00 73 15.15 Time Extensions for Unusually Severe Weather.pdf

PDF 22 KB Posted

Attached to
Construction of Multiple Sclerosis Therapy Center Vrujci, Serbia
Solicitation number
W912GB-17-R-0042
Issued by

About this file

Time Extension

View the file

Other files

File Type Posted
W912GB-17-R-0042_Amendment_02.pdf PDF
Amendment_01.zip ZIP file
Attach 2 Exp Info Sheet 17-R-0042.docx DOCX document
01525 Safety and Occupational Health Requirements for Projects in Emerging Countries —
02 82 14.00 10 Asbestos Hazard Control Activities.pdf PDF
Attach 3 PPQ 17-R-0042.docx DOCX document
01 33 00 Submittal Procedures.pdf PDF
01 35 26 Safety and Occupational Health Requirements —
Attach 6 BLA Sample Template.docx DOCX document
01 32 01.00 10 Project Schedule.pdf PDF
01 78 00 Completion Procedures.pdf PDF
Attach 8 Resume.docx DOCX document
Solicitation W912GB-17-R-0042.pdf PDF
A.01.38_Attachment_1_Location Map.pdf PDF
01 45 01.01 Additional Quality Control Personnel.pdf PDF
Attach 1 Overview Exp 17-R-0042 .docx DOCX document
Attach 4 Price schedule.docx DOCX document
Attach 5 BLG Sample Template.docx DOCX document
00 73 15.01 Government Field Office.pdf PDF
01 45 01.10 USACE QUALITY CONTROL SYSTEM —
Attach 7 Letter of Commitment.docx DOCX document
02 41 00 Demolition and Deconstruction.pdf PDF
A.01.38_Attachment_4_Arch.pdf PDF
01 45 01 USACE Quality Control.pdf PDF
A.01.38_Attachment_2_Site Plan.pdf PDF
01 00 15 Design After Award.pdf PDF
A.01.38_Attachment_5.pdf PDF
A.01.38_Attachment_3_Site Photos.pdf PDF
Construction Signs.pdf PDF
00 73 15 General Conditions —
00 73 15.02 Government Resident Office.pdf PDF
01 78 23 Operation and Maintenance Data.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 00 73 15.15

TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

01/09

1. This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the contract clause entitled "Default: (Fixed Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

c. The delay must occur during the contractual performance period.

Weather delays occurring after the required completion date, prior to Notice to Proceed, or during other non-working days are not excusable under the Defaults clause.

2. The following schedule of monthly anticipated adverse weather delays will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather lays in all weather dependent activities. de

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

WORK DAYS BASED ON (5) DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

Projects Located in Africa 3 3 4 5 7 6 7 4 4 4 3 3

Projects Located in Israel 5 5 4 1 0 0 0 0 0 1 3 5

All Other Countries and Locations 8 6 7 6 5 5 5 4 4 6 7 8

Monthly anticipated adverse weather delays shall be adjusted proportionately should the actual work week be based on more or less than 5 work days (i.e.

if a 6 day work week, the anticipated adverse weather delay work days for a month would be adjusted by multiplying the number shown above by 6/5).

3. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract performance period, the contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Impacted activities shall be identified by name and activity id on the CQC report.

Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the contractor's scheduled work day.

The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather

SECTION 00 73 15.15 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

01/09 delay days exceeds the number of days anticipated in paragraph 2, above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the contract clause entitled "Default (Fixed Price Construction)".

4. When the contract performance period, or any extension thereof, has passed, no extensions for unusually severe weather will be granted.

-- End of Section --