C04-Official Abstract of Bids-W912EQ22B0006.pdf
PDF 155 KB Posted
- Solicitation number
- W912EQ22B0006
About this file
This abstract of bids summarizes offers received in response to solicitation number W912EQ22B0006 for the Rainbow Temporary Housing site in Saint John The Baptist Parish, Louisiana. The opportunity involves constructing a temporary community housing site consisting of 97 housing pads, roads, utilities, drainage, and amenities. Key requirements include furnishing materials and labor to develop gravel roads and pads, install potable water and sewer lines, construct an on-site wastewater treatment plant, provide electric power and site lighting, and install fencing. Ten contractors submitted bids ranging from $5.3 million to $12 million. The government estimate was $10-15 million. The Women-Owned Stafford Act Eligible Business set-aside applies. The Army Corps of Engineers Engineering District Memphis is the contracting agency.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED
NO. DESCRIPTION QTY U/M PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
NO
BREAKDOWN
WATER SERVICE
1 Fire Hydrant, Dry Barrel 36" Bury Depth 4 LF $7,532.50 $30,130.00 $3,500.00 $14,000.00 $9,434.88 $37,739.52 $9,984.00 $39,936.00 $10,000.00 $40,000.00 $12,000.00 $48,000.00 $11,806.07 $47,224.28 $41,168.82 $11,751.28 $47,005.12 $12,848.83 $51,395.32 $6,000.00 $24,000.00
2 3/4" Water Service Pipe 3,038 LF $8.63 $26,217.94 $17.25 $52,405.50 $22.11 $67,170.18 $23.40 $71,089.20 $45.00 $136,710.00 $36.96 $112,284.48 $30.70 $93,266.60 $44,738.35 $19.34 $58,754.92 $28.28 $85,901.45 $7.25 $22,025.50
3 3/4" Water Service Taps 99 EA $895.73 $88,677.27 $402.50 $39,847.50 $1,142.51 $113,108.49 $1,209.00 $119,691.00 $500.00 $49,500.00 $1,680.00 $166,320.00 $3,027.34 $299,706.66 $61,860.65 $593.50 $58,756.50 $657.15 $65,057.70 $950.00 $94,050.00
4 3/4" Water Service Shut Off Valves 99 EA $195.94 $19,398.06 $287.50 $28,462.50 $464.37 $45,972.63 $491.40 $48,648.60 $500.00 $49,500.00 $560.00 $55,440.00 $984.42 $97,457.58 $46,424.07 $237.40 $23,502.60 $510.55 $50,544.01 $475.00 $47,025.00
5 Water Service Coordination & Fees- Main to Meter Install by Utility1 LS $18,126.00 $18,126.00 $4,025.00 $4,025.00 $11,340.00 $11,340.00 $12,000.00 $12,000.00 $15,000.00 $15,000.00 $39,200.00 $39,200.00 $34,778.64 $34,778.64 $10,292.21 $22,219.88 $22,219.88 $13,528.65 $13,528.65 $12,000.00 $12,000.00
6 4" Water Main Pipe 1,848 LF $22.55 $41,672.40 $28.75 $53,130.00 $64.86 $119,861.28 $68.64 $126,846.72 $67.00 $123,816.00 $109.76 $202,836.48 $94.75 $175,098.00 $68,302.08 $44.44 $82,125.12 $37.44 $69,187.63 $48.00 $88,704.00
7 4" Gate Valve w/ Cast Iron Box 2 EA $1,535.00 $3,070.00 $747.50 $1,495.00 $4,054.05 $8,108.10 $4,290.00 $8,580.00 $6,500.00 $13,000.00 $2,800.00 $5,600.00 $2,948.65 $5,897.30 $5,289.90 $1,110.99 $2,221.98 $2,424.68 $4,849.36 $2,100.00 $4,200.00
8 6" Water Main Pipe 3,358 LF $27.35 $91,852.24 $47.32 $158,908.96 $76.66 $257,424.28 $81.12 $272,400.96 $87.00 $292,146.00 $156.80 $526,534.40 $126.89 $426,096.62 $188,106.77 $55.55 $186,536.90 $50.15 $168,400.43 $78.00 $261,955.20
9 6" Gate Valve w/ Cast Iron Box 8 EA $2,254.75 $18,038.00 $1,092.50 $8,740.00 $5,896.80 $47,174.40 $6,240.00 $49,920.00 $7,500.00 $60,000.00 $3,360.00 $26,880.00 $6,577.77 $52,622.16 $32,349.24 $4,406.73 $35,253.84 $4,850.26 $38,802.06 $2,200.00 $17,600.00
10 6" Double Check Valve Backflow Preventer Assembly 1 EA $6,316.00 $6,316.00 $2,875.00 $2,875.00 $25,061.40 $25,061.40 $26,520.00 $26,520.00 $35,000.00 $35,000.00 $44,800.00 $44,800.00 $23,437.57 $23,437.57 $17,643.78 $88,134.62 $88,134.62 $33,428.84 $33,428.84 $14,500.00 $14,500.00
SEWER SERVICE XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX
11 8" Gravity Sewer Pipe 4,535 LF $81.78 $370,872.30 $40.25 $182,533.75 $122.36 $554,902.60 $129.48 $587,191.80 $90.00 $408,150.00 $242.00 $1,097,470.00 $110.43 $500,800.05 $534,268.35 $77.77 $352,686.95 $72.23 $327,542.32 $150.00 $680,250.00
12 4" Gravity Sewer Service Pipe 2,745 LF $30.68 $84,216.60 $28.75 $78,918.75 $98.77 $271,123.65 $104.52 $286,907.40 $75.00 $205,875.00 $144.30 $396,103.50 $59.95 $164,562.75 $161,694.23 $55.55 $152,484.75 $65.43 $179,607.02 $102.00 $279,990.00
13 Cleanout (Service and Main Line) 102 EA $655.13 $66,823.26 $172.50 $17,595.00 $700.25 $71,425.50 $741.00 $75,582.00 $750.00 $76,500.00 $896.00 $91,392.00 $2,282.01 $232,765.02 $90,006.84 $576.04 $58,756.08 $847.65 $86,460.01 $1,400.00 $142,800.00
14 Main Line Service Tee/Wye 99 EA $2,147.07 $212,559.93 $575.00 $56,925.00 $324.32 $32,107.68 $343.20 $33,976.80 $750.00 $74,250.00 $555.00 $54,945.00 $857.39 $84,881.61 $31,185.00 $593.50 $58,756.50 $1,923.42 $190,418.74 $1,250.00 $123,750.00
15 Manhole (Typical) 12 EA $9,066.00 $108,792.00 $5,175.00 $62,100.00 $7,665.84 $91,990.08 $8,112.00 $97,344.00 $7,500.00 $90,000.00 $8,400.00 $100,800.00 $19,531.87 $234,382.44 $91,668.00 $9,998.95 $119,987.40 $9,809.88 $117,718.57 $12,500.00 $150,000.00
16 Connect to Existing Gravity Main 1 LS $31,788.00 $31,788.00 $3,680.00 $3,680.00 $6,928.74 $6,928.74 $7,332.00 $7,332.00 $25,000.00 $25,000.00 $9,775.00 $9,775.00 $13,911.99 $13,911.99 $8,087.31 $35,253.85 $35,253.85 $7,571.95 $7,571.95 $7,500.00 $7,500.00
17 Connect to Existing Manhole 1 LS $31,490.00 $31,490.00 $3,910.00 $3,910.00 $3,464.37 $3,464.37 $3,666.00 $3,666.00 $10,000.00 $10,000.00 $13,800.00 $13,800.00 $3,856.39 $3,856.39 $5,146.68 $37,604.10 $37,604.10 $7,894.99 $7,894.99 $7,500.00 $7,500.00
ELECTRICAL SERVICE XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX
18 Connect to Electric Utility (All Costs Upstream of Metering Structure)1 LS $7,121.00 $7,121.00 $11,500.00 $11,500.00 $32,460.42 $32,460.42 $34,349.64 $34,349.64 $15,000.00 $15,000.00 $34,500.00 $34,500.00 $18,039.24 $18,039.24 $30,832.73 $266,306.45 $266,306.45 $67,677.50 $67,677.50 $52,000.00 $52,000.00
19 30 KVA Pole Mounted Transformer 12 EA $11,394.83 $136,737.96 $20,125.00 $241,500.00 $10,541.27 $126,495.24 $11,154.78 $133,857.36 $11,500.00 $138,000.00 $10,560.00 $126,720.00 $6,000.61 $72,007.32 $120,166.20 $3,328.83 $39,945.96 $20,303.25 $243,639.00 $12,100.00 $145,200.00
20 75 KVA Pole Mounted Transformer 7 EA $11,470.43 $80,293.01 $20,125.00 $140,875.00 $16,554.84 $115,883.88 $17,518.35 $122,628.43 $15,500.00 $108,500.00 $19,800.00 $138,600.00 $15,001.32 $105,009.24 $110,077.28 $4,438.44 $31,069.08 $23,687.13 $165,809.88 $14,300.00 $100,100.00
21 112.5 KVA Pole Mounted Transformer 8 EA $17,066.38 $136,531.04 $20,125.00 $161,000.00 $18,188.68 $145,509.44 $19,247.28 $153,978.24 $22,500.00 $180,000.00 $23,205.00 $185,640.00 $22,502.12 $180,016.96 $138,332.04 $5,548.05 $44,384.40 $30,454.88 $243,639.00 $17,830.00 $142,640.00
22 Primary Power Pole 35 EA $10,223.83 $357,834.05 $4,025.00 $140,875.00 $7,027.51 $245,962.85 $7,436.52 $260,278.20 $6,000.00 $210,000.00 $7,514.00 $262,990.00 $2,239.58 $78,385.30 $233,656.50 $221.92 $7,767.20 $3,722.26 $130,279.19 $1,500.00 $52,500.00
23 Primary Overhead Circuit 4,842 LF $50.34 $243,746.28 $28.74 $139,150.00 $7.89 $38,203.38 $8.35 $40,411.33 $75.00 $363,150.00 $9.78 $47,330.55 $97.04 $469,867.68 $36,351.32 $44.38 $214,887.96 $101.52 $491,541.68 $42.00 $203,364.00
24 Primary Metering Structure 1 LS $7,768.00 $7,768.00 $34,420.50 $34,420.50 $35,724.29 $35,724.29 $37,803.48 $37,803.48 $20,000.00 $20,000.00 $39,900.00 $39,900.00 $18,039.24 $18,039.24 $32,687.39 $110,961.02 $110,961.02 $108,284.00 $108,284.00 $34,000.00 $34,000.00
25 Secondary Overhead Circuit 3,950 LF $27.38 $108,156.48 $28.75 $113,562.50 $15.57 $61,501.50 $16.47 $65,070.72 $28.00 $110,600.00 $16.50 $65,175.00 $97.04 $383,308.00 $63,871.50 $44.38 $175,301.00 $87.98 $347,523.96 $30.00 $118,506.00
26 Below Grade Secondary Circuit (Conduit & Conductors)2,971 LF $52.40 $155,680.40 $258.75 $768,746.25 $48.32 $143,558.72 $51.14 $151,927.43 $125.00 $371,375.00 $59.40 $176,477.40 $181.46 $539,117.66 $267,657.39 $343.98 $1,021,964.58 $115.05 $341,818.75 $18.00 $53,478.00
27 Secondary Power Pole 60 EA $10,377.03 $622,621.80 $4,025.00 $241,500.00 $4,527.64 $271,658.40 $4,791.15 $287,469.00 $3,500.00 $210,000.00 $4,730.00 $283,800.00 $3,137.69 $188,261.40 $258,073.20 $1,109.61 $66,576.60 $3,722.26 $223,335.75 $1,350.00 $81,000.00
28 Site Lighting - Lamp Assembly 21 EA $8,444.62 $177,337.02 $1,437.50 $30,187.50 $2,253.90 $47,331.90 $2,385.08 $50,086.76 $3,000.00 $63,000.00 $2,200.00 $46,200.00 $4,067.67 $85,421.07 $36,746.33 $1,664.42 $34,952.82 $4,737.43 $99,485.93 $3,410.00 $71,610.00
29 MHU Service / Power Disconnect 99 EA $5,288.03 $523,514.97 $517.50 $51,232.50 $8,122.99 $804,176.01 $8,595.76 $850,979.84 $2,500.00 $247,500.00 $8,030.00 $794,970.00 $4,075.23 $403,447.77 $861,475.23 $2,219.22 $219,702.78 $3,045.49 $301,503.26 $2,400.00 $237,600.00
MISC. SITE SERVICE XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX
30 Fencing - 6' with Privacy Screen 2,308 LF $50.55 $116,669.40 $40.25 $92,897.00 $52.45 $121,054.60 $55.50 $128,092.58 $40.00 $92,320.00 $46.20 $106,629.60 $47.18 $108,891.44 $157,278.66 $76.37 $176,261.96 $72.69 $167,758.45 $70.00 $161,560.00
31 Fencing - 8' with Privacy Screen 1,356 LF $87.54 $118,704.24 $51.75 $58,011.75 $89.85 $100,721.85 $95.07 $106,574.86 $50.00 $56,050.00 $79.20 $88,783.20 $72.07 $80,790.47 $111,348.93 $104.83 $117,514.43 $121.14 $135,800.99 $88.00 $119,328.00
32 Fencing Gates (Various Sizes) 1 EA $6,952.00 $6,952.00 $23,000.00 $23,000.00 $20,004.89 $20,004.89 $21,169.20 $21,169.20 $15,000.00 $15,000.00 $4,995.00 $4,995.00 $4,392.06 $4,392.06 $2,793.95 $14,689.10 $14,689.10 $9,691.31 $9,691.31 $5,000.00 $5,000.00
33 Post Mounted Street Sign 8 EA $526.88 $4,215.04 $632.50 $5,060.00 $921.38 $7,371.04 $975.00 $7,800.00 $750.00 $6,000.00 $784.00 $6,272.00 $7,045.63 $56,365.04 $5,885.88 $1,101.68 $8,813.44 $888.38 $7,107.00 $950.00 $7,600.00
34 Flexible Dileneator Posts 1 LS $527.00 $527.00 $5,175.00 $5,175.00 $2,948.40 $2,948.40 $3,120.00 $3,120.00 $7,500.00 $7,500.00 $5,040.00 $5,040.00 $18,985.54 $18,985.54 $5,173.25 $5,875.64 $5,875.64 $807.61 $807.61 $950.00 $950.00
35 Pet Waste Station 1 EA $549.00 $549.00 $862.50 $862.50 $1,547.91 $1,547.91 $1,638.00 $1,638.00 $1,000.00 $1,000.00 $1,680.00 $1,680.00 $5,443.76 $5,443.76 $483.95 $2,937.82 $2,937.82 $4,175.40 $4,175.40 $1,500.00 $1,500.00
36 Bus Stop (Not Including Concrete) 1 EA $16,619.00 $16,619.00 $8,625.00 $8,625.00 $19,164.60 $19,164.60 $20,280.00 $20,280.00 $50,000.00 $50,000.00 $17,528.00 $17,528.00 $26,456.99 $26,456.99 $41,755.56 $58,756.41 $58,756.41 $27,731.91 $27,731.91 $25,000.00 $25,000.00
37 Mail Box Assembly (Not Including Concrete) 1 EA $18,737.00 $18,737.00 $51,750.00 $51,750.00 $40,599.47 $40,599.47 $42,962.40 $42,962.40 $55,000.00 $55,000.00 $36,960.00 $36,960.00 $34,433.44 $34,433.44 $62,507.45 $52,880.77 $52,880.77 $63,616.85 $63,616.85 $21,000.00 $21,000.00
38 Dumpster Pad (Not Including Concrete) 1 EA $10,756.00 $10,756.00 $17,250.00 $17,250.00 $4,186.73 $4,186.73 $4,430.40 $4,430.40 $10,000.00 $10,000.00 $44,800.00 $44,800.00 $11,705.73 $11,705.73 $23,113.86 $29,378.21 $29,378.21 $14,781.40 $14,781.40 $9,500.00 $9,500.00
39 DOTD Driveway Apron (Inc. Concrete) 2 EA $25,343.50 $50,687.00 $28,750.00 $57,500.00 $54,545.40 $109,090.80 $57,720.00 $115,440.00 $43,750.00 $87,500.00 $78,400.00 $156,800.00 $54,121.48 $108,242.96 $112,067.34 $52,880.77 $105,761.54 $128,792.84 $257,585.68 $55,000.00 $110,000.00
40 Concrete - UFAS Pads, Misc. 58,370 SF $8.99 $524,746.30 $8.05 $469,878.50 $9.22 $538,171.40 $9.75 $569,107.50 $12.00 $700,440.00 $18.15 $1,059,415.50 $10.89 $635,649.30 $910,134.23 $15.10 $881,387.00 $36.87 $2,152,142.88 $13.00 $758,810.00
41 Aggregate - MHU Pads, UFAS Pads, Roads, Streets, Misc.259,021 SF $1.53 $396,302.13 $2.88 $744,685.38 $3.39 $878,081.19 $3.59 $929,367.35 $6.00 $1,554,126.00 $5.51 $1,427,853.26 $5.46 $1,414,254.66 $927,424.70 $8.30 $2,149,874.30 $4.55 $1,178,008.86 $15.00 $3,885,315.00
42 Aggregate - Roads / Streets 111,674 SF $2.00 $223,348.00 $2.88 $321,062.75 $4.42 $493,599.08 $4.68 $522,634.32 $7.50 $837,555.00 $6.83 $762,175.05 $47.30 $552,180.20 $490,137.19 $8.30 $926,894.20 $4.70 $524,512.51 $15.00 $1,675,110.00
GENERAL XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX XXX
43 Overhead, Incidentals, and Other Costs Not Otherwise Specified1 LS $2,225,753.00 $2,225,753.00 $273,300.00 $273,300.00 $442,133.36 $442,133.36 $362,497.20 $362,497.20 $2,335,839.00 $2,335,839.00 $2,120,100.00 $2,120,100.00 $1,419,960.53 $1,419,960.53 $1,825,282.29 $1,528,262.22 $1,528,262.22 $1,109,617.20 $1,109,617.20 $928,000.00 $928,000.00
44 Mobilization 1 LS $85,897.00 $85,897.00 $180,877.92 $180,877.92 $146,918.77 $146,918.77 $155,469.60 $155,469.60 $550,000.00 $550,000.00 $702,900.00 $702,900.00 $811,428.07 $811,428.07 $363,540.87 $1,057,615.44 $1,057,615.44 $59,182.32 $59,182.32 $525,000.00 $525,000.00
45 Demobilization 1 LS $40,224.00 $40,224.00 $25,000.00 $25,000.00 $36,327.53 $36,327.53 $38,441.83 $38,441.83 $100,000.00 $100,000.00 $57,750.00 $57,750.00 $426,510.00 $426,510.00 $50,177.27 $916,600.05 $916,600.05 $27,631.15 $27,631.15 $45,000.00 $45,000.00
46 Bonding 1 LS $75,940.00 $75,940.00 $100,000.00 $100,000.00 $123,006.00 $123,006.00 $134,383.09 $134,383.09 $285,000.00 $285,000.00 $263,500.00 $263,500.00 $219,322.06 $219,322.06 $214,862.40 $241,393.46 $241,393.46 $189,497.00 $189,497.00 $285,000.00 $285,000.00
Judy Stallion, Bid Opening Officer
US ARMY, CORPS OF ENGINEERS - MEMPHIS DISTRICT ABSTRACT OF BIDS
OFFICIAL ABSTRACT
$8,932,127.17 $11,928,756.95 $10,192,495.47 $11,833,520.70
38% 11% 7% 30% 44% 35% 14% 43% 28% 42%
$6,918,296.55 $7,219,881.24 $10,484,902.00 $12,057,665.42 $10,966,678.79GRAND TOTAL ITEMS 0001-0046 $7,724,008.12 $5,279,037.01
VARIATION FROM GOVERNMENT ESTIMATE ---------------------------------------------------------------------------------->>>>>>>>>>
INVITATION NO.: W912EQ-22-B-0006 GOVT. ESTIMATE BIDDER #1 BIDDER #2
I certify that I have read all offers received in response to this solicitation and all offers have been recorded on this abstract
TITLE: Rainbow Group Site MEMPHIS
DISTRICT Cypress Solutions LLC Lakey, Inc.
BID OPENING DATE AND TIME: 04/19/2022 AT 11:45AM COST 38562 Cardinal CT 201 E. Frank Avenue Suite 101
SMALL BUSINESS DETERMINATION: Women Owned Stafford
Act Eligible Business
ENGINEERING Prairieville, Louisiana 70769 Lufkin, Texas 75901
NUMBER OF AMENDMENTS: 4
BIDDER #4
BM Grace, Inc.
11505 Perkins Rd. Bldg. 2Ste D
Baton Rouge, LA 70810
BIDDER #3
Vanguard Pacific
14051 County Road 9
Foley, AL 36535
BIDDER #6
WQRI Joint Venture LLC
4203 Gardendale St Ste 210C
San Antonio, TX 78229
BIDDER #5
J. Star Enterprises, Inc.
2882 Allen Street
New Orleans, LA 70119
BIDDER #8
K-Belle Consultants, LLC
8603 Oak Street
New Orleans, LA 70118
BIDDER #7
Quality First Construction, LLC
1254 N. Columbia Street
Covington, LA 70433
BIDDER #9
Titan-Persons JV
130 E. Washington Ave Suite 11
Athens, TN 37303
BIDDER #10
Strategic Planning Associates, LLC
5037 Veterans BLVD, #1D
Metairie, LA 70006
| 2022-04-20T09:33:20-0500 | |
| STALLION.JUDY.E.1230612109 |
| 2022-04-20T13:18:48-0500 | |
| SWEENEY.PRISCILLA.G.1105039618 |
File details come from the government source that posted it. Updated .