A.02.12 Attachment E - Sample Monthly Status Report_Amend 0002.pdf
PDF 412 KB Posted
- Attached to
- Recurring Maintenance and Minor Repair Services Naval Station Rota and Moron Air Base, Spain
- Solicitation number
- W912GB23R0036
- Issued by
-
Department of the Army European Command
View the file
Other files
Show all 41
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT D
Recurring Maintenance and Minor Repairs Program US Army Corp of Engineers- Europe District (CENAU)
Monthly Status Report Contract No. W912GB-23-C-XXXX
Contract title
Submission Date:
Submitted By:
Company Name
TABLE OF CONTENTS
1.0 SERVICE ORDER OVERVIEW
2.0 RECURRING MAINTENANCE OVERVIEW
3.0 CURRENT AVAILABLE FUNDS
4.0 QUALITY
5.0 SAFETY
6.0 PHOTOGRAPHS
7.0 SCHEDULE
8.0 TOP 10 MAINTENANCE REPAIR ITEMS
9.0 POINTS OF CONTACT
10.0 APPENDICES
Appendix A - Safety Report Appendix B - Photographs Appendix C - Schedule
1.0 SERVICE ORDER OVERVIEW
Service Order Overview- As of today current option
SO Category Number of SOs Total Cost Submitted to NAU 93 $532K Approved by NAU 46 $178K Executed 62 $195K Disapproved / Cancelled by NAU 1 $1K Awaiting NAU Approval 100 $859K In-Progress (have not been to NAU) 107 $676K
Service Order Overview- During this Period
SO Category Number of SOs Total Cost Submitted to NAU 93 $532K Approved by NAU 46 $178K Executed 62 $195K Disapproved / Cancelled by NAU 1 $1K
SO # General Description
NTP
Date
Completed Date days after
NTP
date
# days to complete
# days less than
# days over 30 (from
NTP)
Remarks
Every SO submitted during this period shall be included in this table.
2.0 RECURRING MAINTENANCE OVERVIEW
Table 1 Required & Completed Maintenance Visits Completed as of today current option
Site Name Code Phase Quarterly Semi-Annual Annual Required Completed Required Completed Required Completed
Rota ROT A5 4 4 2 2 1 1 Moron MOR A5 4 4 2 2 1 1 Djibouti DJI A5 4 4 2 2 1 1 Sigonella SIG A5 4 4 2 2 1 1 Lakenheath LAK A5 4 4 2 2 1 1 Mildenhall MDH A5 2 1 2 1 1 1 Lajes LJS A5 4 4 2 2 1 1 Wiesbaden WIE A5 2 2 2 2 1 1 Campia Darby DRB A5 4 4 2 2 1 1
Table 2 Number & Total Costs of Maintenance Visits- During this period
Effort Number of Maintenance Visits this Month Total Cost Quarterly Maintenance 14 $102,654.00 Semi-Annual Maintenance 15 $103,479.00 Annual Maintenance 5 $133,036.00
Table 1 Required & Completed Maintenance Visits Completed during this period
Site Name Code Phase Quarterly Semi-Annual Annual Required Completed Required Completed Required Completed
Rota ROT A5 4 0 2 0 1 0 Moron MOR A5 4 0 2 0 1 0 Djibouti DJI A5 4 0 2 0 1 1 Sigonella SIG A5 4 1 2 0 1 0 Lakenheath LAK A5 4 2 2 0 1 1 Mildenhall MDH A5 2 3 2 1 1 0 Lajes LJS A5 4 4 2 0 1 1 Wiesbaden WIE A5 2 2 2 1 2 1 Campia Darby DRB A5 4 4 2 1 1 1
3.0 CURRENT AVAILABLE FUNDS
CLIN Amount Balance (Approved SOs)
Balance (Submitted SOs) Comments
4.0 QUALITY
Customer Feedback Surveys
Sixty-three (63) customer quality feedback surveys were sent for recurring maintenance and repair actions during the reporting period. As of the close of this reporting period, 20 surveys were received.
These surveys reflected neutral to positive comments on the JVs performance to date.
Question
Total Number of Responses
Average of
Responses
Response
1 2 3 4 5 On a scale from 1 to 5 with five being the best, please rate your OVERALL satisfaction with the way contractor performed Recurring Maintenance/Repair activities at your location.
Were timely in reporting to my location
Completed activities according to schedule
Complete the task properly
Effectively communicated with you prior to and during our site visit
Maintained proper housekeeping and left the work area clean and functional
The following comments were received on the surveys:
5.0 SAFETY
A. Reportable Incidents this period:
B. Safety training/briefings this period and (attendees):
Safety reports are included in Appendix A.
6.0 PHOTOGRAPHS
Representative photographs of maintenance repair work are included in Appendix B.
7.0 SCHEDULE
The updated schedule for anticipated RM and MR/ER work is included in Appendix C.
8.0 TOP 10 MAINTENANCE REPAIR ITEMS
Rank Maintenance/Repair Number
9.0 POINTS OF CONTACT
Contract Administrators Program Manager Project Manager Project Engineer Site Manager
10.0 APPENDICES
Appendix A - Safety Report Appendix B - Photographs Appendix C - Schedule
File details come from the government source that posted it. Updated .