Amend_0001_Atch_01_Experience_Overview_Sheet.docx

DOCX document 30 KB Posted

Attached to
Project 13580 - Israel
Solicitation number
W912GB-16-R-0030
Issued by

About this file

Amendment 0001 with Attch 01_Experience Overview Sheet

View the file

Other files

File Type Posted
W912GB-16-R-0030 _Amd_09.pdf PDF
W912GB-16-R-0030 _Amd_08.pdf PDF
W912GB-16-R-0030 _Amd_07.pdf.doc.pdf PDF
W912GB-16-R-0030_Amendment_06_w_Attachments.pdf PDF
Amend_0005_Attch_22_Standard_Form_SF_24_Bid_Bond.pdf PDF
Amend_0005_Attch_17a1_a2_Architectural_Revision_02.pdf PDF
Amendment_0005_W912GB-16-R-0030_Site_13580_Israel.pdf PDF
Amend_0005_Attch_01_Experience_Overview_Sheet_Revision_01.docx DOCX document
Amend_0005_Attch_17d_Electrical_Revision_02.pdf PDF
Amend_0005_Attch_17b_Civil_Revision_01.pdf PDF
Amend_0005_Attch_04_Resume_Site_13580_Revision_01.pdf PDF
Amend_0005_Attch_21_Responses_to_RFIs_88-175.pdf PDF
Amend_0005_Attch_11_SRs_Project_13580_Revision_02.pdf PDF
Amend_0005_Attch_16_Drawings_List_13580_Revision_02.pdf PDF
Amend_0005_Attch_10_Price_Schedule_Site_13580_Revision_02.pdf PDF
Amend_0005_Attch_12_Special_Specifications_Project_13580_Revision_02.pdf PDF
Amendment_0004_W912GB-16-R-0030_Site_13580_Israel.pdf PDF
Amendment_0003_W912GB-16-R-0030_Site_13580_Israel.pdf PDF
Amend_0002_Attch_20_Earthworks.zip ZIP file
Amend_0002_Attch_17c_Structural_Revision01.pdf PDF
Amend_0002_Attch_11_SRs_Project_13580_Revision_01.pdf PDF
Amend_0002_Attch_12_Special_Specifications_-_Project_13580-Revision_01.pdf PDF
Amend_0002_Attch_18_Requests_for_Information_1-87_Site_13580_24May2016.pdf PDF
Amend_0002_Attch_19_13580_Site_Photos.pdf PDF
Amend_0002_Attch_17e_Fuel_Revision01.pdf PDF
Amend_0002_Attch_17a1_a2_Architectural_Revision01.pdf PDF
Amend_0002_Attch_16_Combined_Drawings_List_Site_13580_Revision_01.pdf PDF
Amendment_0002_W912GB-16-R-0030_Site_13580_Israel.pdf PDF
Amend_0002_Attch_17d_Electrical_Revision01.pdf PDF
Amend_0002_Attch_17h_Plumbing_Revision01.pdf PDF
Amend_0002_Attch_10_Price_Schedule_Site_13580_Revision_01.pdf PDF
Amend_0002_Attch_17i_Site_Development.pdf PDF
Amendment_0001_W912GB-16-R-0030_Site_13580_with_Attch_02and03.pdf PDF
Attch_17d_Electrical.pdf PDF
Attch_17a2_Architectural.pdf PDF
Attch_17c_Structural.pdf PDF
Attch_17b_Civil.pdf PDF
Attch_17e_Fuel.pdf PDF
Attch_17g_Mechanical.pdf PDF
Attch_17a1_Architectural.pdf PDF
Attch_17h_Plumbing.pdf PDF
Attch_17f_Cathodic_Protection.pdf PDF
Attch_14_USACE_General_Specifications_Site_13580.pdf PDF
Attch_3_Past_Performance_Questionnaire_13580.pdf PDF
Attch_10_Price_Schedule_Site_13580_14Apr2016.pdf PDF
Attch_2_Experience_Information_Sheet_Site_13580.pdf PDF
Attch_16_Combined_Drawings_List_Site_13580_22Apr16.pdf PDF
Attch_11_SRs_Site_13580_21April2016.pdf PDF
Attch_6_Contractor_Key_Personnel_Performance_Certification_Site_13580.pdf PDF
Attch_15_HNTRs_Site_13580.pdf PDF
Show 40 more

Latest 50 of 59 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Title: 13580 Project Location: Israel Solicitation Number: W912GB-16-R-0030 (Attachment 1)

Project Name
Prime
Sub
Joint Venture
Committed Subcontractor
Total $ Amount
Project Start Date
Project Completion Date
Projects which involve construction of large-scale aircraft operation and maintenance facilities including hangers, support buildings and fuel stations.
Projects with substantial concrete and steel works
Projects with significant road and runway works.
Projects similar in magnitude ($10,000,000 to $25,000,000) and complexity and of a similar duration as the work required under this solicitation
Projects demonstrating experience in Israel.
Project demonstrating that Offeror’s team members (including Key Personnel, subcontractors, commission specialist, and/or Joint Venture partners) have previously worked together.
Projects that are completed (as opposed to in-progress or on-going).
Project performed within the last six (5) years. Projects older than five (5) years will be evaluated but may be considered less relevant.
One (1) project completed within the last 5 years of the solicitation date or currently being performed (at least 50% complete) demonstrating the Prime Contractor’s experience working in the United States of similar magnitude, scope, complexity and schedule to the work required under this solicitation.

SAMPLE New Building Construction Location (City & Country) X

14,500,000
1-Jan-13
1-Jul-14
X
X
X
X
X
X
X

Attachment (1) – Experience Overview Sheet

File details come from the government source that posted it. Updated .