Amend 0005_Attch 21_Responses to RFIs (88-175)

View the file

Other files

File Type Posted
W912GB-16-R-0030 _Amd_09.pdf PDF
W912GB-16-R-0030 _Amd_08.pdf PDF
W912GB-16-R-0030 _Amd_07.pdf.doc.pdf PDF
W912GB-16-R-0030_Amendment_06_w_Attachments.pdf PDF
Amend_0005_Attch_22_Standard_Form_SF_24_Bid_Bond.pdf PDF
Amend_0005_Attch_17a1_a2_Architectural_Revision_02.pdf PDF
Amendment_0005_W912GB-16-R-0030_Site_13580_Israel.pdf PDF
Amend_0005_Attch_01_Experience_Overview_Sheet_Revision_01.docx DOCX document
Amend_0005_Attch_17d_Electrical_Revision_02.pdf PDF
Amend_0005_Attch_17b_Civil_Revision_01.pdf PDF
Amend_0005_Attch_04_Resume_Site_13580_Revision_01.pdf PDF
Amend_0005_Attch_11_SRs_Project_13580_Revision_02.pdf PDF
Amend_0005_Attch_16_Drawings_List_13580_Revision_02.pdf PDF
Amend_0005_Attch_10_Price_Schedule_Site_13580_Revision_02.pdf PDF
Amend_0005_Attch_12_Special_Specifications_Project_13580_Revision_02.pdf PDF
Amendment_0004_W912GB-16-R-0030_Site_13580_Israel.pdf PDF
Amendment_0003_W912GB-16-R-0030_Site_13580_Israel.pdf PDF
Amend_0002_Attch_20_Earthworks.zip ZIP file
Amend_0002_Attch_17c_Structural_Revision01.pdf PDF
Amend_0002_Attch_11_SRs_Project_13580_Revision_01.pdf PDF
Amend_0002_Attch_12_Special_Specifications_-_Project_13580-Revision_01.pdf PDF
Amend_0002_Attch_18_Requests_for_Information_1-87_Site_13580_24May2016.pdf PDF
Amend_0002_Attch_19_13580_Site_Photos.pdf PDF
Amend_0002_Attch_17e_Fuel_Revision01.pdf PDF
Amend_0002_Attch_17a1_a2_Architectural_Revision01.pdf PDF
Amend_0002_Attch_16_Combined_Drawings_List_Site_13580_Revision_01.pdf PDF
Amendment_0002_W912GB-16-R-0030_Site_13580_Israel.pdf PDF
Amend_0002_Attch_17d_Electrical_Revision01.pdf PDF
Amend_0002_Attch_17h_Plumbing_Revision01.pdf PDF
Amend_0002_Attch_10_Price_Schedule_Site_13580_Revision_01.pdf PDF
Amend_0002_Attch_17i_Site_Development.pdf PDF
Amendment_0001_W912GB-16-R-0030_Site_13580_with_Attch_02and03.pdf PDF
Amend_0001_Atch_01_Experience_Overview_Sheet.docx DOCX document
Attch_17d_Electrical.pdf PDF
Attch_17a2_Architectural.pdf PDF
Attch_17c_Structural.pdf PDF
Attch_17b_Civil.pdf PDF
Attch_17e_Fuel.pdf PDF
Attch_17g_Mechanical.pdf PDF
Attch_17a1_Architectural.pdf PDF
Attch_17h_Plumbing.pdf PDF
Attch_17f_Cathodic_Protection.pdf PDF
Attch_14_USACE_General_Specifications_Site_13580.pdf PDF
Attch_3_Past_Performance_Questionnaire_13580.pdf PDF
Attch_10_Price_Schedule_Site_13580_14Apr2016.pdf PDF
Attch_2_Experience_Information_Sheet_Site_13580.pdf PDF
Attch_16_Combined_Drawings_List_Site_13580_22Apr16.pdf PDF
Attch_11_SRs_Site_13580_21April2016.pdf PDF
Attch_6_Contractor_Key_Personnel_Performance_Certification_Site_13580.pdf PDF
Attch_15_HNTRs_Site_13580.pdf PDF
Show 40 more

Latest 50 of 59 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation W912GB-16-R-0030 Project 13580, Israel (Design-Bid-Build) Amendment 0005 - Request for Information

As of 10 June 2016

Question 88: The Proposal due date has been extended due to the amount of scope of work and complexity of the project. We have been receiving significant amount of RFIs from subcontractors and vendors as there are some items – some of which of significant importance – that require further clarification.

To prepare an accurate submission we therefore request that the RFI due date for this proposal also to be extended (obviously for all bidders). If RFIs due date is extended, please see below RFI questions?

Response: Any questions/RFIs submitted after the date and time specified herein may or may not be answered at the discretion of the Contracting Officer.

Question 89: Could the "Automatic Gaging System" and "Fuel Management System" be integrated in a shared PLC and HMI (Monitoring) System?

Response: Yes, the systems could be integrate in a shared PLC and HMI System.

Question 90: Are the level instruments mentioned on page 301 the same instruments as described on page 310?

Response: In reviewing the Special Specifications, we are unable to determine which “level instruments” the question is referring to either on page 301 or page 310. Please provide specific details (Chapter, Section, Paragraph and Subparagraph numbers). Inserting a screen shot of the subject area(s) would also be helpful when expanding on your question.

Question 91: How many units of "Metering System" are included in this scope? Could they be connected to the control system via communication network?

Response: The number of loading metering devices is provided on Drawing F-0001.

Question 92: Page 306 : How many "Control Valves" and “Pilot Valves” are included in the scope ?

and where?

- Which type? (Electrical/ Pneumatic/ Hydraulic?

Response: According to Drawing F-002:

Device No #6: 1 unit.

Device No #5: 1 unit

For more details on the types, see Sections 38.04.05 & 38.04.06 in the Special Specifications.

Question 93: How many "Double Block and Bleed" units are included?

Response: Please see item No #4 on drawing F-002.

Solicitation W912GB-16-R-0030 Site 13580 - Israel (Attachment 21)

As of 10 June 2016

Question 94: Item 38.07.06.5 – Back-up: is totally unclear and should be defined technologically and geographically.

Response: Section 38.07.06.5 describes that the systems data back-up could be done in two ways : on site download by a mobile device such as disk on Key, or remote control via the Internet access.

Question 95: Spec 07.01.02 (g) mentions supply of water and air conditioning but is not shown on any of the drawings. Please advise.

Response: There is no requirement for supply of water for air conditioning, only drainage. The Special Specification has been updated accordingly.

Question 96: According to the specification section 07.05.07, water piping should be according to 07.04 - but it’s not listed in that section. Please advise.

Response: There is no Section 07.05.07 in the Special Specifications. If the reader intended to refer to Section 07.05.01, the piping requirements are clearly provided in Section 07.04 (see

07.04.01 through 07.04.05).

Question 97: According to the specification section 07.05.02 (g), material for external water piping should be black steel, but according to the specification for chapter 57 and the drawings it shows that the external water piping is HDPE. Please clarify.

Response: There is no paragraph 07.05.02 (g) in the Special Specifications, but please note, that black steel pipes shall be used for water hydrants and HDPE shall be used for main water supply piping, all in accordance with the drawings.

Question 98: Specification section 07.06.03 mentions a filter but it’s not shown on the drawings. Please advise.

Response: There is no requirement for a filter. The Special Specification has been updated accordingly.

Question 99: Specification section 07.06.04 mentions a return valve but it’s not shown on the drawings. Please advise.

Response: There is no mention of a return valve in section 07.06.04 of the Special Specifications.

Question 100: Specification section 07.06.04 mentions recursive flow preventive but it’s not shown on the drawings. Please advise.

Response: There is no requirement for recursive flow prevention. The Special Specification has been updated accordingly.

Solicitation W912GB-16-R-0030

As of 10 June 2016

Question 101: Specification section 07.06.06 mentions manometer and a thermometer but they are not shown on the drawings. Please advise.

Response: There is no requirement for manometer and thermometer. The Special Specification has been updated accordingly.

Question 102: Specification section 07.08.02 mentions that all of the materials for sewage and ventilation piping should be HDPE but specification section 07.04.01 and drawings show P.P piping. Please clarify.

Response: The Special Specification has been updated to provide clarification.

Question 103: Specification section 07.09.02 (a) is unclear if the toilet tank is visible or hidden.

Please clarify.

Response: The toilet tank shall be visible. The Special Specification has been updated accordingly.

Question 104: Specification section 57.02.07 mentions a pumping station but it’s not shown on the drawings. Please advise.

Response: There is no requirement for a sewage or water pumping station. The Special Specification has been updated accordingly.

Question 105: Drawings P-301 for building 300, shows on the legend “G.F.” Is that a Garden Faucet?

Response: Correct.

Question 106: The section “06.07 Special Hangar Doors” looks to be from the UFGS (Unified Facilities Guide Specifications) Section 08 34 16.20 – Vertical Lift Fabric Doors which is the design specification for US Military projects. Does UFGS 08 34 16.20 – Vertical Lift Fabric Door specification govern this project?

Response: There is no requirement that the door meets UFGS 08 34 16.20. The requirement shall be compliance with the Special Specification.

Question 107: On sheet A-271 it states “The contractor may suggest other options for hangar doors to the approval of the COR.” Are there any specific specifications or standards that these hangar door options must meet, such as the UFGS (Unified Facilities Guide Specifications) hangar door specifications?

Response: As there are few manufacturers capable of producing such large opening door spans and products on the market have very specific specifications. The referenced note was added in order to allow the Contractor to offer a similar product, as long as it meets the requirements set

Solicitation W912GB-16-R-0030

As of 10 June 2016 forth in the Special Specifications and Drawings. Note: A division of the opening door span by a rising middle rail shall not be allowed.

Question 108: Attachment 2 – Experience Information Sheet: please clarify whether the forth box from the top of page 1, namely – Name, email, phone and fax number of English speaking POC – refers to the bidder’s POC or the client’s POC.

Response: The reference box refers to the Client’s POC.

Question 109: CLIN 0006, Option 5: The Price Schedule states regarding Option 5:

Drawing A-122 states regarding Option 5:

Please advise which CLIN should include Hangars 06 and 12 concrete floors – CLIN 0001 (Base Bid) or CLIN 0006 (Option 5).

Response: Hangars 6 and 12 concrete floors are part of the Base Bid (CLIN 0001). See Drawings S-233, S-263, S-234 and S-264 for more detailed information.

Question 110: We could not find drawing E-121 – Rb red switch board and electrical diagram building no.300 – among the electrical drawings. Please provide.

Response: The entirety of Drawing E-121 was mistakenly not included. The correct version of E-121 is provided.

Question 111: Drawing E-108 includes a fuel controller. Please provide the technical requirements for this controller.

Response: Please see Chapter 38.07 in the Special Specification.

Question 112: The data provided through RFP documents only allows for very inaccurate earthworks quantities estimation:

a. The connection of the designed ground to the existing ground happens almost always outside the cross section borders. This is true for both the civil cross sections and the architectural cross sections.

b. The PDF files provided do not allow for the modelization of the survey.

Please provide sufficient data for accurate earthworks quantities estimation.

Response: a. The cross-sectional areas referenced must be connected to follow-on cross-sections to see the entirety of the ground surfaces. All the required information regarding the design ground and existing ground is provided in the solicitation documents.

b. A DWG file for earthworks was provided in Amendment 2.

Question 113: Several cross sections could not be found among RFP drawings:

Solicitation W912GB-16-R-0030

a. Western runway, civil cross sections 0 to 5

b. Road 4, civil cross sections 14 and 15

c. Road 8, civil cross section 12

d. Apron, civil cross sections 6 and 7

Please provide.

Response:

a. Drawing C-060 has been added with additional cross sections for the Western runway.

b. Road 4, Civil Cross Sections 14 and 15 - Information is in the sections of the Line Zone.

c. Road 8, Civil Cross Section 12 – Information is in the sections of Road 4.

d. Apron, Civil Cross Sections 6 and 7 - Information is in the sections of the Western

Runway.

Question 114: The special specification section 19.03.02 states:

Please confirm that the hangars’ metal structure should not be painted.

Response: The metal structure of the hangars shall be painted per structural drawings for the hangars and per Chapter 19.07 in Special Specifications.

Question 115: Section 02.12 of the special specification require the execution of lean concrete:

The hangar drawings do not include lean concrete. Please confirm that the contractor should perform the work according to the structural drawings with regard to the lean concrete.

Response: Hangars foundations do not include lean concrete. However, other buildings (e.g.

Building 400) do include lean concrete.

Question 116: The special specification, section 06.02.01, item d, states:

Drawing A-371 – Support Building 300 Wood Work Schedule 01 – requires finish type WD-01, which is defined in drawing A-003 – Architectural Finish Schedule – as “Wooden door wings Formica finish acc. to spec”.

Please confirm that the required wooden doors finish is according to drawing A-003.

Response: In accordance with Drawing A-003, the required wooden doors finish is "Formica".

Solicitation W912GB-16-R-0030

As of 10 June 2016

Question 117: In drawing A-461 – Support Building 400 Metal Work Schedule 01 – items 401, 402, 403 and 404 are defined as single wing steel blast & shrapnel resistant with electric control hardware.

a. Please clarify whether these doors are “steel blast & shrapnel resistant for medical institute” or blast doors for protected institute area called “Mamam door”.

b. According to home front command instruction it is forbidden to drill and to perform changes in doors that should be installed in protected areas such as shelters etc. Please clarify whether the contractor should proceed and install the steel blast & shrapnel resistant door with electric control hardware on the door.

c. Please clarify whether this electrical control hardware is an electrical lock such as the electromagnet installed on top of the wing door.

d. Please provide an electrical drawing showing how to connect the electrical compartments for the doors’ electrical control hardware.

e. Please confirm that the installation of the above electrical control hardware is not included in the contractor’s scope of work.

Response:

a. Since the doors have no protecting concrete walls, all blast doors in Bldg. 400 shall be “steel blast & shrapnel resistant for medical institute” type.

b. There shouldn't be any drilling or any changes in blast doors. Special plates were added to the doors to allow electric control hardware installation, see updated Drawing A-461.

c. The electrical control hardware is an electrical lock such as the electromagnet installed on top of the wing door. The contractor's work shall include conduits and preparations only.

Wiring and accessories will be supply and installed by others.

d. All the required information is on drawing E-64.

e. The contractor's work content conduits and preparations only, wiring and accessories will be supply and installed by others.

Question 118: Drawing A-381 detail 40-1-313 and drawing A-382 detail 40-1-310 show the following sequence of work: floor fill “Meda” concrete above the concrete floor, elastomeric modified bitumen coating, another layer of floor fill “Meda” concrete, and ceramic tiling. As common practice it is better to perform wet rooms sealant above concrete floor and to fill the gap between the concrete floor to the ceramic paving with “Sumsum” sand filling. In case of pipe leak it is also easier to open the tiles and fix the leak. Please approve the suggested method.

Response: This inquiry will not be answered during the solicitation, but may be submitted by the Contractor for COR approval during the construction.

Question 119: Drawing A-361 details A-301, A-302 and A-303 include the following remark:

“Electric control hardware will be added after the door assembly”. Please clarify what type of electric control hardware is required and confirm that this installation is not included in the contractor’s scope of work.

Response: The Contractor's work shall include conduits and preparations only. Wiring and accessories will be supply and installed by others. All the required information is on drawing E- 64.

Solicitation W912GB-16-R-0030

As of 10 June 2016

Question 120: Special specification section 12.03.01, item f, includes an unclear description of the interior window’s glass thickness:

Please confirm the performance of window’s glass as follows: 6 mm, +25 mm space between the panes, +6 mm outside pane tempered.

Response: The question refers to Section 12.03.11, item f. The performance of window’s glass as follows: 5 mm, +25 mm space between the panes, +6 mm outside pane tempered. The Special Specifications have been updated accordingly.

Question 121: Drawing A-363-4 detail A-341 requires natural anodized 2 mm aluminum sheet cover below and above the aluminum canopy. Please approve to perform aluminum sheet cover only above the canopy.

Response: The aluminum sheet cover shall be under the canopy in accordance with the drawings.

Question 122: The special specification section 12.05.04 item b:

Please clarify whether the contractor is required to connect canopy drain to the building’s drainage pipe which passes through building columns.

Response: The requirement has been deleted from the Special Specifications.

Question 123: Special specification section 02.04.06 item a:

Drawing A-201W – Hangars 200 Typical Wall Finishes Layout & Legend – defines reference XWL-01 as “Exterior exposed concrete wall with paint finishing acc. to finish schedule”.

Drawing A-003 – Architectural Finishes Schedule – defines XWL-01 as Exposed architectural concrete walls.

Please approve the performance of concrete walls according to drawings A-003.

Response: All concrete walls shall be "Exposed concrete walls" according to "XWL-01" on Drawing A-003.

Solicitation W912GB-16-R-0030

Question 124: In drawing A-461 – Support Building 400 Metal Work Schedule 01 – item M- 413 is described as “Single wing sliding metal doors”. The Details line says “Drawings number 3021, 3022 in IS 4422 part 2”. As per the details line this is a sliding door for a protected space, and the width of the door is above what is approved in the Israeli standard to Israeli door manufacturer such as Palraz and Ringle. The door described above shall have to be specially designed and will have to comply with the criteria and approval of the protection consultant.

Please approve supply and installation of a sliding door in the required dimensions, similar to the protective door as per the standard, yet without compliance to IS 4422 part 2.

Response: Blast doors details shall be according to drawings number 3021 and 3022 in Israeli Standard 4422 Part 2 but with a modification to the opening door dimensions. Therefore, the special blast doors will not have a certification of a standard door. However, aside from the door dimensions, special blast doors shall meet have the same specifications and details as the standard size certificated doors.

Please refer to Special Specification Chapter 6 – Joinery and Steel Metal Works Products, Paragraphs 06.05.02 – Relevant Documents and 06.05.03(b) – Blast Doors Reference Drawing Specifications

Question 125: Please clarify if outside aluminum vertical security 20x20 mm bars spaced 12 cm in all doors and windows, as shown on Drawing A-361, Details A301, A302, and A303 are aluminum 20x20 mm square bars (full) or aluminum 20x20 mm square tubes (hollow)?

Response: The outside aluminum vertical security bars shall be 20x20 hollow aluminum tubes.

Question 126: Section 38.03.02 a) requires that “The equipment's and materials shall be with a proof experience on previous Israeli Air Force similar project of an equal size.” We believe that this requirement effectively renders the pumps a sole source. Please confirm if this is the case or identify the list of approved manufacturers.

Response: The pumps are not a sole source as there is more than one manufacturer that can meet this requirement. Equivalent products or equipment may be acceptable but shall be subject to COR approval. Please see language clarification is Section 38.03.02 a) and b). A list of previously approved manufacturers will not be provided.

Question 127: Since the scope of the site development works in this project is huge and significantly affect project price and schedule, it is crucial that we receive DWG files of these works in order to achieve accurate pricing. Although this is not usually done in your RFPs, we kindly request that this time you provide DWG files for site development works to assist with this crucial aspect of the project. We shall be grateful for your unofficial reply as soon as possible.

Response: A DWG file for earthworks was provided in Amendment 2.

As of 10 June 2016

Question 128: RFP documents require eight Key Personnel: Project Manager, Site Superintendent, Site Safety and Health Officer, Contractor Quality Control Manager, QC Civil, QC Electrical, QC Mechanical and QC Structural. Yet, Attachment 4 – Resume Form – includes only four possible positions among which the relevant position is to be checked:

Please advise whether the contractor is to add the additional QC positions to the head of the Resume Form.

Response: Attachment 4 has been updated to include all key personnel positions.

Question 129: Organization chart: we have read the relevant sections of the USACE General Specifications carefully, yet could not find the required QCM’s reporting chain. Please clarify to whom the QCM reports within the reporting chain.

Response: Please see USACE Specification 01 45 01 USACE Quality Control, Paragraph 3.2.1 “Content of the CQC Plan.” The QCM (also identified as the “CQC System Manager”) shall report to the project superintendent.

Question 130: Please explain the meaning of “Cathodic Protection Line” on the legend of drawing

CP-001.

Response: It's the cathodic protection infrastructure. Please see CP drawings and Chapter 08.18 in the Special Specification for additional information.

Question 131: Drawing E-128 detail 28 – Shed red electrical switchboard front view – shows an electrical socked with interlock, yet the sheds red electrical boards’ drawings show regular electrical sockets, not electrical sockets with interlock. Please advise which sockets the contractor is required to supply.

Response: The socket with interlock. Drawings E-22 to E-25 and E-142 have been corrected accordingly.

Question 132: Drawing A-271 – Line + Aircraft Hangars Metal Work Schedule 01 – shows a vertical lifting fabric door with two integrated access doors which are an integral part of the fabric gate:

a. Please confirm that the lower part of the fabric gate which contains the access doors will be hardened, i.e. it will cover part of the hangar opening.

b. Please advise whether the fabric door should be installed against the existing structure or whether it will require its own structure wall support.

Response:

a. Correct. Minimum clear height required for the hangar doors shall be 4.00 m', the UK of the hangars structural beam is at level +6.07. The fabric gates could be installed in a higher position at the entrance and it will allow storing a full height access door with a solid section above the required clear height.

b. Hangars metal structure at the entrance area is designed to carry the door load. However, whether the doors could be installed against hangars structure or it requires its own structure or any additional support shall be according to the Contractor’s door manufacturer specifications and installation shop drawing details.

Question 133: Drawing P-002A, detail 40-13-06: please confirm that the “Granulary Matter” included in this details is local sand.

Response: Granulary Matter its type "A" sub base material compacted to 96% Modified

AASHO.

Question 134: On the 200-250KVA UPS system what is the Battery Run Time Required? Is it 10min, 15min, 30min or something else.

Response: A 15 minute in maximum load shall be required. See Section 08.01.01 in the Special Specifications.

Question 135: Reference: Special hangar doors.

As these doors are all custom designed to specific local wind loads and wind load design criteria we would like to request the following information so that we can calculate the wind pressure for each door.

CODE: ASCE 7-05 or ASCE 7-10 (Verify) Basic Wind Speed: _________ (MPH) Serviceability Wind Speed: _________(MPH) Occupancy / Risk Category: _________ (II, III, IIV)

Solicitation W912GB-16-R-0030

As of 10 June 2016

Exposure Category: __________(B, C, D) Enclosure Classification: Enclosed or Partially Enclosed (Verify)

Response: Please see Special Specification Section 06.07.04.1, Item a.

CODE: ASCE 7-05

Basic Wind Speed: See Section 06.07.04.1, Item a Serviceability Wind Speed: See Section 06.07.04.1, Item a Occupancy / Risk Category: II Exposure Category: D Enclosure Classification: Type 3

Question 136: Reference: Special hangar doors.

Please clarify what is the minimum clear height required for the hangar doors?

Response: The minimum clear height required for the hangar doors shall be 4.00 m'.

Question 137: Reference: Special hangar doors.

Section 06.070.01.01 Door Design states: “Manufacturer shall design and fabricate the door to fit within the space allocated and in accordance with the criteria specified herein”.

Scope of work for Alternate 6A, Option No. 6, include installation of the vertical lifting door to all opening width, 24 m, with an integrated 2 access doors, integral part of the fabric gate.

Please clarify if it was taken into account that when the vertical lift door have a “solid” section which incorporates access doors, the bottom part with exit door will hang below the lifted part and will require higher head room than shown in the section provided?

Response: See response to question #132a.

Question 138: Reference: Special hangar doors.

Please advise if the vertical lifting fabric door will be installed against existing structure or will require its own support construction.

Response: See response to question #132b.

Question 139: Reference: Special hangar doors.

Section 06.07.01.2 states: “All supporting, bracing and framing steel members shall be designed by a licensed professional engineer for the loads provided by the vertical lift fabric door manufacturer according to the requirements of AISC 325. Refer to Section 05 12 00 STRUCTURAL STEEL for requirements”. Section 05 12 00 STRUCTURAL STEEL is not included with other bid documents. Please provide referenced document.

Response: Section 05 12 00 Structural Steel is found in the American Institute of Steel Construction (AISC) M325 refer to website asic.org.

As of 10 June 2016

Question 140: Following drawings A & B shows that part of the plan roads has excavation works, part of the road has backfill earth works. Drawing C shows existing road level & plan level has different levels, and it probably required bypass road for construction period to allow traffic in construction duration. Please advise if this is the intention and if yes, please provide bypass road requirements.

Drawing A

Drawing B

Drawing C

Response: Please make sure you saw and understood the construction phasing requirements as shown in drawings A-111, A-112.1 to A-121.4. If any additional work roads are required, the

Solicitation W912GB-16-R-0030

As of 10 June 2016 contractor can feel free to execute inside of the work site as long as it does not conflict with the project drawings.

Question 141: The following drawing D shows existing underground sys need to be demo part of the excavation work at this area. Yet there is no by-pass for construction duration. Please advise if by-pass is required?

Drawing D

Response: Please see drawings A-111, A-112.1 to A-112.4, E-3, and E-5.

Question 142: The following plan shows that fuel sys in the option is under plan roads in the base bid. The duration of option exercise is 120 days from award date that could be 2-3 month after NTP date. In that scenario & date, Plan road construction could be backfill by layers, then excavation for the option fuel sys could be ask to be made again as to the fuel sys is LLI. Please advise.

Solicitation W912GB-16-R-0030

Response: As per Drawing A-122, Option #3 is a fuel station only. All the fuel infrastructure in the line zone are part of the Base Bid.

Question 143: Please advise if it was taken into account in the design that when folding fabric doors have a “solid” section which incorporates a pass door that the bottom part with the pass doors will hang below the folded part and will require higher head room than shown in the section provided.

Response: See response to question #132a.

Question 144: Please advise if the fabricated door will be installed against existing structure or will require its own support construction.

Response: See response to question #132b.

Question 145: On the 200-250KVA UPS system the drawing states 250KVA but the specification states 200KVA. Which applies.

Response: The UPS shall be 250 KVA in accordance with the drawings. The Special Specification has been revised accordingly.

Question 146: Section 00 21 00 Factor 3 Management Plan on page 33 of 207 requires the submittal schedule include a detailed resource levelling plan (e.g. time, manpower and budget).

It is not possible to provide this level of cost detail in a schedule at time of proposal because final costs are not known until the day of bid submission. The proposal including CD needs to be hand delivered to Germany several days prior to the date for receipt of proposals. Resource and cost loading of the schedule is normally only required to be submitted after project award. Please consider changing this to require submission of schedule but with no resource or cost loading at time of bid.

As of 10 June 2016

Response: For the resource leveling plan, the contractor shall provide, as part of the technical proposal, the number of personnel or man-hours AND the percent progress payment for each month from contract award to contract completion. This may be shown as a graphical representation.

Question 147: It is our understanding that recently the USACE has adopted the Contractor Performance Assessment Reporting System (CPARS) form as an acceptable evaluation report which replaces the DD2626 (CCASS) report. Is it acceptable to use the CPARS report in lieu of the DD2626 and/or PPQ?.

Response: Yes. The Solicitation has been revised to include CPARS as an acceptable source.

Question 148: This project scope includes a very large quantity of mass excavation (over 350,000 m3) and disposal (over 300,000 m3) which in areas is more than 15m deep. This quantity of earth moving will be very difficult to achieve within the 18 month schedule in Israel with limited trucking resources. Is there any chance that the project construction schedule could be extended to accommodate the massive quantity of earthwork excavation and hauling required.

Response: The period of performance has been assessed and determined to be adequate to achieve all scope requirements.

Question 149: Please provide location where exported excavated material will be hauled to.

Response: A quarry is located approximately 800 meters from the project work site. According to calculations the excavated materials, approximately 200,000 m3, will fit into the quarry. If additional space is needed, there is an alternate quarry approximately 5 km from the project site near the base’s south gate.

Question 150: According to the special specification chapter 18 (communication) the contractor should supply wiring, outlet etc. (optical, copper, telephone) In addition at the Special Specifications chapter 08, (page 202) it is mention that the contractor responsibility include :

However there is no plans that shows all the cables or other part (jumpers, hardware, optical equipment ), All the communication plans are refer to infrastructure: pipes and conduits .

For example: The cables & pipes list in plan E-05, there are no cables for communications only pipes.

If the communication equipment's and wiring are included in the bid and has to be supplied and installed by the contractor, please provide us with full communication plan.

Response: The communication equipment and wiring are not part of the SOW.

Question 151: In Amendment 0002 we received an AutoCAD File - 13580-002- For Distribution.dwg The drawing file does not contain sections that shows the existing situation in the site, so the file can be used in order to calculate the amounts of soil that has to be dig and

Solicitation W912GB-16-R-0030

As of 10 June 2016 transferred. Please provide us AutoCAD files of the current situation sections.

Response: The file provided in Amendment 0002 includes existing site level data from survey measurement and the designed site levels in the same drawing layer.

Question 152: USACE General Specifications, section 3.4:

Please confirm that SSHO is part of the CQC staff and reports directly to the QCM.

Response: Please see USACE Specification Section 01 45 01, subpart 3.2.1 Content of the CQC Plan. The QCM (identified as the QC System Manager) reports to the project superintendent.

Question 153: Attachment 4, Resume Form, experience section:

Please clarify whether “Company” refers to the company which employed the key personnel during the project’s period of performance or whether it refers to the client of this project.

Response: “Company” refers to the company which employed the key personnel during the project’s period of performance.

Question 154: Bid Bond: please advise whether the following Bid Bond wording is acceptable:

1. At the request of US Army Corps of Engineers (the “Principal”), we, [name of the surety] of [address of the surety] undertake to pay to you subject as hereinafter provided such amount as may be claimed by you in writing up to $3,000,000 in respect of the Principal’s tender dated 22 April 2016 for Project 13580 valid for a period of 120 days (the “Tender”) on the occurrence of either of the following events:

2. (1) Where you have indicated in writing your willingness to enter into a contract with the Principal (the “Contract”) either on the terms of the Tender or on such modified terms as may have been agreed between you and the Principal and the Principal has indicated to you that it does not wish to sign or otherwise enter into the Contract; or,

3. (2) Where you have signed the Contract with the Principal and where the Contract would have otherwise come into force except only for the Principal’s failure to provide any performance guarantee or bond required in connection with it by the times and on the conditions stipulated in the Contract.

4. Provided that no such amount shall become due and payable by us under this bond:

5. (1) Where the aggregate amount claimed exceeds $3,000,000;

Solicitation W912GB-16-R-0030

6. (2) More than [one month] after the validity period of the Tender has expired, unless we have been notified by the Principal that the period of validity of the Tender has been extended;

7. (3) Unless your written claim shall have been received by us accompanied by the following documents:

8. (a) In the circumstances provided for under (1) above, a copy certified by a notary public of your written indication to enter into the Contract with the Principal together with evidence of the Principal’s indication not to sign or otherwise enter into the contract;

9. (b) In the circumstances provided for under (2) above a copy, certified by a notary public, of the signed Contract together with evidence that you have fulfilled all your obligations precedent to the coming into force of the Contract and that the Contract would have come into force but for the Principal’s failure as stated above.

10. Our liability under this agreement shall cease and be terminated on whichever of the following events first occurs, upon which event this bond shall be returned to us for cancellation:

11. (1) When we have paid to you the amount of $3,000,000;

12. (2) When you have awarded the Contract to another company or organization or have indicated to the

Principal that the Tender will not be accepted or have otherwise indicated that no contract will be placed with any tenderer, whichever occurs the earlier;

13. (3) [One month] after the validity period of the Tender (including any agreed extension of it) has expired unless before that time we have received your written claim satisfying the conditions set out above.

14. This bond and any claims arising hereunder shall be governed in all respects by the law of province/state and any disputes in connection therewith shall be submitted to arbitration in accordance with applicable state/provincial arbitration legislation.

Response: The language provided is not acceptable. A blank Bid Bond Standard Form SF 24 has been included as an attachment to the Solicitation. Offeror’s shall submit Bid Bond SF 24 for the bid bonding requirement.

Question 155: The special specification, section 18.06, page 120, shows an oil transformer specification, with a list of accessories which includes an electrostatic screen:

a. Please advise whether this is a VSD transformer, and provide driver type.

b. Please clarify whether the rated power should be 630 or 635 kVA.

c. Please clarify whether the LV voltage should be 0,4 or 0,72 kV.

d. The losses and efficiency values are not compatible. Please clarify which values are correct.

Response: The question refers to Section 08.16 vice Section 18.06.

a. This is not a VSD transformer. It is a standard transformer.

b. The rated power shall be 630kVA. The Special Specification has been updated.

c. The voltage shall be 4 kV. The Special Specification has been updated.

d. Corrected in spec. accordingly:

No load losses (W) 600

Load losses (W) 6400

Question 156: Following Amendment 0002, your response to question no. 3:

Spec chapter 08.07.04 – Conduits – reads: “All red conduits shall be metallic and EMI/RFI shielded as specified bellow”.

a. There are discrepancies between the information in spec section 08.07.04 and the information in the excavation details. For example: drawing E-124 shows a PVC pipe.

Please re-check this issue.

b. There are discrepancies between the excavation details and the plans. For example:

drawing E-116:

The plan refers to typical excavation detail no.44 which appears in drawing E-124:

The detail does not show the pipe’s required depth. Please provide.

Drawing E-116 requires 3 pipes. Please provide the relevant detail.

Response: a. Section 08.07.04 refers to interior conduits. Section 08.07.04 has been clarified.

b. Drawing E-116 indicates four (4) not three (3) pipes are required. Detail # 44 on Drawing E-124 has been corrected to show all four (4) pipes. Please see Drawings C- 17 to C-21 for information on the depth of the pipes.

Question 157: Architectural drawing A-112.2 – Construction Phase 1A, Sheet 2 Dismantling and Demolition:

a. The plan requires the demolition of existing communication lines:

Solicitation W912GB-16-R-0030

The communication infrastructure dismantling route, which starts at the manholes located at the northern part of the plan and ends at the southwesterly part of the plan, is not fully included in the drawing E-128 – Dismantling Site Plan.

Please specify according to which plan the contractor should perform lines dismantling.

Please specify the types of pipes and the amount of pipes to be dismantled.

In case the dismantling is to be performed according to drawing A-112.2, please provide the southwesterly part of the plan so we may measure the length of the line to be dismantled.

b. The drawing shows a new electricity line for execution in phase 1A:

This requirement is not included in any of the RFP electrical drawings. Please specify the type of cable and connection points.

c. The drawings shows an existing electricity lighting line:

We could not find a lighting line along the existing roads. Please specify whether there are any existing lines and poles to be dismantled.

Response:

a. There question refers to Drawing E-126 vice E-128. Drawing E-126 has been deleted.

Dismantling and demolition works will be according to Drawings A-111, A-112.1 to

112.4. There is no additional information available about type and amount of pipes.

The scope includes dismantling all marked infrastructures. The southwestern part of the plan is shown on drawing A-112.1.

b. No electricity line is required for execution in Phase 1A. Drawing E-126 has been deleted.

c. The existing electrical lighting line is located along the western runway. Drawings A- 111, A-112.1 to A112.4 have been updated accordingly.

Question 158: Drawing E-83 Legend shows:

a. In additional feed drawings the red communication is marked orange and the black communication is marked red. Please advise whether the mistake is lines color or marking.

b. Please confirm that the red communication line is an existing line.

c. In Amendment 0002 revised drawings the following comment has been added:

Solicitation W912GB-16-R-0030

As per this comment we cannot understand the locations of road crossings. Please provide an updated drawing.

Response: The information has been added to Drawings E-80, 82, 83, and 76.

Question 159: Following Amendment 0002, your response to question no. 37 regarding the cathodic protection line: we could not find the relevant answer in spec chapter 08.18. Please clarify whether you require the addition of a conductor. If so, please specify the perimeter of this conductor.

Response: There are two (2) types of cables included in the Cathodic Protection System Installation. Please see Section 08.18.02, Item E: Cables Installation and Connections.

Question 160: Special specification chapter 08 page 124 requires a fuel system for generators feeding, yet no drawing has been found among RFP drawings for this system. Please provide.

Response: It's an integral fuel system and a part of the generator. Shop drawings shall be provided by a manufacturer according to the Special Specifications.

Question 161: Architectural drawing A-271 includes two alternatives of Option 6 aircraft hangar doors: Alt 6A and Alt 6B. Please clarify to which of the above alternatives should the contractor price.

Response: Both alternatives are acceptable under Option 6. The contractor can bid on the alternative he or she chooses.

Question 162: Special specification chapter 09.04 – Exterior Plaster – requires exterior plaster coating. The architectural drawings do not include exterior plaster coating. Please confirm that no exterior plaster coating is required in this project. In case an exterior plaster costing is required, please refer to the relevant drawings.

Response: The exterior plaster coating is required only as a fix to correcting the finish of exposed concrete if during the inspection and acceptance process the finish does not meet contract requirements. The Contracting Officer or their representative will notify the Contractor of the deficiency. The steps to correct the deficiency shall be submitted by Contractor to the COR for review and approval. Special Specification Section 09.04 and 09.04.01 has been updated to provide clarification.

Question 163: Drawings A-311W and A-312W legends include the following reference:

Special specification chapter 11.06 – Painting of Exposed Concrete Walls, section 11.06.01, item a:

Please confirm that the contractor is not required to paint the external exposed concrete walls with external paint.

Response: The Contractor shall be responsible for correcting the finish to exposed concrete if during the inspection and acceptance process the finish does not meet contract requirements.

The Contracting Officer or their representative will notify the Contractor of the deficiency. The steps to correct the deficiency shall be submitted by Contractor to the COR for review and approval. Pricing of the potential cost of corrective actions shall be included in the proposal response to the RFP.

Question 164: Special specification chapter 11.06 – Painting of Exposed Concrete Walls, section 11.06.01, item d:

Please clarify whether in the above case the contractor shall be required to paint only the specific problematic wall or he shall be required to paint all the project’s exposed concrete walls.

Response: See response to Question 163.

Question 165: Both Option 1 – Construction of Western Runway, and Option 2 – Construction of Eastern Taxiway, must be completed within 90 calendar days after the award dates of the options. The suppliers of the lighting fixtures for both runway and taxiway informed us that these are long lead items for which the delivery time is 15 weeks. Taking into consideration the addition of submittals’ approval time, it is highly unlikely that the runway and the taxiway CLINs will be completed within 90 days. Please consider extending the performance period for the lighting fixtures only by 30 days.

Response: The period of performance for Option 1 and Option 2 has been extended to 120 calendar days. The work on existing runways has operational impacts and therefore, the western and eastern runways shall not be in a non-operational status for a period that exceeds 60 calendar days. SR-0 and the Price Schedule have been updated accordingly.

Question 166: Since the construction area is very large, please confirm that more than one gate may be executed in the construction fence.

Response: The suggested approach may be submitted by the Contractor in their Mobilization Plan for approval.

As of 10 June 2016

Question 167: During the site visit we were told that the site offices area may be located anywhere within the limits of the main works site. Please confirm.

Response: The contractor’s selection of the location for their site offices will need to be included in the Mobilization Plan that is subject to the review and approval of the COR. The southern infrastructural area labeled “AR” must remain operational and the ability for traffic to go in and out of this area must be maintained during execution of the project.

Question 168: The original issue “package” file contains architectural drawings in a pdf file titled “Attch_17a2_Architectural.” This file starts with drawing A-252. Amendment #2 contains architectural drawings in a pdf tile titled “Amend_0002_Attch_17a1_a2_Architectural_Revision01.” This file starts with drawing A-001, which is a list of drawings in the A set and seems to correspond with the combined drawing list.

The second drawing in this amendment 2 file is A-003. The drawing list on A-001 indicates the hardware list is on A-002, but I did not see that drawing. The door details refer to hardware sets on the hardware list. Was drawing A-002 issued? If not, please issue hardware list.

In addition, in reviewing the drawing list, drawings A-004, A-005, the whole of the A-100 series (with the exception of A-123), and drawings prior to A-252 are not contained in the documents.

Is my file corrupt or are these documents not yet issued?

Response: The original posting for the Architectural Drawings were divided into two pdf files:

Attch_17a1_Architectural - Contained Drawings A001 - A248 Attch_17a2_Architectural - Contained Drawings A252 - A801

Drawing A-002 was included in Attch_17a1_Architectural.

The “Amend_0002_Attch_17a1_a2_Architectural_Revision01.pdf” file only included those drawings that were revised under Amendment 02.

Question 169: The road connecting the work site and the spillage site might be damaged in the course of the work.

a. Please provide the typical section and bearing capacity of the road.

b. Please clarify who is responsible for repairing the road.

Response: The requested information is not available on the road. It shall be the Contractor's responsibility to repair all roads damaged by the Contractor during the execution of the project to their original condition.

Question 170: Fuel Station – Building 700: the concrete slab below the underground fuel tanks appears on the architectural drawings, yet structural drawings for this slab are missing. Please provide.

Response: The details for the concrete slab of the fuel tanks are on Drawing F-006.

Solicitation W912GB-16-R-0030

Question 171: Section 38.04.08 requires that “The metering systems shall be manufactured by Liquid control M-5CX-2 type. We believe that this requirement is a sole source. Please confirm if this is the case.

Response: The Special Specification language has been updated to add “or equal.”

Question 172: Chapter 18 is difficult to follow/read as subsections are not formatted. Could this chapter be formatted for better readability?

Response: Yes, Chapter 18 has been formatted for better readability.

Question 173: There is a contradiction between the solicitation proposal preparation instructions and specific instructions in the Price Schedule.

The solicitation document (page 33 of 207) instructs as follows:

In the Price Schedule Revision 01, OPTION 1, it specifically states:

"Option 1 will not be awarded until 60 days after the base award NTP".

And Option 2 specifically states:

"Option 2 will not be issued until the Option 1 work has been completed and accepted by the government."

These contradictions in the documents will directly impact the schedule submittal.

Please clarify the starting date of Options 1 and 2 for the schedule submittal.

Response: The solicitation proposal submission instructions under Section 00 21 00 have been revised to match the Price Schedule and SR-0 as follows:

“For the purposes of this section only, the Offeror shall use the date of 02 January 2017 for Notice to Proceed and should prepare the schedule assuming Option 1 will be awarded 02 April 2017 (90 days after NTP) and Option 2 will be awarded 01 August 2017 (121 days after award of Option 1).”

Question 174: Please provide an additional information for sign painting details inside the hangars.

Response: Please see updated Drawings C-013 and C-014.

Question 175: Communication lines on sheets E-73 to E-83. Amendment 2, question 9, clarifies the red legend communication lines on sheets E-73 to E-83 are existing. The orange legend communication lines on sheets E-73 to E-83 appear to be existing as well, as they route in directions not shown on the drawings. Please confirm the orange legend communication line and

Solicitation W912GB-16-R-0030

As of 10 June 2016 associated manholes and signs are existing and not included in the scope of work.

Response: The orange legend communication line is a new line (i.e. PVC pipe 75 mm) and it's a part of the scope of work. No new manholes are designed as the new orange communication line connects to existing manholes along the route.