The document is a Statement of Requirement (SOR) for a Self-Contained Breathing Apparatus (SCBA) bottle filling station with compressor, issued by the Alabama Army National Guard (46th CST-WMD). The solicitation (W912JA-25-Q-A003) is a 100% small business set-aside under NAICS code 333912, seeking one SCBA Fill Station with Compressor to be delivered to Montgomery, AL. The equipment must meet specific technical requirements, including the ability to fill two SCBA bottles simultaneously, have two 6000 psi fill bank tanks, digital monitoring capabilities, and comply with NFPA, CGA, and OSHA standards.
Quotes are due by 2:00 pm CST on 11 March 2025, to be submitted via email to Reginald Ellis. The government will evaluate offers based on technical compliance, price, and past performance, with the intent to award without discussions. The equipment requires a standard manufacturer's warranty, and the contractor must provide all associated documentation, including owner's and service manuals. The contract will be awarded to the most advantageous offer, considering technical specifications, reasonable pricing, and overall value to the government.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Q and As.pdf | ||
| Statement of Requirement.pdf | ||
| Statement of Requirement.pdf | ||
| Statement of Requirement.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Requirement (SOR}
1. General Information
New requirement for Self-Contained Breathing Apparatus (SCBA} bottle filling station with compressor to support CBRN RECON operations. This equipment is required by the 46th
CST-WMD in Alabama to refill air bottles and ensure operational readiness, as well as maintain health standards within National Fire Protection Association (NFPA} and 29 Code of Federal Regulations (CFR} 1910.120.
1.1. CLIN0001: Qty 001, SCBA Fill Station with Compressor
1.2. Specifications
General Requirements:
1) Must be able to fill at least two SCBA Bottles at the same time
2) Must have a minimum of two 6000 psi Fill Bank tanks
3) Must have Digital Carbon monoxide and water monitoring
4) Noise shall not exceed 76 DB at one meter
5) Compressor: HP 10, 14 cfm
6) Must be NFPA 1901, Compressed Gas Association (CGA) and Occupational Safety and Health
Administration (OSHA) compliant
7) 60 Hertz Current - 1 Phase, 208/230 volts
8) Air pressure switch to automatically start and stop the compressor based on demand
9) Low oil pressure shutdown switch
10) Compressor access door safety shutdown switch
11) Auto-drain condensate reservoir capacity shutdown switch with illuminated indicator
12) The purification system shall be sized to process 35,000 cubic feet of air at 70°F and compressed to 6000 psi between cartridge changes
13) Safety relief valve
14) Drain valve to relieve the system pressure for maintenance.
15) The enclosure shall be designed to contain the impact of suddenly expanded high pressure air and all displaced fragments in the unlikely event of a cylinder or fill component rupture.
16) Installation Required
2. Delivery, Inspection and Acceptance
2.1. Place of Delivery: 3101 Tine Avenue, Montgomery, AL 36108
2.2. Inspection and acceptance will occur at time of delivery by a government representative. A comprehensive bill of lading or delivery receipt shall accompany all deliverables that details, at minimum, all serial numbers associated with the requested cascade system and internal equipment.
3. Warranty
3.1. All equipment shall have the standard manufacturer's warranty. The Contractor shall warranty all items delivered and ensure all items are free from defects in material and workmanship under normal use and service. Additionally, without charge, repair or replace any equipment found to be defective in material or workmanship provided said equipment has been operated within standard procedures and instructions and such defects are not due to abuse, misuse or Acts of God.
4. Documentation
4.1 The contractor shall provide all owner's manuals, service manuals and any other manufacturer documentation that accompanies the purchase of this item. If any equipment installed has its own service and owner's manual these will also be provided by the contractor.