This document is an Amendment to Solicitation W912ES23B0016 for the Fargo Moorhead Metropolitan Area Flood Risk Management Project, Southern Embankment Reach SE-3.
The amendment updates the bid schedule by revising the quantities for several bid items, including excavation, embankment, salvaged base course, topsoil respread, and muck excavation. It also modifies the measurement and payment section of the project specifications accordingly. Additionally, the amendment extends the bid opening date from November 21, 2024 to November 26, 2024. All other solicitation terms and conditions remain unchanged.
The overarching project includes constructing a 1.7-mile-long embankment section, closing a 0.2-mile gap, removing temporary closures and levees, and relocating utilities. The solicitation is a total small business set-aside, with an Invitation for Bid (IFB) procurement method. The anticipated project value is between $25,000,000 and $100,000,000, under NAICS code 237990 - Other Heavy and Civil Engineering Construction.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to remove and replace the Bid Schedule, update Measusrement and Payment Section 01 22 00.00 13, and to extend the date of bid opening date.
All other solicitation terms and conditions remain unchanged
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 18-Nov-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912ES23B0016
X 9B. DATED (SEE ITEM 11)
16-Oct-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
18-Nov-2024
CODE
CONTRACTING DIVISION
USACE, ST PAUL
332 MINNESOTA STREET
SUITE E1500
ST PAUL MN 55101-1323
W912ES 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912ES23B0016
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
SUMMARY OF AMENDMENT 0007
Bid Schedule The following quantities in the Bid Schedule were found to be incorrect and were updated as follows:
CLIN 0013AA - Previously Listed
FIRST 104,030 CY – EXCAVATION : 104,030 CY
Is hereby REMOVED
CLIN 0013AB - Previously Listed
OVER 104,030 CY – EXCAVATION : 15,605 CY
Is hereby REMOVED
CLIN 1010AA - Previously Listed
FIRST 12,257 CY – EXCAVATION : 12,257 CY
Is hereby REMOVED
CLIN 1010AB - Previously Listed
OVER 12,257 CY – EXCAVATION : 1,839 CY
Is hereby REMOVED
CLIN 0014AA - Previously Listed
FIRST 771,331 CY – EMBANKMENT : 771,331 CY
Is herby changed to
FIRST 715,694 CY – EMBANKMENT : 715,694 CY
CLIN 0014AB - Previously Listed
OVER 771,331 CY – EMBANKMENT : 115,700 CY
Is herby changed to
OVER 715,694 CY – EMBANKMENT : 178,923 CY
CLIN 0017AA - Previously Listed
FIRST 7,990 - SALVAGED BASE COURSE : 7,990 CY
Is herby changed to
FIRST 6,391 CY - SALVAGED BASE COURSE : 6,391 CY
CLIN 0017AB - Previously Listed
OVER 7,990 - SALVAGED BASE COURSE : 1,199 CY
Is herby changed to
OVER 6,391 CY - SALVAGED BASE COURSE : 1,598 CY
CLIN 0031 AA - Previously Listed
FIRST 273,787 - TOPSOIL RESPREAD : 273,787 CY
Is herby changed to
FIRST 229,850 CY - TOPSOIL RESPREAD : 229,850 CY
W912ES23B0016
CLIN 0031AB - Previously Listed
OVER 273,787 - TOPSOIL RESPREAD : 41,069 CY
Is herby changed to
OVER 229,850 CY - TOPSOIL RESPREAD : 57,463 CY
CLIN 1011AA - Previously Listed
FIRST 17,778 - MUCK EXCAVATION : 17,778 CY
Is herby changed to
FIRST 14,222 CY - MUCK EXCAVATION : 14,222 CY
CLIN 1011AB - Previously Listed
OVER 17,778 - MUCK EXCAVATION : 2,667 CY
Is herby changed to
OVER 14,222 CY - MUCK EXCAVATION : 3,556 CY
CLIN 0012AA - Previously Listed
FIRST 183,873 – EMBANKMENT : 183,873 CY
Is herby changed to
FIRST 147,098 CY – EMBANKMENT : 147,098 CY
CLIN 0012AB - Previously Listed
OVER 183,873 – EMBANKMENT : 27,581 CY
Is herby changed to
OVER 147,098 CY – EMBANKMENT : 36,774 CY
CLIN 0015AA - Previously Listed
FIRST 70,573 - TOPSOIL RESPREAD : 70,573 CY
Is herby changed to
FIRST 56,458 CY - TOPSOIL RESPREAD : 56,458 CY
CLIN 0015AB - Previously Listed
OVER 70,573 - TOPSOIL RESPREAD : 10,586 CY
Is herby changed to
OVER 56,458 CY - TOPSOIL RESPREAD : 14,114 CY
The bid schedule is replaced with the attached updated bid schedule dated 11-18-2024. There are no impacts to the plans with this amendment, only the listed changes to quantities in the bid schedule.
Project Specifications The following changes to project specifications shall be made as a result of the revisions to the bid schedule:
Section 01 22 00.00 13 Measurement and Payment Paragraph 1.9.2 Excavation , Paragraph 1.9.2.1 Payment, Paragraph 1.9.2.2 Measurement, and Paragraph 1.9.2.3 Unit of Measure shall be removed in their entirety.
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 21-Nov-2024 02:00 PM to 26-Nov-2024 02:00 PM.