W912ES23B0016 0007 Amend Schedule - Bid Opening Date.pdf

PDF 181 KB Posted

Attached to
Fargo Moorhead Metropolitan Area Flood Risk Management Project, Southern Embankment Reach SE-3
Solicitation number
W912ES23B0016
Issued by

About this file

This document is an Amendment to Solicitation W912ES23B0016 for the Fargo Moorhead Metropolitan Area Flood Risk Management Project, Southern Embankment Reach SE-3.

The amendment updates the bid schedule by revising the quantities for several bid items, including excavation, embankment, salvaged base course, topsoil respread, and muck excavation. It also modifies the measurement and payment section of the project specifications accordingly. Additionally, the amendment extends the bid opening date from November 21, 2024 to November 26, 2024. All other solicitation terms and conditions remain unchanged.

The overarching project includes constructing a 1.7-mile-long embankment section, closing a 0.2-mile gap, removing temporary closures and levees, and relocating utilities. The solicitation is a total small business set-aside, with an Invitation for Bid (IFB) procurement method. The anticipated project value is between $25,000,000 and $100,000,000, under NAICS code 237990 - Other Heavy and Civil Engineering Construction.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to remove and replace the Bid Schedule, update Measusrement and Payment Section 01 22 00.00 13, and to extend the date of bid opening date.

All other solicitation terms and conditions remain unchanged

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 18-Nov-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912ES23B0016

X 9B. DATED (SEE ITEM 11)

16-Oct-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

18-Nov-2024

CODE

CONTRACTING DIVISION

USACE, ST PAUL

332 MINNESOTA STREET

SUITE E1500

ST PAUL MN 55101-1323

W912ES 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912ES23B0016

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

SUMMARY OF AMENDMENT 0007

Bid Schedule The following quantities in the Bid Schedule were found to be incorrect and were updated as follows:

CLIN 0013AA - Previously Listed

FIRST 104,030 CY – EXCAVATION : 104,030 CY

Is hereby REMOVED

CLIN 0013AB - Previously Listed

OVER 104,030 CY – EXCAVATION : 15,605 CY

Is hereby REMOVED

CLIN 1010AA - Previously Listed

FIRST 12,257 CY – EXCAVATION : 12,257 CY

Is hereby REMOVED

CLIN 1010AB - Previously Listed

OVER 12,257 CY – EXCAVATION : 1,839 CY

Is hereby REMOVED

CLIN 0014AA - Previously Listed

FIRST 771,331 CY – EMBANKMENT : 771,331 CY

Is herby changed to

FIRST 715,694 CY – EMBANKMENT : 715,694 CY

CLIN 0014AB - Previously Listed

OVER 771,331 CY – EMBANKMENT : 115,700 CY

Is herby changed to

OVER 715,694 CY – EMBANKMENT : 178,923 CY

CLIN 0017AA - Previously Listed

FIRST 7,990 - SALVAGED BASE COURSE : 7,990 CY

Is herby changed to

FIRST 6,391 CY - SALVAGED BASE COURSE : 6,391 CY

CLIN 0017AB - Previously Listed

OVER 7,990 - SALVAGED BASE COURSE : 1,199 CY

Is herby changed to

OVER 6,391 CY - SALVAGED BASE COURSE : 1,598 CY

CLIN 0031 AA - Previously Listed

FIRST 273,787 - TOPSOIL RESPREAD : 273,787 CY

Is herby changed to

FIRST 229,850 CY - TOPSOIL RESPREAD : 229,850 CY

W912ES23B0016

CLIN 0031AB - Previously Listed

OVER 273,787 - TOPSOIL RESPREAD : 41,069 CY

Is herby changed to

OVER 229,850 CY - TOPSOIL RESPREAD : 57,463 CY

CLIN 1011AA - Previously Listed

FIRST 17,778 - MUCK EXCAVATION : 17,778 CY

Is herby changed to

FIRST 14,222 CY - MUCK EXCAVATION : 14,222 CY

CLIN 1011AB - Previously Listed

OVER 17,778 - MUCK EXCAVATION : 2,667 CY

Is herby changed to

OVER 14,222 CY - MUCK EXCAVATION : 3,556 CY

CLIN 0012AA - Previously Listed

FIRST 183,873 – EMBANKMENT : 183,873 CY

Is herby changed to

FIRST 147,098 CY – EMBANKMENT : 147,098 CY

CLIN 0012AB - Previously Listed

OVER 183,873 – EMBANKMENT : 27,581 CY

Is herby changed to

OVER 147,098 CY – EMBANKMENT : 36,774 CY

CLIN 0015AA - Previously Listed

FIRST 70,573 - TOPSOIL RESPREAD : 70,573 CY

Is herby changed to

FIRST 56,458 CY - TOPSOIL RESPREAD : 56,458 CY

CLIN 0015AB - Previously Listed

OVER 70,573 - TOPSOIL RESPREAD : 10,586 CY

Is herby changed to

OVER 56,458 CY - TOPSOIL RESPREAD : 14,114 CY

The bid schedule is replaced with the attached updated bid schedule dated 11-18-2024. There are no impacts to the plans with this amendment, only the listed changes to quantities in the bid schedule.

Project Specifications The following changes to project specifications shall be made as a result of the revisions to the bid schedule:

Section 01 22 00.00 13 Measurement and Payment Paragraph 1.9.2 Excavation , Paragraph 1.9.2.1 Payment, Paragraph 1.9.2.2 Measurement, and Paragraph 1.9.2.3 Unit of Measure shall be removed in their entirety.

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 21-Nov-2024 02:00 PM to 26-Nov-2024 02:00 PM.