Amendment_0002_-_(04-26-18)_-_W912HN-17-R-0023_-_Thurmond_Hybrid.pdf
PDF 692 KB Posted
- Attached to
- Thurmond Project Operations and Maintenance
- Solicitation number
- W912HN-17-R-0023
About this file
Amendment 0002 updates various sections of the PWS and Sections L, updates the clause matrix, and updates Appendices H and I.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912HN-17-R-0023
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
A. Update Paragraph 3.9 (See Summary of Changes).
B. Update Paragraph 3.19.9 (see Summary of Changes).
C. Update Paragraph L.5.1.c (see Summary of Changes).
D. Update Paragraph L.5.2.2.1 (see Summary of Changes).
E. Update Paragraph L.5.2.3.g.8 (see Summary of Changes).
F. Add FAR Clause 52.222-43 -- Fair Labor Standards Act and Service Contract Labor Standards -- Price Adjustment (Multiple Year and Option Contracts (see Summary of Changes).
G. Update Appendices H and I (See Appendices dated 25-Apr-2018).
All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 94
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 26-Apr-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912HN-17-R-0023
X 9B. DATED (SEE ITEM 11)
30-Mar-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
26-Apr-2018
CODE
USACE - SAVANNAH DISTRICT
100 W. OGLETHORPE AVE
SAVANNAH GA 31401
W912HN 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
PERFORMANCE WORK STATEMENT
TECHNICAL PROVISIONS
TABLE OF CONTENTS
THURMOND PROJECT
Section Section Title______________________________________________________
TP-1 General Information
TP-2 Labor
TP-3 Cleaning Services
TP-4 Mowing Services
TP-5 Preventive Maintenance
TP-6 Repairs to Buildings, Structures, Security Systems, Mechanical, Electrical, Water Supply and Sewage Disposal Systems
TP-7 Upkeep of Grass, Trees and Landscaped Areas
TP-8 Repairs to Government Equipment, Vehicles, Boats, Trailers and Attachments
TP-9 Preservation and Repair of Earthen Dams, Dikes, Riprap, Ramps, Beaches, Berms, Bulkhead Walls and Impact Sites
TP-10 Preservation and Repair of Signs, Trails, Walkways, Roads, Barricades, Gates, Parking Areas, Wheel Stops, Fencing and Posts
TP-11 Natural Resource Management
TP-12 Boundary Line Clearing and Marking
TP-13 Upkeep of Aids to Navigation and Courtesy Docks; Encroachment/Refuse
Removal
TP-14 Minor Construction and Shoreline Stabilization
TP-15 Emergency Spill Response Support
PRS Performance Requirements Summary
TP-1 GENERAL
TP-1.0 PURPOSE: The purpose of this contract is to provide for maintenance, repair, minor construction, and operation of the Thurmond Project to include the Project Manager’s Office, campground and day-use parks, boating access areas, dam, power plant, New Savannah Bluff Lock and Dam, the Richard B. Russell Project, and other project resources as specified in Section C.
TP-1.1 SCOPE OF WORK: This contract is a hybrid firm fixed price contract with cost plus fixed fee elements.
Section C is divided into fifteen (15) Technical Provisions (TP) with portions of TP-1 either firm fixed price or cost reimbursement (see TP-1.27), TPs 2-5 firm fixed price, and TPs 6-15 cost reimbursement. All labor and supervision will be charged under TP-2, Labor, unless it is subcontracted, in which case it will be charged to the applicable technical provision.
TP-1.1.1 Except as provided for elsewhere in these specifications, the contractor will furnish all necessary management, personnel, materials, supplies, parts, tools, equipment, vehicles and fuel. All contractor-furnished items are required to be as specified and in strict accordance with all terms, conditions, general, specific and technical provisions, drawings, attachments, appendices, etc. contained herein or incorporated by reference.
TP-1.1.2 The contractor’s work and responsibility includes, but will not be limited to, all planning, programming, administration, quality control and management necessary to assure that all services and minor construction are performed in accordance with the contract and all applicable laws, regulations, codes, or directives. The contractor will ensure that all work meets or exceeds quality standards, Appendix A and tolerances specified or included in referenced documents and applicable publications in TP-1.2. The contractor will perform all related contractor administrative services necessary to perform the work such as supply, procurement, quality control, contractor financial control, and maintenance of accurate and complete records and files.
TP-1.1.3 Areas of work to be performed by the contractor are contained in drawings as specified in Section J - List of Attachments.
TP-1.2 Applicable Documents and References: The contractor will perform technical work in accordance with the following individual standards and codes, manuals, and other documents as applicable:
- Underwriters Laboratories, Inc.
- National Electrical Code
- National Fire Protection Association
- American Society of Heating, Air Conditioning, and Refrigeration Institution
- American Society of Heating, Refrigeration, and Air Conditioning Engineers
- American Welding Society D1.1, D1.3, D1.4
- American National Standards Institute
- American Concrete Institute
- Asphalt Institute
- National Plumbing Standards Code Illustrated
- American Society for Testing and Materials
- GA or SC DOT Standard Specifications for Construction of Roads and Bridges (Latest Edition)
- American Association of Nurserymen, Inc.
- Vehicle and Equipment Manufacturer's Repair and Operating Manuals
- ER 1130-2-540 - "Environmental Stewardship Operations and Maintenance Policies”
- EP 1130-2-540 - "Environmental Stewardship and Maintenance Guidance and Procedures”
- Outdoor Recreation at Civil Works Water Resource Projects
- ER 1130-2-550 - "Recreation Operations and Maintenance Policies”
- EP 1130-2-550 - "Recreation Operations and Maintenance Guidance and Procedures”
- EM 385-1-1 - "Safety and Health Requirements Manual", revised 30 November 2014
- ER 700-1-1 - USACE "Supply Policies and Procedures"
- EP 1165-2-316 - "Rules and Regulations Governing Public Use of Corps of Engineers Water Resource Development Projects"
- U. S. Army Corps of Engineers Sign Standards Manual EP 310-1 6a and EP 310-1 6b
- CFR Title 36 - Code of Federal Regulations
- 40 CFR 260
- Occupational Safety and Health Act (OSHA) current standards
- ER/EP 200-2-3 – “Environmental Compliance Policies”
- EM 1110-1-400 – “Recreation Facility and Customer Service Standards”
- ER 1110-2-400 – “Design of Recreation Sites, Areas, and Facilities”
- U.S. Consumer and Product Safety Commission “Public Playground Safety Handbook”
TP-1.2.1 Permits: All county, state, and federal rules and regulations governing sanitary standards of drinking water, protection of public water sources and solid waste disposal will be met and maintained throughout the performance of the work specified under this contract.
TP-1.2.2 Applicable Documents:
A. EPA 40 CFR CH.1 (7-1-89 Edition) B. South Carolina Health and Environmental Control Department, Solid Waste Management, Title 44
Chapter 55, and Title 61 C. Georgia DNR EPD Chapter 391-3-4 Solid Waste Management
TP-1.3 Location of Work Sites: Project work sites are located in Columbia, Elbert, Lincoln, Warren, McDuffie, Hart, Richmond and Wilkes Counties in Georgia, and Abbeville, Aiken, Anderson, and McCormick Counties in South Carolina. The Thurmond Project Manager’s Office, Power Plant and Dam are located on U.S. Highway 221 in South Carolina. The remaining work sites, such as campgrounds, day use parks, Russell Project, New Savannah Bluff Lock and Dam and other project lands, are located throughout the Savannah River Basin of the twelve-county area.
Reference Appendix B for further information on project and park locations.
TP-1.4 Other Contracts: The government may undertake or award other contracts. The contractor will fully cooperate with such other contractors and government employees and carefully fit their own work to such other additional work as may be directed by the Contracting Officer’s Representative (COR). The contractor will not commit or permit any act which will interfere with the performance of work by another contractor or by government employees. The COR may alter the work schedules of the other contractors, government employees, or the contractor, to avoid possible conflicts.
TP-1.4.1 Transition: At both contract commencement and closeout, the contractor will ensure the continuity of service while implementing its transition plan for all affected activities to preclude any adverse impact on the mission. The contractor will implement the actions necessary for a smooth transition of operations. During this period, which will not exceed fourteen (14) calendar days, the contractor will make all preparations and conduct as many on site investigations as deemed necessary to commence or conclude full performance of work under the contract. The contractor will provide a sufficient number of personnel to ensure effective transfer of all work in progress so as not to impact mission accomplishment. A government and contractor inspection and documentation of the condition of all government furnished equipment and facilities will be completed during this time so that an accurate account of all items can be documented.
TP-1.5 Inclement Weather and Holiday Work: The contractor will maintain the schedule of services regardless of inclement weather. Exceptions can be approved by the COR when severe conditions make it impracticable or dangerous to perform the work. During the recreation season, certain services may be required 7 days a week, including holidays.
TP-1.6 Contractor’s Facilities: During the performance of this contract the government will make available for the contractor’s use the existing government service area compound located at 220 Clarks Hill Hwy in Clarks Hill, South Carolina. Appendix C identifies buildings and other facilities within the provided service area. The government will provide water and electric services and pay the associated costs at these facilities. The contractor will be responsible for establishing and maintaining telephone and internet service at the contractor’s facilities, and the cost will be a fixed price expense. Additionally, the government will provide five storage rooms within the Thurmond and Russell Power Plants for the contractor’s use for performing janitorial services. These rooms are located on the 3rd and
Generator floors at Thurmond, approximately 200 Sq. Ft. each, and 3 at Russell located at the Erection Bay, the Generator Floor and the fishing pier outside the plant and consisting of approximately 430 Sq. Ft.
TP-1.7 Mobilization and Start-Up: The contractor will provide a plan for the mobilization of equipment, personnel and inventory necessary for the performance of services immediately following award of the contract. The plan should clearly indicate a realistic timeframe for the initiation of prompt contract services to minimize performance delays in the applicable technical provisions.
TP-1.8 Safeguarding Government and Contractor Property: The contractor will cooperate with government personnel in safeguarding government property. The contractor will be responsible for reporting to the COR and appropriate local law enforcement agencies, all acts of vandalism, larceny, pilferage, or other damage on the day of occurrence.
In all instances where government property and/or equipment is damaged by contractor employees, a full written report of the incident and extent of such damage will be submitted to the COR within two work days (less weekends and holidays) of the occurrence.
TP-1.9 Identification of Contractor Employees, Vehicles and Equipment: Within thirty days of award, the contractor will provide to his employees (except management and clerical) uniform shirts which must be worn while performing maintenance or other work associated with this contract. Company identification will be accomplished by a patch on the breast pocket or left shoulder. Identification methods will be employed for any subcontractor employees working in the power plant. Vehicles and equipment will also be identified with company name or logo. Uniforms will be charged under TP-2, Labor. While working in power plant facilities, the contractor will comply with current guidance for identification requirements.
TP-1.10 Pre Work Conference: The contractor will attend a pre-work conference at which time the COR will establish the line of authority and government procedures for contractual, administrative and work matters. A review of critical aspects of the contract will be conducted as well as attention brought to specific FARs, technical and special contract clauses. At the pre-work conference, the contractor will submit a detailed accident prevention plan, prepared in accordance with EM-385-1-1 dated 30 November 2014, Section 1, Program Management, for COR review and approval. The contractor will submit at the pre-work conference, or as otherwise required and appropriate in the specifications, the following plans, programs and certificates:
- Section H Required Insurance (52.228-4002)
- TP-1.7 Mobilization and Start-Up Plan
- TP-2.4 Letter of Authority for Superintendent
- TP-1.13 List of Phone Numbers
- TP-1.14 Pesticide Plan
- TP-1.14.1 Pesticide Usage
- TP-1.15 Contractor Quality Control (CQC) Plan
- TP-1.21 Accident Prevention Plan
- TP-1.23 Inventory Control and Property Management Plan
- TP-1.16 Preventive Maintenance Plan
TP-1.10.1 A thorough review, discussion and understanding of the firm fixed price and cost reimbursement technical provisions will be reached.
TP-1.10.2 A brief review of the program submittals as referenced in paragraph TP-1.10 will be performed. A letter of record documenting all pre-work conference discussions will be furnished by the government to all attendees.
TP-1.11 Government Furnished Equipment: The government will furnish equipment listed in Appendix D for work to be accomplished as outlined in this scope of work. Government furnished equipment repairs will be a cost reimbursable expense under TP-8. Equipment replacement will be accomplished by the Corps or under level II services, as determined by the COR.
TP-1.11.1 Durables: The contractor will be provided with additional government furnished equipment that is considered expendable or durable property and thus is not listed on property records as accountable property. This equipment includes items such as power tools, hand tools, etc. that are currently being used on the project by the existing Operations and Maintenance (O&M) contractor. Inventory will be completed prior to existing contract close-out and then issued to the new contractor after award. Appendix E, Durable Tools and Equipment, provides a representative list of accountable property available. Durable tools and equipment repairs will be a cost-reimbursable expense under TP-8. Replacements will be accomplished by the Corps or under level II services, as determined by the
COR.
TP-1.12 Records and Cost Schedule Plan: The contractor will have a cost schedule plan with a work breakdown structure of anticipated cost estimates incurred for each TP for each month of the contract (reference Appendix F).
The plan will be updated monthly. Daily written records will be maintained for all maintenance, repair, and operation activities. The contractor will keep accurate and complete records of these costs by business line and TP and provide to the COR monthly, as well as cumulatively for each contract year. Cost data for each activity will be maintained and is subject to government audit. This cost data will include labor (in hours and dollar value), supplies, materials, or parts costs for each separate scheduled work task. Separate work repair records and reports will be maintained on vehicles and equipment, to include maintaining separate records for vehicles the Corps leases from GSA.
TP-1.12.1 Records: The contractor will maintain as-built sketches of any changes occurring as a result of any repairs to structures, facilities and/or systems. Copies of these records will be provided to the COR.
TP-1.12.2 Capital Improvements: The contractor will provide to the COR specific information relating to the description and cost of each capital improvement accomplished during the performance of this contract. Specifics, as to necessary information to be included in the form and submittal frequency, will be established at the pre-work conference.
TP-1.13 Emergency Services: The contractor will furnish, and keep current, an on-call roster (a list of personnel to contact) in the event emergency repairs or services become necessary 24 hours per day, 7 days per week. The contractor will ensure contact can be made with these individuals by phone within one (1) hour of notification.
Response with appropriate personnel to perform necessary repairs will take place within two (2) hours of initial notification and work will continue until an emergency no longer exists. All unscheduled/emergency services in TPs 1-5 will be handled as Level II services per TP-1.26.2.
TP-1.14 Pesticide Applications: All pest control products and application methods will be in accordance with ER- 1130-2-540, a copy of which will be provided to the contractor at the pre-work orientation. The contractor will submit, NLT 30 days after award of the contract, a pesticide application plan detailing chemicals to be used, application rates for each, user and public safety measures, applicator licensing procedures, safety data sheets, a disposal plan for unused chemicals and areas anticipated to be treated. Areas to be treated may be grouped by use, i.e., beaches, playgrounds, food plots, buildings, etc. No pesticides will be applied prior to approval of this plan.
TP-1.14.1 The contractor will provide to the COR, NLT 30 November annually, a description of the anticipated quantity of the various chemicals intended for use the upcoming year. The contractor will also provide to the COR, NLT 15 January of each calendar year, a complete listing of actual pesticide applications performed during the previous year. Applications will be recorded on the form as attached in Appendix G.
TP-1.15 Contractor Quality Control (CQC): The contractor will develop and maintain an effective quality control (QC) plan incorporating a preparatory, initial, and final inspection process. A preliminary draft of the plan will be submitted for approval at the pre-work conference. The contractor will complete and resubmit the QC plan revision within 30 calendar days after receiving the COR’s review comments. The plan must include an organizational chart identifying lines of authority, letters of appointments detailing specific duties, responsibilities and limitations, and positions within the contractor’s organization.
TP-1.15.1 The CQC will provide for the preparatory planning and inspection of all work activities to ensure conformance to specifications, preparatory inspection agreements, drawings, and referenced documents. The CQC will also be responsible for inspection and documentation of findings for contract work, inventory control, procurement activities, safety implementation and other areas of contract performance. The CQC will not be directly responsible for the direction of on-site corrective actions related to performance deficiencies.
TP-1.15.2 Government quality assurance personnel will assure that contractor quality control is complete, but the presence or absence of government quality assurance will not relieve the contractor of its responsibility for the proper execution of work in accordance with the contract.
TP-1.15.3 The contractor will propose a compliance form that will be approved by the COR for use for all compliance inspections. This recorded information will be provided to the superintendent, and a copy furnished to the COR, within 24 hours following the period of performance the report covers. The form should make provisions to address safety, equipment usage, weather, personnel, type of work being performed, performance results, QC testing and results, discussions with government personnel, directions and agreements, as a minimum.
TP-1.15.4 The text of compliance inspection reports will address acceptable, as well as deficient, performance in management, quality control and workmanship. The CQC is to evaluate performance in all respects and report to management, through daily reports, their findings and other observations concerning the above. The reports must also recommend corrective action to the superintendent, as well as document superintendent-directed corrective actions.
If, in the opinion of the COR, recurrent deficiencies indicate that the quality control system is inadequate, corrective action will be taken as directed by the COR.
TP-1.15.5 Contractor proposed changes to the quality control plan will be submitted to the COR prior to its implementation.
TP-1.16 Preventive Maintenance Plan (PMP): The Contractor will develop a PMP for mechanical equipment and operational systems at the various project facilities. The plan must designate the unit, machine or system to be inspected, frequency and date of planned inspections. Records of inspection findings and services performed will be maintained. A summary report of repairs will be provided to the COR at the end of each contract year.
TP-1.17 Job Order Accounting System: The contractor will establish a system to effectively prioritize and schedule the performance of tasks, whether initiated through the contractor’s own initiatives or through a COR-initiated work order. The system will incorporate a method by which the contractor provides feedback to the COR that the work order has been scheduled and/or services have been performed.
TP-1.17.1 The system will be capable of establishing a budgeted cost as well as capturing all actual costs associated with the completion of the above work tasks. Costs will be appropriately charged to the applicable technical provision as referenced in Section H, Cost Schedule Requirement. In addition, costs will be appropriately charged to the applicable business line and park or location and cost reports submitted with monthly invoice.
TP-1.17.2 Completion and cost data for each work order will be entered by the contractor in the project’s Facility and Equipment Maintenance system (FEM), a Maximo database. The contractor will enter all contractor-initiated and a portion of Corps-initiated work orders in FEM as directed.
TP-1.18 Schedules: The contractor will prepare and submit logical and accurate work schedules to the COR for maintenance, service and construction as described below. Revisions to schedules will be provided to the COR within 24 hours of that revision.
TP-1.18.1 Cleaning schedules, identifying scheduled arrival and departure times for each location identified with peak and non-peak cleaning in Appendix H, will be provided to the COR for approval.
TP-1.18.2 Weekly work schedules for facility maintenance tasks will be submitted each Monday identifying all scheduled routine maintenance. Schedules should indicate task, location, duration, special equipment and tool needs and personnel requirements.
TP-1.18.3 Grass mowing schedules will be provided to the COR for approval, indicating location and date when mowing activities will be accomplished, so as to meet the requirements of TP-4, Mowing.
TP-1.18.4 Schedules for complex repairs and construction tasks, that address start and end dates for different phases of the task, will be provided to the COR for approval. Adequate breakdown of the task will clearly indicate anticipated duration of repairs and construction activities.
TP-1.19 Incidental Work: Incidental work items related to other specific work requirements throughout these specifications, but not specifically identified, described or quantified, may be required of the contractor. Such incidental work will be limited to support maintenance for the operation of existing facilities that cannot be anticipated. Due to the unknown quantities under this TP, it should not be addressed in the contractor’s technical or cost proposal.
TP-1.19.1 The contractor may be required to provide similar O&M support to other Corps projects or activities in the event of emergency situations or the inability of the local O&M contractor to meet contractual obligations. Due to the unknown quantities under this TP, it should not be addressed in the contractor’s technical or cost proposal.
TP-1.20 Improvement or Modification: A facility improvement or modification will not be initiated without the express approval of the COR. An improvement or modification is defined as any change to the original design of a building or structure or installed systems. Improvements or modifications not specifically approved in advance will be considered unauthorized and the contractor may be required to make restoration at no cost to the government.
TP-1.21 Accident Prevention: All accidents will be verbally reported to the COR immediately. The contractor will maintain an accurate record of, and will report to the COR, all accidents within 24 hours of the occurrence.
TP-1.21.1 The contractor will submit to the COR accident exposure and experience incident to this work, in accordance with EM 385-1-1. An exposure report will include all Contractor employee work hours performed during the reporting period. The work hours should be separated as "Work" and "Administrative" and will include all lost time accidents and equipment accidents over $500.00. The report will be submitted to the COR NLT the 30th of each month.
TP-1.21.2 Public Safety: The contractor will be responsible for safeguarding construction and maintenance sites in public recreation use areas. Appropriate signs, warning devices, and barriers will be used to protect the general public, contractor employees, and government employees in accordance with applicable provisions of
EM 385-1-1.
TP-1.22 Hazardous Waste Disposal: All hazardous waste materials as defined in 40 CFR 260, will be disposed of IAW all applicable county, state, and federal regulations. The contractor will submit information regarding the proposed disposal method and facility to the COR for approval a minimum of one week prior to transportation of wastes. The contractor will provide the COR with written proof that the selected disposal facility and transporter possesses all required permits to handle/transport the specific waste. Records of disposal will be maintained for a minimum of five years following the date of individual disposals. Records will include at a minimum the date, materials, quantity, landfill/recycler (as applicable) and signature of deliverer.
TP-1.23 Inventory Control and Property Management: The contractor’s inventory management and control plan, including control of government property, will be prepared and submitted at the pre-work conference for approval by the COR.
TP-1.23.1 The inventory plan will be complete and accurate and contain at a minimum a code designation for each item listing, the item description, unit price, unit of measure, quantity in stock, date last issued and the location for all items. The inventory control program will be computer automated. The contractor will be subject to monthly property management audits by the government.
TP-1.23.2 Major repair costs for government furnished equipment and vehicles, (i.e., those with a parts acquisition and labor cost in excess of $500 per line item) will be coordinated with the COR for approval prior to initiating repairs.
TP-1.23.3 In the event that emergency repair parts are required, and it is not possible to obtain advance service approval from the COR, the contractor is authorized, and will be required to, procure those parts necessary for repair in order to protect personnel and/or property. The COR should be informed of such emergency purchases as soon as possible following the purchase.
TP-1.23.4 The contractor will maintain daily written records of all maintenance and repair of government vehicles and equipment. These records will include labor (including work performed by subcontractors or other vendors), supplies, materials and parts costs for each separately scheduled work task. Records will be kept on forms provided by the government.
TP-1.24 Interruptions to Systems: All work that would necessitate an interruption to the use of project facilities or systems or otherwise disrupt building occupants and/or the visiting public will be fully coordinated with, and advance approval obtained from, the COR prior to commencement of work.
TP-1.25 Determination of Work to be Performed: It is the intent of this contract that the determination of all work required to maintain, clean or repair all facilities, buildings, structures, vehicles, navigational aids, landscaping, signs, and all other project infrastructure in a safe and efficient operating condition, is the responsibility of the contractor. However, the COR may direct the contractor to perform necessary facility repairs or maintenance in instances where such services have failed to be provided. New work requests, as noted throughout the specifications and as directed by the COR, will be requested by the issuance of work orders authorized by the COR only. These work orders will be issued to the contractor through FEM.
TP-1.26 Definition of Services: As stated in TP-1.1, this contract is a hybrid firm fixed price contract with cost plus fixed fee elements. Section C is divided into fifteen (15) Technical Provisions (TP) with portions of TP-1 either firm fixed price or cost reimbursement, TPs 2-5 firm fixed price, and TPs 6-15 cost reimbursement. Firm fixed price work requirements are grouped into two (2) major categories: Level 1 Routine Maintenance (RM) and Level II Service Orders (SO). Level II work will be generated by the government as a service call.
TP-1.26.1 Level I - Routine Maintenance: Level I services are defined as all work specified within the fixed-price technical provisions of the contract.
TP-1.26.2 Level II - Service Orders: Level II services are defined as unanticipated incidences that occur through no fault of the government or contractor, including theft, breakdowns or failures, vandalism, accidents not caused by the contractor, and severe weather or related acts of God/nature. Level II services may include replacement of government furnished equipment or durables as stated in TPs 1.11 and 1.11.1. Level II services also include additional quantities or frequencies of tasks listed as level I services within the technical provisions that are needed due to unanticipated circumstances that occur through no fault of the government or contractor. Upon direction by the COR, the contractor will submit proposals for the additional service and will provide a detailed breakdown of all related costs. This includes, but is not limited to, burdened labor rates, materials & supplies, subcontractor fees, profit and overhead.
Labor rates and profit margins will not be marked up beyond what is proposed within the awarded contract when a level II service is requested. For firm fixed price elements, the contractor will not perform any work outside of level I services without the approval of the COR or the Contracting Officer (KO). Due to the unknown quantities under this TP, it should not be addressed in the contractor’s technical proposal; however, for estimating purposes only, bidders should include $100,000 per contract year in their cost proposal for level II services.
Individual service orders (ISO) related to level II services mentioned above are considered within the scope of this contract, and the contractor will be compensated using a separate CLIN (and corresponding CLINs if the option years are exercised). They are not part of the firm fixed price CLIN pricing.
Upon discovery of these defined incidences, the contractor will notify the COR immediately.
The COR will request a repair proposal from the contractor for each incident.
Upon COR approval the contractor will perform services required to accomplish repair and invoice separately against the specified level II CLIN (and corresponding CLINs if the option years are exercised).
In the event of a COR-determined emergency the contractor may receive verbal or written authorization to proceed with repair to protect government personnel or property, or the general public; however, the contractor must provide repair estimates to the COR as soon as practical.
TP-1.27 Non-Government-Owned Vehicles, Equipment, Tools and Fuel:
TP-1.27.1 All fuel, to include fuel used in vehicles, equipment, and for brush pile burning, will be charged under TP-1 as a cost reimbursable expense. The maintenance facility is equipped with fuel tanks and pumps for both gasoline and diesel, one each. Fuel may be purchased in bulk and stored in the tanks provided.
TP-1.27.2 Vehicles used in the execution of duties under this contract will be charged under TP-1 as a fixed price expense. The contractor will ensure an appropriate number and type of vehicles are available to complete the tasks under this contract. Vehicles will be maintained according to manufacturers’ recommendations and federal and state regulations. Rental vehicles fall under this TP as a firm fixed price expense.
TP-1.27.3 Equipment and tools not owned by the government, to include repairs and replacements, will be charged to TP-1 as a firm fixed price expense. Items should be appropriately marked as contractor-owned. The contractor is responsible for a continuous supply of baseline equipment in order to reduce mobilization time and minimize rental equipment cost. Approved rental equipment will be charged to the TP under which the work is performed.
TP-1.28 Security:
TP-1.28.1 Access and General Protection/Security Policy and Procedures: All contractor and all associated subcontractor employees will comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor will also provide all information required for background checks required for installation access be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the government may require changes in contractor security matters or processes.
TP-1.28.2 iWATCH and/or CorpsWatch Training: The contractor and all associated subcontractors will brief all employees on the local iWATCH, Corps Watch, or See Something, Say Something programs (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training will be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance, with the results reported to the COR NLT 5 calendar days after training is complete.
TP-1.28.3 Contractor Employees Who Require Access to Government Information Systems: All contractor employees with access to a government information system must be registered in the ATCTS (Army Training Certificate Tracking System) at commencement of services and must successfully complete the DOD Information Assurance training prior to access to the information and then annually thereafter IAW AR 380-67 (Personal Security Program) and Homeland Security Presidential Directive 12 (Policy for a Common Identification Standard for Federal Employees and Contractors).
TP-1.28.4 Pre-Employment Eligibility Screening: The contractor must pre-screen candidates using the E-verify Program (http://www.dhs.gov/E-verify) website to meet the established employment eligibility requirements. The vendor must ensure that the candidate has two valid forms of government-issued identification prior to employment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible candidates must be provided to the COR no later than 3 days after the initial contract award.
TP-2 LABOR
TP-2.0 Labor: TP-2 is a firm fixed price technical provision. The contractor will provide adequate labor at all times subject to seasonal needs to meet the requirements of this contract. All supervision and direct labor performed by employees under any part of this contract, including all TPs and level I or level II services, will be charged to this TP. Labor performed by subcontractors will be charged directly to the associated TP under which the work is performed. Additional requests for labor beyond those listed here will be considered level II services as described in TP-1.26.2, Level II Service Orders. Level II services will be bid at the time they are requested, to include labor, and will not be included in the contractor’s proposal for level I services.
TP-2.1 The contractor is required to compensate employees meeting wage requirements as identified by Service Contract Labor Standards.
TP-2.2 Work Schedule: In addition to periods of work already outlined in TP-3 and TP-4, the contractor will ensure appropriate coverage for core hours of operation as follows:
Monday through Friday – 8:00 a.m. to 4:30 p.m. each day Saturday and Sunday 8:00 a.m. to 4:30 p.m. each day, April 1 through July 31 annually
Emergencies: Per TP-1.13, the contractor will provide coverage 24 hours per day, 7 days per week in case of emergency.
TP-2.2.1 Holiday Work: The contractor will provide cleaning services on all federal holidays between Memorial Day and Labor Day as part of level I services.
TP-2.3 Overtime: Labor covered by this firm fixed price technical provision will include all level I services falling under TP1, 3, 4 and 5 and all services falling into the regular work week schedule for all cost reimbursement TPs.
The contractor will anticipate overtime work under level I service. All labor for maintenance related call-ins occurring outside of an employee’s regular work schedule, to include after hours, holidays or weekends, will be covered as a level II service subject to the approval of the COR at the time of the request. Any labor, to include overtime as warranted under a level II service, will be bid at the time of the request for work.
TP-2.4 Supervision: The contractor will give his or her personal superintendence to the work, or have a competent superintendent on the site. The superintendent must have access to the necessary budgetary information and available manpower allocation to effectively plan and manage on-site work, including accurate budget projection and personnel management. The superintendent will possess authority to act on behalf of the contractor. Such authorization will be submitted in writing to the COR.
TP-2.5 Minimum Personnel Qualifications: Service mechanics, technicians, and consultants will have the education and/or experience to enable them to comprehensively understand the systems and components to be operated, maintained and repaired under these specifications. All employees will be subject to such government regulations as are applicable during the time spent on government property.
TP-2.6 Removal of Contractor's Employees: The COR may direct the dismissal and immediate removal of any contractor employee who is incompetent or who endangers persons or property or whose physical or mental condition is such that it would impair the employee's ability to perform his/her work. Notification for removal will be in writing. However, notification may be made telephonically and later confirmed in writing if time and circumstances warrant. Personnel changes, regardless of cause, will not reduce the contractor's obligation to perform all work required under this contract.
TP-2.7 Minimum Manpower Requirements: The contractor will provide an adequate number of fully qualified personnel to supervise, maintain, repair and operate the Thurmond Project and other locations covered under this contract. A minimum number of personnel required to accomplish these tasks and to handle emergency situations must be available, on call, 24 hours per day, 7 days per week.
TP 2.7.1 Staffing for Cleaning, Janitorial, and Mowing: Based on the contract scope of work, the contractor will provide staffing and work plans to efficiently accomplish the cleaning, janitorial, and mowing requirements outlined in TP-3 and TP-4. Staffing plans must consider the seasonal changes in contract requirements allowing for higher frequencies and volume of work during the peak season, typically 15 March to 15 September. Duties include cleaning and janitorial work and mowing and landscape maintenance work. Each person occupying contract positions will meet the minimum skill and experience requirements contained in TP-1.2 and TP-2.
TP 2.7.2 Staffing for Routine Operations, Maintenance, and Repairs: In addition to the contract specifications detailed in the TPs, related appendices, exhibits and other information are provided to assist the contractor in understanding the scope of work. Based on the contract scope of work, the contractor will provide staffing and work plans to efficiently accomplish inspection, operation, maintenance, repair, minor construction and rehabilitation of project facilities and features. The contractor will be capable of transporting and otherwise making all proposed manpower resources available at any location contained in the scope of this contract by providing a sufficient number of vehicles, boats, etc., to facilitate O&M activities. Each of the persons occupying contract positions will meet the minimum skill level and experience necessary to meet the requirements of the work; reference TP-1.2 and TP-2. Additional positions proposed by the contractor will include the minimum skill and experience requirements drafted by the contractor. On-the-job training of these individuals will not be an acceptable method of qualification.
Therefore, these individuals will possess required skills and experience upon entry to the job, excepting the maintenance trades helper/laborer/janitor positions. Types of work include, but are not limited to: carpentry, plumbing, electrical work, welding, vehicle and heavy equipment maintenance, tree cutting, landscape maintenance, and heavy equipment operation.
TP 2.8 Uniforms: Contractor employees will be required to wear company identification on uniform shirts while performing duties under this contract. Reference TP-1.9, Identification of Contractor Employees. Uniforms will be charged under TP-2, Labor.
TP-2.9 Quality Control: This contract requires at least one (1) Quality Control inspector who will perform the duties as outlined in TP 1.15.
TP-2.9.1 The quality control system will be organized with a chief and supplemental personnel as deemed necessary to perform effective quality control. The chief and/or the assistant(s) will be:
a. Employed directly by the contractor, with no assigned duties other than evaluation, documentation and safety.
b. Independent of the contractor's field and supervisory organization.
c. Responsible only to the contractor's top level managers and/or owners.
d. Have a minimum experience of five (5) years in quality control work (chief only).
TP-3 CLEANING SERVICES
TP-3.0 Scope of Work: TP-3 is a firm fixed price technical provision. The contractor will furnish all labor, supervision, equipment, materials and supplies needed to maintain clean and sanitary facilities. Labor will be charged under TP-2, Labor, unless it is subcontracted, in which case it will be charged to this TP. The contractor will satisfactorily clean, remove refuse, provide bulk trash removal and maintain Corps facilities at J. Strom Thurmond and Richard B. Russell Projects and the New Savannah Bluff Lock and Dam as identified in Appendix H. All cleaning and bulk trash removal services identified in this TP will be considered level I services and charged as firm fixed price. Additional requests by the COR for cleaning services and bulk trash removal, beyond those listed here, will be considered level II services as described in TP-1.26.2, Level II Service Orders.
TP-3.1 Schedule of Work: Submit to the COR for approval a schedule of services for cleaning, custodial services and bulk trash removal indicating frequencies, days of the week, time of the day and number of times per day prior to commencing work and prior to changing the schedule between peak months and non-peak months. Reference TP 1.21.1.
TP-3.2 Cleaning Services: The contractor will provide general facility cleaning services at all recreational areas, parks and individual facilities as indicated in Appendix H, to provide clean, safe and functional facilities. All refuse and debris will be disposed of off government property according to county, state, and federal regulations. All facilities open to the public and Corps employees will be thoroughly cleaned and maintained in a sanitary, safe, and stocked condition.
TP-3.2.1 Detergents: Only soap, soap compounds, cleansers and/or biodegradable detergents will be used. If the contractor uses a cleaning compound containing disinfectants and deodorants in lieu of applying these materials separately, the label must state that the compound is biodegradable and contains disinfectant or deodorizer. Non-abrasive cleansers will be used on all stainless steel and porcelain fixtures and mirrors. The manufacturer’s instructions will be followed in mixing proper strength solution for application.
TP-3.2.2 Disinfectants: Only standard, commercial disinfectants will be used. The manufacturer’s instructions will be followed in order to mix the proper strength solution for application. The disinfectant may be mixed with cleaning solution if the manufacturer’s instructions on the disinfectant’s label do not prohibit it. NOTE: Bleach will not be approved as a regular disinfectant for floors due to potential safety hazards.
TP-3.2.3 Deodorizers: Deodorizers must leave a pleasant residual odor. The manufacturer’s instructions will be followed in order to mix the proper strength for application. The deodorant may be mixed with cleaning solution if the manufacturer’s instructions on the deodorant’s label do not prohibit it.
TP-3.2.4 Deodorant Cakes: Cakes will be of standard size and shape, containing no para-dichlorobenzene, and will be changed out when original size has been reduced by two thirds (2/3). Wrapping paper must be removed from the cakes prior to placing in urinals.
TP-3.2.5 Toilet Tissue: Toilet tissue will be a double-ply toilet paper. Toilet tissue will be locked into all available receptacles. Locks will be provided by the government initially. Any replacement locks will be provided by the contractor and be consistent with existing lock/key system.
TP-3.2.6 Bacteria/Enzyme Deodorant for Vault/Pit Toilets, Dumpsters and Fish Cleaning Stations: An organic odor control chemical, such as liquid bacteria or super sewage enzymes, will be applied to vault toilets, pit toilets, dumpsters and fish cleaning stations by the contractor as needed to minimize odors.
TP-3.2.7 Liners: The contractor will provide appropriately sized liners for cans/receptacles/containers.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.