Abstract of Bids - W912HN25BA020.pdf
PDF 354 KB Posted
- Solicitation number
- W912HN25BA020
About this file
This is an Abstract of Offers - Construction document for a 100% Small Business Set-Aside Procurement by the Department of the Army, Corps of Engineers, Savannah District. The project is to construct fixed wing runway shoulders at Fort Benning, Georgia, with Project Number 100818. The solicitation (W912HN25BA020) was issued on 6-Aug-25 and opened on 11-Sep-25, with two amendments issued.
Six contractors submitted bids for three construction phases, with total bid amounts ranging from $14,772,900 to $16,985,347. The government estimate was $14,380,437. Bidders included C&C Contractors, LLC; Don Jones Construction Co., Inc.; Warren-RC Joint Venture; Medvolt Construction Services LLC; and Semper Tek CMS JV, LLC. The project is divided into three phases: Runway Shoulder Phase 1, Phase 2, and Phase 3, each to be completed as a job. Bid security and amendments were acknowledged by all offerors, and the document contains detailed pricing information for each phase and contractor.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2. DATE ISSUED 3. DATE OPENED PAGE OF PAGES
6-Aug-25 11-Sep-25 1 2
DATE SIGNED
11-Sep-25
20% $3,000,000.00 20% $3,000,000.00
7A.
ITEM
NO.
7B. DESCRIPTION OF OFFERED ITEM
7C. EST
QUANTITY
D.
UNIT
E. UNIT
PRICE
F. ESTIMATED
AMOUNT
E. UNIT
PRICE
F. ESTIMATED
AMOUNT
E. UNIT
PRICE
F. ESTIMATED
AMOUNT
0001 Construct Runway Shoulder, Phase 1, Complete 1 Job $1,341,185.64 $1,341,185.64 $2,470,267.00 $2,470,267.00 $2,759,084.00 $2,759,084.00
0002 Construct Runway Shoulder, Phase 2, Complete 1 Job $1,502,768.08 $1,502,768.08 $2,912,185.00 $2,912,185.00 $3,181,786.00 $3,181,786.00
0003 Construct Runway Shoulder, Phase 3, Complete 1 Job $4,659,821.01 $4,659,821.01 $8,997,985.00 $8,997,985.00 $9,354,619.00 $9,354,619.00
$7,503,774.73 $14,380,437.00 $15,295,489.00
“Source Selection Information -- See FAR 2.101 and 3.104.”
NO. 1
Contracting Officer
W912HN25BA020
Department of the Army, Corps of Engineers
ABSTRACT OF OFFERS - CONSTRUCTION
9. OFFERS
NO. 2
I CERTIFY that I have opened, read, and recorded on this abstract all offers received In response to this solicitation.Savannah District Contracting Office
1. SOLICITATION NUMBER:
4. ISSUING OFFICE:
Gerard F. Leo
8. GOVERNMENT ESTIMATE
5. PROJECT TITLE
SIGNATURE
NAME AND TITLE OF CERTIFYING OFFICIAL (Type)
100 W Oglethorpe Ave.
Savannah, GA 31401
PROJECT NUMBER: 100818
CONSTRUCT FIXED WING RUNWAY SHOULDERS
FORT BENNING,GEORGIA
100% SMALL BUSINEES SET-ASIDE PROCUREMENT
Notasulga, AL 36866 B. BID SECURITY (Type and Amount)
C&C Contractors, LLC Don Jones Construction Co., Inc.
6. NUMBER OF AMENDMENTS ISSUED:
X
B. BID SECURITY (Type and Amount)
A. HIRED LABOR
B. REASONABLE CONTRACT
X (Without Profit)
A. OFFEROR(Check A, B or C and complete D, E, and F)
4923 Armour Road
A. OFFEROR
209 Lyon Street
C. AMENDMENTS ACKNOWLEDGEDC. REASONABLE CONTRACT
X (IncludingProfit) YES
Columbus, GA 31904
YES
C. AMENDMENTS ACKNOWLEDGED
TOTAL BID:
PAGE OF PAGES
2 2
20% 20% 20% $3,000,000.00
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
0001 1 Job $2,571,351.00 $2,571,351.00 $2,805,450.00 $2,805,450.00 $2,711,500.00 $2,711,500.00
0002 1 Job $3,189,734.00 $3,189,734.00 $3,462,248.00 $3,462,248.00 $3,039,300.00 $3,039,300.00
0003 1 Job $10,089,176.00 $10,089,176.00 $10,717,649.00 $10,717,649.00 $9,022,100.00 $9,022,100.00
$15,850,261.00 $16,985,347.00 $14,772,900.00
NO. 6
C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED
CONSTRUCT FIXED WING
RUNWAY SHOULDERS
C. AMENDMENTS ACKNOWLEDGED
B. BID SECURITY (Type and Amount) B. BID SECURITY (Type and Amount)
3. CONTRACT TERMS
Kansas City, MO 64108 Lexington,KY 40511
W912HN25BA020
Abstract of Offers - Construction Sheet, when more than 2 offers are received on a construction project. Each Continuation Sheet will accommodate 15 contract items to conform to the number of items which can be entered on page 1. Use additional continuation sheets for contract items in excess of 15 and attach additional continuation Sheets as needed.
1. SOLICITATION NUMBER:
“Source Selection Information -- See FAR 2.101 and 3.104.”
ABSTRACT OF OFFERS -
CONSTRUCTION CONTINUATION SHEET
B. BID SECURITY (Type and Amount) 100% SMALL BUSINEES SET-ASIDE
PROCUREMENT
A. OFFEROR A. OFFEROR
Warren-RC Joint Venture
Greenwood, MS 38930 310 West Park Avenue
PROJECT NUMBER: 100818
4. OFFERS (Continued)2. PROJECT TITLE:
A. OFFEROR
B. BID SECURITY (Type and Amount)
NO. 3 NO. 4 NO. 5
YES
A. OFFEROR
C. AMENDMENTS ACKNOWLEDGED
848 Nandino Blvd., Suite O Medvolt Construction Services LLC Semper Tek CMS JV, LLC 2345 Grand Blvd., Suite 700
A.
ITEM
NO.
C.
UNIT
B.
ESTIMATED
QUANTITY
FORT BENNING,GEORGIA
YESYES
TOTAL BID:
| 2025-09-11T13:17:13-0400 | |
| LEO.GERARD.F.1021058803 |
File details come from the government source that posted it. Updated .