W912ES22Q00050002.pdf

PDF 481 KB Posted

Attached to
Replacement Programable Logic Controllers (PLC) for Dredge Goetz Federal contract opportunity
Solicitation number
W912ES22Q0005
Issued by
Department of the Army Corps of Engineers Engineering District St Paul

View the file

Other files for this federal contract opportunity

Other files attached to Replacement Programable Logic Controllers (PLC) for Dredge Goetz, newest first.
File Type Posted
EI 1 Drawings Issued for Construction.pdf PDF
21Q00050005 Pictures 2.pdf PDF
W912ES22Q00050005.pdf PDF
EI 2 Drawings Issued for Construction.pdf PDF
EI 3 Drawings Issued for Construction.pdf PDF
W912ES22Q0005 Amendment 0004.pdf PDF
Dedge Goetz Automation Drawings PLC and Panel View Program.zip ZIP file
W912ES22Q00050003.pdf PDF
12. Engineering Pnael View Display Program Printout (goetzeng, REV 1.0).pdf PDF
1. Port Console Schematics (659-A598-05-100A to 659-A598-05-600A).pdf PDF
5. Aft I O Schematics (659-A598-05-100E to 659-A598-05-300E).pdf PDF
11. Console Panel View Displays Program Printout (corlever13, REV. 1.3).pdf PDF
8. Winch Logic Flow Chart Diagrams (659-L100-01 to 659-L400-01).pdf PDF
7. Field Instrumentation Drawing (659-C730-01).pdf PDF
13. DACS Dredge Display PC Screen Visual Basic Program Printout (REV 1.0....pdf PDF
10. PLC Program Printout (Rev. 1.0).pdf PDF
2. Starboard Console Schematics (659-A598-05-100B to 659-A598-05-600B).pdf PDF
4. Forward I O Schematics (659-A598-05-100D to 659-A598-05-500D).pdf PDF
9. PLC I O List (659-A598-03).pdf PDF
6. Dredge Automation Network Drawing (DA-1005-01).pdf PDF
3. Main PLC Schematics (659-A598-05-100C to 659-A598-05-1000C).pdf PDF
21Q01117 Pictures.pdf PDF
W912ES22Q00050001.pdf PDF
Allen Bradly Brand_Name_Justification (Signed).pdf PDF
W912ES22Q0005.pdf PDF
Show all 25

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W81G6712458646

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is changing the pre-quote inspection time frame. This amendment w ill also extend the due date and time for quotes.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 8

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 03-Nov-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912ES22Q0005

X 9B. DATED (SEE ITEM 11)

27-Oct-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

03-Nov-2021

CODE

CONTRACTING DIVISION

USACE - ST PAUL

180 FIFTH STREET EAST

SUITE 700

SAINT PAUL MN 55101-1678

W912ES 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912ES22Q0005

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

SOLICITATION/CONTRACT FORM

The required response date/time has changed from 24-Nov-2021 11:00 AM to 01-Dec-2021 12:00 PM.

The following have been modified:

STATEMENT OF WORK

1. PROJECT DESCRIPTION

The Saint Paul District of the U.S. Army Corps of Engineers (USACE) has issued this solicitation for the procurement, installation, testing, and commissioning of new model programable logic controllers and networking for the Dredge Goetz and 852 Booster. The U.S. Army Corps of Engineers, Saint Paul District, operates the Dredge Goetz in the northern sections of the Mississippi River.

The Contractor shall be responsible for procuring, installing, programming, commissioning, and testing of the PLC units on the Dredge Goetz and 852 Booster to include all labor and materials associated with the replacement of the PLC logic controllers and networking system. The Government will furnish all labor and materials to operate the dredge/booster systems during the testing and commissioning of the newly installed variable PLCs. The Government will provide feedback during the testing and commissioning on the new PLCs as to their operational performance. All installation and programming shall take place at our service base, located at 431 North Shore Drive, Fountain City, WI 54629.

The Contractor shall have a representative(s) present onsite to perform testing, commissioning, and provide oversight and programming of the PLC units. The testing of the PLCs shall be performed while the Dredge Goetz is operating under normal dredging conditions. The area of operation and testing shall be near our service base located at, Fountain City, Wisconsin. Any change in cost associated with a change in location shall be modified after award.

2. OPERATIONAL BACKGROUND

The Dredge Goetz is a hydraulic cutter suction dredge with a 22-inch suction and 20-inch discharge pipe. The dredge is 225 feet long by 39 feet wide with an operating draft of 5 feet. The dredge is powered using diesel-electric generator engines that produce a total of 4,000 horsepower at 1,200 rpm. Each generator can produce 1,300 KVA at an 80% continuous duty cycle.

The Dredge Goetz currently has swing winches installed on the port and starboard sides. The winch motors are controlled by individual variable frequency drives (VFDs), manufactured by ABB. The two winches are employed to swing the dredge back and forth across the river, allowing the cutterhead and main dredge pump suction to break up and clear away material from the river bottom. While in operation one winch is hauling and the opposite is paying out cable under variable hold-back tension, with both cables being connected to external anchors.

An operator controls the swing winches, spuds, carriage drive, ladder hoist and dredge pump motors through console-mounted joystick controls and push buttons. Once the dredge completes a swing from one side of the river to the other the swing process is reversed. The dredge is advanced into the dredge cut using a rack and pinion set-up driven by an ABB drive. Once advanced the operator will set the center spud and start the swing process again. The operator has the discretion to independently operate either the port and/or the starboard swing winch for other specific tasks. The dredge operates 24 hours per day 7 days per week for approximately 6 to 8 months out of the year. During a 24-hour period, the dredge typically logs between 16 and 20 hours of run time.

3. SCOPE OF WORK

The Contractor shall assume complete responsibility for providing new model PLCs, instrument panels, push buttons, and control joysticks. The contractor shall be responsible for removing and installing, programming, testing, and commissioning in accordance with the requirements of this contract. Should the Contractor determine at any time that they are unable to fulfill those responsibilities they shall notify the COR immediately of the problem experienced. The Contractor shall then abide by his/her proposed manner of correction.

The 1746 Allen Bradley hardware SLC 500 series shall be replaced with Allen Bradley 5069 compact Logix hardware. The processor must include program storage on non-volatile media. A copy of Studio 5000 shall be provided with this project to allow access to the PLC programming for viewing and editing. The Studio 5000 shall be licensed to the U.S. Army Corps of Engineers, Dredge Goetz. The Allen Bradley 1794 Flex I/O remote shall be replaced by Allen Bradley 5094 I/O hardware. The remote I/O and DH+ network shall be replaced with Ethernet Ring Network. The Dredge Goetz has a booster pump to assist with moving dredged material long distances. The booster and dredge communicate via radio interface. This radio interfaced must be maintained to provide communication from the dredge to the booster. The PLCs at the booster pump shall be replaced with updated Allen Bradley hardware.

The lever house is where the Dredge Goetz is controlled and where the instruments are monitored. The current Allen Bradley Panel View 2711P shall be replaced with Allen Bradley Panel View 5510. The graphic shall be upgraded to commensurate with the additional graphic capabilities. The new Allen Bradley displays shall need to communicate via ethernet network. The InduSoft HMI application on the stand-alone computer shall be replaced with Rockwell Software FactoryTalk View SE. This also needs to communicate on the Ethernet network. The intent of this project is to move many of the pushbuttons, selector switches, pilot lights and potentiometers to the new Allen Bradley panel screens. The new screens shall require replacement mounting plates to replace the existing plates on the current console. The current joysticks are potentiometer style. These joysticks shall be replaced with Hall Effect technology joysticks. Additionally, a fathometer shall be added to the communication with the PLC.

The PLC programming shall be modified, so the fathometer value shall be used to confirm the final digging depth and shall automatically adjust the ladder depth to achieve optimum digging depth. This auto adjust feature must be selectable for being on or off at the Allen Bradley 5510 panel view screen.

There is an engineering Allen Bradley panel screen located in the “hobby room” remotely from the lever control room. The current panel is used by the engineering staff to monitor various operation of the Dredge. This panel screen shall include at a minimum the following: gland seal pressure, cutter flushing pressure, radial thrust bearing oil pressure, cutterhead reduction gear oil pressure, flushing water pressure, pipeline velocity, suction density, dredge pump speed, Hoffer valve operation, motor load, and suction and discharge pressures.

The current Electrical Schematic does not reflect the As Installed system. Some of the I/Os are shown on the incorrect I/O points and others are missing completely. A new set of Electrical Schematics shall be provided using an AutoCAD format and PDF.

The ABB Variable Frequency Drives (VFD) are controlled by Device Net communication. The ABB VFDs must be modified to communicate via Ethernet communications with the new PLCs.

The Contractor shall provide programming and commissioning of the new PLCs. The Contractor shall ensure that the PLCs are configured for the dredge’s operation.

The Contractor shall be required to provide all labor and material necessary to install the equipment. The Government will be responsible for the operation of the dredge and will perform testing on the condition that the Contractor has given the direction that all installation and programming is ready for testing. The Contractor shall have a representative (s) on site during installation and testing of the newly installed PLCs.

4. DEFINITIONS

The following definitions are applicable to phrases and acronyms used throughout this contract:

COR - Contracting Officer’s Representative - a member of the contract management and quality assurance team authorized by the Contracting Officer to perform certain administrative and managerial duties. A copy of the COR’s authority letter is furnished to the Contractor.

K.O. - Contracting Officer - A person with the authority to enter, administer and/or terminate contracts and make related determinations and findings.

QC - Quality Control - Quality Control is a function of the Contractor. Quality Assurance (QA) is a function of the Government.

USACE – Acronym for United States Army Corps of Engineers.

PLC – Programmable Logic Controller

5. CONTRACTOR QUALITY STANDARDS

All material, machinery, and equipment shall be new, of current manufacture, and suitable for the marine service intended. Spare parts and service shall be readily obtainable.

All material, unless otherwise specified in these specifications or in the drawings, shall be of commercial quality to ASTM, ANSI, or SAE specifications.

During construction and before delivery, the Contractor shall be responsible for protection of all material, equipment, etc., intended for the Dredge Goetz.

All materials shall be free of imperfections due to manufacturing processes and from defects which adversely affect appearance or serviceability.

The Contractor shall utilize the specified components to meet specification requirements utilizing construction and testing methods to ensure that the completed PLCs conform to the intended design.

Inspection by the Government is for the purpose of verifying the proper function of the Contractor’s quality control measures and is not to be used as a substitute for control of quality by the Contractor.

6. STANDARD PARTS & MATERIALS

All articles, fittings, equipment, machinery, and supplies and materials used in the construction and outfitting of the PLCs shall be the highest grade, free from defects and imperfections, unused and be the standard product of reputable manufacturers, to the maximum extent practicable. Any material not specified shall be the best of their kind for the purpose intended.

Materials specified herein to meet the requirements of standard specifications published by national authorities shall conform to the respective editions specified, including amendments. No salvage materials shall be used in the work.

7. Programmable Logic Controllers

The existing PLCs are manufactured by Allen Bradley with the following model and specifications:

Dredge Goetz Allen Bradley Series Number: Processor SLC 500 Allen Bradley Part Number: 1747-L543 852 Booster Allen Bradley Series Number: Processor SLC 500 Allen Bradley Part Number: 1747-L532 Dredge Goetz & 852 Booster Allen Bradley Series Number: Processor SLC 500 Allen Bradley Part Number: 1746-NI8 Dredge Goetz & 852 Booster Allen Bradley Series Number: SLC 500 Allen Bradley Part Number: 1746-IF4 Dredge Goetz & 852 Booster Allen Bradley Series Number: SLC 500 Allen Bradley Part Number: 1747-SDN Dredge Goetz & 852 Booster Allen Bradley Series Number: SLC 500 Allen Bradley Part Number: 1747-SN Dredge Goetz & 852 Booster Allen Bradley Series Number: SLC 500 Allen Bradley Part Number: 1746-OW8 Dredge Goetz & 852 Booster Allen Bradley Series Number: SLC 500 Allen Bradley Part Number: 1746-P4 Dredge Goetz Allen Bradley Series Number: Panel View 1000 Color Terminal (Qty 2) Allen Bradley Part Number: 2711-T10C8

8. Ethernet connection to PLC

All new power cables shall be like Seacoast XTA series, 90 degree C rated, armored, USCG & ABS approved.

Armored cables used shall be basket weave armor (aluminum jacket) in accordance with IEEE-45 or equivalent (as classified by UL as IEEE-45 equivalent). The cable armor shall be installed grounded at both ends.

The contractor shall select the size of the cables based on the voltage drop analysis and current distribution requirements from the one-line diagrams.

All new cabling for control, monitoring, and alarm applications shall be suitable for shipboard applications, and shall be in accordance with the requirements from the equipment manufacturer that the cabling is being used for.

All wiring shall be clipped and bracketed to provide straight, vertical, and horizontal runs throughout the dredge.

Care shall be taken to run all power cables separate from all control signal cables to avoid field interference.

All cable installations shall be supported on galvanized steel brackets and shall comply with all applicable provisions of IEEE-45. Cable supports shall be heavy enough to bear the weight of cables without bending, and all supports shall have rough or sharp edges removed so that cable armor will not be damaged. Horizontal runs of cable shall be supported by brackets spaced every 2 feet. Vertical runs of cables shall be supported every 2 feet with individual cable straps and bar hangers or brackets.

If new cable trays are required, the trays shall be routed to avoid mechanical and structural interference. The cable trays shall be routed in the overhead as much as practical. Cable trays shall be like RT&D Inverted “T” Style.

Soldering shall be performed only with resin or other neutral flux. Ends of all wires not tinned by the cable manufacturer shall be tinned before securing to terminals or before applying lugs. Solderless lugs shall be used wherever practicable. Terminals or lugs that will be soldered to cable ends will first be cleaned and tinned or treated with a neutral flux to ensure a good bond.

Connections to equipment and terminal boards shall be made with compression type connectors. Ring tongue compression terminals shall be used for all control terminations. Ends of all cables shall be sealed against moisture by taping in combination with insulating compounds or other approved methods. All electrical junction boxes, switch boxes and outlet boxes shall be cast brass, or bronze.

Cable penetrations throughout non-watertight bulkheads and decks shall have ample bearing surfaces. Cable penetrations through watertight decks or bulkheads shall use multi-cable transits like the ROX System or brass or steel stuffing tubes. Multi-cable transits shall be installed with spares to allow for the addition of cables. Enclosure penetrations shall use brass stuffing tubes.

Existing multi-cable transits may be used as part of this work provided; they do not exceed 90% fill at completion of the work.

Reused cables are to be cut back to proper length if the new location or termination results in excess cable. Excess cable shall not be left hanging in coils or on top of wireways to reduce induction currents. If the new location or termination is further than the existing cable will reach, the cable shall be spliced using an ABS approved splice kit, connection box, or the cable shall be replaced at Contractor's option. If the cable is spliced or a connection box is installed the splice or connection box shall be indicated on the new one-line diagram.

9. Design and Installation Standards

All work performed under this Contract shall be in accordance with the latest edition and interpretations of the rules, regulations, requirements, and standards of the legislation, regulatory agencies, and technical organizations listed as follows or as stipulated in the respective specification clause:

American Boat and Yacht Council (ABYC) – Standards and Technical Information Reports for Small Craft

– Section E – Electrical Division – Rules as applicable based on vessel particulars

American Bureau of Shipping (ABS) - Rules below as applicable based on vessel particulars -o Rules for Building and Classing Steel Vessels o Rules for Building and Classing Steel Vessels Under 90 Meters (295 Feet) in Length o Rules for Building and Classing Steel Vessels for Service on Rivers and Intracoastal Waterways o Rules for Building and Classing Steel Barges

46 CFR - Subchapters below as applicable based on vessel particulars -o Subchapter C – Uninspected Vessels o Subchapter H – Passenger Vessels o Subchapter K – Small Passenger Vessels Carrying More than 150 Passengers or with Overnight

Accommodations for more than 49 Passengers o Subchapter M – Towing Vessels o Subchapter T – Small Passenger Vessels (Under 100 Gross Tons)

46 CFR Subchapter J – Electrical Engineering

U.S. Army Corps of Engineers, Publication No. EM 385-1-1, “Safety and Health Requirements Manual.”

(http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf)

U.S. Army Corps of Engineers, Publication No. ER 385-1-100, “Safety and Occupational Health: Arc Flash Hazard Program” (http://www.publications.usace.army.mil/Portals/76/Publications/EngineerRegulations/ER_385-1- 100.pdf?ver=2014-11-20-123724-203)

Institute of Electrical and Electronic Engineers Standards, Publication No. IEEE-45 – Recommended Practice for Electrical Installations on Shipboard.

Institute of Electrical and Electronic Engineers Standards, Publication No. IEEE-519 "Recommended Practices and Requirements for Harmonic Control in Electrical Power Systems"

National Electric Code (NEC)

10. On-site Acceptance Testing

Upon completion of the installation, the new PLCs system shall be thoroughly tested and operated in the presence of the Physical Support Branch Representative, to such extent as necessary to demonstrate satisfactory operation as designed and specified. All PLC driven system tests shall be performed in accordance with the manufacturer’s recommended factory procedure for the equipment.

1 Electrical Cabling

The Contractor shall inspect all terminations of electrical cabling.

A. Programmable Logic Controllers

Demonstrate the operation of the PLCs. Ensure all PLC driven components work as per the manufacture specification and the operational capacities of the dredge Goetz.

B. Programmable Logic Controllers Testing & Acceptance

Testing of the PLCs shall be performed while the dredge Goetz is operating under normal dredging conditions. The area of operation and testing shall be near our service base located at, Fountain City, Wisconsin. Any change in cost associated with a change in location shall be modified after award.

11. Dredge PRE-PREPOSAL Inspection

Pre-quote inspections are encouraged and may be held by appointment, between November 4, 2021 through November 24, 2021, to allow all prospective offerors to inspect the vessel, existing VFDs, A/C motors, PLCs, and electrical and bus connections prior to submission of a proposal. Currently the Dredge Goetz is located at mile marker 26 on the Missouri River (Saint Louis, Missouri). The Dredge will be in that area until the 8th of November.

The Dredge will then be in transit from Saint Louis from the 9th of November until approximately the 18th of November. During transit back to Fountain City Service Base, inspections can still be performed between 0700 and 1530. Inspections shall be at the offeror’s expense and can be scheduled for any weekday, excluding federal holidays, between the hours of 0700 and 1530. Representatives of prospective offeror’s interested in attending should contact Jake Bernhardt at (651) 290-5981 or Adam Loven (651) 290-5141 to make an appointment.

During the pre-quote inspections, representatives of the Government will be available, but only to the extent necessary to escort offerors and assist with access. Government Representatives on the vessel will not discuss the scope of the work or make any technical clarifications or interpretations.

All technical questions resulting from this inspection must be submitted in writing via email to the contracting official (see Notes to Offeror section). The Government will formally respond to all questions in an amendment to the Solicitation.

12. Foreign Nationals Working on Government Contracts

For a foreign national to be permitted to work on a Government contract, the Contractor must submit a letter requesting such to the Foreign Disclosure Officer (FDO). The FDO will conduct a disclosure review and provide a recommendation to the Contracting Officer. If the request is approved, the foreign national must always be escorted while on Government property or work site. Letters should be mailed to Foreign Disclosure Officer (Carol Bridges), ATTN: CEMVK-PM, 4155 Clay Street, Vicksburg, MS 39183.

13. Warranty

Standard Warranty shall be 12 months from the date of start-up, not to exceed 18 months from the date of shipment.

The warranty shall include all parts and services.

With a certified start-up, warranty shall be 24 months from the date of start-up, not to exceed 30 months from the date of shipment. The warranty shall include all parts, labor, travel time, and expenses.

There shall be 24/365 support available on a toll-free-line.

14. Project timeframe for completion

Once the award has been made to a contractor the work can begin at the completion of the dredging season, tentatively 30 November 2021. The latest completion date shall be no later than 30 April 2021. After 30 April the dredging season typically begins. The operational testing of the new PLCs can take place on the very first dredging job for the season. Simple operational testing at the service base (non-dredging) can begin once the contactor notifies the Physical Support Branch Representative that the equipment can be energized and tested.

15. Manuals

The contractor shall supply manuals for the newly installed equipment.

Delivery and Installation Location Information:

United States Army Corps of Engineers Attn: Dredge Goetz 431 North Shore Drive Fountain City, WI 54629

Hours of Operation:

0700 – 1530: Monday – Friday Closed: Weekends & Holidays

Billing Address:

Adam Loven Plant and Facilities Engineer 431 North Shore Drive Fountain City, WI 54629 Cell #: 651-290-5141 E-mail: Adam.F.Loven@usace.army.mil

On-site Supervisor’s and Technical Point of Contact’s:

Jacob Bernhardt Chief of Physical Support 431 north Shore Drive Fountain City, WI 54629 Office #: 651-290-5981 Work Cell #: 612-770-6455 E-Mail: Jacob.T.Bernhardt@usace.army.mil