W912GB19R0028-00001.pdf

PDF 153 KB Posted

Attached to
Construction of the Explosive and Ammo Loading/Unloading Apron at MK Air Base, Romania
Solicitation number
W912GB19R0028
Issued by

About this file

Amendment 01 to extend the proposal due date.

View the file

Other files

File Type Posted
MKAB_CargoApronRFP_CombinedSurvey_(2).dwg DWG drawing
Bid_Schedule_Sample-_W912GB19R0028_23MAY2019.pdf PDF
MKAB Haz Cargo RFP - RFI Amended Dwgs 20 MAY 2019.pdf PDF
MKAB Haz Cargo RFP - Corrected Final v5.pdf PDF
PumpHouse.pdf PDF
W912GB19R0028-P0002.pdf PDF
Bid Schedule - MKAB Corr Final RFP REV 14MAY2019.pdf PDF
Tank.pdf PDF
20180508_144259.jpg JPG image
20180508_142856.jpg JPG image
7939117 ATTACHMENT Utility Hookups.PDF PDF
CD-102 MKAB Explosive Cargo.pdf PDF
20180508_142823.jpg JPG image
20190422_135411.jpg JPG image
7920099 ATTACHMENT.PDF PDF
20190422_133318.jpg JPG image
7965953 ATTACHMENT.PDF PDF
20180508_142343.jpg JPG image
20180508_143051.jpg JPG image
20180508_143209.jpg JPG image
20180508_141743.jpg JPG image
20180508_144939.jpg JPG image
20190422_135357.jpg JPG image
Compiled_PreProposal_Slides_Explosive_Cargo_Apron_MK_Romania_9Apr19.ppt PPT presentation
Site_Visit_Sign_In_Roster.pdf PDF
Sol_Attachment_6_-_BANK_LETTER_OF_GUARANTEE.docx DOCX document
Sol_Attachment_5_-_BANK_LETTER_OF_ASSURANCE.docx DOCX document
SOW__7.0_-_MKAB_Haz_Cargo_RFP_-_Corrected_Final_v3.pdf PDF
Sol_Attachment_4_-_Letter_of_Commitment_Sample.docx DOCX document
Sol_Attachment_1_-_Overview_Experience.docx DOCX document
SOW_Attachment_7.a._-_RFP_Drawings_MKAB_Haz_Cargo.pdf PDF
Sol_Attachment_3_-_PastPerformanceClientForm.docx DOCX document
SOW_Attachment_7.g._-_Fire_Hydrant_Flow_Test_Report.pdf PDF
SOW_Attachment_7.e._-_Geotechnical_Report_MKAB_Haz_Cargo.pdf PDF
SOW_Attachment_7.d._-_Form_DD_1354_MKAB_Haz_Cargo.pdf PDF
SOW_Attachment_7.f._-_Environmental_Site_Assessment_MKAB_Haz_Cargo.pdf PDF
Sol_Attachment_2_-_Experience_Info_Sheet.docx DOCX document
SOW_Attachment_7.c._-_Price_Schedule_-_Romania_Explosive_Apron_5_FEB_2019.pdf PDF
Price_and_Payment_Procedures_-_Romania_Explosive_Apron_Solicitation.pdf PDF
SOW_Attachment_7.b._-_Project_UFGS_Specifications_List_and_Division_00_and_01_Specifications_MKAB_Haz_Cargo.pdf PDF
W912GB19R0028_Solicitation_Cargo_Apron,_MK_Romania.pdf PDF
01-Base_access_blank_form_MK.XLSX XLSX spreadsheet
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The reason for this Amendment is to extend the proposal due date to 28 May 2019 at 1400hrs CEST to allow for proper responses to Contractor questions. All responses and associated attachments w ill be provided via ProjNet.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 25-Apr-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912GB19R0028

X 9B. DATED (SEE ITEM 11)

28-Mar-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

25-Apr-2019

CODE

CONTRACTING DIVISION

US ARMY CORPS OF ENGINEERS

KONRAD ADENAUER RING 39

D-65187 WIESBADEN GERMANY

WIESBADEN 65187

W912GB 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912GB19R0028

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 07-May-2019 12:00 PM to 28-May-2019 02:00 PM.

The contractor period of performance begin date has increased by 4 days from 3 days to 7 days.

(End of Summary of Changes)

File details come from the government source that posted it.