00 73 15.15 Time Extensions for Unusually Severe Weather.pdf

PDF 22 KB Posted

Attached to
RFI Amendment Federal contract opportunity
Solicitation number
W912GB-16-R-0036
Issued by
Department of the Army Corps of Engineers Engineering District Europe

About this file

00 73 15.15 Time Extensions for Unusually Severe Weather Specifications

View the file

Other files for this federal contract opportunity

Other files attached to RFI Amendment, newest first.
File Type Posted
A.2.11.3_Request_for_Information_2.docx DOCX document
W912GB-16-R-0036_Lachin_IDP_School_AZ_Pre-Proposal_Conf_26Jul16.pptx PPTX presentation
A.2.11.3_Request_for_Information.docx DOCX document
00 73 15.50 General Conditions —
A.2.11.3_Att5letterofcommit.docx DOCX document
A.2.11.3 Att6BidSchedule.docx DOCX document
A.2.11.3 Att3PPQ.docx DOCX document
01 00 15 Design After Award.pdf PDF
01 45 01 USACE Quality Control.pdf PDF
Construction Signs.pdf PDF
A.07.23 W912GB-16-R-0036.pdf PDF
A.2.11.3_Att2expinfosheet.docx DOCX document
A.2.11.3_Att4KeyPersResume.docx DOCX document
A.2.11.3_Att1expovervw.docx DOCX document
A.2.11.3 Att9BLG.Template.doc DOC document
00 73 15.15 Time Extensions for Unusually Severe Weather.pdf PDF
A.07.24 SOW Att 3 - Gift Sign.pdf PDF
01 78 23 Operation and Maintenance Data.pdf PDF
A.07.24 SOW Att 1 - Site Layout.pdf PDF
01 78 00 Completion Procedures.pdf PDF
01 32 01.00 15 Project Schedule —
A.2.11.3_Att8BLA.Template.docx DOCX document
A.2.11.3 Att1expovervw.docx DOCX document
A.07.24 SOW Att 2 - Functional Layout.pdf PDF
A.2.11.3 Att5letterofcommit.docx DOCX document
01 45 01.10 USACE QUALITY CONTROL SYSTEM —
A.2.11.3_Att3PPQ.docx DOCX document
A.2.11.3_Att6BidSchedule.docx DOCX document
01 35 26 Safety and Occupational Health Requirements —
A.2.11.3 Att2expinfosheet.docx DOCX document
00 73 15 General Conditions —
A.2.11.3 Att4KeyPersResume.docx DOCX document
A.2.11.3 Att8BLA.Template.docx DOCX document
A.2.11.3 Att7AzerbaijanTaxInfo.pdf PDF
01 32 01.00 15 Project Schedule —
A.07.24 SOW Att 3 - Gift Sign.pdf PDF
00 73 15.50 General Conditions —
01 00 15 Design After Award.pdf PDF
01 78 00 Completion Procedures.pdf PDF
01 45 01 USACE Quality Control.pdf PDF
02 41 00 Demolition and Deconstruction.pdf PDF
01 45 01.10 USACE QUALITY CONTROL SYSTEM —
A.07.23 W912GB-16-R-0036.pdf PDF
A.07.24 SOW Att 1 - Site Layout.pdf PDF
01 33 00 Submittal Procedures.pdf PDF
Construction Signs.pdf PDF
A.07.24 SOW Att 2 - Functional Layout.pdf PDF
00 73 15 General Conditions —
01 35 26 Safety and Occupational Health Requirements —
01 78 23 Operation and Maintenance Data.pdf PDF
Show all 50

RFI Amendment has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 00 73 15.15

TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

01/09

1. This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the contract clause entitled "Default: (Fixed Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

c. The delay must occur during the contractual performance period.

Weather delays occurring after the required completion date, prior to Notice to Proceed, or during other non-working days are not excusable under the Defaults clause.

2. The following schedule of monthly anticipated adverse weather delays will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather lays in all weather dependent activities. de

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

WORK DAYS BASED ON (5) DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

Projects Located in Africa 3 3 4 5 7 6 7 4 4 4 3 3

Projects Located in Israel 5 5 4 1 0 0 0 0 0 1 3 5

All Other Countries and Locations 8 6 7 6 5 5 5 4 4 6 7 8

Monthly anticipated adverse weather delays shall be adjusted proportionately should the actual work week be based on more or less than 5 work days (i.e.

if a 6 day work week, the anticipated adverse weather delay work days for a month would be adjusted by multiplying the number shown above by 6/5).

3. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract performance period, the contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Impacted activities shall be identified by name and activity id on the CQC report.

Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the contractor's scheduled work day.

The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather

SECTION 00 73 15.15 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

01/09 delay days exceeds the number of days anticipated in paragraph 2, above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the contract clause entitled "Default (Fixed Price Construction)".

4. When the contract performance period, or any extension thereof, has passed, no extensions for unusually severe weather will be granted.

-- End of Section --

File details come from the government source that posted it. Updated .