materials used to comply with MIOSHA and EPA. Reference Contract Clause FAR 52.223-3, “Hazardous Material Identification and Material Safety Data”

D. All refuse, debris, and construction waste shall be legally disposed of off base at the

Contractor’s expense. (Reference FAR 52.236-12 “Cleaning Up.”). Accumulations of refuse on the site will not be permitted.

E. All salvage property removed and not reinstalled under this contract shall be offered to the Government and if not accepted by the COR, shall be properly disposed of at Contractor’s expense.

F. Non-Hazardous Solid Waste must be diverted to recycling, through appropriate means available to the Contractor, if such diversion is less than or equal to the equivalent cost of landfill or incineration.

01 00 00 - 12 GENERAL REQUIREMENTS

G. All excess unsuitable soil from the project shall be disposed of at a licensed disposal facility. The Contractor is responsible for all disposal costs, including testing required by the disposal facility.

H. In accordance with the Deputy Undersecretary of Defense DOD Pollution Prevention

Measure of Merit (Mom) Memorandum, HQ USAF/ILLEV, 6 August 1998, the attached Solid Waste Disposal and Diversion Tracking form must be submitted at the end of each quarter during the contract. Each quarter ends on March 31, June 30, September 30, and December 31.

I. Prior to contract close out the Contractor must supply a report including the following:

1. Amount (in tons) of non-hazardous solid waste, including construction and demolition debris, that is composted, mulched, recycled, reused, donated or otherwise diverted from a disposal facility.

2. Amount (in tons) of solid waste (including construction and demolition debris) transferred to a disposal facility (landfill).

1.23 STORAGE

A. No secure storage space will be provided by the Government. The Government will not be responsible for property belonging to, or under the present control of the Contractor.

The Contractor is to protect his materials. An unsecured, open area will be designated by the Contracting Officer for storage of construction equipment and materials during the period covered by this contract. Reference Contract Clause FAR 52.236-10, “Operations and Storage Areas”.

B. Contractor shall construct such temporary sheds as he may require for the use of his workmen and as required for tool cribs and storage of all work under this Contract.

Temporary sheds shall be confined to the space assigned by the Contracting Officer.

Sheds shall be of approved construction and wood floors, lighting and heat shall be provided in all parts used by workmen. Exterior of sheds shall be painted, all parts maintained in good condition throughout the life of the Contract, and at completion, all parts shall be removed and the premises cleaned up. Reference Contract Clauses FAR 52.236-10, “Operations and Storage Areas” and FAR 52.236-12, “Cleaning Up”.

1.24 SITE VISIT / SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK

A. Prospective bidders shall attend the pre-bid meeting where they will be escorted to the work site in order to visit the site and thoroughly familiarize themselves with the details of the work and working conditions. It is the responsibility of all bidders to have compared the premises and the site with the Specifications and Drawings, and to have satisfied themselves as to all conditions of the premises, the existing obstructions, the actual elevations, and any other conditions affecting the execution and completion of the work prior to submission of his proposal.

B. No allowances or extra construction on behalf of any Contractor will be permitted subsequently by reason of error or oversight on the part of a sub-contractor, or on account of interferences by the activities of the owner or others.

C. All dimensions shown on the drawings are based on available information or existing drawings and, to the extent possible, accurately represent existing conditions; however, 01 00 00 - 13 GENERAL REQUIREMENTS there may be some variance between existing conditions and contract drawings. The Contractor is responsible for verifying all dimensions and for reporting to the Contracting Officer any discrepancies that may affect performance of the work represented by contract drawings and specifications. Reference Contract Clause DFARS 252.236-7001 “Contract Drawings and Specifications”.

D. The Contractor acknowledges that he/she has taken steps reasonably necessary to ascertain the nature and location of the work, and that he/she has investigated and is satisfied as to the general and local conditions which can affect the work or its cost, including but not limited to:

1. Conditions bearing upon transportation, disposal, handling, and storage of materials;

2. The availability of labor, water, electric power, and roads;

3. Uncertainties of weather, water stages, or similar physical conditions at the site;

4. The conformation and conditions of the ground;

5. The character of equipment and facilities needed preliminary to and during work performance. The Contractor also acknowledges that he/she has satisfied themselves as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, including all exploratory work done by the Government, as well as from the drawings and specifications made a part of this contract. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.

E. The Government assumes no responsibility for any conclusions or interpretations made by the Contractor based on the information made available by the Government. Nor does the Government assume responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of its officers or agents before the execution of this contract, unless that understanding or representation is expressly stated in this contract.

F. The Contractor shall protect existing underground and aboveground structures which are to remain from damage. The Contractor shall provide temporary support for all structures in the areas of excavation. Where existing utilities or any other structures are damaged during construction, and which are not included for removal in the design and specifications, the Contractor shall restore them to their original condition at the Contractor's own expense. The Contractor shall notify the Contracting Officer of any damaged underground structure, and make repairs or replacements before backfilling.

G. Data and information furnished or referred to below is for the Contractor’s information.

The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

1. The indications of physical conditions on the drawings and in the specifications are the result of site investigations performed in Sept./Oct. of 2012. Ground water elevations present at the time of the borings are as shown.

01 00 00 - 14 GENERAL REQUIREMENTS

2. The contractor shall not begin excavation until all existing underground facilities within the work area have been marked in the field. Contractor shall coordinate locates with utility locators and appropriate construction management.

3. The information concerning existing underground utilities and existing conditions were compiled from surveys and available Base records and as-builts. The drawings may not reflect as-built conditions from incorrect as-builts or recent projects. Underground obstructions not shown may be encountered. The Contractor is cautioned that the Alpena CRTC, Airport, and Engineer do not guarantee the accuracy of the utility locations, and assume no responsibility for any obstructions either shown or not shown on the plans.

4. The Contractor shall determine the exact locations from available resources and other appropriate means of detection.

1.25 DIFFERING SITE CONDITIONS

A. The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the Contracting Officer of:

1. Subsurface or latent physical conditions at the site which differ materially from those indicated in this contract;

2. Unknown physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract.

B. The Contracting Officer shall investigate the site conditions promptly after receiving the notice. If the conditions do materially so differ and cause an increase or decrease in the Contractor’s cost of, or the time required for, performing any part of the work under this contract, whether or not changed as a result of the conditions, an equitable adjustment shall be made under this clause and the contract modified in writing accordingly.

C. No request by the Contractor for an equitable adjustment to the contract under this clause shall be allowed, unless the Contractor has given the written notice required;

provided, that the time prescribed in paragraph (A) of this clause for giving written notice may be extended by the Contracting Officer

D. No request by the…