A.02.12 Attachment K - Sample SO Submission Form_Amend 0002.pdf

PDF 127 KB Posted

Attached to
Recurring Maintenance and Minor Repair Services Naval Station Rota and Moron Air Base, Spain
Solicitation number
W912GB23R0036
Issued by

View the file

Other files

File Type Posted
A.02.12 SPAIN RMMR PWS 150823 Rev2.pdf PDF
B.08.03 Amend 0004 W912GB23R0036.pdf PDF
B.08.03 Amend 0003 SF30 W912GB23R0036.pdf PDF
B.08.03 Amend 0003 Conformed Copy W912GB23R0036.pdf PDF
A.02.12 Attachment D - Sample Lookahead Schedule_Amend 0002.pdf PDF
A.02.12 Attachment L - SO SSJ Form_Amend 0002.pdf PDF
B.08.03 Conformed Copy Amend 0002 W912GB23R0036.pdf PDF
A.02.12 Attachment N - Spain Country Clearance Requirements_Amend 0002.doc DOC document
B.08.02 Appendix E PIEE Instructions for Proposal Submittal_Amend 0002.pdf PDF
A.02.12 Attachment J - Sample Work Request Submission Form_Amend 0002.pdf PDF
A.02.12 Attachment H - EBS RP Universe Report (Rota & Moron) - Feb 2023_Amend 0002.xlsx XLSX spreadsheet
A.02.12 Attachment G - Real Property Inventory Rota 11 NOV 2022_Amend 0002.pdf PDF
A.02.12 Attachment A - FY18 RMMR-OY4 - Site Specific EIL_Amend 0002.xlsx XLSX spreadsheet
A.02.12 Attachment E - Sample MSR - Appendix C RM Schedule_Amend 0002.xlsx XLSX spreadsheet
A.02.12 Attachment E - Sample Monthly Status Report_Amend 0002.pdf PDF
A.02.12 SPAIN RMMR PWS 230726_R1_Amend 0002.pdf PDF
A.02.12 Attachment I - Recurring Maintenance Report_Amend 0002.pdf PDF
A.02.12 Attachment M- Service Order Tracker_Amend 0002.xlsx XLSX spreadsheet
A.02.12 Attachment C - Sample Operational ISR_Amend 0002.xlsx XLSX spreadsheet
A.02.12 Attachment B - Sample Bulk ISR_Amend 0002.xlsx XLSX spreadsheet
A.02.12 Attachment F - NAVSTA Rota Capitalized Petroleum Facilities_Amend 0002.docx DOCX document
B.08.03 Amend 0002 SF30 W912GB23R0036.pdf PDF
B.08.03 RFP Amendment 0001.pdf PDF
A.02.12 Attachment E Recurring Maintenance Report.pdf PDF
A.02.12 Attachment J - Sample SO Submission Form.pdf PDF
B.08.02 Appendix D Letter of Commitment Sample.docx DOCX document
A.02.12 Attachment G - NAVSTA Rota Capitalized Petroleum Facilities.pdf PDF
A.02.12 Attachment K - SO SSJ Form.pdf PDF
B.08.02 Appendix C Past Performance Questionnaire.pdf PDF
A.02.12 Attachment C - Sample Lookahead Schedule.pdf PDF
A.02.12 Attachment A - Sample Bulk ISR.pdf PDF
A.02.12 SPAIN RMMR PWS 230308.pdf PDF
A.02.12 Attachment D - Sample Monthly Status Report.pdf PDF
A.02.12 Attachment I - EBS RP Universe Report (Rota & Moron) - Feb 2023.xlsx XLSX spreadsheet
A.02.12 Attachment B - Sample Operational ISR.pdf PDF
B.08.02 Appendix B Past Performance Info Sheet.pdf PDF
B.08.02 Appendix A Schedule of Items and Prices.xlsx XLSX spreadsheet
A.02.12 Attachment H - Real Property Inventory Rota 11 NOV 2022.pdf PDF
A.02.12 Attachment F - Service Order Tracker.xlsx XLSX spreadsheet
B.08.02 RFP W912GB23R0036.pdf PDF
A.02.12 Attachment L - Spain Country Clearance Requirements.pdf PDF
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACTOR:

CUSTOMER ORGANIZATION:

DOD SITE CODE:

FACILITY NAME/NUMBER: SO REQUEST NO:

SERVICE ORDER DATE:

Action to be Taken:

One of these boxes must be checked: ROUTINE EMERGENCY CENAU Safety Initial

Check if applicable:

Labor Classification Reg Labor Hours

Reg Labor Rate

Reg Labor Amount OT Hours Contr O/T Rate OT Amount

0.00 $0.00 $0.00 0.00 $0.00 $0.00

0.00 $0.00 $0.00 0.00 $0.00 $0.00

0.00 $0.00 $0.00 0.00 $0.00 $0.00

0.00 $0.00 $0.00 0.00 $0.00 $0.00

0.00 $0.00 $0.00 10.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Qty Unit Unit Price Amount $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Amount $0.00 $0.00 $0.00

$0.00

$0.00

Freight/ShippingSUB Notes:

CORRECTIVE MAINTENANCE SERVICE ORDER FORM

PART I - SERVICE ORDER INFORMATION

LABOR UTILIZED

MATERIALS/SUPPLIES/EQUIPMENT

Total Regular Labor

TOTAL LABOR COST

Safety Verification to be completed by Contractor

One of these boxes must be checked:

Contractor confirms there is an AHA associated with the work being performed in this SO included in the Accident Prevention Plan (APP) Contractor acknowledges there is NOT an AHA associated with the work being performed in this SO included in the APP. AHA is attached for review with the SO.

Contractor acknowledges there is an activity associtated with the SO that requires an additional plan or program that will be included in an APP addendum.

SO Descripton (include LOCATION - attach additional sheets as required):

PART II - COST SUMMARY

Total OT Labor Profit On Labor: 0%

Tax: 0% MSE Charge Rate: 0%

Profit On MSE: 0%

Description

SUBCONTRACTOR COSTS

NOTE: Profit shall not be applied to GSA/JCI Catalog Materials.

Description

Freight/Shipping

Fully Burdened MSE

Safety Officer will inspect before, during and after work. Quality Control Officer will inspect during testing.

MSE Notes:

W912GBXXCXXXX

CONTRACT Year:

SERVICE ORDER NAME:

Labor Notes:

CONTRACT NO.:

CLIN TO BE CHARGED:

SUB Charge Rate: 0%

TOTAL SUB COST

Subtotal MSE

TOTAL MSE COST

CONTRACTOR:

CUSTOMER ORGANIZATION:

DOD SITE CODE:

FACILITY NAME/NUMBER: SO REQUEST NO:

SERVICE ORDER DATE:

Action to be Taken:

One of these boxes must be checked: ROUTINE EMERGENCY

CORRECTIVE MAINTENANCE SERVICE ORDER FORM

PART I - SERVICE ORDER INFORMATION

SO Descripton (include LOCATION - attach additional sheets as required):

W912GBXXCXXXX

CONTRACT Year:

SERVICE ORDER NAME:

CONTRACT NO.:

CLIN TO BE CHARGED:

Amount $0.00 $0.00 $0.00

ODC Notes: $0.00

$0.00

$0.00

Amount $0.00 $0.00

Travel Notes: $0.00

$0.00

CENAU COR: May approve SOs up to $10,000 or as otherwise authorized by the Contracting Officer.

TRAVEL

G&A: 0%

OTHER DIRECT COSTS

TOTAL ODC COST

E-SIGNED & DATED:

CONRACTOR: Receipt & Acceptance Acknowledged.

Description

PART IV - CERTIFICATION OF SERVICES

CONTRACTING OFFICER: Service Orders over $10,000 or as otherwise specified by Contracting Officer.

QUAILITY ASSURANCE EVALUATOR:

E-SIGNED & DATED:

E-SIGNED & DATED:

This is a cost reimbursable service order and the initial prices submitted reflect the Contractor's best estimate to complete the work necessary to satisfy the requriement. This SO is considered technically acceptable and within scope.

DATE/TIME WORK COMPLETED

TOTAL TRAVEL COST

E-SIGNED & DATED:

$0.00TOTAL SO COSTS TO BE INVOICED

PART III - AUTHORIZATION

E-SIGNED & DATED:

CUSTOMER: SO is accepted and requests NTP from USACE.

I certify that the services under the above Service Order have been satisfactorily completed.

Profit on Outside Vendor: 0%

Description

Equipment room flooded. Need to remove excess water for safety purposes.

G&A: 0%

Service Order