This document provides details for a federal contract solicitation to perform construction services for the Central Everglades Planning Project Contract 1 in Miami-Dade County, Florida. The U.S. Army Corps of Engineers Jacksonville District is seeking to install three L-67A levee structures with gated box culverts, remove existing spoil islands, excavate a 3,000-foot gap in the L-67C levee to connect water conservation areas, and backfill an agricultural ditch. Additional scope of work includes using excavated materials to backfill portions of canals and disposal of excess material. The solicitation number is W912EP20R0021 and responses are due based on the dates provided in the attached solicitation documents.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

See Summary of Changes

1. CONTRACT ID CODE PAGE OF PAGES

J 1 312

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EP20R0021

X 9B. DATED (SEE ITEM 11)

28-Jul-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

A00001

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

24-Aug-2020

CODE

USA ENGINEER DISTRICT, JACKSONVILLE

CONTRACTING DIVISION

701 SAN MARCO BLVD

JACKSONVILLE FL 32207-8175

W912EP 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

X 1

W912EP20R0021 1 Amendment 0001

SF 30 CONTINUATION SHEET

CENTRAL EVERGLADES PLANNING PROJECT (CEPP)SOUTH CONTRACT 1,

L-67A STRUCTURES (S-631, S-632, and S-633), SPOIL PILE REMOVAL AND L-67C GAP PROJECT

MIAMI-DADE COUNTY, FLORIDA

SUMMARY OF CHANGES

1. PERMIT ADDITION:

INCLUDE: COMPREHENSIVE EVERGLADES RESTORATION PLAN REGULATION ACT (CERPRA) PERMIT CONSTRUCTION AUTHORIZATION (File No. 0387130-001)

2. SPECIFICATIONS:

The text changes have been updated with additions noted by underlined text and deletions noted by line/cross-outs, and pertain only to changes made by this revision. The entire section is replaced if there is any change. The Project Table of Contents and Submittal Register are replaced without underlines and cross-outs if there are changes to these documents. New sections are added without underlines and cross-outs.

Volume 1 – SF1442:

REVISE SF1442 to extend the proposal due date from 27 Aug 2020 to 1 Sep 2020 DELETE Section 00010A Bid Schedule and REPLACE with the attached Section 00010A Bid Schedule DELETE Section 00800A and REPLACE with the attached Section 00800A

Volume 2 – Technical Specifications:

DELETE Table of Contents and REPLACE with the attached Table of Contents.

DELETE Section 01 11 00 and REPLACE with the attached section 01 11 00.

DELETE Section 01 22 00 and REPLACE with the attached Section 01 22 00.

DELETE Section 01 30 00 and REPLACE with the attached Section 01 30 00.

DELETE Submittal Register and REPLACE with the attached Submittal Register.

DELETE Section 01 52 10 and REPLACE with the attached Section 01 52 10.

DELETE Section 01 57 20 and REPLACE with the attached Section 01 57 20.

DELETE Section 05 50 15 and REPLACE with the attached Section 05 50 15.

DELETE Section 26 32 16 and REPLACE with the attached Section 26 32 16.

DELETE Section 26 42 14 and REPLACE with the attached Section 26 42 14.

DELETE Section 31 23 00 and REPLACE with the attached Section 31 23 00.

ADD Section 33 29 00.

DELETE Section 35 20 16 and REPLACE with the attached Section 35 20 16.

DELETE Section 35 41 00 and REPLACE with the attached Section 35 41 00.

3. DRAWINGS:

DELETE Drawing C-01 and REPLACE with the attached Drawing C-01.

DELETE Drawing C-02 and REPLACE with the attached Drawing C-02.

DELETE Drawing C-03 and REPLACE with the attached Drawing C-03.

DELETE Drawing C-04 and REPLACE with the attached Drawing C-04.

DELETE Drawing C-05 and REPLACE with the attached Drawing C-05.

DELETE Drawing C-06 and REPLACE with the attached Drawing C-06.

DELETE Drawing C-10 and REPLACE with the attached Drawing C-10.

DELETE Drawing C-11 and REPLACE with the attached Drawing C-11.

DELETE Drawing C-12 and REPLACE with the attached Drawing C-12.

DELETE Drawing C-17 and REPLACE with the attached Drawing C-17.

DELETE Drawing C-19 and REPLACE with the attached Drawing C-19.

DELETE Drawing C 20 and REPLACE with the attached Drawing C-20.

DELETE Drawing C-25 and REPLACE with the attached Drawing C-25.

W912EP20R0021 2 Amendment 0001

SF 30 CONTINUATION SHEET

CENTRAL EVERGLADES PLANNING PROJECT (CEPP)SOUTH CONTRACT 1,

L-67A STRUCTURES (S-631, S-632, and S-633), SPOIL PILE REMOVAL AND L-67C GAP PROJECT

MIAMI-DADE COUNTY, FLORIDA

DELETE Drawing G-05 and REPLACE with the attached Drawing G-05.

DELETE Drawing G-06 and REPLACE with the attached Drawing G-06.

DELETE Drawing G-07 and REPLACE with the attached Drawing G-07.

DELETE Drawing G-08 and REPLACE with the attached Drawing G-08.

DELETE Drawing G-09 and REPLACE with the attached Drawing G-09.

DELETE Drawing S-01 and REPLACE with the attached Drawing S-01.

DELETE Drawing S-06 and REPLACE with the attached Drawing S-06.

DELETE Drawing S-09 and REPLACE with the attached Drawing S-09.

DELETE Drawing S-25 and REPLACE with the attached Drawing S-25.

DELETE Drawing S-26 and REPLACE with the attached Drawing S-26.

DELETE Drawing S-27 and REPLACE with the attached Drawing S-27.

DELETE Drawing S-28 and REPLACE with the attached Drawing S-28.

DELETE Drawing E-02 and REPLACE with the attached Drawing E-02.

DELETE Drawing E-03 and REPLACE with the attached Drawing E-03.

DELETE Drawing E-06 and REPLACE with the attached Drawing E-06.

DELETE Drawing E-07 and REPLACE with the attached Drawing E-07.

DELETE Drawing E-08 and REPLACE with the attached Drawing E-08.

DELETE Drawing E-11 and REPLACE with the attached Drawing E-11.

DELETE Drawing E-14 and REPLACE with the attached Drawing E-14.

DELETE Drawing E-15 and REPLACE with the attached Drawing E-15.

DELETE Drawing E-16 and REPLACE with the attached Drawing E-16.

DELETE Drawing E-21 and REPLACE with the attached Drawing E-21.

DELETE Drawing E-22 and REPLACE with the attached Drawing E-22.

DELETE Drawing E-23 and REPLACE with the attached Drawing E-23.

DELETE Drawing T-01 and REPLACE with the attached Drawing T-01.

DELETE Drawing T-02 and REPLACE with the attached Drawing T-02.

DELETE Drawing T-04 and REPLACE with the attached Drawing T-04.

DELETE Drawing T-08 and REPLACE with the attached Drawing T-08.

DELETE Drawing T-09 and REPLACE with the attached Drawing T-09.

DELETE Drawing T-10 and REPLACE with the attached Drawing T-10.

(End of Summary of Changes)

W912EP20R0021 3 Amendment 0001

SECTION 00010A

LINE ITEMS AND PRICING SCHEDULE

CENTRAL EVERGLADES PLANNING PROJECT (CEPP)

SOUTH CONTRACT 1 - L-67A STRUCTURES, (S-631, S-632, AND S-633),

SPOIL PILE REMOVAL AND L-67C GAP PROJECT

MIAMI-DADE COUNTY, FLORIDA

LINE ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL

0001 SITE SIGNAGE JOB $_______________

0002 CONTRACTING OFFICER'S FIELD OFFICE 49 MONTH $___________ $_______________

0003 PARTNERING REGROUP EACH $___________ $_______________

0004 TRAFFIC CONTROL JOB $_______________

0005 ENVIRONMENTAL & TURBIDITY MONITORING JOB $_______________

0006 CLEARING, GRUBBING AND STRIPPING ACRE $___________ $_______________

0007 EARTHEN COFFERDAMS CUBIC YARD $___________ $_______________

0008 DEWATERING JOB $_______________

0009 EXCAVATION CUBIC YARD $___________ $_______________

0010 ROCK EXCAVATION CUBIC YARD $___________ $_______________

0011 CONCRETE FILLING OF VOIDS CUBIC YARD $___________ $_______________

0012 TEMPORARY SHEET PILE CUTOFF WALL JOB $_______________

0013 MUD MAT JOB $_______________

0014 STRUCTURE REINFORCED CONCRETE JOB $_______________

0015 VERTICAL SLIDE GATE WITH ACTUATOR JOB $_______________

0016 STILLING WELLS JOB $_______________

0017 EMBEDDED METALS JOB $_______________

0018 MISCELLANEOUS METALS, GUARD RAILS & JOB $_______________

POSTS

0019 BEDDING STONE AND GEOTEXTILE SQUARE YARD $___________ $_______________

0020 RIP RAP SQUARE YARD $___________ $_______________

0021 EMBANKMENT FILL CUBIC YARD $___________ $_______________

0022 CONTROL BUILDING JOB $_______________

0023 PROPANE GAS SYSTEM AND GENERATOR JOB $_______________

0024 # 57 STONE SQUARE YARD $___________ $_______________

0025 LIMEROCK SURFACE SQUARE YARD $___________ $_______________

0026 TOPSOIL AND SOD

STRUCTURE S-631

4.4

7,300

10,270

1,740

1,740

18,650

2,200

3,870 SQUARE YARD $___________ $_______________

0027 ELECTRICAL AND TELECOMMUNICATIONS WORK JOB $_______________

AND EQUIPMENT FOR EACH STRUCTURE

0028 EROSION PROTECTION & SEDIMENT CONTROL JOB $_______________

0029 FLOATING DEBRIS BARRIER JOB $_______________

00010A-1

W912EP20R0021 4 Amendment 0001

CENTRAL EVERGLADES PLANNING PROJECT (CEPP)

SOUTH CONTRACT 1 - L-67A STRUCTURES, (S-631, S-632, AND S-633),

SPOIL PILE REMOVAL AND L-67C GAP PROJECT

MIAMI-DADE COUNTY, FLORIDA

LINE ITEM DESCRIPTION UNIT UNIT PRICE TOTAL

0030 CLEARING, GRUBBING AND STRIPPING ACRE $___________ $_______________

0031 EARTHEN COFFERDAMS CUBIC YARD $___________ $_______________

0032 DEWATERING JOB $_______________

0033 EXCAVATION CUBIC YARD $___________ $_______________

0034 ROCK EXCAVATION CUBIC YARD $___________ $_______________

0035 CONCRETE FILLING OF VOIDS

QUANTITY

STRUCTURE S-632

4.4

6,850

10,450

750 CUBIC YARD $___________ $_______________

0036 TEMPORARY SHEET PILE CUTOFF WALL JOB $_______________

0037 MUD MAT JOB $_______________

0038 STRUCTURE REINFORCED CONCRETE JOB $_______________

0039 VERTICAL SLIDE GATE WITH ACTUATOR JOB $_______________

0040 STILLING WELLS JOB $_______________

0041 EMBEDDED METALS JOB $_______________

0042 MISCELLANEOUS METALS, GUARD RAILS & JOB $_______________

POSTS

0043 BEDDING STONE AND GEOTEXTILE 1,740 SQUARE YARD $___________ $_______________

0044 RIP RAP 1,740 SQUARE YARD $___________ $_______________

0045 EMBANKMENT FILL 18,540 CUBIC YARD $___________ $_______________

0046 CONTROL BUILDING JOB $_______________

0047 PROPANE GAS SYSTEM AND GENERATOR JOB $_______________

0048 # 57 STONE 175 SQUARE YARD $___________ $_______________

0049 LIMEROCK SURFACE 2,200 SQUARE YARD $___________ $_______________

0050 TOPSOIL AND SOD SQUARE YARD $___________ $_______________

0051 ELECTRICAL AND TELECOMMUNICATIONS WORK JOB $_______________

AND EQUIPMENT FOR EACH STRUCTURE

0052 EROSION PROTECTION & SEDIMENT CONTROL JOB $_______________

0053 FLOATING DEBRIS BARRIER JOB $_______________

0054 CLEARING, GRUBBING AND STRIPPING ACRE $___________ $_______________

0055 EARTHEN COFFERDAMS CUBIC YARD $___________ $_______________

0056 DEWATERING JOB $_______________

0057 EXCAVATION CUBIC YARD $___________ $_______________

0058 ROCK EXCAVATION CUBIC YARD $___________ $_______________

0059 CONCRETE FILLING OF VOIDS

3,870

STRUCTURE S-633

4.4

6,850

10,270

750 CUBIC YARD $___________ $_______________

00010A-2

W912EP20R0021 5 Amendment 0001

CENTRAL EVERGLADES PLANNING PROJECT (CEPP)

SOUTH CONTRACT 1 - L-67A STRUCTURES, (S-631, S-632, AND S-633),

SPOIL PILE REMOVAL AND L-67C GAP PROJECT

MIAMI-DADE COUNTY, FLORIDA

LINE ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL

0060 TEMPORARY SHEET PILE CUTOFF WALL JOB $_______________

0061 MUD MAT JOB $_______________

0062 STRUCTURE REINFORCED CONCRETE JOB $_______________

0063 VERTICAL SLIDE GATE WITH ACTUATOR JOB $_______________

0064 STILLING WELLS JOB $_______________

0065 EMBEDDED METALS JOB $_______________

0066 MISCELLANEOUS METALS, GUARD RAILS & JOB $_______________

POSTS

0067 BEDDING STONE AND GEOTEXTILE 1,740 SQUARE YARD $___________ $_______________

0068 RIP RAP 1,740 SQUARE YARD $___________ $_______________

0069 EMBANKMENT FILL 18,360 CUBIC YARD $___________ $_______________

0070 CONTROL BUILDING JOB $_______________

0071 PROPANE GAS SYSTEM AND GENERATOR JOB $_______________

0072 # 57 STONE 175 SQUARE YARD $___________ $_______________

0073 LIMEROCK SURFACE 2,200 SQUARE YARD $___________ $_______________

0074 TOPSOIL AND SOD 3,870 SQUARE YARD $___________ $_______________

0075 ELECTRICAL AND TELECOMMUNICATIONS WORK JOB $_______________

AND EQUIPMENT FOR EACH STRUCTURE

0076 EROSION PROTECTION & SEDIMENT CONTROL JOB $_______________

0077 FLOATING DEBRIS BARRIER JOB $_______________

0078 CLEARING, GRUBBING AND STRIPPING 6.3 ACRE $___________ $_______________

0079 EXCAVATION 50,300 CUBIC YARDS $___________ $_______________

0080 EROSION PROTECTION & SEDIMENT CONTROL JOB $_______________

0081 CLEARING, GRUBBING AND STRIPPING 3.5 ACRE $___________ $_______________

0082 EXCAVATION 13,175 CUBIC YARDS $___________ $_______________

0083 EROSION PROTECTION & SEDIMENT CONTROL JOB $_______________

0084 CLEARING, GRUBBING AND STRIPPING 15.0 ACRE $___________ $_______________

0085 EXCAVATION 7,500 CUBIC YARDS $___________ $_______________

0086 COMMON FILL 22,870 CUBIC YARDS $___________ $_______________

0087 JOB $_______________EROSION PROTECTION & SEDIMENT CONTROL

SPOIL PILE REMOVAL

LEVEE 67-C EXCAVATION

BACKFILL OF EAST-WEST AGRICULTURAL CANAL

00010A-3

W912EP20R0021 6 Amendment 0001

CENTRAL EVERGLADES PLANNING PROJECT (CEPP)

SOUTH CONTRACT 1 - L-67A STRUCTURES, (S-631, S-632, AND S-633),

SPOIL PILE REMOVAL AND L-67C GAP PROJECT

MIAMI-DADE COUNTY, FLORIDA

LINE ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL

TOTAL BID (LINE ITEMS 0001 THROUGH 0087) $_______________

NOTES: (1) OFFER MUST PRICE ALL LINE ITEMS. SEE SECTION 00100 "INSTRUCTIONS TO OFFERORS".

00010A-4

W912EP20R0021 7 Amendment 0001

Section 00800A – WAGE DETERMINATION & OTHER ATTACHMENTS

52.200-1 LIST OF CONSTRUCTION CONTRACT ATTACHMENTS

LIST OF CONSTRUCTION CONTRACT ATTACHMENTS

NO. TITLE DATE NO. OF PAGES

1 General Decision Number FL20200125 14 Aug 2020 7 2 General Decision Number FL20200215 15 May 2020 6

W912EP20R0021 8 Amendment 0001

NOTE NOTE NOTE

THIS PROJECT INCORPORATES THE HEAVY CONSTRUCTION AND BUILDING

CONSTRUCTION WAGE DECISIONS FOR MIAMI-DADE COUNTY, FL

THE BUILDING CONSTRUCTION WAGE DECISION WILL BE USED FOR THE

CONSTRUCTION OF AND ANY WORK INCIDENTAL TO THE CONTROL

BUILDINGS

EXECUTIVE ORDER (EO) 13658 ESTABLISHES AN HOURLY MINIMUM WAGE OF

$10.80 FOR 2020 THAT APPLIES TO ALL CONTRACTS SUBJECT TO THE

DAVIS-BACON ACT FOR ALL HOURS PERFORMED ON THE CONTRACT IN

CALENDAR YEAR 2020

IF YOU HAVE ANY QUESTIONS CONCERNING THE APPLICATION OF THE

WAGE DECISIONS FURNISHED FOR THIS PROJECT, PLEASE CONTACT:

FRAN RUSSELL, OFFICE OF COUNSEL, JACKSONVILLE DISTRICT, U.S. ARMY

CORPS OF ENGINEERS AT fran.g.russell@usace.army.mil

W912EP20R0021 9 Amendment 0001

"General Decision Number: FL20200125 08/14/2020

Superseded General Decision Number: FL20190125

State: Florida

Construction Type: Heavy

County: Miami-Dade County in Florida.

HEAVY CONSTRUCTION PROJECTS (Including Sewer and Water Lines)

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.80 for calendar year 2020 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.80 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2020. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(l)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.l(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number

ELEC0349-007 09/02/2019

Publication Date 01/03/2020 08/14/2020

Rates

ELECTRICIAN ...................... $ 35.36

Fringes

12.77 https:l/beta.sam.gov/wage-determination/FL20200125/1 ?keywords=fl20200125&sort=-relevance&index=wd&is_active=true&page= 1 1/7

Updated wage rates in Section 00800A:

W912EP20R0021 10 Amendment 0001

8/19/2020

ENGI0487-017 07/01/2013

Rates

OPERATOR: Backhoe (Except Loader Combo) .................... $ 28.32 OPERATOR: Crane

All Tower Cranes (Must have 2 operators) Mobile, Rail, Climbers, Static Mount; All Cranes with Boom Length 150 Feet & Over (With or without jib) Friction, Hydro, Electric or Otherwise; Cranes 150 Tons & Over (Must have 2 operators); Cranes with 3 Drums {When 3rd drum is rigged for work); Gantry & Overhead Cranes; Hydro Cranes Over 25 Tons but not more than 50 Tons (Without Oiler/Apprentice);

Hydro/Friction Cranes without Oiler/Apprentices when Approved by Union; & All Type of Flying Cranes;

Boom Truck .................. $ 29.05 Cranes with Boom Length Less than 150 Feet (With or without jib); Hydro Cranes 25 Tons & Under, & Over 50 Tons (With Oiler/Apprentice); Boom Truck ....................... $ 28.32

OPERATOR: Drill ................. $ 25.80

OPERATOR: Loader ................ $ 25.64 OPERATOR: Oiler ................. $ 22.99

IRON0272-005 10/01/2019

Rates

IRONWORKER, STRUCTURAL ........... $ 25.49

LABO1652-004 05/01/2018

Rates

Fringes

8.80

8.80

8.80

8.80

8.80

8.80

Fringes

11.99

Fringes beta.SAM.gov https:l/beta.sam.gov/wage-determination/FL20200125/1 ?keywords=fl20200125&sort=-relevance&index=wd&is_active=true&page= 1 2/7 W912EP20R0021 11 Amendment 0001

LABORER: Grade Checker .......... $ 22.05

* PAIN0365-007 08/01/2020

Rates

PAINTER: Brush, Roller and Spray ............................ $ 20.21

SUFL2009-164 06/24/2009

Rates

CARPENTER, Includes Form Work .... $ 17.00

CEMENT MASON/CONCRETE FINISHER ... $ 16.61

LABORER: Common or General ...... $ 13.09

LABORER: Landscape .............. $ 7.25

LABORER: Power Tool Operator (Hand Held Drills/Saws, Jackhammer and Power Saws Only) ............................ $ 10.63

OPERATOR: Asphalt Paver ......... $ 11.59

OPERATOR: Backhoe Loader Combo ............................ $ 16.10

OPERATOR: Bulldozer ............. $ 14.95

OPERATOR: Excavator ............. $ 21.16

OPERATOR: Grader/Blade .......... $ 16.00

OPERATOR: Mechanic .............. $ 14.32

OPERATOR: Roller ................ $ 10.95

OPERATOR: Scraper ............... $ 11.00

OPERATOR: Trackhoe .............. $ 20.92

OPERATOR: Tractor ............... $ 10.54

TRUCK DRIVER, Includes Dump

7.27

Fringes

11.83

Fringes

2.51

5.52

1.26

0.00

2.20

0.00

2.44

0.81

1.67

2.84

0.00

0.00

1.74

5.50

0.00 https:l/beta.sam.gov/wage-determination/FL20200125/1 ?keywords=fl20200125&sort=-relevance&index=wd&is_active=true&page= 1 3/7 W912EP20R0021 12 Amendment 0001

Truck ............................ $ 9.60

TRUCK DRIVER: Lowboy Truck ...... $ 12.73

TRUCK DRIVER: Off the Road Truck ............................ $ 12.21

0.00

0.00

1.97

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

https:l/beta.sam.gov/wage-determination/FL20200125/1 ?keywords=fl20200125&sort=-relevance&index=wd&is_active=true&page= 1 4/7 W912EP20R0021 13 Amendment 0001

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage https:l/beta.sam.gov/wage-determination/FL20200125/1 ?keywords=fl20200125&sort=-relevance&index=wd&is_active=true&page= 1 5/7 W912EP20R0021 14 Amendment 0001 determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

https:l/beta.sam.gov/wage-determination/FL20200125/1?keywords=fl20200125&sort=-relevance&index=wd&is_active=true&page= 1 6/7 W912EP20R0021 15 Amendment 0001

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION"

https:l/beta.sam.gov/wage-determination/FL20200125/1 ?keywords=fl20200125&sort=-relevance&index=wd&is_active=true&page= 1 7/7 W912EP20R0021 16 Amendment 0001

W912EP20R0021 17 Amendment 0001

W912EP20R0021 18 Amendment 0001

W912EP20R0021 19 Amendment 0001

W912EP20R0021 20 Amendment 0001

W912EP20R0021 21 Amendment 0001

W912EP20R0021 22 Amendment 0001 https://floridadep.gov/

FLORIDA DEPARTMENT OF

Environmental Protection

Marjory Stoneman Douglas Building 3900 Commonwealth Boulevard

Tallahassee, FL 32399

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Noah Valenstein Secretary

August 17, 2020

Ms. Angela Dunn Chief, Environmental Branch U.S. Army Corps of Engineers, Jacksonville District 701 San Marco Blvd.

Jacksonville, FL 32207-0019

Dear Ms. Dunn, Enclosed is the permit (File No. 0387130-001) for the Central Everglades Planning (CEPP) South Project issued under the authority of the Comprehensive Everglades Restoration Plan Regulation Act (CERPRA), Section 373.1502, Florida Statutes (F.S.); Title 62, Florida Administrative Code (F.A.C.) and pursuant to the Department’s authority under Chapters 373 and 403, F.S.

Please review this document carefully and make copies for the project site and all appropriate persons associated with the project. Please discuss the document with your staff, contracted/hired personnel, and applicable others to ensure compliance with the conditions and requirements contained therein.

Any party to this order (permit) has the right to seek judicial review of the permit under Section 120.68 of the Florida Statutes, by the filing of a Notice of Appeal under Rule 9.110 of the Florida Rules of Appellate Procedure, with the Clerk of the Department of Environmental Protection, Office of General Counsel, Mail Station 35, 3900 Commonwealth Boulevard, Tallahassee, Florida 32399-3000 and by filing a copy of the notice of appeal accompanied by the applicable filing fees with the appropriate district court of appeal. The notice of appeal must be filed within thirty days after this notice is filed with the Clerk of the Department.

If you have any questions regarding this, please contact Katie Wallace at (850) 245-3183. When referring to this application, please use the file number indicated above.

Sincerely, Natalie Barfield Environmental Manager Office of Water Policy and Ecosystems Restoration

NB/kw

Electronic Copies Furnished To:

Angela Dunn, USACE Andy LoSchiavo, USACE Ken Bradshaw, USACE Fred Sklar, SFWMD Leslye Waugh, SFWMD Jennifer Leeds, SFWMD

Adam Blalock, FDEP Frank Powell, FDEP Edward Smith, FDEP Jordan Tedio, FDEP Deinna Nicholson, FDEP Natalie Barfield, FDEP

W912EP20R0021 23 Amendment 0001

Ms. Dunn File No.: 0387130-001 August 17, 2020 https://floridadep.gov/

Matt Morrison, SFWMD Nirmala Jeyakumar, SFWMD FWCConservationPlanningServices@myfwc.com James Erskine, FFWCC Marsha Ward, FFWCC Angela Chelette, FDACS Rebecca Elliot, FDACS Agnes McLean, NPS Laura Brandt, FWS DCPPermits@deo.myflorida.com Ray Eubanks, FDEO Compliancepermits@dos.myflorida.com verobeach@fws.gov Audrey M. Edmonson, Miami-Dade County Commission

Katie Wallace, FDEP Chad Kennedy, FDEP Inger Hansen, FDEP Cortney Deal, FDEP Paul Julian, FDEP Alyssa Gilhooly, FDEP Kelli Edson, FDEP RPPS_Comp@FloridaDEP.gov Dee Ann Miller, FDEP Kenny Hayman, FDEP Brian Dougherty, FDEP Cheri Albin, FDEP Kent Edwards, FDEP

W912EP20R0021 24 Amendment 0001 https://floridadep.gov/ mailto:FWCConservationPlanningServices@myfwc.com mailto:DCPPermits@deo.myflorida.com mailto:Compliancepermits@dos.myflorida.com mailto:verobeach@fws.gov mailto:RPPS_Comp@FloridaDEP.gov

FLORIDA DEPARTMENT OF

Environmental Protection

Marjory Stoneman Douglas Building 3900 Commonwealth Boulevard

Tallahassee, FL 32399

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Noah Valenstein Secretary

COMPREHENSIVE EVERGLADES RESTORATION PLAN

REGULATION ACT (CERPRA) PERMIT

CONSTRUCTION AUTHORIZATION

PERMITTEE: ATTENTION:

U.S. Army Corps of Engineers, Jacksonville District Ms. Angela Dunn 701 San Marco Boulevard Chief, Environmental Branch Jacksonville, FL 32207 Planning Division

Permit Number: 0387130-001 Date of Original: August 17, 2020 Project: CEPP South Permit Issuance: August 17, 2020 Phase: S-631, S-632, S-633, and L-67C Interim Gap Expiration Date: August 17, 2025 County: Miami-Dade

This permit is issued under the authority of the Comprehensive Everglades Restoration Plan Regulation Act (CERPRA), Chapter 373.1502, Florida Statutes (F.S.); Title 62, Florida Administrative Code (F.A.C.); and pursuant to the Department of Environmental Protection (Department) authority under Chapter 373 and 403, F.S. The activity is not exempt from the requirement to obtain a CERPRA Permit.

The above-named permittee is hereby authorized to initiate the activities described on the application, associated drawing(s), plans, and other documents attached hereto or on file with the Department and made a part hereof. The activities authorized by this permit must be conducted in conformance with all the provisions of this permit. Failure to comply with all permit conditions and documents referenced herein shall constitute grounds for revocation of the permit and appropriate enforcement action.

This permit constitutes a finding of consistency with Florida’s Coastal Zone Management Program, as required by Section 307 of the Coastal Management Act, 14 U.S.C. § 1456, and constitutes certification of compliance with water quality standards under Section 401 of the Clean Water Act, 33 U.S.C. § 1341. Activities described in the related documents are not authorized until the project is determined to be in conformance with all applicable rules and with the general and specific conditions of this permit/certification/authorization, as specifically described below.

PROJECT DESCRIPTION:

The Central Everglades Planning Project (CEPP) South, a “project component,” as defined in Section 373.1501(1), F.S., is a Comprehensive Everglades Restoration Plan (CERP) Project. The Water Resources Development Act of 2000 approved CERP under Section 601 as a framework for modifications to the Central and Southern Florida Project necessary to restore the South Florida ecosystem. The overall CEPP includes a suite of storage treatment, conveyance, and seepage management measures that will provide the necessary components to deliver additional fresh water from Lake Okeechobee south to Water Conservation Area 3A (WCA 3A), WCA 3B, Everglades National Park (ENP), and Florida Bay. CEPP will restore quantity, quality, timing, and distribution of water flow to the Greater Everglades. The Final Integrated Project Implementation Report (PIR) for CEPP was published in the Federal Register in July 2014, the Chief of Engineers Report was signed in December 2014, and the Record of Decision was signed in August 2015.

The South Florida Water Management District (District) Governing Board Resolution was approved on April 10, 2014, and the Department’s Final Order was executed on April 10, 2014, outlining the District’s agreement to participate as the local sponsor of the CEPP. CEPP received Congressional authorization in December of 2016 and the Post Authorization Change Control Report (PACR) was Congressionally Authorized in October of 2018. This

W912EP20R0021 25 Amendment 0001

Permittee: U.S. Army Corps of Engineers Project: Central Everglades Planning Project South Phase: S-631, S-632, S-633, and L-67C Interim Gap File No.: 0387130-001 https://floridadep.gov/ project was recommended in the U. S. Army Corps of Engineers’ December 2014 CEPP Final Integrated PIR and Environmental Impact Statement.

The goals and objectives of the CEPP South Project are to expand on the efforts initiated with the pre-CERP Combined Operations Plan (COP) to reverse over 100 years of human induced environmental degradation within the central portion of the Everglades ecosystem. Restored water depth, duration, and distribution in WCA 3A, WCA 3B, and ENP will serve to recreate a landscape characteristic of a pre-drained system to support a healthy mosaic of plant and animal life. The restored hydrology of the Everglades ecosystem will more closely resemble a natural occurring rainfall driven system with wet and dry cycles essential to flora and fauna propagation. Improved water depth and spatial sheet-flow distribution will begin to re-establish the unique ridge, slough, and tree island micro-topography that once provided sustenance to the vast diversity of the species inhabiting the Everglades.

This permit authorizes the U.S. Army Corps of Engineers (USACE) first construction contract for the CEPP South Project, S-631, S-632, S-633 and L67C Interim Gap Project, which includes the construction of three gated, 500-cfs spillways in the L-67A levee; removal of approximately 3,000 feet of existing spoil piles northwest of the L-67A canal where the S-631 and S-632 structures will be built; degrading 3,000 feet of the L-67C levee to the southeast of the S- 633; and backfilling the East-West Agricultural Ditch with suitable excavated material generated by the project (Figure 1). The permit also authorizes backfilling of up to 0.5 miles of the L-67 Extension Canal, and the use of temporary pumps and active vegetation management to enhance flows in historic sloughs in WCA 3B.

The Corps is the federal sponsor of this project component and is responsible for its repair, replacement, and rehabilitation. All conditions found herein apply to the Corps.

PROJECT LOCATION:

This proposed work for CEPP South is within WCA 3A and WCA 3B, on or near L-67C levees, south of Tamiami Trail (US 41) and northeast of Tamiami Trail (US 41) in Miami-Dade County, Florida. The project is located in Sections 3, 4, 5, 6, and 30, Township 54 South, Range 37 East; Section 6, Township 55 South, Range 37 East; Sections 17, 20, 29, 30, 31, and 32, Township 53 South, Range 37 East; and Section 25, Township 52 South, Range 37 East.

PROJECT COMPONENTS:

This proposed work for CEPP South, as shown in Figure 2, consist of the following components:

Gated Culverts: Three gated, 500 cfs structures, to be named S-631, S-632, and S-633 from north to south will be constructed on the L-67A levee. The current design calls for the installation of two 10’ by 6’ concrete box culverts with automatic operable gates at each structure. The structures will only be able to carry the design flow of 500 cfs if a hydraulic head of 0.45 feet can be maintained at the structures. Based upon observations of flows and head-differentials at the adjacent S-152 structure, only about 0.2 feet of hydraulic head can be maintained during the wet season. The Corps is proposing to adaptively manage the vegetation downstream to address the limited conveyance of the structures, to improve conveyance and flows into the sloughs.

Remove 3,000 feet of existing spoil piles: The permittee will remove approximately 3,000 feet of existing spoil piles northwest of L-67A canal where the S-631 and S-632 structures will be built.

Degrade 3,000 feet of L-67C Levee: The permittee will degrade approximately 3,000 feet of the L-67C levee to the southeast of the S-633 gated culvert.

Backfill of East-West Agricultural Ditch: Suitable excavated material generated by the project will be used to backfill the East-West Agricultural Ditch. The L-67C will be temporarily filled but the canal will be returned to pre-project state after completion of the ditch backfill.

W912EP20R0021 26 Amendment 0001

Phase: S-631, S-632, S-633, and L-67C Interim Gap File No.: 0387130-001 https://floridadep.gov/

Backfill portions of the L-67 Extension Canal: Backfill up to 0.5 miles at the southernmost terminus of the L-67 Extension Canal (adjacent to the levee terminus) to natural grade using fill material taken from CEPP Projects (e.g., CEPP South Contract 1 and/or Old Tamiami Trail (OTT) Road Removal projects, etc) that is unsuitable for construction use, except for disposal/backfill. Fill material shall be suitable for backfill and will not include HTRW, asphalt, trash, or vegetation. With regard to OTT backfill material, no OTT fill will be used for CEPP South Contract 1, and only material that is unsuitable for construction use (i.e., muck or poor mixtures) will be used to fill the L-67 Extension Canal, as discussed in the SFWMD to MTIF letter dated June 3, 2020.

L-29 Canal Temporary Pumps and Active Vegetation Management: Design refinements are proposed to enhance flows in historic sloughs in WCA 3B once the S-631, S-632, & S-633 Structures and L-67C Gap Interim Phase features have been constructed. This includes active vegetation management in the Blue Shanty Flowway to enhance flow by reconnecting historic sloughs and installation of temporary pumps to allow the sloughs to flow south. The temporary pumps would be installed between L-67A and the CEPP South L-67D, within the alignment of the planned CEPP Blue Shanty flowway. Since the location is west of S-355A, additional pump collection sumps may need to be installed immediately adjacent and north of the L-29 Levee at the one or two selected optimal temporary pump locations. When the pumps are removed in advance of the L-29 levee segment removal, the sump excavations will be returned to the pre-installation condition. Based on the use of temporary pumps during the 2016 and 2018 deviations, it is expected that no more than two sumps (100 cfs each) at approximately 25-50 feet length (north-south dimension) by 12-25 feet width (east-west dimension) is expected.

DECLARATION OF REASONABLE ASSURANCES:

In issuing this permit, the Department finds that the Permittee has given reasonable assurances sufficient to satisfy the requirements of the CERPRA, Section 373.1502, F.S. The Department bases this finding on the following documents:

1. United States Army Corps of Engineers, Central Everglades Planning Project Final Integrated Project Implementation Report and Environmental Impact Statement (dated July 2014 and revised December 2014)

2. United States Army Corps of Engineers, Central Everglades Planning Project (CEPP) South Application and Associated Materials, (received April 24, 2020 and updated June 19, 2020), File No. 0387130-001

3. United States Army Corps of Engineers, Central Everglades Planning Project (CEPP) South Contract 1, L67A Structures (S-631, S-632, and S633), Spoil Pile Removal and L-67C Gap Project Draft Engineering Plans and Specs, (received May 20, 2020), File No. 0387130-001

4. United States Army Corps of Engineers, Central Everglades Planning Project (CEPP) South Draft Design Report, (received June 1, 2020), File No. 0387130-001

5. United States Army Corps of Engineers, Central Everglades Planning Project (CEPP) South Final draft Uniform Mitigation Assessment Method (UMAM) report dated June 26, 2020, (received June 26, 2020), File No. 0387130-

6. United States Army Corps of Engineers, Central Everglades Planning Project (CEPP) South Request for Additional Information (RAI-1) Response, (received June 19, 2020, and additional information received June 29, 2020 and July 14, 2020), File No. 0387130-001

7. United States Army Corps of Engineers, Central Everglades Planning Project (CEPP) South Draft Compliance Monitoring Plan (CMP) revised July 13, 2020 (received July 14, 2020), File No. 0387130-001

Specifically, there are reasonable assurances, pursuant to Section 373.1502, F.S., that:

• “The project component will achieve the design objectives set forth in the detailed design documents submitted as part of the application.”

• “State water quality standards, including water quality criteria and moderating provisions, will be met. Under no circumstances shall the project component cause or contribute to violation of state water quality standards.”

• “Discharges from the project component will not pose a serious danger to public health, safety or welfare.”

W912EP20R0021 27 Amendment 0001

Phase: S-631, S-632, S-633, and L-67C Interim Gap File No.: 0387130-001 https://floridadep.gov/

• “Any impacts to wetlands or threatened or endangered species resulting from implementation of the project component will be avoided, minimized, and mitigated as appropriate.”

The Corps agrees to construct, operate, and maintain the project in accordance with the provisions of this permit, permit application, and associated documentation on file with the Department. To the extent sovereign immunity has been waived under 33 U.S.C. §§ 1323 and 1344(t), the Corps’ agreement to construct and perform interim operations for the project in accordance with the provisions of this permit and supporting documentation is an enforceable condition of this permit.

The Corps is the federal sponsor of this project. The Corps and its designees are responsible for activities performed during the period of construction and interim operations. If interim operations or additional activities authorized by this permit are performed by any non-federal sponsors, then the permit may be transferred in advance of such activities, or an additional authorization may be required. All conditions found herein apply to the Corps.

GENERAL CONDITIONS:

In accordance with Subsection 373.1502(3)(e)(2) of the CERPRA, this permit may include any standard conditions provided by Department rule, which are appropriate and consistent with the CERPRA.

1. This permit, including its general and specific conditions, shall be construed in light of the February 2006 Interagency Cooperative Agreement for Civil Works Projects (ICA) between the Department and the Corps. As recognized in the ICA, the Department has the authority to include reasonable conditions in this permit. All of the conditions in this permit, both general and specific, are enforceable to the extent sovereign immunity has been waived under 33 U.S.C. §§ 1323 and 1344(t). The ICA is incorporated herein by reference.

2. All activities approved shall be implemented as set forth in the drawings incorporated by reference and in compliance with the conditions and requirements of this document. The Corps shall notify the Department in writing of any anticipated changes in:

A. operational plans;

B. project dimensions, size, or location;

C. ability to adhere to permit conditions;

D. project description included in the permit; and E. monitoring plans.

If the Department determines that a modification to the permit is required, then the Corps shall apply for and obtain the modification. Department approval of the modification shall be obtained prior to implementing the change, unless the change is determined by the Department to reduce the scope of work from that authorized under the original permit and will not affect compliance with permit conditions or monitoring requirements.

3. If, for any reason, the Corps does not comply with any condition or limitation specified herein, the Corps shall immediately provide the Department with a written report containing the following information:

A. a description of and cause of noncompliance;

B. the period of noncompliance, including dates and times;

C. the impacts resulting or likely to result from the non-compliance;

D. steps being taken to correct the non-compliance; and E. the steps being taken to reduce, eliminate, and prevent recurrence of the noncompliance.

Compliance with the provisions of this condition shall not preclude the Department from taking any enforcement action allowed under state law with respect to any non-compliance.

W912EP20R0021 28 Amendment 0001

Phase: S-631, S-632, S-633, and L-67C Interim Gap File No.: 0387130-001 https://floridadep.gov/

4. The Corps shall obtain any applicable licenses, permits, or other authorizations, which may be required by federal, state, local or special district laws and regulations. Nothing herein constitutes a waiver or approval of other Department permits or authorizations that may be required for other aspects of the total project.

5. Nothing herein conveys to the Corps or creates in the Corps any property right, any interest in real property, any title to land or water, constitutes State recognition or acknowledgment of title, or constitutes authority for the use of Florida’s sovereign submerged lands seaward of the mean high-water line or an established erosion control line, unless herein provided, and the necessary title, lease, easement, or other form of consent authorizing the proposed use has been obtained from the State.

6. Any delineation of the extent of a wetland or other surface water submitted as part of the application, including plans or other supporting documentation, shall not be considered specifically approved unless a specific condition of this authorization or a formal determination under section 373.421(2), F.S., provides otherwise.

7. Nothing herein authorizes any entrance upon or activities on property, which is not owned or controlled by the Corps or local sponsor, or conveys any vested rights or any exclusive privileges.

8. This document or a copy thereof, complete with all conditions, attachments, modifications, and time extensions shall be kept at the work site of the authorized activity. The Corps shall require the contractor to review this document prior to commencement of the authorized activity.

9. The Corps specifically agrees to allow Department personnel with proper identification, at reasonable times and in compliance with Corps specified safety standards access to the premises where the authorized activity is located or conducted for the purpose of ascertaining compliance with the terms of this document and with the rules of the Department and to have access to and copy any records that shall be kept; to inspect the facility, equipment, practices, or operations regulated or required; and to sample or monitor any substances or parameters at any location reasonably necessary to assure compliance. Reasonable time may depend on the nature of the concern being investigated.

10. At least forty-eight (48) hours prior to the commencement of authorized activity, the Corps shall submit to the Department a written notice of commencement of activities indicating the anticipated start date and the anticipated completion date.

11. If historic or archaeological artifacts such as, but not limited to, Indian canoes, arrowheads, pottery or physical remains, are discovered at any time on the project site, the Corps shall immediately stop all activities in the immediate area which disturbed the soil and notify the Department and the State Historic Preservation Officer. In the event that unmarked human remains are encountered during permitted activities, all work shall stop in the immediate area and the proper authorities notified in accordance with Section 872.05, Florida Statutes.

12. Within a reasonable time after completion of construction activities authorized…