LD3 AMEND 0002 SECTION 01 22 00 00 13 MEAS AND PAY.pdf

PDF 63 KB Posted

Attached to
RECOVERY--Z--PROJECT NUMBER 153882, LOCK AND DAM 3 SPOT DIKES
Solicitation number
W912ES-09-B-0008
Issued by

About this file

Measurement and Payment

View the file

Other files

Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Lock and Dam 3 Upper Embankments LD3UPEMB

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.00 13

MEASUREMENT AND PAYMENT

10/2006

PART 1 GENERAL

1.1 REFERENCES

1.2 COMPENSATION

1.3 APPROVAL OF MATERIALS OR ALTERNATES

1.4 QUANTITY SURVEYS

1.5 MEASUREMENT BY WEIGHT

1.6 MEASUREMENT UNITS

1.7 LUMP SUM PAYMENT ITEMS

1.7.1 Stripping

1.7.2 Clearing and Grubbing

1.7.3 Protection for Cultural Resource

1.7.4 Contractor Haul Road

1.7.5 Control Structure

1.7.6 Topsoil & Seeding

1.8 UNIT PRICE PAYMENT ITEMS

1.8.1 Excavation

1.8.1.1 Payment

1.8.1.2 Measurement

1.8.1.3 Unit of Measure

1.8.2 Geotextile

1.8.2.1 Payment

1.8.2.2 Measurement

1.8.3 Aggregate Surface Material for Minimum Access Trail Section and

Spot Dikes

1.8.3.1 Payment

1.8.3.2 Measurement

1.8.4 Breaker Rock for Minimum Access Trail Section

1.8.4.1 Payment

1.8.4.2 Measurement

1.8.5 24" and 36" Riprap

1.8.5.1 Payment

1.8.5.2 Measurement

1.8.6 B2 Bedding

1.8.6.1 Payment

1.8.6.2 Measurement

1.8.7 Sheet Pile

1.8.7.1 Payment

1.8.7.2 Measurement

1.8.8 Vehicle Gates

1.8.8.1 Payment

1.8.8.2 Measurement

PART 2 PRODUCTS (Not Applicable)

SECTION 01 22 00.00 13 Page 1

PART 3 EXECUTION (Not Applicable)

-- End of Section Table of Contents --

SECTION 01 22 00.00 13 Page 2

SECTION 01 22 00.00 13

MEASUREMENT AND PAYMENT

10/2006

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY (NIST)

NIST HB 44 (2007) NIST Handbook 44: Specifications, Tolerances, and Other Technical Requirements for Weighing and Measuring Devices

1.2 COMPENSATION

The payment provided for in the contract shall constitute full compensation for furnishing all materials and for performing all work under the contract in a complete and acceptable manner. The contract work shall include providing plant, equipment, tools, supplies, labor, supervision, incidental materials, quality control, environmental protection, and meeting safety requirements, and for performing all work required for which separate payment is not otherwise provided. Compensation for all work shown, specified, or essential to completion of the project (whether or not the specific material or operation is indicated) shall be included on the bidding schedule. The payment provided for in the contract includes compensation for all risk, loss, damage, and expense arising out of the nature of the work or its prosecution, subject to conditions of the contract. Payment for each contract line item will constitute full compensation for furnishing the materials and constructing the work complete in place as specified.

1.3 APPROVAL OF MATERIALS OR ALTERNATES

Requests for approval of materials and products, or substitutes thereof, will not be considered prior to award of the contract.

1.4 QUANTITY SURVEYS

The Contractor shall provide quantity surveys for bulk materials measured by volume or weight, unless an alternate method of measurement is specified. Quantity surveys are specified in Section 01 71 23.00 13

CONTRACTOR SURVEYS.

1.5 MEASUREMENT BY WEIGHT

Bulk materials paid for by weight will be measured by weighing each truck

SECTION 01 22 00.00 13 Page 3 load on an approved scale before being placed in the work. Scales shall be of sufficient length to permit simultaneous weighing of all axle loads and shall be sensitive to a change in load of 0.2 percent throughout the range of the scale. The scale's accuracy shall conform to the applicable requirements of NIST HB 44 and shall be certified by a scale servicing company or by an inspector of the State Inspection Bureau. Each load shall be accompanied by a delivery ticket certified by the weighmaster. Delivery tickets shall be collected by the Contractor, and copies thereof shall be furnished to the Contracting Officer. As a minimum, each ticket shall contain the following information:

(1) Date and time.

(2) Vehicle number.

(3) Gross weight.

(4) Vehicle tare weight.

(5) Net weight.

(6) Job total for material weighed.

(7) Signature of weighmaster.

(8) Signature of Contractor's receiver.

1.6 MEASUREMENT UNITS

When materials are measured in units other than the measurement units specified as the basis of payment, the measured quantities shall be converted to the specified unit of measure. Factors for conversions from one basis or unit of measurement to another shall be approved by the Contracting Officer.

1.7 LUMP SUM PAYMENT ITEMS

Payment items for the work of this contract for which contract lump sum payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum or unit price item most closely associated with the work involved. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.7.1 Stripping

Payment will be made at the contract lump sum price bid for all materials, equipment, labor, and incidentals required to perform stripping within the work limits shown on the drawings, unless specifically addressed under another bid item. Work shall include, but not be limited to stripping vegetation, topsoil, and organic material within the limits shown, stockpiling of topsoil, and disposing of excess stripped materials.

1.7.2 Clearing and Grubbing

Payment for clearing and grubbing will be made at the contract lump sum price bid. This price shall constitute full compensation for all labor, equipment, materials, and incidentals necessary to complete the work as shown and specified, unless specifically addressed under another bid item.

Any material that can be salvaged shall be stored for later use. Debris shall be properly disposed of off site at an approved facility. No

SECTION 01 22 00.00 13 Page 4 allowances will be made for clearing and grubbing outside the limits of construction unless authorized.

1.7.3 Protection for Cultural Resource

Payment for Protection for Cultural Resource will be made at the contract lump sum price bid. This price shall constitute full compensation for all labor, equipment, materials, and incidentals necessary to complete the work as shown and specified. Work includes, but is not limited to clearing trees and brush; placing geotextile, sand, and interlocking composite mat to protect the site during construction; removal of geotextile, sand, and interlocking composite mat after construction is complete; and restoration of the site, including seedbed preparation and seeding. When no longer required, the geotextile, sand, and composite mat will become the property of the Contractor and shall be removed from the site and disposed of in accordance with all local, state, and federal regulations.

1.7.4 Contractor Haul Road

Payment for Contractor Haul Road will be made at the contract lump sum price bid. This price shall constitute full compensation for all labor, equipment, materials, and incidentals necessary to complete the Contractor Haul Road, exclusive of the minimum access trail section covered elsewhere in this section. Work includes, but is not limited to haul road design, clearing and grubbing, excavation for placement of haul road materials, placement of haul road materials, and restoration of the site when construction is complete, including any required backfilling, topsoil placement, and seeding. Removal and proper off site disposal of any excess material as well as any other incidentals associated this work will be included in the lump sum price.

1.7.5 Control Structure

Payment will be made at the contract lump sum bid price for furnishing all materials, equipment and labor and performing all operations necessary for construction of the control structure as shown and specified. Work includes, but is not limited to all earthwork, including excavation, backfill, compaction, and grading; all concrete work, including formwork, installation of reinforcement, concrete placement and curing, and installation of waterstops; and all metal work including furnishing and installing stoplogs and grooves complete with seal pads, stoplog sill, stoplog locking mechanism with padlock and keys, and stoplog hooks. Trial installation and removal of the stoplogs by the Contractor to verify the operability of the system is incidental to the bid price.

1.7.6 Topsoil & Seeding

Payment will be made at the contract lump sum bid price for furnishing all materials, equipment, and labor and performing all operations necessary to complete topsoil and seeding as shown and specified and within the limits indicated, unless specifically addressed under another bid item. Work includes, but is not limited to, placing topsoil, seedbed preparation, seeding, mulching, watering, maintenance and work incidental to seeding. No additional payment will be made for seeding outside the limits of required seed as indicated on the drawings. No additional payment will be made for restoration of areas damaged by Contractor operations or for topsoil and seeding areas incidental to other work.

SECTION 01 22 00.00 13 Page 5

1.8 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.

1.8.1 Excavation

1.8.1.1 Payment

Payment will be made for costs associated with excavation for placement of geotextile, bedding, and riprap at the spot dikes as shown and specified.

Work includes, but is not limited to, performing required excavation, stockpiling of materials, backfilling and compacting with excavated material, and removal and proper off site disposal of excess excavated material as shown and specified.

1.8.1.2 Measurement

Excavation shall be measured for payment by the cubic yard, in the original position, using the average-end-area method based on original ground lines prior to excavation and the ground lines when excavation is complete as determined by the required surveys.

1.8.1.3 Unit of Measure

Unit of measure: cubic yard.

1.8.2 Geotextile

1.8.2.1 Payment

Payment will be made for furnishing all materials, equipment, and labor and performing all operations necessary for placement of geotextile as shown and specified, unless specifically addressed under another bid item. Price will constitute full compensation for furnishing all labor, materials, equipment, and incidentals and constructing the work complete in place.

1.8.2.2 Measurement

Measurement shall be made based on surveys of the square yard surface area covered by geotextile. No allowance will be made for waste, overlaps, damaged materials, repairs, or materials used for the convenience of the Contractor.

1.8.3 Aggregate Surface Material for Minimum Access Trail Section and Spot Dikes

1.8.3.1 Payment

Payment will be made by the ton (TN)(2,000 pounds avoirdupois) for furnishing all materials, equipment, and labor and performing all operations necessary for placement of aggregate surface material for the minimum access trail section and spot dikes as shown and specified. No

SECTION 01 22 00.00 13 Page 6 separate payment will be made for stockpiling materials.

1.8.3.2 Measurement

Aggregate Surface Material shall be measured in accordance with paragraph:

MEASUREMENT BY WEIGHT.

1.8.4 Breaker Rock for Minimum Access Trail Section

1.8.4.1 Payment

Payment will be made by the ton (TN)(2,000 pounds avoirdupois) for furnishing all materials, equipment, and labor and performing all operations necessary for placement of breaker rock for the minimum access trail section as shown and specified. Any additional breaker rock used for construction of a haul road shall be covered under the lump sum bid item Contractor Haul Road. No separate payment will be made for stockpiling materials. Stripping required for placement of breaker rock is covered under the bid item Stripping.

1.8.4.2 Measurement

Breaker rock shall be measured in accordance with paragraph: MEASUREMENT BY

WEIGHT.

1.8.5 24" and 36" Riprap

1.8.5.1 Payment

Payment will be by the ton (TN)(2,000 pounds avoirdupois) for all 24" and 36" riprap material acceptably placed within the tolerances specified.

Price(s) and payment(s) will be made at the contract unit price and will constitute full compensation for furnishing all plant, labor, materials and equipment and constructing the work complete in place as specified. No separate payment will be made for stockpiling materials.

Deductions. All stone permitted by the Contracting Officer to remain outside the tolerances specified will be deducted from the quantity for which payment is to be made. Volume of excess stone will be computed, using the average-end-area of excess above the tolerance line. The excess volume will be deducted for the payment quantity at the rate of 1.4 tons per cubic yard, regardless of actual weight per cubic yard.

1.8.5.2 Measurement

Riprap shall be measured in accordance with paragraph: MEASUREMENT BY

WEIGHT.

1.8.6 B2 Bedding

1.8.6.1 Payment

Payment will be by the ton (TN)(2,000 pounds avoirdupois) for all bedding material acceptably placed within the tolerances specified. Price(s) and payment(s) will be made at the contract unit price and will constitute full compensation for furnishing all labor, materials and equipment and constructing the work complete in place as specified. No separate payment will be made for stockpiling materials.

SECTION 01 22 00.00 13 Page 7

Deductions. All stone permitted by the Contracting Officer to remain outside the tolerances specified will be deducted from the quantity for which payment is to be made. Volume of excess bedding will be computed, using the average-end-area of excess above the tolerance line. The excess volume will be deducted for the payment quantity at the rate of 1.4 tons per cubic yard, regardless of actual weight per cubic yard.

1.8.6.2 Measurement

Bedding shall be measured in accordance with paragraph: MEASUREMENT BY

WEIGHT.

1.8.7 Sheet Pile

1.8.7.1 Payment

Sheetpile will be paid for by the square foot (SF). Payment shall constitute full compensation for furnishing all materials, equipment, labor, and incidentals required for installing the sheetpile and sheet pile cover as shown and specified. Work includes, but is not limited to delivering the materials, handling, driving, cutting off piles to the cutoff elevation, welding the pile cover to the top of the pile, backfilling voids around piles and shaping the adjacent ground surface to meet project requirements, compiling and submitting pile driving records, and any other items incidental to driving piles to the required elevation.

No additional payment will be made for: damaged, rejected, or misplaced piles; withdrawn piles; backdriving; cutting off piles; splicing;

build-ups; or any cutoff length of piles.

1.8.7.2 Measurement

Sheetpile shall be measured by the Square Foot from cutoff elevations to the plan tip elevations in the vertical plane.

1.8.8 Vehicle Gates

1.8.8.1 Payment

Payment will be made for costs associated with operations necessary for fabrication and installation of the vehicle gates as shown and specified.

1.8.8.2 Measurement

Vehicle gates will be measured by the number of units constructed complete-in-place.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable) -- End of Section --

SECTION 01 22 00.00 13 Page 8

PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
GENERAL
01 00 00.00 13 - GENERAL
PART 1 GENERAL
1.1 ORGANIZATION OF SPECIFICATIONS
1.2 MEASUREMENT AND PAYMENT
PART 2 PRODUCTS
2.1 RECYCLED/RECOVERED MATERIALS
PART 3 EXECUTION
3.1 DISPOSAL OF DEBRIS AND WASTE
3.1.1 Burning
3.1.2 Disposal offsite for useful purposes
3.1.3 Disposal in a locally operated sanitary landfill
3.1.4 Disposal of Solid Construction Debris and Waste
3.2 SCHEDULING
3.2.1 General
3.2.2 Notification
3.2.3 Lock and Dam Operations
3.3 OTHER CONTRACTS
3.3.1 Mechanical Dredging
3.3.2 Corps Island Unloading
3.3.3 Hydraulic Maintenance Dredging
WORK RESTRICTIONS
01 14 00.00 13 - WORK RESTRICTIONS
PART 1 GENERAL
1.1 SUBMITTALS
1.2 MEASUREMENT AND PAYMENT
1.3 GROUNDS AND ROADWAYS
1.3.1 Parking
1.3.2 Snow Removal

1.4 BLASTING

PART 2 PRODUCTS
2.1 COMPOSITE MAT
PART 3 EXECUTION
3.1 ARCHEOLOGICAL SITE
3.1.1 Site Protection
3.1.2 Site Clean Up
3.2 EXISTING UTILITIES
3.2.1 General
3.2.2 Buried Utilities
3.2.3 Interruption of Services
3.2.4 Wisconsin Diggers Hotline
3.3 PROTECTION OF TREES
3.3.1 Restoration of Damaged Trees
3.4 PROTECTION OF EAGLE NESTS
3.4.1 Protection of Eagle Nests
3.4.2 Location of Eagle Nests
3.5 SITE ACCESS RESTRICTIONS
3.6 FLOATING PLANT
3.6.1 Equipment and Personnel
3.6.2 Navigable Waters
3.6.3 Sewage and Bilge Water Disposal
MEASUREMENT AND PAYMENT
01 22 00.00 13 - MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 REFERENCES
1.2 COMPENSATION
1.3 APPROVAL OF MATERIALS OR ALTERNATES
1.4 QUANTITY SURVEYS
1.5 MEASUREMENT BY WEIGHT
1.6 MEASUREMENT UNITS
1.7 LUMP SUM PAYMENT ITEMS
1.7.1 Stripping
1.7.2 Clearing and Grubbing
1.7.3 Protection for Cultural Resource
1.7.4 Contractor Haul Road
1.7.5 Control Structure
1.7.6 Topsoil & Seeding
1.8 UNIT PRICE PAYMENT ITEMS
1.8.1 Excavation
1.8.1.1 Payment
1.8.1.2 Measurement
1.8.1.3 Unit of Measure
1.8.2 Geotextile
1.8.2.1 Payment
1.8.2.2 Measurement
1.8.3 Aggregate Surface Material for Minimum Access Trail Section and Spot
1.8.3.1 Payment
1.8.3.2 Measurement
1.8.4 Breaker Rock for Minimum Access Trail Section
1.8.4.1 Payment
1.8.4.2 Measurement
1.8.5 24" and 36" Riprap
1.8.5.1 Payment
1.8.5.2 Measurement
1.8.6 B2 Bedding
1.8.6.1 Payment
1.8.6.2 Measurement
1.8.7 Sheet Pile
1.8.7.1 Payment
1.8.7.2 Measurement
1.8.8 Vehicle Gates
1.8.8.1 Payment
1.8.8.2 Measurement
PART 2 PRODUCTS Not Applicable
PART 3 EXECUTION Not Applicable
PROJECT SCHEDULE
01 32 01.00 13 - PROJECT SCHEDULE
PART 1 GENERAL
1.1 SUBMITTALS
1.2 QUALIFICATIONS
PART 2 PRODUCTS
2.1 COMPUTER SOFTWARE REQUIREMENTS
PART 3 EXECUTION
3.1 GENERAL
3.2 BASIS FOR PAYMENT
3.3 SOFTWARE
3.3.1 Use of the Critical Path Method
3.3.2 Level of Detail Required
3.3.2.1 Activity Durations
3.3.2.2 Procurement Activities
3.3.2.3 Critical Activities
3.3.2.4 Government Activities
3.3.2.5 Responsibility
3.3.2.6 Feature of Work
3.3.3 Scheduled Project Completion
3.3.3.1 Constraint of Last Activity
3.3.3.2 Early Project Completion
3.3.4 Interim Completion Dates
3.3.5 Default Progress Data Disallowed
3.3.6 Out-of-Sequence Progress
3.3.7 Extended Non-Work Periods
3.3.8 Negative Lags
3.4 PROJECT SCHEDULE SUBMISSIONS
3.4.1 Initial Project Schedule Submission
3.4.2 Periodic Updates
3.4.3 Standard Activity Coding Dictionary
3.5 SUBMISSION REQUIREMENTS
3.5.1 Earnings Report
3.5.2 Network Diagram
3.6 PERIODIC PROGRESS MEETINGS
3.6.1 Meeting Attendance
3.6.2 Update Submission Following Progress Meeting
3.6.3 Progress Meeting Contents
3.7 REQUESTS FOR TIME EXTENSIONS
3.7.1 Justification of Delay
3.7.2 Submission Requirements
3.8 DIRECTED CHANGES
3.9 OWNERSHIP OF FLOAT
SUBMITTAL PROCEDURES
01 33 00 - SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUBMITTAL IDENTIFICATION
1.2 SUBMITTAL CLASSIFICATION
1.2.1 Government Approved
1.2.2 Information Only
1.3 APPROVED SUBMITTALS
1.4 DISAPPROVED SUBMITTALS
1.5 WITHHOLDING OF PAYMENT
1.6 MEASUREMENT AND PAYMENT
PART 2 PRODUCTS Not Applicable
PART 3 EXECUTION
3.1 GENERAL
3.2 SUBMITTAL REGISTER ENG FORM 4288
3.3 SCHEDULING
3.4 TRANSMITTAL FORM ENG FORM 4025
3.5 SUBMITTAL PROCEDURE
3.5.1 Submittal Copies
3.5.2 Schedule
3.5.3 Shop Drawings
3.5.4 Warranties
3.5.5 Deviations
3.6 CONTROL OF SUBMITTALS
3.7 GOVERNMENT APPROVED SUBMITTALS
3.8 INFORMATION ONLY SUBMITTALS
3.9 STAMPS
SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS
01 35 29.00 13 - SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 DEFINITIONS
1.4 REGULATORY REQUIREMENTS
1.5 SITE QUALIFICATIONS, DUTIES AND MEETINGS
1.5.1 Personnel Qualifications
1.5.1.1 Site Safety and Health Officer SSHO
1.5.1.2 Crane Operators
1.5.2 Personnel Duties
1.5.2.1 Site Safety and Health Officer SSHOSuperintendent
1.5.3 Meetings
1.5.3.1 Preconstruction Conference
1.5.3.2 Safety Meetings
1.6 ACCIDENT PREVENTION PLAN APP
1.6.1 EM 385-1-1 Contents
1.7 ACTIVITY HAZARD ANALYSIS AHA
1.8 DISPLAY OF SAFETY INFORMATION
1.9 SITE SAFETY REFERENCE MATERIALS
1.10 EMERGENCY MEDICAL TREATMENT
1.11 REPORTS
1.11.1 Accident Reports
1.11.2 Monthly Exposure Reports
1.11.3 Crane Reports
1.11.4 Certificate of Compliance
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 CONSTRUCTION AND/OR OTHER WORK
3.1.1 Hazardous Material Exclusions
3.1.2 Unforeseen Hazardous Material
3.2 PRE-OUTAGE COORDINATION MEETING
3.3 FALL HAZARD PROTECTION AND PREVENTION PROGRAM
3.3.1 Training
3.3.2 Fall Protection Equipment and Systems
3.3.2.1 Personal Fall Arrest Equipment
3.3.3 Existing Anchorage
3.3.4 Horizontal Lifelines
3.3.5 Guardrails and Safety Nets
3.3.6 Rescue and Evacuation Procedures
3.4 EQUIPMENT
3.4.1 Material Handling Equipment
3.4.2 Weight Handling Equipment
3.5 EXCAVATIONS
3.5.1 Utility Locations
3.5.2 Utility Location Verification
3.5.3 Shoring Systems
3.5.4 Trenching Machinery
3.6 UTILITIES WITHIN CONCRETE SLABS
3.7 ELECTRICAL
3.7.1 Conduct of Electrical Work
3.7.2 Portable Extension Cords
WISCONSIN POLLUTANT DISCHARGE ELIMINATION SYSTEM
01 41 26.00 13 - WISCONSIN POLLUTANT DISCHARGE ELIMINATION SYSTEM
PART 1 GENERAL
1.1 GENERAL
1.1.1 Definitions
1.1.2 Contract Drawings
1.2 REFERENCES
1.3 SUBMITTALS
1.4 PERMIT COMPLIANCE AND ADDITIONAL REQUIREMENTS
1.4.1 Schedule
1.4.2 Construction Site Erosion Control Plan
1.4.3 Notice of Intent NOI

1.5 MEASUREMENT AND PAYMENT

PART 2 PRODUCTS
2.1 SILT FENCE
2.2 STRAW BALES
2.3 OTHER PRODUCTS
PART 3 EXECUTION
3.1 IMPLEMENTATION
3.2 MAINTENANCE
3.3 RECORDS
3.4 ATTACHMENTS
SOURCES FOR REFERENCE PUBLICATIONS
01 42 00 - SOURCES FOR REFERENCE PUBLICATIONS
PART 1 GENERAL
1.1 REFERENCES
1.2 ORDERING INFORMATION
QUALITY CONTROL SYSTEM QCS
01 45 02.00 10 - QUALITY CONTROL SYSTEM QCS
PART 1 GENERAL
1.1 GENERAL
1.1.1 Correspondence and Electronic Communications
1.1.2 Other Factors
1.2 QCS SOFTWARE
1.3 SYSTEM REQUIREMENTS
1.4 RELATED INFORMATION
1.4.1 QCS User Guide
1.4.2 Contractor Quality ControlCQC Training
1.5 CONTRACT DATABASE
1.6 DATABASE MAINTENANCE
1.6.1 Administration
1.6.1.1 Contractor Information
1.6.1.2 Subcontractor Information
1.6.1.3 Correspondence
1.6.1.4 Equipment
1.6.1.5 Management Reporting
1.6.2 Finances
1.6.2.1 Pay Activity Data
1.6.2.2 Payment Requests
1.6.3 Quality Control QC
1.6.3.1 Daily Contractor Quality Control CQC Reports.
1.6.3.2 Deficiency Tracking.
1.6.3.3 Three-Phase Control Meetings
1.6.3.4 Accident/Safety Tracking.
1.6.3.5 Features of Work
1.6.3.6 QC Requirements
1.6.4 Submittal Management
1.6.5 Schedule
1.6.6 Import/Export of Data
1.7 IMPLEMENTATION
1.8 DATA SUBMISSION VIA CD-ROM
1.8.1 File Medium
1.8.2 CD-ROM Labels
1.8.3 File Names
1.9 MONTHLY COORDINATION MEETING
1.10 NOTIFICATION OF NONCOMPLIANCE
CONTRACTOR QUALITY CONTROL
01 45 04.00 13 - CONTRACTOR QUALITY CONTROL
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 QUALITY CONTROL ORGANIZATION
1.3.1 Personnel Requirements
1.3.2 CQC System Manager
1.3.3 Additional Requirement
1.3.4 Organizational Changes

1.4 PAYMENT

PART 2 PRODUCTS Not Applicable
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
3.2 QUALITY CONTROL PLAN
3.2.1 General
3.2.2 Content of the CQC Plan
3.2.3 Acceptance of Plan
3.2.4 Notification of Changes
3.3 COORDINATION MEETING
3.4 SUBMITTALS AND DELIVERABLES
3.5 CONTROL
3.5.1 Preparatory Phase
3.5.2 Initial Phase
3.5.3 Follow-up Phase
3.5.4 Additional Preparatory and Initial Phases
3.6 TESTS
3.6.1 Testing Procedure
3.6.2 Testing Laboratories
3.6.2.1 Capability Check
3.6.2.2 Capability Recheck
3.6.3 Onsite Laboratory
3.6.4 Furnishing or Transportation of Samples for Testing
3.7 COMPLETION INSPECTION
3.7.1 Punch-Out Inspection
3.7.2 Pre-Final Inspection
3.7.3 Final Acceptance Inspection
3.8 DOCUMENTATION
3.9 NOTIFICATION OF NONCOMPLIANCE
TEMPORARY CONSTRUCTION FACILITIES
01 50 02.00 13 - TEMPORARY CONSTRUCTION FACILITIES
PART 1 GENERAL
1.1 SUBMITTALS
1.2 GROUNDS AND ROADWAYS
1.2.1 Availability of Grounds
1.2.2 Drainage Facilities
1.3 PAVEMENT REMOVAL AND REPLACEMENT
1.4 AVAILABILITY AND USE OF UTILITY SERVICES
1.4.1 Temporary Electrical Facilities
1.4.2 Sanitation
1.4.3 Telephone
1.5 PROTECTION AND MAINTENANCE OF TRAFFIC
1.5.1 Off-Site Haul routes
1.5.2 On-Site Haul Roads
1.5.3 Barricades
1.6 CONTRACTOR'S TEMPORARY FACILITIES
1.6.1 Administrative Field Offices
1.6.2 Staging Area
1.7 PLANT COMMUNICATION
1.8 TEMPORARY PROJECT SAFETY FENCING
PART 2 PRODUCTS
2.1 BULLETIN BOARD, PROJECT SIGN, AND PROJECT SAFETY SIGN
2.1.1 Bulletin Board
2.1.2 Project and Safety Signs
2.2 GOVERNMENT FIELD OFFICE
2.2.1 Location
2.2.2 Construction.
2.2.3 Utilities.
2.2.4 Furnishings.
2.2.5 Furniture
2.2.6 Office Equipment
2.2.7 Maintenance.
PART 3 EXECUTION
3.1 MAINTENANCE OF GROUNDS
3.2 CLEANUP
3.3 RESTORATION OF STORAGE AND WORK AREAS
ENVIRONMENTAL PROTECTION
01 57 20.00 13 - ENVIRONMENTAL PROTECTION
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.2.1 Environmental Pollution and Damage
1.2.2 Environmental Protection
1.2.3 Contractor Generated Hazardous Waste
1.2.4 Land Application for Discharge Water
1.2.5 Pesticide
1.2.6 Pests
1.2.7 Surface Discharge
1.2.8 Waters of the United States
1.2.9 Wetlands
1.3 GENERAL REQUIREMENTS
1.4 SUBCONTRACTORS
1.5 PAYMENT
1.6 SUBMITTALS
1.7 ENVIRONMENTAL PROTECTION PLAN
1.7.1 Compliance
1.7.2 Contents
1.7.3 Appendix
1.8 PROTECTION FEATURES
1.9 ENVIRONMENTAL ASSESSMENT OF CONTRACT DEVIATIONS
1.10 NOTIFICATION
PART 2 PRODUCTS NOT USED
PART 3 EXECUTION
3.1 PERMITS
3.2 LAND RESOURCES
3.2.1 Work Area Limits
3.2.2 Landscape
3.2.3 Erosion and Sediment Controls
3.2.4 Contractor Facilities and Work Areas
3.3 WATER RESOURCES
3.3.1 Cofferdams, Diversions, and Dewatering Operations
3.3.2 Stream Crossings
3.3.3 Wetlands
3.4 AIR RESOURCES
3.4.1 Particulates
3.4.2 Odors
3.4.3 Sound Intrusions
3.5 CHEMICAL MATERIALS MANAGEMENT AND WASTE DISPOSAL
3.5.1 Solid Wastes
3.5.2 Chemicals and Chemical Wastes
3.5.3 Contractor Generated Hazardous Wastes/Excess Hazardous Materials
3.5.4 Fuel and Lubricants
3.5.5 Waste Water
3.6 RECYCLING AND WASTE MINIMIZATION
3.7 HISTORICAL, ARCHAEOLOGICAL, AND CULTURAL RESOURCES
3.8 BIOLOGICAL RESOURCES
3.9 PESTICIDES
3.9.1 Pesticide Delivery and Storage
3.9.2 Qualifications
3.9.3 Pesticide Handling Requirements
3.9.4 Application
3.10 PREVIOUSLY USED EQUIPMENT
3.11 MAINTENANCE OF POLLUTION FACILITIES
3.12 TRAINING OF CONTRACTOR PERSONNEL
3.13 POST CONSTRUCTION CLEANUP
CONTRACTOR SURVEYS
01 71 23.00 13 - CONTRACTOR SURVEYS
PART 1 GENERAL
PART 2 PRODUCTS NOT APPLICABLE
PART 3 EXECUTION
3.1 FIELD LAYOUT SURVEYS
3.1.1 Alignment Changes

3.2 QUANTITY SURVEYS FOR MEASUREMENT AND PAYMENT

CLOSEOUT SUBMITTALS
01 78 02.00 10 - CLOSEOUT SUBMITTALS
PART 1 GENERAL
1.1 SUBMITTALS
1.2 AS-BUILT DRAWINGS
1.3 CONTRACTOR RECORD DRAWINGS
1.3.1 Changes and Corrections
1.3.2 Drawing Standards

1.4 PAYMENT

PART 2 PRODUCTS NOT USED
PART 3 EXECUTION NOT USED
DIVISION 03 - CONCRETE
STRUCTURAL CONCRETE FORMWORK
03 11 13.00 10 - STRUCTURAL CONCRETE FORMWORK
PART 1 GENERAL
1.1 REFERENCES
1.2 DESIGN REQUIREMENTS
1.3 SUBMITTALS
1.4 STORAGE AND HANDLING
PART 2 PRODUCTS
2.1 FORM MATERIALS
2.1.1 Forms For Class C Finish
2.1.2 Form Ties
2.1.3 Form Releasing Agents
PART 3 EXECUTION
3.1 INSTALLATION
3.1.1 Formwork
3.2 CHAMFERING
3.3 COATING
3.4 FORM REMOVAL
3.5 TABLE 1: TOLERANCES FOR FORMED SURFACES
CONCRETE REINFORCEMENT
03 20 01.00 10 - CONCRETE REINFORCEMENT
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 WELDING
1.4 DELIVERY AND STORAGE
PART 2 PRODUCTS
2.1 FABRICATED BAR MATS
2.2 WIRE TIES
2.3 SUPPORTS
PART 3 EXECUTION
3.1 REINFORCEMENT
3.1.1 Placement
3.1.2 Splicing
CAST-IN-PLACE STRUCTURAL CONCRETE
03 31 00.00 10 - CAST-IN-PLACE STRUCTURAL CONCRETE
PART 1 GENERAL
1.1 REFERENCES
1.2 LUMP SUM CONTRACT
1.3 SUBMITTALS
1.4 QUALIFICATIONS
1.5 GENERAL REQUIREMENTS
1.6 Tolerances
1.6.1 Strength Requirements and w/c Ratio
1.6.1.1 Strength Requirements
1.6.2 Air Entrainment
1.6.3 Slump
1.6.4 Concrete Temperature
1.6.5 Size of Coarse Aggregate
1.6.6 Special Properties and Products
1.7 MIXTURE PROPORTIONS
1.7.1 Proportioning Studies for Normal Weight Concrete
1.7.2 Proportioning Studies for Flexural Strength Concrete
1.7.3 Average Compressive Strength Required for Mixtures
1.7.3.1 Computations from Test Records
1.7.3.2 Computations without Previous Test Records

1.7.4 Average Flexural Strength Required for Mixtures

1.8 STORAGE OF MATERIALS
1.9 GOVERNMENT ASSURANCE INSPECTION AND TESTING
1.9.1 Materials
1.9.2 Fresh Concrete
1.9.3 Hardened Concrete
1.9.4 Inspection
PART 2 PRODUCTS
2.1 CEMENTITIOUS MATERIALS
2.1.1 Portland Cement
2.1.2 High-Early-Strength Portland Cement
2.1.3 Pozzolan Fly Ash
2.2 AGGREGATES
2.2.1 Fine Aggregate
2.2.2 Coarse Aggregate
2.3 CHEMICAL ADMIXTURES
2.3.1 Air-Entraining Admixture
2.3.2 Accelerating Admixture
2.3.3 Water-Reducing or Retarding Admixture
2.3.4 High-Range Water Reducer
2.3.5 Surface Retarder
2.3.6 Expanding Admixture
2.3.7 Other Chemical Admixtures
2.4 CURING MATERIALS
2.4.1 Impervious-Sheet
2.4.2 Membrane-Forming Compound
2.4.3 Burlap and Cotton Mat
2.5 WATER
2.6 NONSHRINK GROUT
2.7 LATEX BONDING AGENT
2.8 EPOXY RESIN
2.9 JOINT MATERIALS
2.9.1 Joint Fillers, Sealers, and Waterstops
PART 3 EXECUTION
3.1 DEWATERING
3.1.1 Design
3.1.2 Regulations
3.2 PREPARATION FOR PLACING
3.2.1 Concrete on Earth Foundations
3.3 CONCRETE PRODUCTION
3.3.1 Batching, Mixing, and Transporting Concrete
3.3.2 General
3.4 CONVEYING CONCRETE ON SITE
3.4.1 Buckets
3.4.2 Transfer Hoppers
3.4.3 Trucks
3.4.4 Chutes
3.4.5 Belt Conveyors
3.4.6 Concrete Pumps
3.5 PLACING CONCRETE
3.5.1 Depositing Concrete
3.5.2 Consolidation
3.5.3 Cold Weather Requirements
3.5.4 Hot Weather Requirements
3.5.5 Prevention of Plastic Shrinkage Cracking
3.6 JOINTS
3.6.1 Construction Joints
3.6.2 Expansion Joints
3.7 FINISHING FORMED SURFACES
3.7.1 Class C and Class D Finish
3.8 REPAIRS
3.8.1 Damp-Pack Mortar Repair
3.8.2 Repair of Major Defects
3.8.2.1 Surface Application of Mortar Repair
3.8.2.2 Repair of Deep and Large Defects
3.9 FINISHING UNFORMED SURFACES
3.9.1 General
3.9.2 Rough Slab Finish
3.10 CURING AND PROTECTION
3.10.1 General
3.10.2 Moist Curing
3.10.3 Membrane Forming Curing Compounds
3.10.4 Impervious Sheeting
3.10.5 Cold Weather Curing and Protection
3.11 SETTING BASE PLATES AND BEARING PLATES
3.11.1 Damp-Pack Bedding Mortar
3.11.2 Nonshrink Grout
3.11.2.1 Mixing and Placing of Nonshrink Grout
3.11.2.2 Treatment of Exposed Surfaces
3.12 TESTING AND INSPECTION FOR CONTRACTOR QUALITY CONTROL
3.12.1 Grading and Corrective Action
3.12.1.1 Fine Aggregate
3.12.1.2 Coarse Aggregate
3.12.2 Quality of Aggregates
3.12.3 Scales, Batching and Recording
3.12.4 Batch-Plant Control
3.12.5 Concrete Mixture
3.12.6 Inspection Before Placing
3.12.7 Placing
3.12.8 Vibrators
3.12.9 Curing Inspection
3.12.10 Cold-Weather Protection
3.12.11 Mixer Uniformity
3.12.12 Reports

3.13 FLOWABLE CEMENTITIOUS FILL

DIVISION 05 - METALS
METAL: MISCELLANEOUS AND FABRICATIONS
05 50 00 - METAL: MISCELLANEOUS AND FABRICATIONS
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 DETAIL DRAWINGS
1.4 QUALIFICATION OF WELDERS AND WELDING OPERATORS
1.5 DELIVERY, STORAGE, AND PROTECTION
PART 2 PRODUCTS
2.1 MATERIALS
2.1.1 Materials Orders
2.1.2 Materials List
2.1.3 Shipping Bill
2.1.4 Structural Carbon Steel
2.1.5 Structural Tubing
2.1.6 Steel Pipe and Pipe Fittings
2.1.7 Welding Electrodes
2.1.8 Aluminum
2.1.9 Rubber Seal Pad and Adhesive
2.1.10 Anchor Bolts
2.1.10.1 Bolts, Nuts, Studs and Rivets
2.1.10.2 Powder Driven Fasteners
2.1.10.3 Washers

2.1.11 Metal Sheet Piling

2.2 FABRICATION
2.2.1 Structural Fabrication
2.2.1.1 Dimensional Tolerances for Structural Work
2.2.1.2 Structural Steel Fabrication
2.2.1.3 Structural Aluminum Fabrication
2.2.2 Welding
2.2.2.1 Welding of Structural Steel
2.2.2.2 Welding of Aluminum
2.2.2.3 Welding of Steel Studs
2.2.3 Bolted Connections
2.2.3.1 Bolted Structural Steel Connections
2.2.3.2 Bolted Aluminum Connections
2.2.4 Machine Work
2.2.4.1 Finished Surfaces
2.2.4.2 Unfinished Surfaces
2.3 FABRICATION FINISHES
2.3.1 Galvanizing
2.3.2 Galvanize
2.3.3 Repair of Zinc-Coated Surfaces
2.3.4 Shop Cleaning and Painting
2.4 VEHICLE GATE
2.5 MISCELLANEOUS PLATES AND SHAPES
2.6 SAFETY CHAINS
2.7 STOPLOG GROOVES AND SILLS
2.8 STOPLOG HOOKS
PART 3 EXECUTION
3.1 GENERAL INSTALLATION REQUIREMENTS
3.2 WORKMANSHIP
3.3 ANCHORAGE, FASTENINGS, AND CONNECTIONS
3.4 BUILT-IN WORK
3.5 WELDING
3.6 FINISHES
3.6.1 Dissimilar Materials
3.6.2 Field Preparation
3.6.3 Environmental Conditions
3.6.4 Aluminum Finishes
3.7 SHEETPILE INSTALLATION
3.7.1 Placing and Driving
3.7.1.1 Placing
3.7.1.2 Driving
3.7.2 Cutting
3.7.3 Inspection of Driven Piling
3.8 PROTECTION OF FINISHED WORK
3.8.1 Machined Surfaces
3.8.2 Galvanized Surfaces
3.8.3 Aluminum
DIVISION 31 - EARTHWORK
CLEARING AND GRUBBING
31 11 00 - CLEARING AND GRUBBING
PART 1 GENERAL
1.1 SUBMITTALS
PART 2 PRODUCTS Not Applicable
PART 3 EXECUTION
3.1 PROTECTION
3.1.1 Roads and Walks
3.1.2 Trees, Shrubs, and Existing Facilities
3.1.3 Archeological Site
3.2 CLEARING
3.3 TREE REMOVAL
3.4 GRUBBING
3.5 DISPOSAL OF MATERIALS
3.5.1 Nonsaleable Materials
3.5.1.1 ACCEPTANCE
METAL SHEET PILING
31 41 16 - METAL SHEET PILING
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 DELIVERY, STORAGE AND HANDLING
PART 2 PRODUCTS
2.1 METAL SHEET PILING
2.1.1 General Requirements
2.2 APPURTENANT METAL MATERIALS
2.3 TESTS, INSPECTIONS, AND VERIFICATIONS
2.3.1 Materials Tests
PART 3 EXECUTION
3.1 INSTALLATION
3.1.1 Pile Driving Equipment
3.1.1.1 Driving Hammers
3.1.2 Placing and Driving
3.1.2.1 Placing
3.1.2.2 Driving
3.1.3 Cutting-Off and Splicing
3.1.4 Inspection of Driven Piling
3.1.5 Pulling and Redriving

3.2 INSTALLATION RECORDS

DIVISION 32 - EXTERIOR IMPROVEMENTS
SEEDING
32 92 19.00 13 - SEEDING
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 DELIVERY, INSPECTION, STORAGE, AND HANDLING
1.3.1 Inspection
1.3.2 Storage
1.3.3 Handling
1.3.4 Soil Amendments
PART 2 PRODUCTS
2.1 SEED
2.1.1 Seed Classification
2.1.2 Permanent Seed Species and Mixtures
2.1.3 Seeding Rates
2.1.4 Temporary Seed Species
2.1.5 Quality
2.2 MULCH
2.2.1 Straw Mulch
2.3 WATER
2.4 SPECIAL SEEDING AND MULCHING EQUIPMENT
2.4.1 Equipment
2.4.2 Seed Mix
PART 3 EXECUTION
3.1 INSTALLING SEED
3.1.1 Preparation
3.1.2 Notification
3.1.3 Seeding Time
3.1.4 Seeding Conditions
3.2 SEEDING
3.2.1 Equipment
3.2.2 Broadcast Seeding
3.2.3 Drill Seeding
3.2.4 Hydroseeding
3.2.5 Mulching
3.2.5.1 Hay or Straw Mulch
3.2.5.2 Mechanical Anchor

3.2.6 Initial Watering

3.3 RESTORATION AND CLEAN UP
3.4 MAINTENANCE
3.4.1 Maintenance Watering
3.4.2 Mowing
3.4.3 General Maintenance
3.4.3.1 Repair or Reinstall

3.4.4 Maintenance Record

3.5 ACCEPTANCE
3.6 SURFACE EROSION CONTROL
DIVISION 33 - UTILITIES
EXCAVATION, TRENCHING, AND BACKFILLING
33 00 00.00 13 - EXCAVATION, TRENCHING, AND BACKFILLING
PART 1 GENERAL
1.1 DEFINITIONS
PART 2 PRODUCTS
2.1 MATERIALS
2.1.1 Satisfactory Materials
2.1.2 Unyielding Material
PART 3 EXECUTION
3.1 EXCAVATION
3.1.1 Trench Excavation
3.1.1.1 Bottom Preparation
3.1.1.2 Unyielding Material
3.1.1.3 Unstable Material
3.1.1.4 Excavation for Appurtenances

3.1.2 Stockpiles

3.2 BACKFILLING AND COMPACTION
3.2.1 Bedding and Initial Backfill
3.2.2 Final Backfill

3.3 DISPLACEMENT OF SEWERS

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
STOPLOGS
35 20 14 - STOPLOGS
PART 1 GENERAL
1.1 REFERENCES
1.2 PAYMENT
1.3 SUBMITTALS
1.4 QUALIFICATION OF WELDERS AND WELDING OPERATORS
1.5 DELIVERY, STORAGE AND HANDLING
1.5.1 Rubber Seals
PART 2 PRODUCTS
2.1 MATERIALS
2.1.1 Metals
2.1.1.1 Structural Steel
2.1.1.2 Structural Aluminum
2.1.2 Rubber Seals
2.1.2.1 General Requirements
2.1.2.2 Fabrication
2.2 MANUFACTURED UNITS
2.2.1 Bolts, Nuts and Washers
2.2.2 Screws
2.2.3 Clips and Clip Bolts for Aluminum Panels
2.3 FABRICATION
2.3.1 Detail Drawings
2.3.1.1 Fabrication Drawings
2.3.1.2 Shop Assembly Drawings
2.3.1.3 Delivery Drawings
2.3.1.4 Field Installation Drawings
2.3.2 Structural Fabrication
2.3.3 Welding
2.3.4 Bolted Connections
2.3.5 Machine Work
2.3.6 Fabrications
2.3.6.1 Stoplogs
2.3.6.2 Stoplog Guides and Sill
2.3.6.3 Miscellaneous Embedded Metals

2.3.7 Seal Assemblies

2.4 TESTS, INSPECTIONS, AND VERIFICATIONS
2.4.1 Testing of Rubber Seals
PART 3 EXECUTION
3.1 INSTALLATION
3.1.1 Embedded Metals
3.1.2 Seal Assemblies
3.2 PROTECTION OF FINISHED WORK
3.3 ACCEPTANCE TRIAL OPERATION
STONE PROTECTION
35 31 19.00 13 - STONE PROTECTION
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
PART 2 PRODUCTS
2.1 STONE SOURCES AND EVALUATION
2.1.1 Alternate Sources
2.1.2 Acceptance of Materials
2.2 RIPRAP
2.2.1 General
2.3 B2 BEDDING
2.4 AGGREGATE SURFACE MATERIAL
2.5 BREAKER ROCK/PIT SCREENINGS
2.6 GEOTEXTILE
2.7 SOURCE QUALITY CONTROL
2.7.1 Sampling Requirements
2.7.2 Riprap Gradation Testing
2.7.2.1 Riprap Test Method A
2.7.2.2 Riprap Test Method B
2.7.3 Bedding Gradation and Aggregate Testing
2.7.3.1 Bedding and Filter Material Gradation Testing
2.7.3.2 Aggregate Gradation Testing

2.8 STOCKPILES

PART 3 EXECUTION
3.1 CONSTRUCTION TOLERANCES
3.2 CLEARING AND GRUBBING
3.3 FOUNDATION PREPARATION
3.4 PLACEMENT OF BEDDING LAYERS
3.5 PLACEMENT OF GEOTEXTILE
3.5.1 Covering Geotextile
3.6 PLACEMENT OF RIPRAP
3.6.1 Layer Requirements
3.6.2 Construction Methods
3.6.3 Riprap Placement on Geotextile
3.6.4 Riprap Placement in Water
3.7 ACCESS TRAIL
3.7.1 Proof Rolling
3.8 MAINTENANCE
3.9 CONTRACTOR QUALITY CONTROL

File details come from the government source that posted it. Updated .