B.1.1 - Abstract of Offers - W912HV20B0008 Repl Water Supply Ctrl Sys CZ R1.pdf
PDF 207 KB Posted
- Solicitation number
- W912HV-20-B-0008
About this file
This abstract of offers summarizes bids received for the Replace Water Supply Control System project at Camp Zama, Japan. The U.S. Army Engineer District in Japan received three bids in response to solicitation W912HV-20-B-0008 by the August 20, 2020 deadline. Bid amounts were 273 million Japanese yen by Johnson Controls, 206.5 million Japanese yen by an unnamed offeror, and 260.7 million Japanese yen by an unnamed offeror. All bids included the required 20% bid bond and acknowledged the three amendments issued. The government estimate for the project was between 500 million and 1 billion Japanese yen. The project scope involves replacing the water supply control system across four buildings on the base with a new central controller and localized control panels.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 3 PAGES
7A. ITEM
NO.
7C. EST.
QUANTITY
D.
UNIT
E. UNIT
PRICE
F. ESTIMATED
AMOUNT
D. UNIT
PRICE
D. UNIT
PRICE
0001 1 JB
JB ¥ 701,187,797 JB JB
¥ 701,187,797
¥ 701,187,797
AUTHORIZED FOR LOCAL REPRODUCTION NOTE: If more than two offers are received, continue on OF 1419A. OPTIONAL FORM 1419 (11-88) Previous edition is usable
ABSTRACT OF OFFERS - CONSTRUCTION
1. SOLICITATION NUMBER 2. DATE ISSUED 3. DATE OPENED PAGE OF
W912HV-20-B-0008 5/15/2020 8/20/2020
4. ISSUING OFFICE
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
NAME AND TITLE OF CERTIFYING OFFICIAL (Type)
U.S. Army Engineer District, Japan Norman G. Mackie, Contracting Officer
SIGNATURE DATE SIGNED
5. PROJECT TITLE
8. GOVERNMENT ESTIMATE
(Check A, B or C and complete D, E, and F)
9. OFFERS
Replace Water Supply Control System, Camp Zama, Japan NO. 1 NO. 2
A. OFFEROR A. OFFEROR
A. HIRED LABOR ACTY Johnson Controls
B. REASONABLE CONTRACT
(Without Profit)
B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount)
Bid Bond, 20%
7B. DESCRIPTION OF OFFERED ITEM E. ESTIMATED
AMOUNT
E. ESTIMATED
AMOUNT
Bid Bond, 20%
6. NUMBER OF AMENDMENTS ISSUED
C. REASONABLE CONTRACT
(Including Profit)
C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED
3 No Yes
Replace Water Supply Control System, Camp Zama, Japan ¥ 273,000,000 ¥ 206,500,000
Total Base Schedule ¥ 273,000,000 ¥ 206,500,000
TOTAL PROPOSAL ¥ 273,000,000 ¥ 206,500,000
3 PAGES
D. UNIT
PRICE
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
0001 1 JB JB
AUTHORIZED FOR LOCAL REPRODUCTION OPTIONAL FORM 1419A (11-88)
Previous edition is usable
¥ 260,700,000
¥ 260,700,000
A.
ITEM
NO.
B.
ESTIMATED
QUANTITY
C.
UNIT
Yes
E. ESTIMATED
AMOUNT
Total Base Schedule
C. AMENDMENTS ACKNOWLEDGED
¥ 260,700,000
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
3. CONTRACT ITEMS C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED
A. OFFEROR
B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount)B. BID SECURITY (Type and amount)
Bid Bond, 20% B. BID SECURITY (Type and amount)
ABSTRACT OF OFFERS - CONSTRUCTION
CONTINUATION SHEET
1. SOLICITATION NUMBER PAGE OF
W912HV-20-B-0008 2
INSTRUCTIONS Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation Sheet will accommodate 13 contract items to conform to the number of items which can be entered on the OF1419. Use additional OF1419's for contract items in excess of 13 and attach additional continuation Sheets (OF 1419A) as needed.
TOTAL PROPOSAL
2. PROJECT TITLE 4. OFFERS (Continued) Replace Water Supply Control System, Camp Zama, Japan
NO.3 NO.4 NO.5 NO.6
A. OFFEROR A. OFFEROR A. OFFEROR
TECC
| OF1419 |
| OF1419A1 |
| 2020-08-21T08:30:01+0900 | |
| MACKIE.NORMAN.G.1161658975 |