Attachment B-PERFORMANCE DISTRIBUTION STATEMENT.pdf

PDF 87 KB Posted

Attached to
Amendment 0004 - Kingdom of Saudi Arabia Multiple Award Task Order Contract (MATOC)
Solicitation number
W912ER-22-R-0019
Issued by

About this file

This document includes an attachment and federal contract opportunity related to construction projects in the Kingdom of Saudi Arabia. The attachment provides a performance distribution statement template requiring contractors to list major subcontractors performing 10% or more of the total work, along with the scope and percentage of each subcontractor's work. The federal contract opportunity is a multiple award task order contract solicitation from the U.S. Army Corps of Engineers to provide design-build, site-adapted construction, design-bid-build, renovation and repair services for facilities to support Saudi Arabia's foreign military sales program and U.S. forces within the Central Command area of responsibility in the Kingdom of Saudi Arabia. The phase one closing date is October 28, 2021.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

"Source Selection Information - See FAR 2.101 and 3.104"

ATTACHMENT B

PERFORMANCE DISTRIBUTION STATEMENT

(Only for Task Order Level Use)

1. Although not all subcontractors need to be listed, statement must include all major subcontractors, defined as those performing 10% or more of the total dollar value ($) of the contract.

2. Add more lines, if needed, to list more subcontractors.

3. The total “% of Work” column cannot total more than 100%.

4. REMINDER: All subcontractors completing 10% or more of the work require a letter of intent to be submitted.

5. See example below for details.

Line Company / Entity Role Scope of Work % of Work

1 ABC Company Offeror

Management, safety, QC, paving, surveying, masonry, misc. 50%

2 Hamid & Sons, Inc.

Major Sub MEP 20%

3 Overhead Door Co.

Major Sub Specialty roll-up doors 15%

Line Company / Entity Role Scope of Work % of Work

1 Offeror