Replacement Programable Logic Controllers (PLC) for Dredge Goetz Federal contract opportunity
Solicitation number
W912ES22Q0005
Issued by
Department of the Army Corps of Engineers Engineering District St Paul

View the file

Other files for this federal contract opportunity

Other files attached to Replacement Programable Logic Controllers (PLC) for Dredge Goetz, newest first.
File Type Posted
EI 2 Drawings Issued for Construction.pdf PDF
EI 3 Drawings Issued for Construction.pdf PDF
W912ES22Q00050005.pdf PDF
EI 1 Drawings Issued for Construction.pdf PDF
21Q00050005 Pictures 2.pdf PDF
W912ES22Q0005 Amendment 0004.pdf PDF
Dedge Goetz Automation Drawings PLC and Panel View Program.zip ZIP file
13. DACS Dredge Display PC Screen Visual Basic Program Printout (REV 1.0....pdf PDF
10. PLC Program Printout (Rev. 1.0).pdf PDF
2. Starboard Console Schematics (659-A598-05-100B to 659-A598-05-600B).pdf PDF
4. Forward I O Schematics (659-A598-05-100D to 659-A598-05-500D).pdf PDF
9. PLC I O List (659-A598-03).pdf PDF
6. Dredge Automation Network Drawing (DA-1005-01).pdf PDF
11. Console Panel View Displays Program Printout (corlever13, REV. 1.3).pdf PDF
8. Winch Logic Flow Chart Diagrams (659-L100-01 to 659-L400-01).pdf PDF
7. Field Instrumentation Drawing (659-C730-01).pdf PDF
W912ES22Q00050003.pdf PDF
12. Engineering Pnael View Display Program Printout (goetzeng, REV 1.0).pdf PDF
1. Port Console Schematics (659-A598-05-100A to 659-A598-05-600A).pdf PDF
5. Aft I O Schematics (659-A598-05-100E to 659-A598-05-300E).pdf PDF
3. Main PLC Schematics (659-A598-05-100C to 659-A598-05-1000C).pdf PDF
W912ES22Q00050002.pdf PDF
21Q01117 Pictures.pdf PDF
W912ES22Q00050001.pdf PDF
Allen Bradly Brand_Name_Justification (Signed).pdf PDF
Show all 25

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ADDENDUM

(No Collect Calls)

W912ES22Q0005 27-Oct-2021

b. TELEPHONE NUMBER

651-290-5415

8. OFFER DUE DATE/LOCAL TIME

11:00 AM 24 Nov 2021

5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA – FAR (48 CFR) 53.212

(TYPE OR PRINT)

(SIGNATURE OF CONTRACTING OFFICER)

ADDENDA ARE

26. TOTAL AWARD AMOUNT (For Gov t. Use Only )

23.

CODE 10. THIS ACQUISITION IS

SUCH ADDRESS IN OFFER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT

BELOW IS CHECKED

TELEPHONE NO.

W912ES9. ISSUED BY

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

THEODORE R. HECHT

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER

(TYPE OR PRINT)

30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA

0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.

25. ACCOUNTING AND APPROPRIATION DATA

1. REQUISITION NUMBER

20.

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

W81G6712458646

ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

. YOUR OFFER ON SOLICITATION

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

% FOR:SET ASIDE:UNRESTRICTED OR X

SMALL BUSINESSX

17a.CONTRACTOR/ CODE FACILITY

OFFEROR CODE

CONTRACTING DIVISION

USACE - ST PAUL

180 FIFTH STREET EAST

SUITE 700

SAINT PAUL MN 55101-1678

18a. PAYMENT WILL BE MADE BY CODE

RATED ORDER UNDER

DPAS (15 CFR 700)

13a. THIS CONTRACT IS A

13b. RATING

CODE15. DELIVER TO CODE 965605 16. ADMINISTERED BY

12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

14. METHOD OF SOLICITATION

RFQ IFB RFPX

DREDGE - GOETZ

ADAM FREDE LOVEN

DREDGE GOETZ 431 NORTH SHORE DRIVE

FOUNTAIN CITY WI 54629

TEL: 651-290-5141 FAX:

FAX:

TEL: 651-290-5414 SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

8(A)

HUBZONE SMALL

BUSINESS

SIZE STANDARD:

NAICS:

334513

X

OFFER DATED

29. AWARD OF CONTRACT: REF.

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

EMAIL:

TEL:

31c. DATE SIGNED

SEE SCHEDULE

SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT

24.22.21.19.

WOMEN-OWNED SMALL BUSINESS (WOSB)

ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

(CONTINUED)

PAGE 2 OF37

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

37. CHECK NUMBER

FINALPARTIALCOMPLETE

36. PAYMENT35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER

FINAL

33. SHIP NUMBER

PARTIAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV. 2/2012) BACK

Prescribed by GSA – FAR (48 CFR) 53.212

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

SEE SCHEDULE

20.

SCHEDULE OF SUPPLIES/ SERVICES

21.

QUANTITY UNIT

22. 23.

UNIT PRICE

24.

AMOUNT

19.

ITEM NO.

W912ES22Q0005

Section SF 1449 - CONTINUATION SHEET

STATEMENT OF WORK

1. PROJECT DESCRIPTION

The Saint Paul District of the U.S. Army Corps of Engineers (USACE) has issued this solicitation for the procurement, installation, testing, and commissioning of new model programable logic controllers and networking for the Dredge Goetz and 852 Booster. The U.S. Army Corps of Engineers, Saint Paul District, operates the Dredge Goetz in the northern sections of the Mississippi River.

The Contractor shall be responsible for procuring, installing, programming, commissioning, and testing of the PLC units on the Dredge Goetz and 852 Booster to include all labor and materials associated with the replacement of the PLC logic controllers and networking system. The Government will furnish all labor and materials to operate the dredge/booster systems during the testing and commissioning of the newly installed variable PLCs. The Government will provide feedback during the testing and commissioning on the new PLCs as to their operational performance. All installation and programming shall take place at our service base, located at 431 North Shore Drive, Fountain City, WI 54629.

The Contractor shall have a representative(s) present onsite to perform testing, commissioning, and provide oversight and programming of the PLC units. The testing of the PLCs shall be performed while the Dredge Goetz is operating under normal dredging conditions. The area of operation and testing shall be near our service base located at, Fountain City, Wisconsin. Any change in cost associated with a change in location shall be modified after award.

2. OPERATIONAL BACKGROUND

The Dredge Goetz is a hydraulic cutter suction dredge with a 22-inch suction and 20-inch discharge pipe. The dredge is 225 feet long by 39 feet wide with an operating draft of 5 feet. The dredge is powered using diesel-electric generator engines that produce a total of 4,000 horsepower at 1,200 rpm. Each generator can produce 1,300 KVA at an 80% continuous duty cycle.

The Dredge Goetz currently has swing winches installed on the port and starboard sides. The winch motors are controlled by individual variable frequency drives (VFDs), manufactured by ABB. The two winches are employed to swing the dredge back and forth across the river, allowing the cutterhead and main dredge pump suction to break up and clear away material from the river bottom. While in operation one winch is hauling and the opposite is paying out cable under variable hold-back tension, with both cables being connected to external anchors.

An operator controls the swing winches, spuds, carriage drive, ladder hoist and dredge pump motors through console-mounted joystick controls and push buttons. Once the dredge completes a swing from one side of the river to the other the swing process is reversed. The dredge is advanced into the dredge cut using a rack and pinion set-up driven by an ABB drive. Once advanced the operator will set the center spud and start the swing process again. The operator has the discretion to independently operate either the port and/or the starboard swing winch for other specific tasks. The dredge operates 24 hours per day 7 days per week for approximately 6 to 8 months out of the year. During a 24-hour period, the dredge typically logs between 16 and 20 hours of run time.

3. SCOPE OF WORK

The Contractor shall assume complete responsibility for providing new model PLCs, instrument panels, push buttons, and control joysticks. The contractor shall be responsible for removing and installing, programming, testing, and commissioning in accordance with the requirements of this contract. Should the Contractor determine at any time that they are unable to fulfill those responsibilities they shall notify the COR immediately of the problem experienced. The Contractor shall then abide by his/her proposed manner of correction.

The 1746 Allen Bradley hardware SLC 500 series shall be replaced with Allen Bradley 5069 compact Logix hardware. The processor must include program storage on non-volatile media. A copy of Studio 5000 shall be provided with this project to allow access to the PLC programming for viewing and editing. The Studio 5000 shall be licensed to the U.S. Army Corps of Engineers, Dredge Goetz. The Allen Bradley 1794 Flex I/O remote shall be replaced by Allen Bradley 5094 I/O hardware. The remote I/O and DH+ network shall be replaced with Ethernet Ring Network. The Dredge Goetz has a booster pump to assist with moving dredged material long distances. The booster and dredge communicate via radio interface. This radio interfaced must be maintained to provide communication from the dredge to the booster. The PLCs at the booster pump shall be replaced with updated Allen Bradley hardware.

The lever house is where the Dredge Goetz is controlled and where the instruments are monitored. The current Allen Bradley Panel View 2711P shall be replaced with Allen Bradley Panel View 5510. The graphic shall be upgraded to commensurate with the additional graphic capabilities. The new Allen Bradley displays shall need to communicate via ethernet network. The InduSoft HMI application on the stand-alone computer shall be replaced with Rockwell Software FactoryTalk View SE. This also needs to communicate on the Ethernet network. The intent of this project is to move many of the pushbuttons, selector switches, pilot lights and potentiometers to the new Allen Bradley panel screens. The new screens shall require replacement mounting plates to replace the existing plates on the current console. The current joysticks are potentiometer style. These joysticks shall be replaced with Hall Effect technology joysticks. Additionally, a fathometer shall be added to the communication with the PLC.

The PLC programming shall be modified, so the fathometer value shall be used to confirm the final digging depth and shall automatically adjust the ladder depth to achieve optimum digging depth. This auto adjust feature must be selectable for being on or off at the Allen Bradley 5510 panel view screen.

There is an engineering Allen Bradley panel screen located in the “hobby room” remotely from the lever control room. The current panel is used by the engineering staff to monitor various operation of the Dredge. This panel screen shall include at a minimum the following: gland seal pressure, cutter flushing pressure, radial thrust bearing oil pressure, cutterhead reduction gear oil pressure, flushing water pressure, pipeline velocity, suction density, dredge pump speed, Hoffer valve operation, motor load, and suction and discharge pressures.

The current Electrical Schematic does not reflect the As Installed system. Some of the I/Os are shown on the incorrect I/O points and others are missing completely. A new set of Electrical Schematics shall be provided using an AutoCAD format and PDF.

The ABB Variable Frequency Drives (VFD) are controlled by Device Net communication. The ABB VFDs must be modified to communicate via Ethernet communications with the new PLCs.

The Contractor shall provide programming and commissioning of the new PLCs. The Contractor shall ensure that the PLCs are configured for the dredge’s operation.

The Contractor shall be required to provide all labor and material necessary to install the equipment. The Government will be responsible for the operation of the dredge and will perform testing on the condition that the Contractor has given the direction that all installation and programming is ready for testing. The Contractor shall have a representative (s) on site during installation and testing of the newly installed PLCs.

4. DEFINITIONS

The following definitions are applicable to phrases and acronyms used throughout this contract:

COR - Contracting Officer’s Representative - a member of the contract management and quality assurance team authorized by the Contracting Officer to perform certain administrative and managerial duties. A copy of the COR’s authority letter is furnished to the Contractor.

K.O. - Contracting Officer - A person with the authority to enter, administer and/or terminate contracts and make related determinations and findings.

QC - Quality Control - Quality Control is a function of the Contractor. Quality Assurance (QA) is a function of the Government.

USACE – Acronym for United States Army Corps of Engineers.

PLC – Programmable Logic Controller

5. CONTRACTOR QUALITY STANDARDS

All material, machinery, and equipment shall be new, of current manufacture, and suitable for the marine service intended. Spare parts and service shall be readily obtainable.

All material, unless otherwise specified in these specifications or in the drawings, shall be of commercial quality to ASTM, ANSI, or SAE specifications.

During construction and before delivery, the Contractor shall be responsible for protection of all material, equipment, etc., intended for the Dredge Goetz.

All materials shall be free of imperfections due to manufacturing processes and from defects which adversely affect appearance or serviceability.

The Contractor shall utilize the specified components to meet specification requirements utilizing construction and testing methods to ensure that the completed PLCs conform to the intended design.

Inspection by the Government is for the purpose of verifying the proper function of the Contractor’s quality control measures and is not to be used as a substitute for control of quality by the Contractor.

6. STANDARD PARTS & MATERIALS

All articles, fittings, equipment, machinery, and supplies and materials used in the construction and outfitting of the PLCs shall be the highest grade, free from defects and imperfections, unused and be the standard product of reputable manufacturers, to the maximum extent practicable. Any material not specified shall be the best of their kind for the purpose intended.

Materials specified herein to meet the requirements of standard specifications published by national authorities shall conform to the respective editions specified, including amendments. No salvage materials shall be used in the work.

7. Programmable Logic Controllers

The existing PLCs are manufactured by Allen Bradley with the following model and specifications:

Dredge Goetz Allen Bradley Series Number: Processor SLC 500 Allen Bradley Part Number: 1747-L543 852 Booster Allen Bradley Series Number: Processor SLC 500 Allen Bradley Part Number: 1747-L532 Dredge Goetz & 852 Booster Allen Bradley Series Number: Processor SLC 500 Allen Bradley Part Number: 1746-NI8 Dredge Goetz & 852 Booster Allen Bradley Series Number: SLC 500 Allen Bradley Part Number: 1746-IF4 Dredge Goetz & 852 Booster Allen Bradley Series Number: SLC 500 Allen Bradley Part Number: 1747-SDN Dredge Goetz & 852 Booster Allen Bradley Series Number: SLC 500 Allen Bradley Part Number: 1747-SN Dredge Goetz & 852 Booster Allen Bradley Series Number: SLC 500 Allen Bradley Part Number: 1746-OW8 Dredge Goetz & 852 Booster Allen Bradley Series Number: SLC 500 Allen Bradley Part Number: 1746-P4 Dredge Goetz Allen Bradley Series Number: Panel View 1000 Color Terminal (Qty 2) Allen Bradley Part Number: 2711-T10C8

8. Ethernet connection to PLC

All new power cables shall be like Seacoast XTA series, 90 degree C rated, armored, USCG & ABS approved.

Armored cables used shall be basket weave armor (aluminum jacket) in accordance with IEEE-45 or equivalent (as classified by UL as IEEE-45 equivalent). The cable armor shall be installed grounded at both ends.

The contractor shall select the size of the cables based on the voltage drop analysis and current distribution requirements from the one-line diagrams.

All new cabling for control, monitoring, and alarm applications shall be suitable for shipboard applications, and shall be in accordance with the requirements from the equipment manufacturer that the cabling is being used for.

All wiring shall be clipped and bracketed to provide straight, vertical, and horizontal runs throughout the dredge.

Care shall be taken to run all power cables separate from all control signal cables to avoid field interference.

All cable installations shall be supported on galvanized steel brackets and shall comply with all applicable provisions of IEEE-45. Cable supports shall be heavy enough to bear the weight of cables without bending, and all supports shall have rough or sharp edges removed so that cable armor will not be damaged. Horizontal runs of cable shall be supported by brackets spaced every 2 feet. Vertical runs of cables shall be supported every 2 feet with individual cable straps and bar hangers or brackets.

If new cable trays are required, the trays shall be routed to avoid mechanical and structural interference. The cable trays shall be routed in the overhead as much as practical. Cable trays shall be like RT&D Inverted “T” Style.

Soldering shall be performed only with resin or other neutral flux. Ends of all wires not tinned by the cable manufacturer shall be tinned before securing to terminals or before applying lugs. Solderless lugs shall be used wherever practicable. Terminals or lugs that will be soldered to cable ends will first be cleaned and tinned or treated with a neutral flux to ensure a good bond.

Connections to equipment and terminal boards shall be made with compression type connectors. Ring tongue compression terminals shall be used for all control terminations. Ends of all cables shall be sealed against moisture by taping in combination with insulating compounds or other approved methods. All electrical junction boxes, switch boxes and outlet boxes shall be cast brass, or bronze.

Cable penetrations throughout non-watertight bulkheads and decks shall have ample bearing surfaces. Cable penetrations through watertight decks or bulkheads shall use multi-cable transits like the ROX System or brass or steel stuffing tubes. Multi-cable transits shall be installed with spares to allow for the addition of cables. Enclosure penetrations shall use brass stuffing tubes.

Existing multi-cable transits may be used as part of this work provided; they do not exceed 90% fill at completion of the work.

Reused cables are to be cut back to proper length if the new location or termination results in excess cable. Excess cable shall not be left hanging in coils or on top of wireways to reduce induction currents. If the new location or termination is further than the existing cable will reach, the cable shall be spliced using an ABS approved splice kit, connection box, or the cable shall be replaced at Contractor's option. If the cable is spliced or a connection box is installed the splice or connection box shall be indicated on the new one-line diagram.

9. Design and Installation Standards

All work performed under this Contract shall be in accordance with the latest edition and interpretations of the rules, regulations, requirements, and standards of the legislation, regulatory agencies, and technical organizations listed as follows or as stipulated in the respective specification clause:

American Boat and Yacht Council (ABYC) – Standards and Technical Information Reports for Small Craft

– Section E – Electrical Division – Rules as applicable based on vessel particulars

American Bureau of Shipping (ABS) - Rules below as applicable based on vessel particulars -o Rules for Building and Classing Steel Vessels o Rules for Building and Classing Steel Vessels Under 90 Meters (295 Feet) in Length o Rules for Building and Classing Steel Vessels for Service on Rivers and Intracoastal Waterways o Rules for Building and Classing Steel Barges

46 CFR - Subchapters below as applicable based on vessel particulars -o Subchapter C – Uninspected Vessels o Subchapter H – Passenger Vessels o Subchapter K – Small Passenger Vessels Carrying More than 150 Passengers or with Overnight

Accommodations for more than 49 Passengers o Subchapter M – Towing Vessels o Subchapter T – Small Passenger Vessels (Under 100 Gross Tons)

46 CFR Subchapter J – Electrical Engineering

U.S. Army Corps of Engineers, Publication No. EM 385-1-1, “Safety and Health Requirements Manual.”

(http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf)

U.S. Army Corps of Engineers, Publication No. ER 385-1-100, “Safety and Occupational Health: Arc Flash Hazard Program” (http://www.publications.usace.army.mil/Portals/76/Publications/EngineerRegulations/ER_385-1- 100.pdf?ver=2014-11-20-123724-203)

Institute of Electrical and Electronic Engineers Standards, Publication No. IEEE-45 – Recommended Practice for Electrical Installations on Shipboard.

Institute of Electrical and Electronic Engineers Standards, Publication No. IEEE-519 "Recommended Practices and Requirements for Harmonic Control in Electrical Power Systems"

National Electric Code (NEC)

10. On-site Acceptance Testing

Upon completion of the installation, the new PLCs system shall be thoroughly tested and operated in the presence of the Physical Support Branch Representative, to such extent as necessary to demonstrate satisfactory operation as designed and specified. All PLC driven system tests shall be performed in accordance with the manufacturer’s recommended factory procedure for the equipment.

1 Electrical Cabling

The Contractor shall inspect all terminations of electrical cabling.

A. Programmable Logic Controllers

Demonstrate the operation of the PLCs. Ensure all PLC driven components work as per the manufacture specification and the operational capacities of the dredge Goetz.

B. Programmable Logic Controllers Testing & Acceptance

Testing of the PLCs shall be performed while the dredge Goetz is operating under normal dredging conditions. The area of operation and testing shall be near our service base located at, Fountain City, Wisconsin. Any change in cost associated with a change in location shall be modified after award.

11. Dredge PRE-PREPOSAL Inspection

Pre-quote inspections are encouraged and may be held by appointment, between September 27th through October 15, 2021, to allow all prospective offerors to inspect the vessel, existing VFDs, A/C motors, PLCs, and electrical and bus connections prior to submission of a proposal. Inspections shall be at the offeror’s expense and can be scheduled for any weekday, excluding federal holidays, between the hours of 0700 and 1530. Representatives of prospective offeror’s interested in attending should contact Jake Bernhardt at (651) 290-5981 or Adam Loven (651) 290-5141 to make an appointment.

During the pre-quote inspections, representatives of the Government will be available, but only to the extent necessary to escort offerors and assist with access. Government Representatives on the vessel will not discuss the scope of the work or make any technical clarifications or interpretations.

All technical questions resulting from this inspection must be submitted in writing via email to the contracting official (see Notes to Offeror section). The Government will formally respond to all questions in an amendment to the Solicitation.

12. Foreign Nationals Working on Government Contracts

For a foreign national to be permitted to work on a Government contract, the Contractor must submit a letter requesting such to the Foreign Disclosure Officer (FDO). The FDO will conduct a disclosure review and provide a recommendation to the Contracting Officer. If the request is approved, the foreign national must always be escorted while on Government property or work site. Letters should be mailed to Foreign Disclosure Officer (Carol Bridges), ATTN: CEMVK-PM, 4155 Clay Street, Vicksburg, MS 39183.

13. Warranty

Standard Warranty shall be 12 months from the date of start-up, not to exceed 18 months from the date of shipment.

The warranty shall include all parts and services.

With a certified start-up, warranty shall be 24 months from the date of start-up, not to exceed 30 months from the date of shipment. The warranty shall include all parts, labor, travel time, and expenses.

There shall be 24/365 support available on a toll-free-line.

14. Project timeframe for completion

Once the award has been made to a contractor the work can begin at the completion of the dredging season, tentatively 30 November 2021. The latest completion date shall be no later than 30 April 2021. After 30 April the dredging season typically begins. The operational testing of the new PLCs can take place on the very first dredging job for the season. Simple operational testing at the service base (non-dredging) can begin once the contactor notifies the Physical Support Branch Representative that the equipment can be energized and tested.

15. Manuals

The contractor shall supply manuals for the newly installed equipment.

Delivery and Installation Location Information:

United States Army Corps of Engineers Attn: Dredge Goetz 431 North Shore Drive Fountain City, WI 54629

Hours of Operation:

0700 – 1530: Monday – Friday Closed: Weekends & Holidays

Billing Address:

Adam Loven

Plant and Facilities Engineer 431 North Shore Drive Fountain City, WI 54629 Cell #: 651-290-5141 E-mail: Adam.F.Loven@usace.army.mil

On-site Supervisor’s and Technical Point of Contact’s:

Jacob Bernhardt Chief of Physical Support 431 north Shore Drive Fountain City, WI 54629 Office #: 651-290-5981 Work Cell #: 612-770-6455 E-Mail: Jacob.T.Bernhardt@usace.army.mil

NOTES TO QUOTERS

NOTES TO QUOTERS

This section provides general guidance for preparing the quotation in response to this solicitation. The Quoter’s response to this solicitation must include all data and information requested herein in accordance with these instructions.

Price Proposal: This is the solicitation in its entirety. Quoter to complete the following:

Standard Form 1449 Solicitation/Contract/Order for Commercial Items - Complete Blocks 17, and 30a/b/c

Acknowledgement of Amendments – Complete only as necessary and provide signed copies of the Standard Form 30 Amendment of Solicitation/Modification of Contract with your quote.

Price Quote– All pricing (unit, total, subtotal, grand total, etc.) must be in whole penny amounts.

FAR Clause 52.212-3 Offeror Representations and Certifications – Commercial Items (Feb 2021) Alternate I (Oct 2014) – This provision is included by reference. Review paragraph (b)(2) “Annual Representations and Certifications” of the basic clause at https://www.acquisition.gov/, complete as necessary and return one copy with your quote.

Technical Documents: N/A

Submitting Quotes – All transmittals shall be submitted electronically to Theodore.R.Hecht@usace.army.mil and be clearly marked in the subject line of the email with the solicitation number, W912ES22Q0005. Quotes must be received no later than the date and time stated in the solicitation. Quotes received after the deadline are Late and may not be considered for contract award.

Questions – All questions concerning the solicitation document shall be submitted no later than COB November 15, 2021 via email to Theodore.R.Hecht@usace.army.mil. Answers to questions will be provided to all quoters being solicited though an amendment, giving due regard to the proper protection of proprietary information.

QUOTERS SHALL BE REGISTERED IN SAM (System for Award Management) https://www.sam.gov to include the FAR and DFARS Reps and Certs sections (refer to FAR Clause 52.204-13 “System for Award Management Maintenance”).

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Set Allen Bradley 5069 compact Logix

FFP

Replacing Allen Bradley SLC 500 series hardware FOB: Destination

PURCHASE REQUEST NUMBER: W81G6712458646

PSC CD: J020

NET AMT

0002 1 Each Studio 5000 Software

FFP

Licensed to U.S. Army Corps of Engineers - Dredge Goetz FOB: Destination

0003 1 Set Allen Bradley 5094 I/O Hardware

FFP

Allen Bradley 5094 I/O Hardware to replace Allen Bradley 1794 Flex I/O remote FOB: Destination

0004 1 Set Booster Pump PLCs

FFP

Replace PLC at booster pump with updated Allen Bradley hardware FOB: Destination

0005 1 Set Allen Bradley Panel View 5510

FFP

Current Allen Bradley Panel View 2711P shall be replaced with Allen Bradley Panel View 551 FOB: Destination

0006 1 Set Rockwell Software FactoryTalk View SE

FFP

Rockwell Software FactoryTalk View SE replacing the InduSoft HMI application on the stand-alone computer FOB: Destination

0007 1 Set Hall Effect technology joysticks

FFP

Hall Effect technology joysticks to replace potentiometer style current joysticks FOB: Destination

0008 1 Job Add Fathometer to PLC Communication

FFP

Fathometer shall be added to the communication with the PLC. The PLC programming shall be modified, so the fathometer value shall be used to confirm the final digging depth and shall automatically adjust the ladder depth to achieve optimum digging depth. This auto adjust feature must be selectable for being on or off at the Allen Bradley 5510 panel view screen.

FOB: Destination

0009 1 Job Replace Engineering Panel Screen

FFP

There is an engineering Allen Bradley panel screen located in the “hobby room” remotely from the lever control room. The current panel is used by the engineering staff to monitor various operation of the Dredge. This panel screen shall include at a minimum the following: gland seal pressure, cutter flushing pressure, radial thrust bearing oil pressure, cutterhead reduction gear oil pressure, flushing water pressure, pipeline velocity, suction density, dredge pump speed, Hoffer valve operation, motor load, and suction and discharge pressures.

FOB: Destination

0010 1 Job Installation and Programming

FFP

FOB: Destination

0011 1 Job Testing and Commissioning

FFP

FOB: Destination

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 Destination Government Destination Government 0002 Destination Government Destination Government 0003 Destination Government Destination Government 0004 Destination Government Destination Government 0005 Destination Government Destination Government 0006 Destination Government Destination Government 0007 Destination Government Destination Government 0008 Destination Government Destination Government 0009 Destination Government Destination Government 0010 Destination Government Destination Government 0011 Destination Government Destination Government

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 30-APR-2022 1 DREDGE - GOETZ

ADAM FREDE LOVEN

DREDGE GOETZ 431 NORTH SHORE

DRIVE

FOUNTAIN CITY WI 54629

651-290-5141 FOB: Destination

965605

0002 30-APR-2022 1 (SAME AS PREVIOUS LOCATION)

0003 30-APR-2022 1 (SAME AS PREVIOUS LOCATION)

0004 30-APR-2022 1 (SAME AS PREVIOUS LOCATION)

0005 30-APR-2022 1 (SAME AS PREVIOUS LOCATION)

0006 30-APR-2022 1 (SAME AS PREVIOUS LOCATION)

0007 30-APR-2022 1 (SAME AS PREVIOUS LOCATION)

0008 30-APR-2022 1 (SAME AS PREVIOUS LOCATION)

0009 30-APR-2022 1 (SAME AS PREVIOUS LOCATION)

0010 30-APR-2022 1 (SAME AS PREVIOUS LOCATION)

0011 30-APR-2022 1 (SAME AS PREVIOUS LOCATION)

CLAUSES INCORPORATED BY REFERENCE

52.203-3 Gratuities APR 1984 52.203-12 Limitation On Payments To Influence Certain Federal

Transactions

JUN 2020

52.204-7 System for Award Management OCT 2018 52.204-13 System for Award Management Maintenance OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-18 Commercial and Government Entity Code Maintenance AUG 2020 52.204-19 Incorporation by Reference of Representations and

Certifications.

DEC 2014

52.204-22 Alternative Line Item Proposal JAN 2017 52.204-24 Representation Regarding Certain Telecommunications and

Video Surveillance Services or Equipment.

OCT 2020

52.211-6 Brand Name or Equal AUG 1999 52.212-1 Instructions to Offerors--Commercial Items SEP 2021 52.212-3 Alt I Offeror Representations and Certifications--Commercial

Items (FEB 2021) Alternate I

OCT 2014

52.212-4 Contract Terms and Conditions--Commercial Items OCT 2018 52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business

Subcontractors

DEC 2013

252.201-7000 Contracting Officer's Representative DEC 1991

252.203-7000 Requirements Relating to Compensation of Former DoD Officials

SEP 2011

252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7005 Representation Relating to Compensation of Former DoD

Officials

NOV 2011

252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7012 Safeguarding Covered Defense Information and Cyber

Incident Reporting

DEC 2019

252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support

MAY 2016

252.204-7016 Covered Defense Telecommunications Equipment or Services -- Representation

DEC 2019

252.204-7017 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services -- Representation

MAY 2021

252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services

JAN 2021

252.223-7008 Prohibition of Hexavalent Chromium JUN 2013 252.225-7048 Export-Controlled Items JUN 2013 252.225-7050 Disclosure of Ownership or Control by the Government of a

Country that is a State Sponsor of Terrorism

DEC 2018

252.225-7974 (Dev) Representation Regarding Business Operations with the Maduro Regime (DEVIATION 2020-O0005)

FEB 2020

252.232-7010 Levies on Contract Payments DEC 2006 252.232-7017 Accelerating Payments to Small Business Subcontractors--

Prohibition on Fees and Consideration

APR 2020

252.243-7001 Pricing Of Contract Modifications DEC 1991 252.243-7002 Requests for Equitable Adjustment DEC 2012 252.244-7000 Subcontracts for Commercial Items JAN 2021

CLAUSES INCORPORATED BY FULL TEXT

52.212-2 EVALUATION--COMMERCIAL ITEMS (OCT 2014)

(a) The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The following factors shall be used to evaluate offers:

Past Perfornance and Price

(End of provision)

52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR

EXECUTIVE ORDERS--COMMERCIAL ITEMS (SEP 2021)

(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial items:

(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L.

113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).

(2) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (Jul 2018) (Section 1634 of Pub. L. 115-91).

(3) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (AUG 2020) (Section 889(a)(1)(A) of Pub. L. 115-232).

(4) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015).

(5) 52.233-3, Protest After Award (AUG 1996) (31 U.S.C. 3553).

(6) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Public Laws 108-77 and 108-78 (19 U.S.C. 3805 note)).

(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial items: (Contracting Officer check as appropriate.)

XXX (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (JUN 2020), with Alternate I (Oct 1995) (41 U.S.C. 4704 and 10 U.S.C. 2402).

___ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (JUN 2020) (41 U.S.C. 3509).

___ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (JUN 2010) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009.)

XXX (4) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020) (Pub. L.

109-282) (31 U.S.C. 6101 note).

___ (5) [Reserved]

___ (6) 52.204-14, Service Contract Reporting Requirements (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).

___ (7) 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts (Oct 2016) (Pub.

L. 111-117, section 743 of Div. C).

XXX (8) 52.209-6, Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (JUN 2020) (31 U.S.C. 6101 note).

___ (9) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (OCT 2018) (41 U.S.C. 2313).

____ (10) [Reserved]

____ (11) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (SEP 2021) (15 U.S.C. 657a).

____ (12) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (SEP 2021) (if the offeror elects to waive the preference, it shall so indicate in its offer) (15 U.S.C. 657a).

____ (13) [Reserved]

XXX (14)(i) 52.219-6, Notice of Total Small Business Set-Aside (NOV 2020) (15 U.S.C. 644).

____ (ii) Alternate I (MAR 2020) of 52.219-6.

____ (15)(i) 52.219-7, Notice of Partial Small Business Set-Aside (NOV 2020) (15 U.S.C. 644).

____ (ii) Alternate I (MAR 2020) of 52.219-7.

XXX (16) 52.219-8, Utilization of Small Business Concerns (OCT 2018) (15 U.S.C. 637(d)(2) and (3)).

____ (17)(i) 52.219-9, Small Business Subcontracting Plan (SEP 2021) (15 U.S.C. 637(d)(4)).

____ (ii) Alternate I (NOV 2016) of 52.219-9.

____ (iii) Alternate II (NOV 2016) of 52.219-9.

____ (iv) Alternate III (JUN 2020) of 52.219-9.

____ (v) Alternate IV (SEP 2021) of 52.219-9.

____ (18) (i) 52.219-13, Notice of Set-Aside of Orders (MAR 2020) (15 U.S.C. 644(r)).

____ (ii) Alternate I (MAR 2020) of 52.219-13.

XXX (19) 52.219-14, Limitations on Subcontracting (SEP 2021) (15 U.S.C. 657s).

____ (20) 52.219-16, Liquidated Damages—Subcontracting Plan (SEP 2021) (15 U.S.C. 637(d)(4)(F)(i)).

____ (21) 52.219-27, Notice of Service-Disabled Veteran-Owned Small Business Set-Aside (SEP 2021) (15 U.S.C.

657f).

XXX (22) (i) 52.219-28, Post-Award Small Business Program Rerepresentation (SEP 2021) (15 U.S.C. 632(a)(2)).

____ (ii) Alternate I (MAR 2020) of 52.219-28.

____ (23) 52.219-29, Notice of Set-Aside for, or Sole-Source Award to, Economically Disadvantaged Women- Owned Small Business Concerns (SEP 2021) (15 U.S.C. 637(m)).

____ (24) 52.219-30, Notice of Set-Aside for, or Sole-Source Award to, Women-Owned Small Business Concerns Eligible Under the Women-Owned Small Business Program (SEP 2021) (15 U.S.C. 637(m)).

____ (25) 52.219-32, Orders Issued Directly Under Small Business Reserves (MAR 2020) (15 U.S.C. 644(r)).

____ (26) 52.219-33, Nonmanufacturer Rule (SEP 2021) (15 U.S.C. 657s).

XXX (27) 52.222-3, Convict Labor (JUN 2003) (E.O. 11755).

(28) 52.222-19, Child Labor--Cooperation with Authorities and Remedies (JAN 2020) (E.O. 13126).

XXX (29) 52.222-21, Prohibition of Segregated Facilities (APR 2015).

XXX (30)(i) 52.222-26, Equal Opportunity (SEPT 2016) (E.O. 11246).

____ (ii) Alternate I (FEB 1999) of 52.222-26.

XXX (31)(i) 52.222-35, Equal Opportunity for Veterans (JUN 2020) (38 U.S.C. 4212).

____ (ii) Alternate I (JUL 2014) of 52.222-35.

XXX (32)(i) 52.222-36, Equal Opportunity for Workers with Disabilities (JUN 2020) (29 U.S.C. 793).

____ (ii) Alternate I (JUL 2014) of 52.222-36.

XXX (33) 52.222-37, Employment Reports on Veterans (JUN 2020) (38 U.S.C. 4212).

XXX (34) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (DEC 2010) (E.O.

13496).

XXX (35)(i) 52.222-50, Combating Trafficking in Persons (OCT 2020) (22 U.S.C. chapter 78 and E.O. 13627).

____ (ii) Alternate I (MAR 2015) of 52.222-50 (22 U.S.C. chapter 78 and E.O. 13627).

____ (36) 52.222-54, Employment Eligibility Verification (OCT 2015). (E. O. 12989). (Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial items as prescribed in 22.1803.)

____ (37)(i) 52.223-9, Estimate of Percentage of Recovered Material Content for EPA–Designated Items (MAY 2008) (42 U.S.C. 6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)

____ (ii) Alternate I (MAY 2008) of 52.223-9 (42 U.S.C. 6962(i)(2)(C)). (Not applicable to the acquisition of commercially available off-the-shelf items.)

____ (38) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (JUN 2016) (E.O. 13693).

____ (39) 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners

(JUN 2016) (E.O. 13693).

____ (40) (i) 52.223-13, Acquisition of EPEAT® Registered Imaging Equipment (JUN 2014) (E.O.s 13423 and 13514).

____ (ii) Alternate I (OCT 2015) of 52.223-13.

____ (41)(i) 52.223-14, Acquisition of EPEAT® Registered Televisions (JUN 2014) (E.O.s 13423 and 13514).

____ (ii) Alternate I (JUN 2014) of 52.223-14.

____ (42) 52.223-15, Energy Efficiency in Energy-Consuming Products (MAY 2020) (42 U.S.C. 8259b).

____ (43)(i) 52.223-16, Acquisition of EPEAT®-Registered Personal Computer Products (OCT 2015) (E.O.s 13423 and 13514).

____ (ii) Alternate I (JUN 2014) of 52.223-16.

XXX (44) 52.223-18, Encouraging Contractor Policies to Ban Text Messaging While Driving (JUN 2020) (E.O.

13513).

XXX (45) 52.223-20, Aerosols (JUN 2016) (E.O. 13693).

____ (46) 52.223-21, Foams (JUN 2016) (E.O. 13693).

____ (47)(i) 52.224-3, Privacy Training (JAN 2017) (5 U.S.C. 552a).

____ (ii) Alternate I (JAN 2017) of 52.224-3.

____ (48) 52.225-1, Buy American--Supplies (JAN 2021) (41 U.S.C. chapter 83).

____ (49) (i) 52.225-3, Buy American--Free Trade Agreements--Israeli Trade Act (JAN 2021) (41 U.S.C. chapter 83, 19 U.S.C. 3301 note, 19 U.S.C. 2112 note, 19 U.S.C. 3805 note, 19 U.S.C. 4001 note, Pub. L. 103-182, 108-77, 108-78, 108-286, 108-302, 109-53, 109-169, 109-283, 110-138, 112-41, 112-42, and 112-43.

____ (ii) Alternate I (JAN 2021) of 52.225-3.

____ (iii) Alternate II (JAN 2021) of 52.225-3.

____ (iv) Alternate III (JAN 2021) of 52.225-3.

____ (50) 52.225-5, Trade Agreements (OCT 2019) 19 U.S.C. 2501, et seq., 19 U.S.C. 3301 note).

XXX (51) 52.225-13, Restrictions on Certain Foreign Purchases (FEB 2021) (E.O.'s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).

____ (52) 52.225-26, Contractors Performing Private Security Functions Outside the United States (OCT 2016) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. 2302 Note).

____ (53) 52.226-4, Notice of Disaster or Emergency Area Set-Aside (NOV 2007) (42 U.S.C. 5150

____ (54) 52.226-5, Restrictions on Subcontracting Outside Disaster or Emergency Area (NOV 2007) (42 U.S.C.

5150).

____ (55) 52.229-12, Tax on Certain Foreign Procurements (FEB 2021).

____ (56) 52.232-29, Terms for Financing of Purchases of Commercial Items (FEB 2002) (41 U.S.C. 4505, 10 U.S.C. 2307(f)).

____ (57) 52.232-30, Installment Payments for Commercial Items (JAN 2017) (41 U.S.C. 4505, 10 U.S.C. 2307(f)).

XXX (58) 52.232-33, Payment by Electronic Funds Transfer—System for Award Management (OCT 2018) (31 U.S.C. 3332).

____ (59) 52.232-34, Payment by Electronic Funds Transfer—Other than System for Award Management (JUL 2013) (31 U.S.C. 3332).

____ (60) 52.232-36, Payment by Third Party (MAY 2014) (31 U.S.C. 3332).

____ (61) 52.239-1, Privacy or Security Safeguards (AUG 1996) (5 U.S.C. 552a).

____ (62) 52.242-5, Payments to Small Business Subcontractors (JAN 2017)(15 U.S.C. 637(d)(13)).

____ (63)(i) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (FEB 2006) (46 U.S.C.

55305 and 10 U.S.C. 2631).

____ (ii) Alternate I (APR 2003) of 52.247-64.

____ (iii) Alternate II (FEB 2006) of 52.247-64.

(c) The Contractor shall comply with the FAR clauses in this paragraph (c), applicable to commercial services, that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial items: (Contracting Officer check as appropriate.)

XXX (1) 52.222-41, Service Contract Labor Standards (AUG 2018) (41 U.S.C. chapter 67).

XXX (2) 52.222-42, Statement of Equivalent Rates for Federal Hires (MAY 2014) (29 U.S.C. 206 and 41 U.S.C.

chapter 67).

_____ (3) 52.222-43, Fair Labor Standards Act and Service Contract Labor Standards--Price Adjustment (Multiple Year and Option Contracts) (AUG 2018) (29 U.S.C. 206 and 41 U.S.C. chapter 67).

_____ (4) 52.222-44, Fair Labor Standards Act and Service Contract Labor Standards--Price Adjustment (MAY 2014) (29 U.S.C 206 and 41 U.S.C. chapter 67).

_____ (5) 52.222-51, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment--Requirements (MAY 2014) (41 U.S.C. chapter 67).

_____ (6) 52.222-53, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services--Requirements (MAY 2014) (41 U.S.C. chapter 67).

XXX (7) 52.222-55, Minimum Wages Under Executive Order 13658 (NOV 2020) (E.O. 13658).

XXX (8) 52.222-62, Paid Sick Leave Under Executive Order 13706 (JAN 2017) (E.O. 13706).

_____ (9) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations (JUN 2020) (42 U.S.C. 1792).

(d) Comptroller General Examination of Record. The Contractor shall comply with the provisions of this paragraph

(d) if this contract was awarded using other than sealed bid, is in excess of the simplified acquisition threshold, as defined in FAR 2.101, on the date of award of this contract, and does not contain the clause at 52.215-2, Audit and Records--Negotiation.

(1) The Comptroller General of the United States, or an authorized representative of the Comptroller General, shall have access to and right to examine any of the Contractor's directly pertinent records involving transactions related to this contract.

(2) The Contractor shall make available at its offices at all reasonable times the records, materials, and other evidence for examination, audit, or reproduction, until 3 years after final payment under this contract or for any shorter period specified in FAR Subpart 4.7, Contractor Records Retention, of the other clauses of this contract. If this contract is completely or partially terminated, the records relating to the work terminated shall be made available for 3 years after any resulting final termination settlement. Records relating to appeals under the disputes clause or to litigation or the settlement of claims arising under or relating to this contract shall be made available until such appeals, litigation, or claims are finally resolved.

(3) As used in this clause, records include books, documents, accounting procedures and practices, and other data, regardless of type and regardless of form. This does not require the Contractor to create or maintain any record that the Contractor does not maintain in the ordinary course of business or pursuant to a provision of law.

(e) (1) Notwithstanding the requirements of the clauses in paragraphs (a), (b), (c), and (d) of this clause, the Contractor is not required to flow down any FAR clause, other than those in this paragraph (e)(1)in a subcontract for commercial items. Unless otherwise indicated below, the extent of the flow down shall be as required by the clause—

(i) 52.203-13, Contractor Code of Business Ethics and Conduct (JUN 2020) (41 U.S.C. 3509).

(ii) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L.

113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).

(iii) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (Jul 2018) (Section 1634 of Pub. L. 115-91).

(iv) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (AUG 2020) (Section 889(a)(1)(A) of Pub. L. 115-232).

(v) 52.219-8, Utilization of Small Business Concerns (Oct 2018) (15 U.S.C. 637(d)(2) and (3)), in all subcontracts that offer further subcontracting opportunities. If the subcontract (except subcontracts to small business concerns) exceeds the applicable threshold specified in FAR 19.702(a) on the date of subcontract award, the subcontractor must include 52.219-8 in lower tier subcontracts that offer subcontracting opportunities.

(vi) 52.222-21, Prohibition of Segregated Facilities (Apr 2015).

(vii) 52.222-26, Equal Opportunity (Sep 2016) (E.O. 11246).

(viii) 52.222-35, Equal Opportunity for Veterans (JUN 2020) (38 U.S.C. 4212).

(ix) 52.222-36, Equal Opportunity for Workers with Disabilities (JUN 2020) (29 U.S.C. 793).

(x) 52.222-37, Employment Reports on Veterans (JUN 2020) (38 U.S.C. 4212).

(xi) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) (E.O. 13496).

Flow down required in accordance with paragraph (f) of FAR clause 52.222-40.

(xii) 52.222-41, Service Contract Labor Standards (Aug 2018), (41 U.S.C. chapter 67).

(xiii) XXX (A) 52.222-50, Combating Trafficking in Persons (OCT 2020) (22 U.S.C. chapter 78 and E.O. 13627).

_____ (B) Alternate I (March 2, 2015) of 52.222-50 (22 U.S.C. chapter 78 and E.O. 13627).

(xiv) 52.222-51, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment--Requirements (May 2014) (41 U.S.C. chapter 67.)

(xv) 52.222-53, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services--Requirements (May 2014) (41 U.S.C. chapter 67)

(xvi) 52.222-54, Employment Eligibility Verification (Oct 2015) (E. O. 12989).

(xvii) 52.222-55, Minimum Wages Under Executive Order 13658 (NOV 2020) (E.O. 13658).

(xviii) 52.222-62, Paid Sick Leave Under Executive Order 13706 (Jan 2017) (E.O. 13706).

(xix) (A) 52.224-3, Privacy Training (Jan 2017) (5 U.S.C. 552a).

(B) Alternate I (Jan 2017) of 52.224-3.

(xx) 52.225-26, Contractors Performing Private Security Functions…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .