W912ES23B0019 0003 Amendment 0003.pdf
PDF 285 KB Posted
- Attached to
- Fargo Moorhead Metropolitan Area Flood Risk Management Project, Southern Embankment Reach SE-3
- Solicitation number
- W912ES23B0016
About this file
This document is an Amendment to a Solicitation for the Fargo Moorhead Metropolitan Area Flood Risk Management Project, Southern Embankment Reach SE-3. The amendment makes changes to the specifications and plans, removes and replaces the Bid Schedule, and adds a page to the Submittal Register. The key changes include revisions to the demolition payment provisions, aggregate surface course requirements, and addition of salvaged base course specifications. The solicitation is a small business set-aside Invitation for Bid (IFB) with a NAICS code of 237990, Other Heavy and Civil Engineering Construction. The anticipated contract value is between $25,000,000 and $100,000,000. Work to be performed includes constructing a 1.7-mile embankment, installing box culverts, removing temporary closures and levees, and utility relocations. Offerors must be registered in the System for Award Management (SAM) prior to award.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to make changes to the specif ications and plans, remove and replace the Bid Schedule, and add a page to the Submittal Register.
All other solicitation terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 7
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 06-Nov-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912ES23B0016
X 9B. DATED (SEE ITEM 11)
16-Oct-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
06-Nov-2024
CODE
CONTRACTING DIVISION
USACE, ST PAUL
332 MINNESOTA STREET
SUITE E1500
ST PAUL MN 55101-1323
W912ES 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912ES23B0016
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
SUMMARY OF AMENDMENT 0003
Plans:
Volume 2, Section 40, Sheet No. 1-2 is hereby removed and replaced by Volume 2, Section 40, Sheet No. 1-2, Amendment 003 (See W912ES23B0016_Amendment3 Vol2_Sec40_Sheet 1-2.pdf).
Submittal Register:
The following Submittals have been added to the required submittals following the revisions to the Project Specifications and should be added to the final Submittal Register (See W912ES23B0016_Amendment 0003 Submittal Register Addition.pdf):
Added:
SD-04 Samples Stockpile SD-06 Test Reports Salvaged Base Course
Specifications:
Section 01 22 00.00 13 Measurement and Payment Paragraph 1.8.2.1 Payment, which formerly read:
Payment will be made in the Base Bid for furnishing all materials, equipment, and labor and performing all operations necessary for demolition as indicated. Work includes, but is not limited to, the removal and disposal of existing utilities to be relocated, culverts, aggregate surface removal, and bituminous pavement.
If awarded, payment will be made in Option 1 for furnishing all materials, equipment, and labor and performing all operations necessary for demolition as indicated. Work includes, but is not limited to, the removal and disposal of flapgates, bulkheads, and culverts.
Offsite disposal fees are incidental to the work.
Is hereby changed to read:
Payment will be made in the Base Bid for furnishing all materials, equipment, and labor and performing all operations necessary for demolition as indicated. Work includes, but is not limited to, the removal and disposal of existing utilities to be relocated, culverts, aggregate surface removal, concrete and bituminous pavement.
If awarded, payment will be made in Option 1 for furnishing all materials, equipment, and labor and performing all operations necessary for demolition as indicated. Work includes, but is not limited to, the removal and disposal of flapgates, bulkheads, and culverts.
Offsite disposal fees are incidental to the work.
Section 02 41 00 Demolition Paragraph 3.3 Roadways, which formerly read:
Removal of roadways includes the aggregate surface and any granular subbase.
Is hereby changed to read:
Removal of roadways includes the aggregate surface, concrete pavement, bituminous pavement, and any granular subbase.
Section 31 00 00.00 13 Earthwork Paragraph 3.7 Existing Road Removal, which formerly read:
Strip the existing asphalt and aggregate surface from the existing road as indicated on the project plans and in accordance with NDDOT 216 and NDDOT 302.
Is hereby changed to read:
Strip the existing asphalt, concrete pavement, and aggregate surface from the existing road as indicated on the project plans and in accordance with NDDOT 216 and NDDOT 302.
Section 32 11 16.00 13 AGGREGATE SURFACE COURSE Paragraph 1.1 References, which formerly read:
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
NORTH DAKOTA DEPARTMENT OF TRANSPORTATION (NDDOT)
NDDOT 151 (2020) Standard Specifications for Road and Bridge Construction, General Equipment NDDOT 302 (2020) Standard Specifications for Road and Bridge Construction, Aggregate Base and Surface Course NDDOT 816 (2020) Standard Specifications for Road and Bridge Construction, Aggregates NDDOT 151 (2020) Standard Specifications for Road and Bridge Construction, Geosynthetics
Is hereby changed to read:
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
NORTH DAKOTA DEPARTMENT OF TRANSPORTATION (NDDOT)
NDDOT 151 (2020) Standard Specifications for Road and Bridge Construction, General Equipment NDDOT 302 (2020) Standard Specifications for Road and Bridge Construction, Aggregate Base and Surface Course NDDOT 816 (2020) Standard Specifications for Road and Bridge Construction, Aggregates NDDOT 817 (2020) Standard Specifications for Road and Bridge Construction, Salvaged Base Course NDDOT 151 (2020) Standard Specifications for Road and Bridge Construction, Geosynthetics
Paragraph 1.2 Submittals, which formerly read:
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals Aggregate Sources Aggregate material sources as specified in Paragraph MATERIAL SOURCES.
SD-04 Samples Aggregate Sample Samples of aggregate as specified in Paragraph MATERIAL SOURCES.
SD-06 Test Reports Testing Testing results as specified in Paragraph TESTING.
Is hereby changed to read:
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals Aggregate Sources Aggregate material sources as specified in Paragraph MATERIAL SOURCES.
SD-04 Samples Aggregate Sample Samples of aggregate as specified in Paragraph MATERIAL SOURCES.
Stockpile Stockpile Concrete and Bituminous stockpile samples and documentation of source origin.
SD-06 Test Reports Testing Testing results as specified in Paragraph TESTING.
Salvaged Base Course Blend and gradation testing.
Paragraph 2 Products, which formerly read:
2.1 Aggregate
NDDOT 816, Class 13 Aggregate.
2.2 MATERIAL SOURCES
It shall be the responsibility of the Contractor to make its own investigations for a source of suitable materials and to make its own arrangements with the owners of the pits for procuring the required quantity of suitable material. The Contractor shall designate in writing only one source or one combination of sources from which it proposes to furnish aggregate. A 50 pound aggregate sample shall be provided to the Contracting Officer. Approval of samples from a source of aggregate is not to be construed as approval of all materials from that source. The right is reserved to reject materials from certain localized areas, zones, strata, or channels when such materials are unsuitable for aggregate as determined by the Contracting Officer. Materials produced from an approved source shall meet all the requirements of this section.
2.3 GEOTEXTILE
Geotextile shall be a separation geotextile fabric meeting the requirements of Geotextile Type 2, in accordance with
SECTION 31 05 19 GEOTEXTILE.
Is hereby changed to read:
2.1 Aggregate
NDDOT 816, Class 13 Aggregate.
NDDOT 817, Salvaged Base Course.
2.2 MATERIAL SOURCES
It shall be the responsibility of the Contractor to make its own investigations for a source of suitable materials and to make its own arrangements with the owners of the pits for procuring the required quantity of suitable material. The Contractor shall designate in writing only one source or one combination of sources from which it proposes to furnish aggregate. A 50 pound aggregate sample shall be provided to the Contracting Officer. Approval of samples from a source of aggregate is not to be construed as approval of all materials from that source. The right is reserved to reject materials from certain localized areas, zones, strata, or channels when such materials are unsuitable for aggregate as determined by the Contracting Officer. Materials produced from an approved source shall meet all the requirements of this section.
Utilize all removed bituminous and concrete pavement into the salvaged base course meeting NDDOT 817. If a shortage of onsite salvageable material is encountered to obtain the minimum 30% blend, the remainder of the material may comprise of an approved stockpile of bituminous or concrete material proposed by the Contractor or virgin aggregate base course class 5. In the event virgin aggregate base course class 5 is utilized, salvaged base course is to be installed to the maximum uniform depth feasible across the full typical section width and full project length and the virgin aggregate base course class 5 installed above the salvaged base course to meet the full aggregate section shown in the plans.
2.3 GEOTEXTILE
Geotextile shall be a separation geotextile fabric meeting the requirements of Geotextile Type 2, in accordance with
SECTION 31 05 19 GEOTEXTILE.
Salvaged Base Course geotextile shall meet Geotextile Type R1 in accordance with Section 31 05 19
GEOTEXTILE.
Paragraph 3.1 General, which formerly read:
Aggregate surface course shall be constructed in accordance with the requirements of NDDOT 302 unless specified otherwise.
Is hereby changed to read:
Aggregate surface course shall be constructed in accordance with the requirements of NDDOT 302 unless specified otherwise. Salvaged Base Course shall be constructed in accordance with the requirements of NDDOT 302 except the term "engineer' referenced in the state standard specification shall mean the contracting officer.
SECTION 00 10 00 - SOLICITATION
The following have been modified:
BID SCHEDULE
CLIN DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL PRICE
0001 PERFORMANCE AND PAYMENT BONDS 1 JOB
0002 DEMOLITION 1 JOB
0003 TEMPORARY TRAFFIC CONTROL 1 JOB
0004 TEMPORARY EROSION CONTROL 1 JOB
0005 WATER AND SEWER 1 JOB
0006 COMUNICATION AND ELECTRICAL 1 JOB
0007 TOPSOIL STRIPPING 1 JOB
0008 PAVEMENT MARKING 1 JOB
0009 PERMANENT HIGHWAY SIGNS 1 JOB
0010 TEMPORARY IRRIGATION SYSTEM 1 JOB
0011 WATERING 1 JOB
0012 INSPECTION TRENCH 8,600 LF
0013 EXCAVATION
0013AA FIRST 104,030 CY - EXCAVATION 104,030 CY
0013AB OVER 104,030 CY - EXCAVATION 15,605 CY
0014 EMBANKMENT
0014AA FIRST 771,331 CY - EMBANKMENT 771,331 CY
0014AB OVER 771,331 CY - EMBANKMENT 115,700 CY
0015 TURF REINFORCEMENT MAT (TRM) 879,968 SF
0016 AGGREGATE SURFACE 18,719 TON
0017 SALVAGED BASE COURSE
0017AA FIRST 7,990 - SALVAGED BASE COURSE 7,990 CY
0017AB OVER 7,990 - SALVAGED BASE
COURSE
1,199 CY
0018 PERMANENT CR81 ASPHALT
PAVEMENT
16,499 SY
0019 PIPE CORRUGATED STEEL; .064IN
24IN
90 LF
0020 PIPE CORRUGATED STEEL; .064IN 30IN 92 LF
0021 PIPE CORRUGATED STEEL; .064IN 36IN 52 LF
0022 END SECTION CORRUGATED STEEL;
.064IN 24IN
4 EA
0023 END SECTION CORRUGATED STEEL;
.064IN 30IN
4 EA
0024 END SECTION CORRUGATED STEEL;
.064IN 36IN
2 EA
0025 PRECAST REINFORCED CONCRETE BOX
(RCB) CULVERT; 10 X 5
92 LF
0026 PRECAST REINFORCED CONCRETE BOX
(RCB) CULVERT; 10 X 7
45 LF
0027 PRECAST REINFORCED CONCRETE BOX
(RCB) CULVERT; 10 X 10
364 LF
0028 PRECAST CONCRETE END SECTION; 10
X 5
2 EA
0029 PRECAST CONCRETE END SECTION; 10
X 7
2 EA
0030 PRECAST CONCRETE END SECTION; 10
X 10
4 EA
0031 TOPSOIL RESPREAD
0031AA FIRST 273,787 - TOPSOIL RESPREAD 273,787 CY
0031AB OVER 273,787 - TOPSOIL RESPREAD 41,069 CY
0032 SEEDING 140.11 AC
0033 RIPRAP; R20 634 TON
0034 RIPRAP; R30 442 TON
0035 RIPRAP; R80 384 TON
0036 RIPRAP; R140 664 TON
0037 ACCESS GATE 2 EA
TOTAL OF AMOUNTS
(ITEM NOS. 0001 THROUGH 0037 INCL.)
OPTION 1
1001 PERFORMANCE AND PAYMENT BONDS 1 JOB
1002 DEMOLITION 1 JOB
1003 TEMPORARY TRAFFIC CONTROL 1 JOB
1004 TEMPORARY EROSION CONTROL 1 JOB
1005 TOPSOIL STRIPPING 1 JOB
1006 PERMANENT HIGHWAY SIGNS 1 JOB
1007 TEMPORARY IRRIGATION SYSTEM 1 JOB
1008 WATERING 1 JOB
1009 INSPECTION TRENCH 2,176 LF
1010 EXCAVATION
1010AA FIRST 12,257 - EXCAVATION 12,257 CY
1010AB OVER 12,257 - EXCAVATION 1,839 CY
1011 MUCK EXCAVATION
1011AA FIRST 17,778 - MUCK EXCAVATION 17,778 CY
1011AB OVER 17,778 - MUCK EXCAVATION 2,667 CY
1012 EMBANKMENT
1012AA FIRST 183,873 - EMBANKMENT 183,873 CY
1012AB OVER 183,873 - EMBANKMENT 27,581 CY
1013 TURF REINFORCEMENT MAT (TRM) 198,281 SF
1014 AGGREGATE SURFACE 578 TON
1015 TOPSOIL RESPREAD
1015AA FIRST 70,573 - TOPSOIL RESPREAD 70,573 CY
1015AB OVER 70,573 - TOPSOIL RESPREAD 10,586 CY
1016 ARTICULATED CONCRETE BLOCK 27,326 SF
1017 SEEDING 38.73 AC
1018 RIPRAP; R20 84 TON
TOTAL PRICE OF OPTION 1 (ITEMS 1001 THROUGH 1018 INCL.)
TOTAL PRICE BASE AND OPTION 1
(End of Summary of Changes)