W912HV23B0003 Preproposal Conference slides.pptx
PPTX presentation 7 MB Posted
- Attached to
- FY23 AFSOC103008, Squadron Operations / MSRP Parts Warehouse / Group HQ Facilities, Yokota Air Base, Japan
- Solicitation number
- W912HV23B0003
About this file
This document contains slides from a pre-proposal conference for a federal design-bid-build construction contract. The solicitation seeks the construction of squadron operations facilities, an MRSP warehouse, and group headquarters facilities at Yokota Air Base in Japan.
The scope of work includes constructing concrete foundations and steel frame buildings with masonry or steel walls and metal roofs for the squadron operations and warehouse facilities. Functional areas for the squadron operations building include staff and administration, planning and briefing, mobility storage, life support equipment storage and maintenance. The warehouse is structured for materials handling and storage racking. All facilities require associated site improvements, utilities and infrastructure.
The pre-proposal conference covered the solicitation requirements, contracting rules, and project scope, schedule and documentation processes. Bids are due by May 26, 2023. The period of performance is 930 days from notice to proceed. Construction must follow Japanese licensing and EM 385-1-1 safety standards. Questions must be submitted through ProjNet by February 23 and the contractor must use the RMS documentation system.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Prepared by: 製作者: Brian Foster, Project Manager ブライアン・フォスター(プロジェクトマネージャー) Nakiba Jackson, Contracting Officer ナキーバ・ジャクソン(契約官) Chase Willson, Contract Specialist チェイス・ウイルソン(契約専門官) Bruce MacNicol, Technical Lead ブルース・マックニコル (技術リード) Bonitto Housen, Yokota AB Project Engineer ボニト・ハウゼン(横田空軍基地プロジェクトエンジニア) TBD, Resident Engineer 未定(工事監理事務所長) Hiroko Yamaguchi, Translator 山口博子(翻訳)
AFSOC103008 OPERATIONS AND WAREHOUSE FACILITIES
yokota air base, Japan pre-bid conference date: 31 JANUARY 2023
AFSOC103008 作戦施設及び倉庫施設の建設工事
米空軍横田基地
入札前会議 日付: 2023年1月31日
本プレゼンテーションに含まれる見解、意見及び所見は著者のものであり、他の公的な書類で示されていない場合、公式な米陸軍省の見解、方針又は決定と解釈されるべきではありません。
“The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”
.59
Welcome 歓 迎
Virtual Roll Call 実質的な参加者の点呼
Your Company name will be called. Please have one representative from your company identify themselves and identify who is on the line.
会社名をお呼びしましたら、代表の方が今回参加されている全員の方のお名前をお伝えください。
Introduction of Government Personnel 米政府関係者紹介
USACE, Japan Engineer District 米陸軍工兵隊・日本地区
All kanji I highlighted in red will have to be verified 11/17/2020 IF THERE IS ANY CONFLICT BETWEEN INFORMATION IN THESE SLIDES AND THE SOLICITATION, THE TERMS AND CONDITIONS OF THE SOLICITATION WILL GOVERN.
Discussion overview 説明会概要 Rules of Conference 説明会のルール Quick tips for Solicitations 入札公告の参考情報 Contracting requirements 契約要件
| General Scope of Work | 全般的工事内容 | |
| Construction Requirements | 工事要件 | |
| Site Visit Location | 現場視察場所 |
IF THERE IS ANY CONFLICT BETWEEN INFORMATION IN THESE SLIDES AND THE SOLICITATION, THE TERMS AND CONDITIONS OF THE SOLICITATION WILL GOVERN.
Please keep your phones on mute 電話はミュートにして下さい。
Conference will be presented in English. The Japanese translation is provided as a courtesy 本会議は英語で行われます。日本語の翻訳は厚意によるものです。
Unofficial and non-binding 非公式で法的拘束力はありません。
If there is any conflict between the information discussed during this conference and the solicitation, the terms and conditions of the solicitation will govern 当説明会で協議される情報と入札案内に矛盾がある場合は、入札案内の契約条件が優先されます。
All questions are to be submitted in writing via Projnet.
質問/問合わせは全てPROJNETを通じ書面で提出して下さい。
Rules for conference 説明会のルール
Review all the solicitation requirements 全ての入札要件を確認する。
Follow solicitation format as required 入札要件に指示されているフォーマットに従う。
Acknowledge all amendment(s) 全ての改訂(アメンドメント)を確認同意する。
Respond to every submission requirement 全ての提出要件に回答・対応する。
Quick tips for all solicitations 全ての入札公告に対する参考情報
IF THERE IS ANY CONFLICT BETWEEN INFORMATION IN THESE SLIDES AND THE SOLICITATION, THE TERMS AND CONDITIONS OF THE SOLICITATION WILL GOVERN.
IFB SOLICITATION FORMAT
IFB入札公告 書式
Standard Form 1442 フォーム1442 Section 00 10 00, Solicitation CLIN Schedule 契約項目一覧表 Section 00 21 13, Instructions to Bidders 入札者への説明 Section 00 45 00, Representation and Certifications 表明と証明書 Section 00 70 00, Conditions of the Contract 契約条件 Section 00 73 00, Supplementary Conditions 補足条件 Division 01, General Requirements 一般要件 Divisions 02 thru 33, Technical Divisions 技術要件 Drawings 図面
6/14/2018 IF THERE IS ANY CONFLICT BETWEEN INFORMATION IN THESE SLIDES AND THE SOLICITATION, THE TERMS AND CONDITIONS OF THE SOLICITATION WILL GOVERN.
Make sure to note the bid due date and time in Block 13A of SF1442.
SF1442のブロック13Aに記載された入札提出期日および時間を必ず確認
する。 Bids currently due 26 May 2023 at 1400 hrs JST.
現在、入札提出期限は2023年5月26日、日本時間午後2時。 Period for acceptance of bids shall be no less than 120 calendar days for Government acceptance (see block 13D).
政府が受諾するための入札価格の有効期間は120日間以上とする。 (ブロック13D参照) Fill out Blocks 14, 15, 17, 19, 20A, 20B, and 20C.
ブロック14, 15, 17, 19, 20A, 20B, 20Cにもれなく記入する。
STANDARD FORM (SF) 1442
SF1442
IF THERE IS ANY CONFLICT BETWEEN INFORMATION IN THESE SLIDES AND THE SOLICITATION, THE TERMS AND CONDITIONS OF THE SOLICITATION WILL GOVERN.
SECTION 00 10 00
SOLICITATION CONTRACT LINE ITEM (CLIN)
契約項目一覧
| ITEM NO. | DESCRIPTION | QUANTITY | UNIT | AMOUNT |
| BASE SCHEDULE | BASE SCHEDULE | |||
| 0001 | Construction of Squad Operations |
| JB | ¥ | |
| 0002 | Construction of Group Headquarters |
| JB | ¥ | |
| 0003 | Construction of MSRP Warehouse |
| JB | ¥ | |
| TOTAL BASE CLIN SCHEDULE | ¥ | |
| Option Schedule | Option Schedule | |
| 0004 | Landscaping (OPTION 1) |
JB
TOTAL (BASE + OPTION ITEMS) CLIN SCHEDULE ¥
IF THERE IS ANY CONFLICT BETWEEN INFORMATION IN THESE SLIDES AND THE SOLICITATION, THE TERMS AND CONDITIONS OF THE SOLICITATION WILL GOVERN.
File Name
NOTES:
1. Failure of the bidder to bid prices for all items in the CLIN Schedule may be cause for rejection of the bid as unacceptable.
2. See Section 01 20 00, for additional line item description.
3. Any reference to “proposal”, “proposer”, or “bidding schedule” shall be construed to mean “bid”, “bidder” and “CLIN schedule”
4. In accordance with FAR 52.217-5, Evaluation of Options, the Government will evaluate bids for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of option will not obligate the Government to exercise the option.
5. The Government reserves the right to exercise option item(s) by written notice to the Contractor either singularly or in any combination for up to one hundred twenty (120) calendar days after award of the Base Schedule, at the prices stated in the CLIN Schedule. Completion of the added option(s) shall continue at the same schedule as the Base Schedule unless otherwise noted in Section 00 70 00, 52.211-10, COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
6. LEGEND: JB = Job
注記:
1. 契約項目一覧表の全ての項目に対し金額を提案しない入札者は、入札が認められない場合がある。
2. 追加の契約項目内容についてはセクション01 20 00を参照。
3. 「proposal」 、「proposer」又は「bidding schedule」は「bid」、「bidder」、「CLIN schedule」と読み替える。
4. FAR 52.217-5 「オプション評価」に従い、米政府は全てのオプションの合計金額を基本要件の合計金額に加算して、契約目的に鑑み入札を評
価する。オプション評価は米政府にオプションの実施の義務を課さない。
5. 政府は契約項目一覧表の価格で基本契約の締結後最長で120日後までに、業者へ書面で通知することによりオプション項目を任意の組み合わせで行使する権利を有する。追加オプションが行使されても工事完了は、セクション00 70 00, 52.211-10、開始、施工、工事完了に記載が無ければ、基本契約と同じ工期とする。
6. LEGEND 凡例: JB = Job 作業
SECTION 00 10 00
SOLICITATION CONTRACT LINE ITEM (CLIN)
契約項目一覧
Magnitude of the Proposed Project: 工事の規模: ► ¥2,500,000,000 and ¥10,000,000,000 25億円から100億円
Requests For Information (RFIs): ALL Questions / Inquiries shall be submitted via the PROJNET Bidder Inquiry Module at: https://www.projnet.org/projnet/ . Please see the solicitation for additional details and instructions.
質問書(RFI):全ての質問/問い合わせはPROJNETのサイトhttps://www.projnet.org/projnet/ を介して提出する。追加の詳細および手順に関しては入札案内書を参照。
Requests For Information (RFIs) Due: RFI(質問書)期日: ► 11:59 (midnight) on February 23, 2023 (JST) 2023年2月23日日本時間深夜11時59分 ► The Bidder Inquiry Key is: MU7D7S-2NS9BU
入札者の照会キー: MU7D7S-2NS9BU
SECTION 00 21 13
INSTRUCTIONS TO BIDDERS 入札者への説明
IF THERE IS ANY CONFLICT BETWEEN INFORMATION IN THESE SLIDES AND THE SOLICITATION, THE TERMS AND CONDITIONS OF THE SOLICITATION WILL GOVERN.
SIGNATURE OF BIDS. Bid must be signed by an officer of the company or an individual who is authorized to sign bids for and on behalf of the company. An individual, other than an officer of the company, who signs a bid must submit evidence of his authority to sign such bid. This evidence must accompany the bid. Failure to comply with this requirement may be cause for rejection of the bid.
入札書類の署名。 入札書類は、会社を代表して入札書類に署名する権限を持つ会社の役員または個人が署名しなければなりません。役員以外の個人が入札書類に署名する場合は、署名する権限があることを示す証拠を入札書類に添付して提出しなければなりません。この要件に従わない場合は、入札が却下される可能性があります。
SECTION 00 21 13
INSTRUCTIONS IFB PROVISIONS
IFB条件の説明
IF THERE IS ANY CONFLICT BETWEEN INFORMATION IN THESE SLIDES AND THE SOLICITATION, THE TERMS AND CONDITIONS OF THE SOLICITATION WILL GOVERN.
BIDDER ELIGIBILITY 入札者適格性。 This contract will be performed in its entirety in the country of Japan and is intended only for local sources. 本契約は日本国内で全て施工され、日本の業者だけを意図しています。
Specifically, a prospective bidder must be duly authorized to operate and conduct business in Japan and must fully comply with all applicable laws, decrees, labor standards, and regulations of Japan during the performance of the resulting contracts. 特に将来の入札者は、日本で事業を運営する正式な権限を持ち、契約履行中に該当する日本の法律、条令、労働基準及び規則を全て満たさなくてはなりません。
Bidders must be registered with the Government of Japan to do construction work in Japan and possess necessary construction licenses and permits to perform work required under this solicitation at the time a bid is submitted. 入札者は、日本で建設作業を行うために日本政府に登録され、入札が提出される時点で本契約事案で必要な作業を行うために必要な建設業許可証を保有していなければなりません。
Construction license will be verified through the Government of Japan – Ministry of Land, Infrastructure, Transport, and Tourism (MILT) https://etsuran.mlit.go.jp/TAKKEN.
建設業許可証は国土交通省 https://etsuran.mlit.go.jp/TAKKENを通じて確認されます。
* See solicitation for full Bidder Eligibility provision.
入札者適格性条項の全文は入札案内を参照して下さい。
SECTION 00 21 13
INSTRUCTIONS IFB PROVISIONS
IFB条件の説明
IF THERE IS ANY CONFLICT BETWEEN INFORMATION IN THESE SLIDES AND THE SOLICITATION, THE TERMS AND CONDITIONS OF THE SOLICITATION WILL GOVERN.
Completed and Signed SF1442 SF1442の必要事項を全て記入し署名を行う。 Acknowledge SF30 Amendments (if issued) SF30改訂(アメンドメント)があれば改訂を確認し了承する。 Completed Section 00 10 00 セクション 00 10 00 の必要事項を全て記入する。 Completed Section 00 45 00 – Representations and Certifications セクション 00 45 00 - 表明と証明書の必要事項を全て記入する。 Bid Guarantee (FAR 52.228-1) -- 20% or ¥300,000,000 (whichever is less) – Also see Original Bid Bond Requirements.
入札保証ボンド(FAR 52.228-1) 20%または3億円(いずれか低い額)-入札保証ボ
ンドの原文も確認する。 Joint Venture Agreement (if applicable) ジョイントベンチャー合意書(該当する場合) Deliver Bids to: ELECTRONIC BID SUBMISSION - See solicitation for details.
入札法:電子入札法 - 詳細は入札案内を参照。 Submitted via the PIEE Solicitation Module PIEE入札モジュール経由で入札する。 Emailed Bids are strictly prohibited Eメールによる入札は認められない。
SECTION 00 21 13
SUBMISSION OF BIDS
入札書類の提出
IF THERE IS ANY CONFLICT BETWEEN INFORMATION IN THESE SLIDES AND THE SOLICITATION, THE TERMS AND CONDITIONS OF THE SOLICITATION WILL GOVERN.
Ensure the following is completed and submitted with bid:
以下も必要事項を全て記入し提出して下さい。
Corporate Certificate FAR Clause 52.204-8, Annual Representation and Certification FAR Clause 52.204-24, Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment FAR Clause 52.209-7, Information Regarding Responsibility Matters FAR Clause 52.229-11 Tax on Certain Foreign Procurements – Notice and Representation DFARs Clause 252.204-7007 ALT A, Annual Representations and Certifications DFARs Clause 252.204-7017, Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services - Representation DFARs Clause 252.229-7001, Tax Relief
SECTION 00 45 00
Representations and certifications 表明と証明書
These requirements after corporate certificate can also be updated on SAM.gov under rep and certs
6/14/2018 IF THERE IS ANY CONFLICT BETWEEN INFORMATION IN THESE SLIDES AND THE SOLICITATION, THE TERMS AND CONDITIONS OF THE SOLICITATION WILL GOVERN.
FAR Clause 52.211-10, Commencement, Prosecution, and Completion of Work
連邦調達規則(FAR) 52.211-10 作業の開始、実行及び完了
Period of Performance: 930 Calendar Days after receipt of NTP 契約期間:着工命令の受領から930歴日
FAR Clause 52.211-12, Liquidated Damages – Construction ¥419,000 for each Calendar Day of delay
連邦調達規則(FAR) 52.211-12 遅延損害-建設工事 遅延損害金1暦日に
つき419,000円
SECTION 00 70 00
CONDITIONS OF THE CONTRACT
契約条件
IF THERE IS ANY CONFLICT BETWEEN INFORMATION IN THESE SLIDES AND THE SOLICITATION, THE TERMS AND CONDITIONS OF THE SOLICITATION WILL GOVERN.
DFARS 252.225-7045, Balance of Payments Program – Construction Material Under Trade Agreements – Basic (Deviation 2020-O0019) – See solicitation for full clause.
DFARS 252.225-7045、国際収支プログラム-建設資材貿易合意-基本(逸脱 2020-O0019)-全項は入札案内を参照。
(c) The contractor shall use only domestic (U.S.) or designated country construction material in performing this contract, except for – 業者は下記を除き、本契約の実施に際し、米国製又は指定された国で製造された建設資材のみを使用すること。
Construction material valued at or below the simplified acquisition threshold in part 2 of the Federal Acquisition Regulation;
連邦政府契約規則のパート2の単純契約限度額以下の建設資材
(2) Information Technology that is a commercial item;
市販品である情報技術
The construction material or components listed by the Government as follows: See clause.
政府による建設資材又は構成部品リストは下記の通り:条項を参照
SECTION 00 70 00
IF THERE IS ANY CONFLICT BETWEEN INFORMATION IN THESE SLIDES AND THE SOLICITATION, THE TERMS AND CONDITIONS OF THE SOLICITATION WILL GOVERN.
DFARS 252.225-7045, Balance of Payments Program – Construction Material Trade Agreements – Basic (Deviation 2020-O0019) – continued
DFARS 252.225-7045、国際収支プログラム-建設資材貿易合意-基本(逸脱
2020-O0019)-続き
“Simplified Acquisition Threshold” means $250,000 「単純契約限度額」とは25万ドルです。
“Designated Country” includes Japan. See clause in solicitation for full list of designated countries.
「指定された国」には日本を含みます。指定された国の全リストは入札案内書の条項を参照して下さい。
SECTION 00 70 00
IF THERE IS ANY CONFLICT BETWEEN INFORMATION IN THESE SLIDES AND THE SOLICITATION, THE TERMS AND CONDITIONS OF THE SOLICITATION WILL GOVERN.
DFARS 252.247-7023, Transportation of Supplies by Sea 海路による輸送 Required to utilize U.S. ocean transportation 米国の海上輸送会社を利用することが要求されます。 Submit any request for use of foreign-flag vessels in writing to the Contracting Officer at least 45 days prior to the sailing date necessary to meet its delivery schedules 外国の海上輸送会社の使用を希望する場合は、納期を満たすために必要な出航日の少なくとも45日前までに、契約担当官に書面で提出すること。
SECTION 00 70 00
IF THERE IS ANY CONFLICT BETWEEN INFORMATION IN THESE SLIDES AND THE SOLICITATION, THE TERMS AND CONDITIONS OF THE SOLICITATION WILL GOVERN.
GENERAL SCOPE OF WORK
全般的工事内容 MRSP Warehouse
MRSP倉庫
Group Headquarters グループ本部
Squadron Operations 飛行中隊作戦施設
IF THERE IS ANY CONFLICT BETWEEN INFORMATION IN THESE SLIDES AND THE SOLICITATION, THE TERMS AND CONDITIONS OF THE SOLICITATION WILL GOVERN.
SITE PLAN
敷地図
Haul Route
Staging Area 資材置き場 Project Site プロジェクト現場
Reference: Drawing G-100
IF THERE IS ANY CONFLICT BETWEEN INFORMATION IN THESE SLIDES AND THE SOLICITATION, THE TERMS AND CONDITIONS OF THE SOLICITATION WILL GOVERN.
SITE PLAN
敷地図 Squadron Operations 飛行中隊作戦施設 Existing Pump House 既設ポンプ建屋 Hangar/AMU – Under Construction 格納庫/機体整備施設-建設中 Existing Simulator 既設シミュレーター MRSP Warehouse
MRSP倉庫
Existing Roads 既設道路
Existing Roads 既設道路 Group Headquarters グループ本部 Hotel (By Others) ホテル(他者による) Reference: Drawing CS101
引用:図面CS101
IF THERE IS ANY CONFLICT BETWEEN INFORMATION IN THESE SLIDES AND THE SOLICITATION, THE TERMS AND CONDITIONS OF THE SOLICITATION WILL GOVERN.
Squadron Operations Floor Plans 飛行中隊作戦施設 平面図
First Floor 1階 Second Floor 2階
AFE
Mobility/Supply Storage 機動性/補給品保管 Training 訓練室 Mission Planning ミッション計画室 Operations 作戦室 Gear Storage 用具保管室 Vault 貴重品倉庫 Break 休憩室 Command Suite 司令部室 Reference: Drawing 3A-131 引用:図面3A-131
IF THERE IS ANY CONFLICT BETWEEN INFORMATION IN THESE SLIDES AND THE SOLICITATION, THE TERMS AND CONDITIONS OF THE SOLICITATION WILL GOVERN.
GENERAL SCOPE OF WORK
全般的工事内容
Squadron Operations Exterior/Section 飛行中隊作戦施設 外観/断面図
Gear Storage 用具保管室 Mission Planning ミッション計画室 Break 休憩室 Training 訓練室 Reference: Drawings 3G-001 & 3A-132 引用:図面3G-001 & 3A-132
IF THERE IS ANY CONFLICT BETWEEN INFORMATION IN THESE SLIDES AND THE SOLICITATION, THE TERMS AND CONDITIONS OF THE SOLICITATION WILL GOVERN.
Group Headquarters Floor Plan グループ本部 平面図
Medical 医務室 Command Suite 司令部室 Open Office 広い事務室 Open Office 広い事務室 OSS Intel
OSS諜報室
Reference: Drawing 4A-131 引用:図面4A-131
IF THERE IS ANY CONFLICT BETWEEN INFORMATION IN THESE SLIDES AND THE SOLICITATION, THE TERMS AND CONDITIONS OF THE SOLICITATION WILL GOVERN.
GENERAL SCOPE OF WORK
全般的工事内容
Group Headquarters Exterior/Section グループ本部 外観/断面図
Reference: Drawings 4G-001 & 4A-132 引用:図面4G-001 & 4A-132
IF THERE IS ANY CONFLICT BETWEEN INFORMATION IN THESE SLIDES AND THE SOLICITATION, THE TERMS AND CONDITIONS OF THE SOLICITATION WILL GOVERN.
MRSP Warehouse Floor Plan
MRSP倉庫 平面図
Staging Parts Storage Office Reference: Drawing 5A-131 引用:図面5A-131 部品保管 集結場所 事務所
IF THERE IS ANY CONFLICT BETWEEN INFORMATION IN THESE SLIDES AND THE SOLICITATION, THE TERMS AND CONDITIONS OF THE SOLICITATION WILL GOVERN.
GENERAL SCOPE OF WORK
全般的工事内容
MRSP Warehouse Exterior/Section
MRSP倉庫 外観/断面図
Staging Parts Storage Office Reference: Drawings 5G-001 & 5A-132 引用:図面5G-001 & 5A-132 部品保管 事務所 集結場所
IF THERE IS ANY CONFLICT BETWEEN INFORMATION IN THESE SLIDES AND THE SOLICITATION, THE TERMS AND CONDITIONS OF THE SOLICITATION WILL GOVERN.
File Name Pre-Construction Submittals after NTP and prior to the project kickoff conference.
This list is not all inclusive; the Contractor shall review all the requirements prior to commencing work.
着工命令後かつキックオフ会議の前までに必要な着工前提出物の一覧です。これが全てではないので、業者は着工前の要件を全て注意深く確認して下さい。
Project Schedule プロジェクト日程 SPEC Section 01 32 01
Submittal Register 提出物登録 SPEC Section 01 33 00
Accident Prevention Plan 事故防止計画 SPEC Section 01 35 26
Contractor Quality Control Plan 業者品質管理計画 SPEC Section 01 45 00
Environmental Protection Plan 環境保護計画 SPEC Section 01 57 19
CONSTRUCTION GENERAL REQUIREMENTS
工事の一般要件
File Name
CONSTRUCTION GENERAL REQUIREMENTS
工事の一般要件 Below is a summary of Pre-Construction Submittals required after Award and prior to the project kickoff conference. This list is not all inclusive; the contractor shall review all the requirements prior to commencing work.
以下は契約締結後かつプロジェクトのキックオフ会議前までに必要な着工前提出物一覧です。これが全てではないので、業者は着工前の要件を全て確認して下さい。
| Preconstruction Submittals List | |||
| No | Submittals/Activities | Submission Dates | Specifications |
| 1 | Organization Chart with key personnel qualifications | 5 days after NTP | 01 11 00.00 10 1.6 |
| 2 | Qualifications & background history of interpreter | 15 days after Award | 01 11 00.00 10 1.6.3 |
| 3 | Contract cost breakdown | 30 days after NTP | 01 20 00 3.3 |
| 4 | Preliminary Project Schedule | 15 days after NTP | 01 32 01.00 10 3.4.1 |
| 5 | Initial Material Status Report | 15 days after NTP | 01 33 00 1.16 |
| 6 | Accident Prevention Plan (AAP) | 15 days prior to PreCon | 01 35 26 1.7 |
| 7 | Contractor Quality Control Plan (CQC) | 15 days after NTP | 01 45 00.00 10 3.2 |
| 8 | Environmental Protection Plan (EPP) | 15 days after Award | 01 57 19.01 1.9 |
CONSTRUCTION GENERAL REQUIREMENTS
工事の一般要件 This project is required to complete documentation through the RMS Contractor Module system. New Project now uses RMS 3.0. https://rmsdocumentation.com/ (本プロジェクトはRMSの業者側モジュールを通して書類提出を完成させることが義務付けられています。新しいいプロジェクトは現在RMS 3.0. https://rmsdocumentation.com/ 使用しています。)
This contract is required to implement the Three Phase Inspection process for all features of work as part of the Contractor’s Quality Control Plan.
(本契約は、業者の品質計画の一部として、全ての工種項目において3段階検査プロセスに従うことが義務付けられています。)
Project schedule reviews and updates shall be made and submitted monthly with the requested progress payments.
(工期全体のプロジェクト日程を作成、更新し、そして毎月の進捗に応じた支払いの請求時に提出しなければなりません。)
The project will be required to follow EM 385-1-1 Nov 2014.
(本プロジェクトは2014年11月バージョンのEM385-1-1に従わなくてはなりません。)
Contract regular working hours are Mon~ Fri 0700~1700. Weekend, federal holiday, and other than normal working hours may be arranged if coordinated in advance and if approved by the government.
(契約の通常の作業時間は平日午前7時から午後5時までです。もし事前に調整し承認されれば、週末、米国の祭日及び他の通常の作業時間以外の作業時間を交渉しても構いません。)
TYPICAL CHALLENGES FOR CONTRACTORS
業者が頻繁に直面する課題 Communication (コミュニケーション) Lost in translation (通訳/翻訳の誤差により間違った理解をしてしまう) Do your research (下調べや準備を行なってください) Understand the differences between construction in Japan vs. US MILCON (一般的な日本の工事と米国予算工事の違いを理解してください) Scheduling (日程) Understanding requirements (要求事項を理解すること) Impacts to project schedules on long lead items (調達に時間のかかる材料はプロジェクト日程に影響を与える) Submittal documentation (承認願い提出物の書類化) Not reading and understanding the specifications (仕様書を読んでいない) Impacts to project schedules (プロジェクト日程に影響がある) U.S. manufactured products vs. Japanese manufactured products (米国製品vs. 日本製品) Working with multiple stakeholders at Yokota Air Base (横田空軍基地の多数の関係者と働く必要があるということ) Using Form AF103 (書式AF103を使うこと) Airfield/Base access (滑走路/基地への出入り)
SITE VISIT LOCATION
現場視察場所
SITE VISIT LOCATION
現場視察場所
THANK YOU
どうもありがとうございました image9.png image10.png image11.png image12.png image13.png image14.png image15.png image16.png image17.png image18.png image19.png image20.png image21.png image22.png image23.png image24.jpg image1.png image2.png image3.png image4.png image5.png image6.png image7.png image8.png