This document provides details for a federal solicitation for the Central Everglades Planning Project Contract 11A. The solicitation is for clearing, grubbing, de-mucking, blasting, foundation preparation, installation of a seepage cutoff wall, canal backfilling, and related work to prepare approximately 15.3 miles of foundation for a 17.3 mile embankment dam within the Everglades Agricultural Area. The work is estimated between $250-500 million and has an estimated period of performance of 2,044 calendar days. A pre-proposal conference will be held on June 22, 2022. Award will be made using best value procedures evaluating technical merit, past performance, small business participation, and price. The solicitation is issued by the Department of the Army Corps of Engineers Engineering District Jacksonville.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912EP22R0005
Jacksonville District
CENTRAL EVERGLADES PLANNING PROJECT
(CEPP) CONTRACT 11A, EAA A-2 RESERVOIR
FOUNDATION AND CUTOFF WALL
Palm Beach County, Florida
Construction Solicitation and Specifications
Amendment 0002
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
1. Provide Changes to Section SF1442.
2. Provide Changes to Section 00010A–Attachment A.
3. Provide Changes to Volume II–Technical Specifications.
4. Provide Changes to Drawings.
All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EP22R0005
X 9B. DATED (SEE ITEM 11)
10-Jun-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
08-Jul-2022
CODE
USA ENGINEER DISTRICT, JACKSONVILLE
CONTRACTING DIVISION
701 SAN MARCO BLVD
JACKSONVILLE FL 32207-8175
W912EP 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912EP22R0005 Amendment 0002
SF 30 CONTINUATION SHEET
CENTRAL EVERGLADES PLANNING PROJECT
(CEPP) CONTRACT 11A, EAA A-2 RESERVOIR
FOUNDATION AND CUTOFF WALL
PALM BEACH COUNTY, FLORIDA
Amendment 0002
SUMMARY OF CHANGES
1. GENERAL:
A. In Volume 1 sections, the text changes have been updated with additions noted by green colored text and deletions noted by line/cross-outs and/or red text and pertain only to changes made by this amendment. For certain sections, the entire section is replaced if there is any change.
B. In Volume 2 sections, the text changes have been updated with additions noted by underlined text and deletions noted by line/cross-outs and pertain only to changes made by this amendment. The entire section is replaced if there is any change. The Project Table of Contents and Submittal Register are replaced without underlines and cross-outs if there are changes to these documents.
2. SOLICITATION AND SPECIFICATIONS:
VOLUME 1 OF 2:
DELETE Section SF1442 and REPLACE with the attached Section SF1442.
DELETE Section 00010A and REPLACE with the attached Section 00010A.
VOLUME 2 OF 2:
DELETE Section 01 22 00 and REPLACE with the attached revised Section 01 22 00.
DELETE Section 31 00 00 and REPLACE with the attached revised Section 31 00 00.
DELETE Section 31 66 10 and REPLACE with the attached revised Section 31 66 10.
DRAWINGS:
DELETE Drawing C-101 and REPLACE with the attached revised Drawing C-101.
DELETE Drawing C-121 and REPLACE with the attached revised Drawing C-121.
(End of Summary of Changes)
SOLICITATION, OFFER, 1. SOLICITA TlON NO. 2. TYPE OF SOLICITA TlON 3. DA 1E ISSUED PAGE OF PAGES
AND AWARD □ SEALEDBID (FB) 1 0-Jun-2022 (Construction, Alteration, or Repair)
W912EP22R0005
� NEGOTIA 1ED (RFP)
IMPORTANT-The "offer" section on the reverse must be fully completed by offerer.
4. CONTRACT NO. 5. REQUISITlON/PUROiASE REQUEST NO. 6. PROJECT NO.
7. ISSUEDBY CODE IW912EP 8. ADDRESS OFFER TO (If Other Than Item 7) CODE I
USA ENGINEER DISTRICT, JACKSONVILLE
CONTRACTING DIVISION See Item 7
701 SAN MARCO BLVD
JACKSONVILLE FL 32207-8175
lEL: FAX: lEL: FAX:
9. FOR INFORMI\ TION A. NAIVE B. TB.EPHONE NO. (Include area code) (NO COLLECT CALLS)
CALL: MARlHA G SEQUffiA 904-232-1792
SOLICITATION
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMI\NCE OF THE WORK DESCRIBED IN THESE DQCl.11,ENTS (Title, identifying no., date):
Central Everglades Planning A"oject (CEPP) Contract 11A, Everglades Agricultural Area (EAA) A-2 Reservoir Foundation & Cutoff Wall A"oject, Palm Beach County, Florida.
DESCRIPTION OF WORK: REFER TO SECTION 01 11 00 FOR COMPLETE PROJECT DESCRIPTION.
DRAWINGS: SEE DFARS CLAUSE 252.236-7001, IN SECTION 00100.
MAGNITUDE OF CONSTRUCTION IS BETWEEN $250,000,000 and $500,000,000.
THIS IS AN UNRESTRICTED SOLICITATION AND ALL RESPONSIBLE OFFERORS ARE B'IICOURAGED TO PARTICIPATE
THE NAICS CODE IS 237990 AND THE SMALL BUSINESS SIZE STANDARD IS $39,500,000.00.
OFFERORS ARE NOTIFIED THAT REAL ESTA 1E IS NOT CURRENTLY CLEARED FOR CONSTRUCTION BUT WILL BE BY ISSUANCE OF THE
FULL NOTICE TO PROCEED.
,_BLOCK 11 - SEE SECTION 00700, CLAUSE52.211-10 FOR PERIOD OF PERFORMI\NCE
A SITE VISIT WILL BE HB..D SEE FAR CLAUSE 52.236-27 IN SECTION 00100.
YOU MUST BEREGISlERED IN SAM NORDER TO REC8VEAN AWARD FROM THIS SOLICITATlON. THE SAM WEBSITE IS LOCAlEDATVWWV.SAMGOV.
11. The Contractor shall begin performance within 60 calendar days and complete it within 2044 calendar days after receiving
Daw ard, 0 notice to proceed. This performance period is � mandatory, D negotiable. (See FAR 52.211-10 .)
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMI\NCEAND PA YMB'IIT BONDS? 128. CALENDAR DAYS (If "YES," indicate v.nthin how many calendar days after award in Item 128.)
�YES □ NO
13. ADDITlONAL SOLICITATION REQUIB.ENTS:
A. copies to perform the w ork required are due at the place specified in tern 8 by 02:00 PM (hour) Sealed offers in original and
B. An offer guarantee � is, D is not required.
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than 90
NSN 7540-01-155-3212
calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e) local time 19 25 Jul 2022 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offerer's name and address, the solicitation number, and the date and time offers are due.
SECTION 00010A, Attachment A
INSTRUCTIONS FOR TECHNICAL INQUIRIES AND QUESTIONS
Technical inquiries and questions relating to this solicitation are to be submitted via Bidder Inquiry in ProjNet at (https://www.projnet.org) No Later Than (NLT) 6 July 12 July 2022, 5:00 P.M. Local Time.
To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via email, followed by an answer to the comment/question after it has been processed by our technical team.
The Solicitation Number is: W912EP22R0005
The Bidder Inquiry Key is: DP9TJP-SGQGF7
Specific Instructions for ProjNet Bid Inquiry Access from ProjNet home page:
1. Identify the Agency. This should be marked as USACE.
2. Email. Enter the email address you would like to use for communication.
3. Key. Enter the Bidder Inquiry Key listed above.
4. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.
5. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret
Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.
6. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.
Specific Instructions for Future ProjNet Bid Inquiry Access from ProjNet home page:
1. For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.
2. Identify the Agency. This should be marked as USACE.
3. Email. Enter the email address you used to register previously in ProjNet.
4. Key. Enter the Bidder Inquiry Key listed above.
5. Click Continue. A page will then open asking you to enter the answer to your Secret Question.
6. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.
Central Everglades Planning Project (CEPP) Contract 11A EAA A-2 Reservoir Foundation and Cutoff Wall, Palm Beach County, Florida
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUMMARY
1.1.1 Reference
1.2 RESIDENT MANAGEMENT SYSTEM (RMS)
1.2.1 Definition
1.2.2 Instructions
1.3 SUBMITTALS
1.4 JOB PAYMENT ITEMS
1.4.1 Project Initiation Activities (Line Items 0001)
1.4.2 Surface and Subsurface Water Management (Line Items 0004, 0025, 0041, and 0057)
1.4.3 Data Management (Line Items 0013, 0031, 0047, and 0063)
1.4.4 Access Road Maintenance (Line Items 0017, 0034, 0050, and 0066)
1.4.5 Relocation of Consruction Field Office (Line Item 0018)
1.4.6 Environmental Monitoring (Line Items 0019, 0035, 0051, and
0067)
1.5 UNIT PRICE PAYMENT ITEMS
1.5.1 Clearing and Grubbing (Line Items 0002, 0023, 0039, and 0055)
1.5.1.1 Payment
1.5.1.2 Measurement
1.5.1.3 Unit of Measure
1.5.2 Preliminary Foundation Preparation (Line Items 0003, 0024, 0040, and 0056)
1.5.2.1 Payment
1.5.2.2 Measurement
1.5.2.3 Unit of Measure
1.5.3 Final Foundation Preparation (Line Items 0005, 0026, 0042, and
0058)
1.5.3.1 Payment
1.5.3.2 Measurement
1.5.3.3 Unit of Measure
1.5.4 Select Fill (Line Item 0006)
1.5.4.1 Payment
1.5.4.2 Measurement
1.5.4.3 Unit of Measure
1.5.5 Lime Rock Base (Line Item 0007)
1.5.5.1 Payment
1.5.5.2 Measurement
1.5.5.3 Unit of Measure
1.5.6 Controlled Low Strength Material (CLSM) (Line Items 0008, 0027, 0043, and 0059)
1.5.6.1 Payment
1.5.6.2 Measurement
1.5.6.3 Unit of Measure
1.5.7 CLSM Top Cover (Line Items 0009, 0028, 0044, and 0060)
SECTION 01 22 00 Page 1
1.5.7.1 Payment
1.5.7.2 Measurement
1.5.7.3 Unit of Measure
1.5.8 Cutoff Wall (Line Items 0010, 0029, 0045, and 0061)
1.5.8.1 Payment
1.5.8.2 Measurement
1.5.8.3 Unit of Measure
1.5.9 Verification Drilling/Testing (Line Items 0011, 0030, 0046, and 0062)
1.5.9.1 Payment
1.5.9.2 Measurement
1.5.9.3 Unit of Measure
1.5.10 Standby Time (Line Item 0012)
1.5.10.1 Payment
1.5.10.2 Measurement
1.5.10.3 Unit of Measure
1.5.11 Sodding (Line Item 0014)
1.5.11.1 Payment
1.5.11.2 Measurement
1.5.11.3 Unit of Measure
1.5.12 Partnering Regroup - Meeting (Line Items 0015, 0032, 0048, and 0064)
1.5.12.1 Payment
1.5.12.2 Measurement
1.5.12.3 Unit of Measure
1.5.13 Partnering Regroup - Venue (Line items 0016, 0033, 0049, and
0065)
1.5.13.1 Payment
1.5.13.2 Measurement
1.5.13.3 Unit of Measure
1.5.14 Contracting Officer's Field Office (Line Items 0020, 0036, 0052, and 0068)
1.5.14.1 Payment
1.5.14.2 Measurement
1.5.14.3 Unit of Measure
1.5.15 Additional Contracting Officer's Field Office (Line Items
0021, 0037, 0053, and 0069)
1.5.15.1 Payment
1.5.15.2 Measurement
1.5.15.3 Unit of Measure
1.5.16 Temporary Quality Assurance Lab (Line Items 0022, 0038, 0054, and 0070)
1.5.16.1 Payment
1.5.16.2 Measurement
1.5.16.3 Unit of Measure
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 PAYMENT PROCEDURES
3.1.1 Requesting Progress Payment
3.1.2 Options and Modification CLINS
-- End of Section Table of Contents --
SECTION 01 22 00 Page 2
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUMMARY
This section describes how Line Items will be measured and paid for when making progress payments. Work to be measured is described in specification sections listed for each Line Item. Measurement procedures for payment, required quantity survey or procurement documentation and payment restrictions are described in applicable specification sections.
Allocate costs for work not specifically mentioned to the Line Item most closely associated with work involved. Unless there is a specific Line Item for administrative costs, such as Quality Control and Safety, allocate such costs proportionally across all Line Items. The Contractor must conduct the surveys for any periods for which progress payments are requested and must make computations based on those surveys. The Contractor must provide 72 hours advance notice, in writing, to the Contracting Officer or their duly appointed representative for all progress payments requiring survey other than the initial and final survey.
1.1.1 Reference
The publication listed below forms a part of this specification to the extent referenced. This publication is referred to in the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM D6023 (2016) Standard Test Method for Density (Unit Weight), Yield, Cement, Content, and Air Content (Gravimetric) of Controlled Low-Strength Material (CLSM)
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.2 RESIDENT MANAGEMENT SYSTEM (RMS)
1.2.1 Definition
The terms Contract Line Item Number (CLIN) and Line Item are interchangeable herein (e.g.: CLIN 0001 is Line Item 0001). The term CLIN is a contracting term used in the Resident Management System (RMS) payment data base.
1.2.2 Instructions
See Section 01 45 00 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM) for more information on CLINs, schedule of values of pay activities and
SECTION 01 22 00 Page 3 construction schedule, and payment procedures. The Contractor mode user manual with in-depth instructions can be downloaded from the RMS web site indicated in Section 01 45 00 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE
(RMS CM).
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Transmit submittal items in accordance with Section 01 33 00 SUBMITTAL PROCEDURES. Submit the following preconstruction submittal items no later than 30 calendar days after Notice to Proceed:
SD-01 Preconstruction Submittals
Schedule of Values ; G, RO
SD-07 Certificates
Request for Progress Payment ; G, RO
1.4 JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract lump sum payments will be made are listed in the LINE ITEMS AND PRICING SCHEDULE with the unit JOB and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, shall be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports approved by the Government, and for performing all work required for which separate payment is not otherwise provided.
Progress payments for job CLINs will be made in accordance with the Payments Under Fixed-Price Construction Contracts clause of Section 00700 CONTRACT CLAUSES in Volume 1. Submit Schedule of Values for Government approval with the baseline schedule submittal (see Section 01 32 01 PROJECT SCHEDULE). Include a list of pay activities to breakdown bid for each job CLIN as part of the RMS Schedule. Schedule of Values will become basis for CLIN and Pay Activity data in the RMS payment data base. An unbalanced Schedule of Values and Pay Activity Schedule will be returned for revision. If this contract contains either the Continuing Contracts clause or the Continuing Contracts (Alternate) clause, take into account the amount reserved for contract payments when preparing the construction schedule.
1.4.1 Project Initiation Activities (Line Items 0001)
Job payment will be made for costs associated with and incidental to activities including preparatory work, installation of silt fence, mobilization/demobilization, establishment of site access roads, staging areas, and other infrastructure to maintain Government and Contractor access to and use of the site, establishment of initial project management and coordination to include an initial partnering meeting, and
SECTION 01 22 00 Page 4 establishment and maintenance of project controls and any initial maintenance clearing, grubbing, and stripping required. See Clause PAYMENT FOR MOBILIZATION AND PREPARATORY WORK of Section 00700 CONTRACT CLAUSES in Volume 1.
Construct Plant and Equipment described in 252.236-7003 of Section 00700 CONTRACT that may include:
a. Mobile or stationary rock processing equipment including any ancillary equipment necessary for processing (crushing, screening, and/or blending) and stockpiling excavated material.
b. Batch plant(s) including any ancillary equipment necessary for processing and producing (1) Controlled Low Strength Material (CLSM) and (2) Cutoff Wall Slurry material.
c. Staging areas and associated security fencing as applicable.
1.4.2 Surface and Subsurface Water Management (Line Items 0004, 0025, 0041, and 0057)
Job payment will be made for costs associated with and incidental to the design, installation, operation, maintenance, and removal of surface and subsurface water management systems. This includes required permitting and preparation of the Surface and Subsurface Water Management Plan.
Review paragraph JOB PAYMENT ITEMS above, regarding progress payments for this job-related item. See Section 31 52 10 DEWATERING for additional details and performance requirements.
1.4.3 Data Management (Line Items 0013, 0031, 0047, and 0063)
Payment will be made for costs associated with and incidental to creating and maintaining a Construction Data Report and a Data Management System.
See Section 35 42 01 CUTOFF WALL CONSTRUCTION DATA REPORT and Section
01 45 08 DATA MANAGEMENT AND DATA REQUIREMENTS.
1.4.4 Access Road Maintenance (Line Items 0017, 0034, 0050, and 0066)
Job payment will be made for costs associated with and incidental to the maintenance activities required to maintain the 4.15-mile access road from U.S. Highway 27, across the A-1 FEB levee, and into the project construction limits in good order and in accordance with Section 04.B of EM 385-1-1 and contract specifications 01 50 02 TEMPORARY CONSTRUCTION FACILITIES and 01 55 26 TRAFFIC CONTROL. Review paragraph JOB PAYMENT ITEMS above, regarding progress payments for this job-related item.
1.4.5 Relocation of Consruction Field Office (Line Item 0018)
Payment will be made for costs associated with or incidental to the relocation of all construction field office trailers and associated temporary structures to include but not be limited to temporary utilities, contractor trailer(s), government trailer(s), temporary storage containers, site signage, chain link fencing, etc., from the construction field office location first established by the Contractor as indicated on the construction plans to a second location designated on the construction plans at a time directed by the Contracting Officer or their duly appointed representative. The Contractor will only be paid for the relocation if the relocation is determined necessary and directed by the Contracting Officer or their duly appointed representative. Review
SECTION 01 22 00 Page 5 paragraph JOB PAYMENT ITEMS above, regarding progress payments for this job-related item.
1.4.6 Environmental Monitoring (Line Items 0019, 0035, 0051, and 0067)
Payment will be made for costs associated with or incidental to all required environmental monitoring for the amount of time that the environmental monitoring is required within the duration of the contract.
See Section 01 57 20 ENVIRONMENTAL PROTECTION for additional details.
Review paragraph JOB PAYMENT ITEMS above, regarding progress payments for this job-related item.
1.5 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the LINE ITEMS AND PRICING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports approved by the Government, and for performing all work required for each of the unit price items.
Each Unit Price CLIN may be a single pay activity item or may be broken down into pay activities with smaller quantities equal to CLIN total.
Contract unit price multiplied by agreed quantity is full compensation.
1.5.1 Clearing and Grubbing (Line Items 0002, 0023, 0039, and 0055)
1.5.1.1 Payment
Payment will be made for costs associated with or incidental to clearing and grubbing the construction area as noted on the construction drawings.
Payment will also be made for costs associated with or incidental to clearing and grubbing of haul roads, stockpile areas, or borrow areas within the limits of construction as identified on the Contractors approved Construction Sequence and Turnover Plan (CSTP). The Government will not pay for clearing and grubbing of the full limits of construction
1.5.1.2 Measurement
The total amount of area to be paid for under this contract will be measured by the area of land cleared and grubbed and approved by the Government by land survey.
1.5.1.3 Unit of Measure
Acre.
1.5.2 Preliminary Foundation Preparation (Line Items 0003, 0024, 0040, and 0056)
1.5.2.1 Payment
Payment will be made for costs associated with or incidental to Preliminary Foundation Preparation activities as specified in Section 31 66 10 ROCK FOUNDATION PREPARATION, to include de-mucking the dam embankment foundation, canals, and ditches for the full toe to toe dam foundation width as noted on the construction drawings. This work also
SECTION 01 22 00 Page 6 includes (1) transportation and disposal of materials; hauling and stockpiling of the muck soils (overburden); and transportation and disposal of organic and non-organic debris within the embankment foundation footprint to locations identified in the Contractors approve Construction Sequence and Turnover Plan (CSTP); (2) Inspection and mapping of the foundation by the Government with the assistance and deliverables required of the Contractor. Government will not pay for Preliminary Foundation Preparation activities in areas beyond the toe to toe dam foundation limits shown in the drawings.
1.5.2.2 Measurement
The total amount of area to be paid for under this contract will be measured by the area of embankment foundation that received preliminary foundation preparation (to include inspection and mapping of the foundation by the Government with assistance from the Contractor) approved by the Government by land survey.
1.5.2.3 Unit of Measure
Square yard.
1.5.3 Final Foundation Preparation (Line Items 0005, 0026, 0042, and 0058)
1.5.3.1 Payment
Payment will be made for costs associated with or incidental to foundation preparation as described in Section 31 66 10 ROCK FOUNDATION PREPARATION, of the project specifications for the full toe to toe foundation width as noted on the construction drawings.
1.5.3.2 Measurement
The total amount of area to be paid for under this contract will be measured by the area of foundation cleaned, prepared, inspected, tested, and approved by the Government by land survey.
1.5.3.3 Unit of Measure
Square yard.
1.5.4 Select Fill (Line Item 0006)
1.5.4.1 Payment
Payment will be made for all costs associated with and incidental to procurement (to include drilling and blasting as outlined in Section 31 23 16 BLASTING AND ROCK REMOVAL and excavation where necessary), processing, hauling/transport, stockpiling, placement, compaction, tests and reports approved by the Government, and overbuild required for select fill material to the lines and grades shown on the contract drawings.
Contractor's sources to obtain material will be to degrade the STA 3 /4 Levee adjacent to the southern embankment segment between stations 457+00 and 711+00 to the lines and grades shown on contract drawings (top of levee will not be less than 17.5 ft, NAVD88), borrow area(s) as shown on contract drawings, or by import from off-site.
SECTION 01 22 00 Page 7
1.5.4.2 Measurement
The total volume of material placed and to be paid under this contract, will be verified by cross section surveys of completed and accepted work.
Surveys will be taken before and after the placement of the select fill material. The survey taken before placement of the select fill material may be the survey taken after the placement of CLSM. The Government will perform initial and final surveys in accordance with the clause QUANTITY SURVEYS of Section 00700 CONTRACT CLAUSES in Volume 1. The Contractor must give one (1) week advance notice, in writing, to the Contracting Officer or their duly appointed representative of the need for a pre-fill (initial) survey or after-fill (final) survey for final acceptance of the volume placed within specific project stations.
1.5.4.3 Unit of Measure
Cubic yard.
1.5.5 Lime Rock Base (Line Item 0007)
1.5.5.1 Payment
Payment will be made for all costs associated with or incidental to procurement (to include drilling, blasting, and excavation where necessary), processing, hauling/transport, stockpiling, placement, quality control, protection, and maintenance of aggregate surface coarse on the degraded STA 3/4 Levee between stations 457+00 and 711+00 to the neat lines and grades shown on the drawings.
1.5.5.2 Measurement
The total amount of area to be paid for under this contract will be measured by the area of limerock base placed and prepared on the degraded STA 3/4 Levee between stations 457+00 and 711+00 by land survey, inspected, tested, and approved by the Government.
1.5.5.3 Unit of Measure
Square yard.
1.5.6 Controlled Low Strength Material (CLSM) (Line Items 0008, 0027, 0043, and 0059)
1.5.6.1 Payment
Payment will be made for costs associated with and incidental to procurement, stockpiling, processing, hauling/transport, placement, and overbuild required for CLSM dental treatment as specified in Section 31 23 24 CONTROLLED LOW STRENGTH MATERIAL (CLSM) within the limits shown on the contract drawings, and where special treatment as specified in Section 31 66 10 ROCK FOUNDATION PREPARATION may be directed within the toe to toe foundation width. to the lines and grades shown on the contract drawings.
1.5.6.2 Measurement
The total quantity of CLSM material placed and to be paid under this contract, will be measured by volume in place and quantities determined by delivery / batch tickets and by Government survey. Volume of CLSM derived
SECTION 01 22 00 Page 8 from delivery / batch tickets will be determined by dividing the total weight of the materials by the average unit weight or density of the approved mixture determined in accordance with ASTM D6023. Average unit weight will consider a running average of the three most recent tests of the same mix designation. The Government will perform initial and final surveys following submission of the final delivery / batch ticket for the segment in question in accordance with the clause QUANTITY SURVEYS of Section 00700 CONTRACT CLAUSES in Volume 1. The Contractor must give one
(1) week advance notice, in writing, to the Contracting Officer or their duly appointed representative of the need for a pre-fill (initial) survey or after-fill (final) survey for final acceptance of the volume placed within specific project stations and include any and all applicable delivery / batch tickets .
1.5.6.3 Unit of Measure
Cubic yard.
1.5.7 CLSM Top Cover (Line Items 0009, 0028, 0044, and 0060)
1.5.7.1 Payment
Payment will be made for costs associated with and incidental to procurement, processing, hauling/transport, placement, compaction, and overbuild and maintenance required for CLSM Top Cover material to the lines and grades shown on the contract drawings that includes protection of the 2H:1V transition slope(s) from top of CLSM Top Cover to natural grade as indicated on the construction drawings.
1.5.7.2 Measurement
The total amount to be paid for under this contract will be measured by the total distance of CLSM Top Cover placed, inspected, tested, and approved by the Government by land survey. Verification of grade high point will be required every 50 linear feet.
1.5.7.3 Unit of Measure
Linear foot.
1.5.8 Cutoff Wall (Line Items 0010, 0029, 0045, and 0061)
1.5.8.1 Payment
Payment will be made for costs associated with and incidental to placement of the cutoff wall, including a working platform if required by the Contractor.
1.5.8.2 Measurement
Cutoff wall will be measured for payment by the area accepted by the Contracting Officer or their duly appointed representative in accordance with Section 02 35 29 CUTOFF WALL, Paragraph ACCEPTANCE CRITERIA as measured between two Government accepted verification borings.
1.5.8.3 Unit of Measure
Square yard.
SECTION 01 22 00 Page 9
1.5.9 Verification Drilling/Testing (Line Items 0011, 0030, 0046, and 0062)
1.5.9.1 Payment
Payment will be made for costs associated with or incidental to the completion of verification drilling and testing in accordance with Section
02 32 00 VERIFICATION DRILLING AND PERMEABILITY TESTING OF IN-PLACE CUTOFF
WALL.
1.5.9.2 Measurement
The total amount to be paid for under this contract will be measured by the number of verification borings performed and approved by the Government in a complete verification boring report.
1.5.9.3 Unit of Measure
Each.
1.5.10 Standby Time (Line Item 0012)
1.5.10.1 Payment
Standby time will be paid for each calendar day as exercised by the Contracting Officer or their duly appointed representative. Standby time must be associated with and incidental to the verification testing and acceptance for the Cutoff Wall Demonstration Section. See Section
02 35 29 CUTOFF WALL.
1.5.10.2 Measurement
Standby time, when exercised by the Contracting Officer, will be measured for payment by each day, or part thereof, that the plant is not in operation. Standby time will not be provided for the initial 24 hour period following an endangered or threatened species take. Standby time will not be provided for the required temporary cessation of work due to the presence of endangered or threatened species in proximity to equipment as identified within Section 01 57 20 ENVIRONMENTAL PROTECTION. Standby time will not be provided for equipment maintenance or breakdowns.
1.5.10.3 Unit of Measure
Day.
1.5.11 Sodding (Line Item 0014)
1.5.11.1 Payment
Payment will be made for all costs associated with or incidental to sodding as specified in Section 32 92 23 SODDING. Payment constitutes full compensation for furnishing, planting, or placing and maintaining sodded areas, that result in a healthy stand of grass cover as required, including the provision and use of equipment, erosion control methods and materials, fertilizers, soil amendments, mulch, pesticides, and water.
1.5.11.2 Measurement
Sodding will be measured for payment by the area sodded as determined by land survey.
SECTION 01 22 00 Page 10
1.5.11.3 Unit of Measure
Square Yard.
1.5.12 Partnering Regroup - Meeting (Line Items 0015, 0032, 0048, and 0064)
1.5.12.1 Payment
Payment will be made for costs associated with and incidental to conducting a partnering regroup meeting. See Section 01 30 00 ADMINISTRATIVE PROCEDURES. The initial partnering meeting will not be paid for under this line item as it is a distributed cost mandatory administrative action. The Contractor will only be paid for the actual number of partnering regroups conducted.
1.5.12.2 Measurement
The basis for payment will be for the completion of each partnering regroup meeting and Government receipt of all completed work products.
1.5.12.3 Unit of Measure
Each.
1.5.13 Partnering Regroup - Venue (Line items 0016, 0033, 0049, and 0065)
1.5.13.1 Payment
Payment will be made for costs associated with and incidental to securing a venue for a partnering regroup meeting at a location other than a Government owned or leased facility. See Section 01 30 00 ADMINISTRATIVE PROCEDURES. The Contractor will only be paid for the actual number of times a venue is secured for a partnering regroup meeting.
1.5.13.2 Measurement
The basis for payment will be for the completion of securing a venue for a partnering regroup meeting and Government receipt of the venue invoice after completion of the partnering regroup meeting.
1.5.13.3 Unit of Measure
Each.
1.5.14 Contracting Officer's Field Office (Line Items 0020, 0036, 0052, and 0068)
1.5.14.1 Payment
Payment will be made for costs associated with and incidental to providing, maintaining, and final disposition of the Contracting Officer's Field Office including all costs for renting or procuring, and provision of all services and equipment indicated in Section 01 52 10 CONTRACTING OFFICER'S FIELD OFFICE. In addition, payment will include the cost for maintaining the existing parking area. Costs for provision and maintenance of the Contractor's own field office and other facilities will not be paid for under this line item.
SECTION 01 22 00 Page 11
1.5.14.2 Measurement
The basis for payment will be the amount of time that the Contracting Officer's Field Office, services, and equipment are available to the Government within the duration of the contract. Payment will not be made for this line item if construction extends beyond required contract completion as a result of contractor delays; however, the office must still be made available for use by the Government.
1.5.14.3 Unit of Measure
Month.
1.5.15 Additional Contracting Officer's Field Office (Line Items 0021, 0037, 0053, and 0069)
1.5.15.1 Payment
Payment will be made for costs associated with and incidental to providing, maintaining, and final disposition of the Additional Contracting Officer's Field Office including all costs for renting or procuring, and provision of all services and equipment indicated in Section 01 52 11 ADDITIONAL CONTRACTING OFFICERS'S FIELD OFFICE. Payment will only be made for the Additional Contracting Officer's Field Office if it is determined necessary and the Contractor is directed by the Contracting Officer or their duly appointed representative to install the Additional Contracting Officer's Field Office.
1.5.15.2 Measurement
The basis for payment will be the amount of time that the Additional Contracting Officer's Field Office, services, and equipment are available to the Government within the duration of the contract. Payment will only be made for this line item if it is determined necessary and the Contractor is directed by the Contracting Officer or their duly appointed representative to install the Additional Contracting Officer's Field Office. Payment will not be made for this line item if construction extends beyond required contract completion as a result of contractor delays; however, the office must still be made available for use by the Government.
1.5.15.3 Unit of Measure
Month.
1.5.16 Temporary Quality Assurance Lab (Line Items 0022, 0038, 0054, and 0070)
1.5.16.1 Payment
Payment will be made for costs associated with and incidental to providing, maintaining, and final disposition of the Temporary Quality Assurance Lab including all costs for renting or procuring, and provision of all services and equipment indicated in Section 01 52 10 CONTRACTING OFFICER'S FIELD OFFICE associated with the Quality Assurance Laboratory.
In addition, payment will include the cost for maintaining the existing parking area. Costs for provision and maintenance of the Contractor's own field office and other facilities will not be paid for under this line item.
SECTION 01 22 00 Page 12
1.5.16.2 Measurement
The basis for payment will be the amount of time that the Temporary Quality Assurance Lab, services, and equipment are available to the Government within the duration of the contract. Payment will not be made for this line item if construction extends beyond required contract completion as a result of contractor delays; however, the office, equipment, and services must still be made available for use by the Government.
1.5.16.3 Unit of Measure
Month.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 PAYMENT PROCEDURES
Upon receiving initial Resident Management System import file, go to PAY ACTIVITIES and establish a link between bid breakdown schedule of values of PAY ACTIVITIES to contract CLINs using SCHEDULE ACTIVITIES data entry page.
3.1.1 Requesting Progress Payment
For progress payments, ensure ACTIVITY SCHEDULE, FEATURE SCHEDULE, submittal register, and punchlists are all up to date. Use PROGRESS PAYMENTS to REQUREST ACTIVITY for both ACTIVITY EARNINGS data entry page and OTHER EARNING. Provide hard copies of supporting invoices and quantity measurements to support all requested earnings. Ensure that sums of payment activities do not exceed contract award CLIN funding amounts, or unbalanced CLINs error will prevent processing the payment. Submit a request for progress payment monthly in accordance with Clause 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS of Section 00700 CONTRACT CLAUSES. In addition to the items listed in Clause the following in the request for progress payment:
a. Approved construction schedule for the requested billing period.
b. Up-to-date payroll records for prime and subcontractors per FAR
52.222-8(b).
c. Current submittal register.
d. Approved submittals on installed property.
e. QA/QC deficiency tracking list per FAR 52.232-5(b)(1)(v).
f. Environmental reports.
g. Progress photographs.
h. Working/current as-built drawings.
i. Updated schedule of values.
j. Proper Invoice per FAR 52.232-27(a)(2).
k. Documentation to substantiate payment per FAR 52.232-27(a)(2)(viii).
l. Payment Certification Form that includes all subcontractor information required by FAR 52.232-5(b)(1)(ii thru iv).
m. Copy of letter to subcontractors regarding withholding (if applicable) per FAR 52.232-27(d)(3)(ii).
n. Verification that man-hour exposure reports for prime and subcontractors are current per EM 385-1-1 .
o. Monthly adverse weather documented and agreed upon per ER 415-1-15.
SECTION 01 22 00 Page 13
p. Required safety meetings held and documented.
q. Up-to-date CQC reports.
Once the complete pay application package is received to include the Contractor's signed ENG 93, the 14 calendar days will commence.
3.1.2 Options and Modification CLINS
When additional work is added by modification, existing CLINs funding amounts must be updated, or new CLINs for modification will be created.
If contract has option CLINs not yet awarded, option CLINs will appear as zero dollar CLINs until option is awarded by modification. No payment may be requested for Options or Modification CLINs until contract modification has been funded and signed.
-- End of Section --
SECTION 01 22 00 Page 14
SECTION TABLE OF CONTENTS
DIVISION 31 - EARTHWORK
SECTION 31 00 00
EARTHWORK
PART 1 GENERAL
1.1 SUMMARY
1.2 REFERENCES
1.3 PROJECT SAFETY
1.4 DEFINITIONS
1.4.1 Satisfactory Materials
1.4.1.1 Select Fill
1.4.1.2 Uncompacted Fill
1.4.1.3 Limerock Base
1.4.1.4 Fine Aggregate (Sand)
1.4.2 Unsatisfactory Materials
1.4.3 "Free of"
1.4.4 Degree of Compaction
1.4.5 Muck
1.4.6 Overburden
1.4.7 De-mucking
1.4.8 Excavation and Degrading
1.4.9 Embankment
1.4.10 Hard/Unyielding Materials
1.4.11 Rock
1.4.12 Unstable Satisfactory Soils
1.4.13 Proof of Concept
1.4.14 Pass
1.4.15 Embankment Termination/Resumption Locations
1.4.16 Topsoil
1.5 SYSTEM DESCRIPTION
1.5.1 Materials Encountered
1.5.2 Ground Water Elevation
1.5.3 Borrow Areas
1.5.4 Stockpiling
1.5.5 Drainage Requirements
1.5.6 Haul Roads
1.5.7 Classification of Excavation
1.5.8 Blasting
1.5.9 Rolled Erosion Control Product (RECP)
1.6 SUBMITTALS
1.7 SUBMITTAL REQUIREMENTS
1.7.1 Contractor Earthwork Quality Control Plan
1.7.2 Excavation, Degrading, and Stockpiling Plan
1.7.3 Earthwork Plan
1.7.4 Laboratory Validation
1.7.5 Survey of Embankment
1.7.6 Professional Geotechnical Engineer
1.7.7 Contractor Quality Control Testing Results
1.7.8 Quality Control Laboratory and Field Testing Equipment
SECTION 31 00 00 Page 1
Calibration
1.7.9 Laboratory Testing Personnel Qualifications
1.7.10 Nuclear Density
1.8 GENERAL PROVISIONS
1.8.1 Conduct on the Work
1.9 REGULATORY REQUIREMENTS
1.10 PERMITS
1.11 INSPECTION AND TESTING COORDINATION
1.12 DATA MANAGEMENT
PART 2 PRODUCTS
2.1 REQUIREMENTS FOR IMPORTED AND BORROW MATERIALS
2.2 SELECTION OF ONSITE BORROW MATERIAL
2.3 ROLLED EROSION CONTROL PRODUCT (RECP)
2.4 RECP PINS
PART 3 EXECUTION
3.1 CLEARING, GRUBBING, AND DE MUCKING
3.2 PROOF OF CONCEPT DEMONSTRATION
3.3 PROTECTION
3.4 EXCAVATION (GENERAL)
3.4.1 Over Excavation
3.4.2 Existing Southern Seepage Canal
3.4.3 Existing STA 3/4 Levee
3.4.4 Existing Ditches or Swales
3.4.5 Opening and Drainage of Borrow Areas
3.5 UTILIZATION OF EXCAVATED MATERIALS
3.6 SUBGRADE PREPARATION
3.6.1 ROCK FOUNDATIONS
3.6.2 STA 3/4 Levee Road
3.6.3 Canal and Ditch Bottoms
3.7 PROOF ROLLING FOR THE SOUTHERN SEEPAGE CANAL
3.8 PLACING
3.8.1 Limerock Base
3.8.2 Select Fill (General)
3.8.2.1 Select Fill Placement
3.8.3 Final Dressing
3.8.4 Compaction
3.9 FINISHING AND TOLERANCES
3.10 ROLLED EROSION CONTROL PRODUCT (RECP)
3.10.1 RECP Installation Plan
3.10.2 Conditions
3.10.3 Placement
3.10.4 Installation
3.10.5 Patching and Replacement
3.11 CONTRACTOR QUALITY CONTROL TESTING
3.11.1 Soil Classification Tests
3.11.2 Moisture Density Relationships
3.11.3 Water (Moisture) Content Tests
3.11.4 In-place Density Tests
3.12 DIGITAL DATA RECORDS
-- End of Section Table of Contents --
SECTION 31 00 00 Page 2
SECTION 31 00 00
EARTHWORK
PART 1 GENERAL
1.1 SUMMARY
Provide all labor, equipment, materials, and incidentals necessary for processing of borrow material, excavation/degrading of the STA 3/4 Levee, construction of the STA 3/4 Levee road, excavation/shaping and soil filling of the southern seepage canal, construction of CLSM Top Cover, and other project earthwork and excavation work as may be necessary to complete the construction as specified herein and as shown on the contract Drawings. Related Sections include but are not necessarily limited to:
a. Section 01 45 08 DATA MANAGEMENT AND DATA REQUIREMENTS
b. Section 31 23 24 CONTROLLED LOW STRENGTH MATERIAL (CLSM)
c. Section 31 66 10 ROCK FOUNDATION PREPARATION
d. Section 31 52 10 DEWATERING
e. Section 32 11 23 LIMEROCK BASE FOR ROADS
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM C136/C136M (2019) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates
ASTM D1140 (2017) Standard Test Methods for Determining the Amount of Material Finer than 75-µm (No. 200) Sieve in Soils by Washing
ASTM D1556/D1556M (2015; E 2016) Standard Test Method for Density and Unit Weight of Soil in Place by Sand-Cone Method
ASTM D1557 (2021) Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3)
ASTM D2216 (2019) Standard Test Methods for Laboratory Determination of Water (Moisture) Content of Soil and Rock by Mass
SECTION 31 00 00 Page 3
ASTM D2487 (2017; E 2020) Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System)
ASTM D2974 (2020; E 2020) Moisture, Ash, and Organic Matter of Peat and Other Organic Soils
ASTM D4643 (2017) Standard Test Method for Determination of Water Content of Soil and Rock by Microwave Oven Heating
ASTM D4718/D4718M (2015) Standard Practice for Correction of Unit Weight and Water Content for Soils Containing Oversize Particles
ASTM D5035 (2011) Breaking Force and Elongation of Textile Fabrics (Strip Method)
ASTM D6938 (2017a) Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)
ASTM D6459 (2019) Standard Test Method for Determination of Rolled Erosion Control Product (RECP) Performance in Protecting Hillslopes from Rainfall-Induced Erosion
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.3 PROJECT SAFETY
Complete all work in accordance with EM 385-1-1 and Section 01 35 26
GOVERNMENTAL SAFETY REQUIREMENTS.
1.4 DEFINITIONS
1.4.1 Satisfactory Materials
1.4.1.1 Select Fill
Select fill is material free of debris, peat, excessive roots, seeds of nuisance or exotic species, excessive organic material, and rocks exceeding six (6) inches US Sieve particle size (measured in any direction) and is not gap graded. Select fill must contain by weight maximum 30 percent retained on the 3 inch sieve, minimum 20 percent retained on the No. 4 sieve, and maximum 15 percent passing the No. 200 sieve. Select fill used for the Southern Seepage Canal filling does not need to meet the minimum percent retained on the No. 4 sieve. All soils classified as gravel must have a minimum of 50 percent of the material sample by weight passing the No. 4 sieve. Select fill must have an average organic content of not more than 2 percent or have an individual test value of not more than 4 percent, as tested in accordance with ASTM D2974. Individual roots must not exceed 1/2 inch in diameter, nor 6 inches in length, and must not be present in concentrations, root balls, SECTION 31 00 00 Page 4 or mats. Select fill must meet any of the following USCS designations in accordance with ASTM D2487: SW-SC, SW-SM, SM, SC, SP-SC, SP-SM, GM, GW-GM, or GP-GM. Perform grain size analyses in accordance with ASTM C136/C136M and ASTM D1140.
1.4.1.2 Uncompacted Fill
See Section 02 35 29 CUTOFF WALL. Select fill, deposited in layers on top of the uncured cutoff wall but not compacted except by the controlled movement of hauling and spreading material. Previously placed and compacted select fill used for CLSM top cover can be re-used for uncompacted fill.
1.4.1.3 Limerock Base
See Section 32 11 23 LIMEROCK BASE COURSE. Limerock base must be processed to meet the requirements for limerock base specified in FDOT Standard Specifications for Road and Bridge Construction, Section 911, Base and Stabilized Base Materials. As an exception, Section 911-3.3, Carbonates, must not apply.
1.4.1.4 Fine Aggregate (Sand)
See Section 31 23 24 CONTROLLED LOW STRENGTH MATERIAL (CLSM). Fine aggregate (sand) is used in the production of CLSM.
1.4.2 Unsatisfactory Materials
Materials which do not comply with the requirements for satisfactory materials are unsatisfactory, unless approved by the Contracting Officer.
Unsatisfactory materials also include muck, man-made fills, trash, refuse, sediment, soft or pumping subgrades (see definition of Unstable Satisfactory Soils in this section), and material classified as satisfactory which contains a fines content (percent passing No. 200 U.S.
sieve) or root and other organic matter that exceed the allowable limits specified in paragraph satisfactory materials. Notify the Contracting Officer when encountering any contaminated materials.
1.4.3 "Free of"
Specifications for fill materials commonly require the material to be free of deleterious materials such as roots, organic material, litter, trash, or particles greater than a certain particle size. In this context, "free of" means that when carefully visually examined there is no apparent presence of the deleterious material. In general, if less than 1 percent by weight of the material is composed of the deleterious items, the material shall be considered "free of" the items.
1.4.4 Degree of Compaction
Degree of compaction required, except as noted in the second sentence, is expressed as a percentage of the maximum density obtained by the test procedure presented in ASTM D1557 abbreviated as a percent of laboratory maximum density.
If a material has more than 30 percent by weight passing the 3/4-inch sieve, the degree of compaction will be expressed as a percentage of the maximum density in accordance with ASTM D4718/D4718M .
SECTION 31 00 00 Page 5
1.4.5 Muck
Muck is a local name for the brown to black, organic and nutrient rich surficial soil prevalent in the Everglades Agricultural Area or sediments that have settled on the bottoms and slopes of…