SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 4 PAGES

Lock and Dam 3 Upper Embankments

01 14 00.00 13 SD-01 Preconstruction Submittals Composite Mat

01 32 01.00 13 SD-01 Preconstruction Submittals

3.4.1 G CORInitial Project Schedule

3.4.2 G CORPeriodic Updates

SD-04 Samples 2.1Software

01 35 29.00 13 SD-01 Preconstruction Submittals

1.6 G AAccident Prevention Plan (APP)

1.7 G AActivity Hazard Analysis (AHA)

1.6.1 G ACrane Critical Lift Plan

1.5.1.2 G ACrane Operators

SD-06 Test Reports 1.11Reports 1.11.2Monthly Exposure Reports 1.11.1Accident Reports 1.11.3Crane Reports

Regulatory Citations and Violations

SD-07 Certificates 1.11.4Certificate of Compliance

01 41 26.00 13 SD-01 Preconstruction Submittals G PMNotice of Intent (NOI)

SD-02 Shop Drawings Temporary Erosion And Sediment Control Plan

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P H

C L A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 4 PAGES

01 41 26.00 13 SD-11 Closeout Submittals Notice of Termination (NOT)

01 45 04.00 13 SD-01 Preconstruction Submittals G AQuality Control Plan (QCP) G AQuality Management Manual

01 50 02.00 13 SD-02 Shop Drawings Site Plan

01 57 20.00 13 SD-01 Preconstruction Submittals

1.7 G ENVEnvironmental Protection Plan

01 78 02.00 10 SD-11 Closeout Submittals G GENAs-Built Drawings

03 11 13.00 10 SD-02 Shop Drawings 3.1.1Formwork

SD-03 Product Data 1.2Design 2.1Form Materials 2.1.3Form Releasing Agents

03 20 01.00 10 SD-02 Shop Drawings

3.1 G ECReinforcement

SD-03 Product Data 1.3Welding

SD-07 Certificates 2.1Reinforcing Steel

03 31 00.00 10 SD-03 Product Data

1.7 GMixture Proportions

SD-06 Test Reports

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 4 PAGES

03 31 00.00 10 3.12 GTesting and Inspection for Contractor Quality Control

SD-07 Certificates 1.4Qualifications

05 50 00 SD-02 Shop Drawings G STRmiscellaneous metal items

2.5 G STRangles and plates

SD-04 Samples Miscellaneous metal items;

31 11 00 SD-03 Product Data

3.5.1 GNonsaleable Materials

31 41 16 SD-02 Shop Drawings

2.1 G STRMetal Sheet Piling

SD-03 Product Data 3.1.2.2Driving

3.1.1 G STRPile Driving Equipment

3.1.5 G STRPulling and Redriving

SD-06 Test Reports 2.3.1Materials Tests

SD-11 Closeout Submittals 3.2Pile Driving Record

32 92 19.00 13 SD-03 Product Data Manufacturer's Literature

SD-06 Test Reports Seed Test Quantity Check

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 4 OF 4 PAGES

32 92 19.00 13 Maintenance Record SD-07 Certificates Certificates of Compliance

SD-08 Manufacturer’s Instructions Proof of Seed Order Experience Statement

35 20 14 SD-02 Shop Drawings

2.3.1 G STRDetail Drawings

SD-03 Product Data 2.3.3Welding 2.1Materials

SD-06 Test Reports 2.4Tests, Inspections, and

Verifications 35 31 19.00 13 SD-01 Preconstruction Submittals

G GTMaterial Sources SD-03 Product Data Geotextile Data

SD-06 Test Reports Gradation Test

SD-07 Certificates Certified Weight Scale Tickets

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR