W912EP-18-R-0048
Jacksonville District
Guajataca Dam Stage 2 Spillway and Channel Reinforcement
Isabela and Quebradillas Municipalities, Puerto Rico
Construction Solicitation and Specifications Volume 2 of 2
See Volume 1 of 2 for Issue Date
Guajataca Dam Spillway and Channel Reinforcement Isabela and Quebradillas, Puerto Rico
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 31 21 CONTROL MONUMENT DESCRIPTIONS
00 31 32 GEOTECHNICAL DATA REPORT (SEE SEPARATE FILE)
00 33 50 WEATHER, WATER STAGE AND TIDE DATA
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 22 00 MEASUREMENT AND PAYMENT
01 30 00 ADMINISTRATIVE PROCEDURES
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 45 00 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 04 CONTRACTOR QUALITY CONTROL
01 50 02 TEMPORARY CONSTRUCTION FACILITIES
01 52 10 CONTRACTING OFFICER'S FIELD OFFICE
01 55 26 TRAFFIC CONTROL
01 57 20 ENVIRONMENTAL PROTECTION
01 78 02 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 22 13 VIBRATION MONITORING
DIVISION 03 - CONCRETE
03 11 13 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING
03 15 00 CONCRETE ACCESSORIES
03 20 00 CONCRETE REINFORCING
03 31 01 CAST-IN-PLACE STRUCTURAL CONCRETE FOR CIVIL WORKS
03 35 00 CONCRETE FINISHING
03 37 13 SHOTCRETE
03 39 00 CONCRETE CURING
DIVISION 05 - METALS
05 50 14 STRUCTURAL METAL FABRICATIONS
05 50 15 CIVIL WORKS FABRICATIONS
DIVISION 26 - ELECTRICAL
26 20 00 GROUNDING SYSTEM
26 42 14.00 10 CATHODIC PROTECTION SYSTEM (SACRIFICIAL ANODE)
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 00 01 SLOPE STABILIZATION
31 05 19 GEOTEXTILE
31 32 24 FLOWABLE FILL
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 11 24 GRADED-CRUSHED AGGREGATE BASE COURSE
PROJECT TABLE OF CONTENTS Page 1
W912EP-18-R-0048 RTA
32 12 17 HOT-MIX ASPHALT (HMA) FOR ROADS
32 92 19 SEEDING
32 92 23 SODDING
DIVISION 33 - UTILITIES
33 11 00 WATER DISTRIBUTION PIPING AND APPURTENANCES
33 40 00 STORM DRAINAGE UTILITIES
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 06 00 REGULATING OUTLET WITHDRAWAL VALVE
35 31 19 GROUTED RIPRAP
35 73 13 ROCK FILL
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 2
W912EP-18-R-0048 SECTION 00 31 21 Page 1
SECTION 00 31 21
CONTROL MONUMENT DESCRIPTIONS
GUAJATACA DAM - Survey Monument Descriptions
No descriptive text available. Refer to plan set documents for coordinates of monuments.
W912EP-18-R-0048 SECTION 00 31 21 Page 2
SECTION 00 33 50
WEATHER, WATER STAGE, AND TIDE DATA
1. The following is provided as input for Section 00 33 50 of the subject Plans and Specifications. The below stated is for information only and is not to be utilized in conjunction with any contract related hydro-meteorological surveying. Historical water levels and flows are not necessarily indicative of future water levels and flows.
2. The project area is located approximately five miles south of Quebradillas, Puerto Rico. Water levels in the project area are affected by direct rainfall, evaporation, local runoff, ground water levels and water management operations at the Guajataca Dam.
3. The climate of the area is tropical and humid.
Temperatures below freezing are rare. The hurricane season is from June through November. Traditionally, the wet season in Puerto Rico is defined as April through November. In general, the winter months constitute the dry season and the summer months comprise the wet season. Occasionally, daily rainfall in the any season can be quite heavy. Mean annual precipitation at the Guajataca Dam station (RQC00663904) is approximately 76 inches per year. The project site is subject to tropical storms and hurricanes from June through November, and to windy and/or rainy weather throughout the year. Due to the mountainous terrain in Puerto Rico, rainfall inland has the potential to create flash floods. During extreme rainfall events water may spill over the Guajataca Dam emergency spillway. Guajataca Dam releases can occur at any time. Weather forecasts as well as actual rainfall amounts upstream of locations where personnel, equipment and/or material are with the river channel or floodplain should be continuously monitored. Weather forecasts as well as actual rainfall information from the National Weather Service San Juan, PR forecast office can be found at:
http://www.srh.noaa.gov/sju/
4. It shall be the contractor's responsibility to obtain information concerning rain and wind. Reference is made to the following publication, which contains climatological and meteorological observations and data. The National Oceanic and Atmospheric Administration (NOAA) publication entitled Local Climatological Data - Monthly Summary contains wind, rain and temperature data for the project area and is available from NOAA: http://www.ncdc.noaa.gov/ http://www.srh.noaa.gov/sju/ http://www.ncdc.noaa.gov/
5. During project construction, the contractor shall not interfere with the normal operations of the Guajataca Dam. The contractor shall not interfere with or hinder access to project water control structures.
6. The contractor should be aware that there could be extended periods of high discharges and high water surface elevations during the contract period, depending on hydro-meteorological conditions. The contractor should not expect that work can be done under “no flow,” “low flow,” or dry conditions.
7. The following data is provided:
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS
BASED ON 5-DAY WORK WEEK
The average number of days in each calendar month with precipitation greater than, or equal to, 0.50 inches is provided for the project area in the following table. This information is based on data obtained from the Guajataca Dam station (RQC00663904), located at latitude 18.3963˚ N and longitude 66.9244˚ W. The data were obtained from Climatography of the United States No. 20 Monthly Station Climate Summaries for Puerto Rico, published by the National Climatic Data Center, NOAA, for the period of record 1981-2010. The values in the table have been rounded. NOAA data for this station is available at the following website:
https://www.ncdc.noaa.gov/cdo-web/datasets/NORMAL_MLY/stations/GHCND:RQC00663904/detail
Average Number of Days per Month with Precipitation ≥ 0.5 Inches
Gage Name Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Guajataca Dam 2 1 2 3 5 3 2 3 4 4 3 2
8. The USGS is the official source of water level data for Lago Guajataca. The USGS maintains a gauge to monitor the water level data, USGS 50010800 Lago Guajataca at Damsite nr Quebradillas, PR.
a) Current water surface elevation data is available at:
https://waterdata.usgs.gov/nwis/uv?site_no=50010800
b) Historical water surface elevation data is available at:
https://waterdata.usgs.gov/nwis/inventory?agency_code=USGS&site_ no=50010800
c) The 10th, 25th, 50th, 75th, and 90th percentile exceedance curves for USGS 50010800 are provided in Figure 1.
For example, for a given day, the 10th percentile exceedance curve shows the water surface elevation at which 10 percent of https://www.ncdc.noaa.gov/cdo-web/datasets/NORMAL_MLY/stations/GHCND:RQC00663904/detail https://www.ncdc.noaa.gov/cdo-web/datasets/NORMAL_MLY/stations/GHCND:RQC00663904/detail https://waterdata.usgs.gov/nwis/uv?site_no=50010800 https://waterdata.usgs.gov/nwis/inventory?agency_code=USGS&site_no=50010800 https://waterdata.usgs.gov/nwis/inventory?agency_code=USGS&site_no=50010800 the values on that day of the year were greater during the period of record. Likewise, for a given day, the 75th percentile exceedance curve shows the water surface elevation at which 75 percent of the values on that day of the year were greater during the period of record. This figure can be used as a rough indicator of probable seasonal variations in water surface elevations. However, water surface elevations outside of those shown can and have occurred. The contractor should understand that historical water elevations are not necessarily indicative of future water elevations. An exceedance plot for the approved USGS data has been provided below in Figure 1.
Figure 1
9. The dam owner is responsible for operations of the outlet works and to maintain the reservoir levels below the spillway crest. Post-Hurricane Maria the dam owner has maintained and operated the pool level at a significantly lower level than Pre- Hurricane Maria. During the period of construction, the dam owner’s target reservoir elevation will be 191m (6 meters below the spillway crest), however the contractor shall expect variations in this pool elevation depending on inflows. The Contractor shall monitor the weather forecast daily and coordinate daily with the Contracting Officer’s Representative.
This is for the safety of personal working in the spillway and damage of equipment in the spillway. The below reservoir stage graph illustrates reservoir stage versus precipitation storm frequencies that may lead to overflowing of the spillway.
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 REFERENCES
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
1.2.1.1 Base Work
1.2.2 Definitions
1.2.3 Location
1.2.4 Safety Requirements
1.2.5 Work Performed by Others
1.3 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
1.4 LIQUIDATED DAMAGES - CONSTRUCTION
1.5 PHYSICAL DATA
1.5.1 Physical Conditions
1.5.2 Contractor Investigation
1.6 LAYOUT OF WORK
1.6.1 Established Project Control
1.6.2 Layout
1.6.3 Survey
1.7 DAMAGE TO WORK
1.8 EXISTING WORK
1.9 LOCATION OF UNDERGROUND FACILITIES
1.9.1 Notification Prior to Excavation
1.10 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER (31 OCT 1989)
1.10.1 Schedule of Monthly Anticipated Adverse Weather Delays
1.10.2 Contractor Responsibility
1.11 UNITS OF MEASURE
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION (NOT APPLICABLE)
-- End of Section Table of Contents --
SECTION 01 11 00 Page 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
GDR Section 00 31 32, Geotechnical Data Report
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The Guajataca Dam and Reservoir, owned by the Puerto Rico Electric Power Authority (PREPA), supplies domestic water and public irrigation to northwest Puerto Rico. The hydraulic-fill embankment dam was constructed in 1928. It stands 121 feet in height with a crest of approximately 1,037 feet in length, 31.2 feet in width, at an elevation of 664.4 feet. During historic flood events, water may overflow via the emergency spillway, which is of concrete construction, and has crest length of 250 feet at an elevation of 646.4 feet (197.0 meters). It includes a 750 foot concrete-lined trapezoidal chute that discharges into the Rio Guajataca River, known as the 'River Outlet' and is controlled by a high pressure sluice gate. There is a second outlet which discharges into the water supply canal to a downstream treatment plant, known as the 'Canal Outlet'.
Portable pumps may be in operation which may discharge into one or both of these outlets, to supplement lowering of the water level.
During Hurricane Maria, the unprecedented spillway discharge volume eroded earth at the end of the chute that caused undermining. The loss of earth resulted in downstream portions of the spillway failing. In addition, the dam's water canal supply pipe running under the spillway was destroyed.
Work under this contract entails reforming the concrete spillway, which is the emergency overflow for when the dam overtops in flood events, and forming a grouted riprap stilling basin within the downstream spillway area. The spillway will be a concrete lined and grouted riprap trapezoidal channel with a grouted riprap weir at the downstream boundary of the stilling basin and 48" RCP culvert. At one side of the spillway is a 36" diameter fixed cone valve outlet which releases water from behind the dam and requires connecting new piping to existing, constructing a concrete headwall at the outlet. The stilling basin will provide more energy dissipation from high velocity water flowing over the spillway, which will then flow over a grouted riprap weir and out to the river. The work at the spillway area includes excavation, backfilling with a 18" diameter minus
SECTION 01 11 00 Page 2 rock fill base, 18" to 36" diameter riprap laid on top and grouted with high strength flowable fill. An 18" structural concrete slab with dowels and water stops at the joints will be constructed as an overlay in the upper portion of the existing spillway slab and grouted riprap zone. Other work includes construction of an asphalt road and reconstruction the river outlet work channel. Work at the intake includes stabilizing an earthen slope above the reservoir pool with ground anchors and shotcrete cover.
Other miscellaneous work includes hand rails, grass seeding or sodding, cathodic protection for the steel water piping, and buried drainage and weep hole piping.
1.2.1.1 Base Work
The base contract line items include work which repairs the emergency spillway and stabilizes the slope behind the intake tower.
1.2.2 Definitions
Reservoir: The reservoir is the water pool that is held behind the dam. The reservoir may be referred to as the upstream pool, and its water elevation may be referred to as the headwater.
Spillway: A passage for surplus water from the dam. The spillway is the crest from which water uncontrollably spills over during a major flood event. This spillway is known as the emergency spillway and is of concrete construction.
Siphon: A tube used to convey liquid upwards from a reservoir and then down to a lower level of its own accord. Once the liquid has been forced into the tube, typically by suction or immersion, flow continues unaided.
Canal Outlet: The dam supplies water from the reservoir to two discharges.
The canal outlet, also known as the water supply canal, is used for municipal drinking water supply.
River Outlet: The dam supplies water from the reservoir to two discharges.
The river outlet supplies water to the Rio Guajataca River.
1.2.3 Location
The work is located at the Guajataca Dam in northwest Puerto Rico, approximately 6 miles south of the municipality of Quebradillas.
1.2.4 Safety Requirements
See Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS and EM 385-1-1.
1.2.5 Work Performed by Others
See paragraph PROJECT COORDINATION of Section 01 30 00 ADMINISTRATIVE
PROCEDURES.
1.3 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
Read this paragraph in conjunction with the Clause COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (FAR 52.211-10) of Section 00700 CONTRACT CLAUSES in Volume 1.
SECTION 01 11 00 Page 3
1.4 LIQUIDATED DAMAGES - CONSTRUCTION
Refer to the Clause LIQUIDATED DAMAGES - CONSTRUCTION (FAR 52.211-12) of Section 00700 CONTRACT CLAUSES in Volume 1.
1.5 PHYSICAL DATA
Read this paragraph in conjunction with the Clause PHYSICAL DATA (FAR 52.236-4) of Section 00700 CONTRACT CLAUSES in Volume 1.
1.5.1 Physical Conditions
The indications of physical conditions on the drawings and in the specifications are the result of site investigations by surveys and/or by core borings. When the indicated physical conditions are the result of site investigations by core borings, the core boring logs and laboratory data are in Section 00 31 32 GEOTECHNICAL DATA REPORT (GDR) and the core boring locations are shown on the drawings. Also, see the GDR for instructions concerning availability of core borings for inspection.
1.5.2 Contractor Investigation
Refer to the Clause SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (FAR 52.236-3) of Section 00700 CONTRACT CLAUSES in Volume 1.
1.6 LAYOUT OF WORK
Read this paragraph in conjunction with the Clause LAYOUT OF WORK (FAR 52.236-17) of Section 00700 CONTRACT CLAUSES in Volume 1.
1.6.1 Established Project Control
The Government has established monuments along the work site(s). Each monument is represented in the contract drawings by a Designation and in most cases, an alphanumeric Permanent Identifier (PID). Information concerning the location and elevations can be found within the Survey Notes on the plan sheets. The Survey Notes for each included field survey will cite a particular survey number, and specify the control used to conduct that survey. Additional information is included in the Survey Notes that must be duplicated if an attempt to recreate the subject survey is desired.
See Section 00 31 21 CONTROL MONUMENT DESCRIPTIONS.
1.6.2 Layout
From the monuments, control data and elevations established by the Government, the Contractor shall complete the layout of the work and shall be responsible for all measurements that may be required for the execution of the work to the location and limit marks prescribed in the specifications or on the contract drawings, subject to such modifications as the Contracting Officer may require to meet changed conditions or as a result of necessary modifications to the contract work.
1.6.3 Survey
The Contractor shall furnish, at his own expense, such stakes, templates, platforms, equipment, tools and material, and all labor as may be required in laying out any part of the work from the monuments, control data and elevations established by the Government. It shall be the responsibility
SECTION 01 11 00 Page 4 of the Contractor to maintain and preserve all monuments, stakes and other marks established by the Contracting Officer until authorized to remove them, and if such marks or monuments are destroyed by the Contractor or through his negligence, prior to their authorized removal, they may be replaced by the Contracting Officer, at his discretion, and the expense of replacement will be deducted from any amounts due or to become due the Contractor. The Contracting Officer may require that work be suspended at any time when location and limit marks established by the Contractor are not reasonably adequate to permit checking of the work.
1.7 DAMAGE TO WORK
The responsibility for damage to any part of the permanent work shall be as set forth in Clause PERMITS AND RESPONSIBILITIES of Section 00700 CONTRACT CLAUSES in Volume 1. However, if, in the judgment of the Contracting Officer, any part of the permanent work performed by the Contractor is damaged by flood, earthquake, hurricane, or tornado, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor will make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit or job prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there are no contract unit or job prices applicable to any part of such work, an equitable adjustment pursuant to Clause CHANGES of Section 00700 CONTRACT CLAUSES in Volume 1 will be made as full compensation for the repairs of that part of the permanent work for which there are no applicable contract unit or job prices. Except as herein provided, damage to all work (including temporary construction), utilities, materials, equipment and plant shall be repaired to the satisfaction of the Contracting Officer at the Contractor's expense, regardless of the cause of such damage.
a. The responsibility for damage to any part of the work to be performed under this contract shall be as set forth in Clause PERMITS AND RESPONSIBILITIES of Section 00700 CONTRACT CLAUSES in Volume 1.
However, if the spillway overtops by a rain or flood event and causes damaged to the construction site, or if any part of the permanent work is damaged by flood, earthquake, hurricane, or tornado, which damage is not due to the failure of the Contractor to take reasonable precaution or to exercise sound engineering and construction practices in the conduct of the work, the Contractor will make the repairs ordered by the Contracting Officer. The Contractor shall be compensated for any such repairs in accordance with the Clause CHANGES of Section 00700 CONTRACT CLAUSES in Volume 1. The equitable adjustment shall be based on the contract unit or job prices applicable to any part of the damaged work.
1.8 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that
SECTION 01 11 00 Page 5 which existed before new work started.
1.9 LOCATION OF UNDERGROUND FACILITIES
The Contractor is required to obtain digging permits prior to start of excavation. Scan the construction site with electromagnetic or sonic equipment, and mark the surface of the ground where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated or specified to be removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, channel construction and other work to be installed. Any utilities found which are not shown on the construction drawings must be brought to the Contracting Officer's attention prior to proceeding with construction.
1.9.1 Notification Prior to Excavation
Notify the Contracting Officer and Local Authority at least 14 days prior to starting excavation work. Contact PREPA at 787-521-3434 prior to excavating. Contractor is responsible for marking all utilities not marked by PREPA and other utility companies such as PRASA.
1.10 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER (31 OCT 1989)
This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the Clause DEFAULT (FIXED-PRICE CONSTRUCTION) of Section 00700 CONTRACT CLAUSES in Volume 1. In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
a. The weather experienced at the project site during the contract period must be found to be unusually severe; that is, more severe than the adverse weather anticipated for the project location during any given month.
b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
1.10.1 Schedule of Monthly Anticipated Adverse Weather Delays
The schedule of monthly anticipated adverse weather delays is based upon National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
See Section 00 33 50 WEATHER, WATER STAGE AND TIDE DATA to obtain MONTHLY
ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS BASED ON 5-DAY WORK WEEK. A
reasonable number of anticipated weather delay work days is obtained from the average number of days per month (rounded to the nearest whole number) with precipitation greater than that indicated in Section 00 33 50 WEATHER, WATER STAGE AND TIDE DATA.
1.10.2 Contractor Responsibility
Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CQC report the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on
SECTION 01 11 00 Page 6 critical activities for 50 percent or more of the Contractor's scheduled work day. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in Section 00 33 50 WEATHER, WATER STAGE AND TIDE DATA (rounded to the nearest whole number), the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the Clause DEFAULT (FIXED PRICE CONSTRUCTION) of Section 00700 CONTRACT CLAUSES in Volume 1.
1.11 UNITS OF MEASURE
The standard U.S. system or the metric systems of measure may be utilized by the Contractor in the performance of his work. All survey records, official documentation, engineering data, and all correspondence, including any submittals and shop drawings, shall clearly denote which system of measure is being utilized, referenced or discussed. Any omission inaccurate use of a unit of measure on the part of the Contractor shall not relieve him of his responsibilities under the contract terms. The unit of measure used in this specification is the standard U.S. system. The contract drawings denote both standard U.S. system and metric system where appropriate. If no unit of measure is indicated on the drawing such as on ranges, stations, slope elevations, and distance numbers, submit an RFI for clarification.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION (NOT APPLICABLE)
-- End of Section --
SECTION 01 11 00 Page 7
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUMMARY
1.2 RESIDENT MANAGEMENT SYSTEM (RMS)
1.2.1 Definition
1.2.2 Instructions
1.3 SUBMITTALS
1.4 JOB PAYMENT ITEMS
1.4.1 Mobilization and Demobilization (Line Item 0001)
1.4.2 Turbidity Monitoring (Line Item 0011)
1.4.3 Cross Drain Culvert (Line Item 0012)
1.4.4 Fixed Cone Valve (Line Item 0015)
1.4.5 Water Distribution Piping and Appurtenances (Line Item 0016)
1.4.6 Cathodic Protection (Line Item 0017)
1.4.7 Ductile Iron Piping (Line Item 0018
1.4.8 Traffic Control (Line Item 0022)
1.4.9 Embedded Metals (Line Item 0023)
1.4.10 Galvanized Steel Railings, Handrails and Operating Platform
(Line Item 0024)
1.4.11 Vibration Control and Monitoring (Line Item 0026)
1.4.12 Removal and Reinstallation of Existing Spillway Pipes (Line
Item 0027)
1.4.13 Demolition (Line Item 0028)
1.4.14 Excavation - Miscellaneous (Line Item 0029)
1.4.15 Municipal Taxes (Line Item 0032)
1.5 UNIT PRICE PAYMENT ITEMS
1.5.1 Spillway Flowable Fill - Low Strength (Line Item 0002)
1.5.1.1 Payment
1.5.1.2 Measurement
1.5.1.3 Unit of Measure
1.5.2 Spillway Flowable Fill - High Strength (Line Item 0003)
1.5.2.1 Payment
1.5.2.2 Measurement
1.5.2.3 Unit of Measure
1.5.3 Intake Structure Slope Stabilization - Shotcrete (Line Item
0004)
1.5.3.1 Payment
1.5.3.2 Measurement
1.5.3.3 Unit of Measure
1.5.4 Intake Structure Slope Stabilization - Ground Anchors (Line
Item 0005)
1.5.4.1 Payment
1.5.4.2 Measurement
1.5.4.3 Unit of Measure
1.5.5 Sodding/Hydroseeding (Line Item 0006)
1.5.5.1 Payment
SECTION 01 22 00 Page 1
1.5.5.2 Measurement
1.5.5.3 Unit of Measure
1.5.6 Structural Cast-in-Place Concrete - Spillway Slab (Line Item
0007)
1.5.6.1 Payment
1.5.6.2 Measurement
1.5.6.3 Unit of Measure
1.5.7 Structural Cast-in-Place Concrete - Headwall Staircase (Line
Item 0008)
1.5.7.1 Payment
1.5.7.2 Measurement
1.5.7.3 Unit of Measure
1.5.8 Structural Cast-in-Place Concrete - Cone Valve Headwall (Line
Item 0009)
1.5.8.1 Payment
1.5.8.2 Measurement
1.5.8.3 Unit of Measure
1.5.9 Mud Mat (Line Item 0010)
1.5.9.1 Payment
1.5.9.2 Measurement
1.5.9.3 Unit of Measure
1.5.10 Riprap (Line Item 0013)
1.5.10.1 Payment
1.5.10.2 Measurement
1.5.10.3 Unit of Measure
1.5.11 Rock Fill (Line Item 0014)
1.5.11.1 Payment
1.5.11.2 Measurement
1.5.11.3 Unit of Measure
1.5.12 Graded Aggregate Base (Line Item 0019)
1.5.12.1 Payment
1.5.12.2 Measurement
1.5.12.3 Unit of Measure
1.5.13 Hot Mix Asphalt (Line Item 0020)
1.5.13.1 Payment
1.5.13.2 Measurement
1.5.13.3 Unit of Measure
1.5.14 Contracting Officer's Field Office (Line Item 0021)
1.5.14.1 Payment
1.5.14.2 Measurement
1.5.14.3 Unit of Measure
1.5.15 PVC Drain Pipe (Line Item 0025)
1.5.15.1 Payment
1.5.15.2 Measurement
1.5.15.3 Unit of Measure
1.5.16 Backfill Stone (Line Item 0030)
1.5.16.1 Payment
1.5.16.2 Measurement
1.5.16.3 Unit of Measure
1.5.17 Geotextile (Line Item 0031)
1.5.17.1 Payment
1.5.17.2 Measurement
1.5.17.3 Unit of Measure
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
SECTION 01 22 00 Page 2
3.1 PAYMENT PROCEDURES
3.1.1 Requesting Progress Payment
3.1.2 Options and Modification CLINS
-- End of Section Table of Contents --
SECTION 01 22 00 Page 3
SECTION 01 22 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SUMMARY
This section describes how Line Items will be measured and paid for when making progress payments. Work to be measured is described in specification sections listed for each Line Item. Measurement procedures for payment, required quantity survey or procurement documentation and payment restrictions are described in applicable specification sections.
Allocate costs for work not specifically mentioned to the Line Item most closely associated with work involved. Unless there is a specific Line Item for administrative costs, such as Quality Control and Safety, allocate such costs proportionally across all Line Items.
1.2 RESIDENT MANAGEMENT SYSTEM (RMS)
1.2.1 Definition
The terms "Contract Line Item Number (CLIN)" and "Line Item" are interchangeable herein (e.g.: CLIN 0001 is Line Item 0001). The term "CLIN" is a contracting term used in the Resident Management System (RMS) payment data base.
1.2.2 Instructions
See Section 01 45 00 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM) for more information on CLINs, schedule of values of pay activities and construction schedule, and payment procedures. The Contractor mode user manual with in-depth instructions can be downloaded from the RMS web site indicated in Section 01 45 00 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE
(RMS CM).
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Transmit submittal items in accordance with Section 01 33 00 SUBMITTAL PROCEDURES. Submit the following preconstruction submittal items no later than 15 calendar days after Notice to Proceed:
SD-01 Preconstruction Submittals
Schedule of Values; G, RO
Provide a breakdown of job items into proposed pay activities as part of the initial project schedule. Schedule of Values will become basis for CLIN and Pay Activity data in the RMS payment data base.
SECTION 01 22 00 Page 4
SD-03 Product Data
Weight Certificates; G, DO
SD-07 Certificates
Request for Progress Payment; G, RO
Submit monthly in accordance with subparagraph "Requesting Progress Payment" below.
Delivery Tickets; G, RO
Submit concrete and rock delivery tickets for payment under the required CLIN's as stated below.
1.4 JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract job payments will be made are listed in the LINE ITEMS AND PRICING SCHEDULE with the unit "JOB" and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, shall be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
Progress payments for job CLINs will be made in accordance with the Payments Under Fixed-Price Construction Contracts clause of Section 00700 CONTRACT CLAUSES in Volume 1. Submit a list of pay activities, (Schedule of Values) to breakdown bid for each job CLIN. The Schedule of Values shall be submitted for Government approval with the baseline schedule submittal (see Section 01 32 01 PROJECT SCHEDULE). An unbalanced Schedule of Values and Pay Activity Schedule will be returned for revision. If this contract contains either the Continuing Contracts clause or the Continuing Contracts (Alternate) clause, the Contractor should take into account the amount reserved for contract payments when preparing the construction schedule.
1.4.1 Mobilization and Demobilization (Line Item 0001)
Payment will be made for costs associated with and incidental to mobilization and demobilization and establishment of initial project management and coordination. See Clause PAYMENT FOR MOBILIZATION AND DEMOBILIZATION of Section 00700 CONTRACT CLAUSES in Volume 1.
1.4.2 Turbidity Monitoring (Line Item 0011)
Payment will be made for costs associated with and incidental to monitoring the turbidity of water sources which may be impacted by construction activities. These water sources include the dam's reservoir, water supply channel, and Guajataca River.
SECTION 01 22 00 Page 5
1.4.3 Cross Drain Culvert (Line Item 0012)
Payment will be made for costs associated with and incidental to the installing the Reinforced Concrete Pipe (RCP) Culvert as defined in SECTION 33 40 00 STORM DRAINAGE UTILITIES. Storm drainage system include but not limited to concrete pipes, pipe joints, mitered end section, high strength flowable fill, geotextile, installation, testing, etc.
1.4.4 Fixed Cone Valve (Line Item 0015)
Payment will be made for costs associated with and incidental to installing the fixed cone valve.
1.4.5 Water Distribution Piping and Appurtenances (Line Item 0016)
Payment will be made for costs associated with and incidental to installing the water discharge pipe to the stilling basin.
1.4.6 Cathodic Protection (Line Item 0017)
Payment will be made for costs associated with and incidental to designing and installing cathodic protection on steel pipe.
1.4.7 Ductile Iron Piping (Line Item 0018
Payment will be made for costs associated with and incidental to installing ductile iron weep hole piping, pipes connections to the existing drain pipes and new pipes, and drain pipes.
1.4.8 Traffic Control (Line Item 0022)
Payment will be made for costs associated with and incidental to traffic control.
1.4.9 Embedded Metals (Line Item 0023)
Payment will be made for costs associated with and incidental to furnishing and installation of embedded metals required for the valve thimble as shown on the drawings.
1.4.10 Galvanized Steel Railings, Handrails and Operating Platform (Line Item 0024)
Payment will be made for costs associated with and incidental to furnishing, installing and finishing of all required materials for the Galvanized Steel Railings, Handrails and Operating Platform. This price shall constitute full compensation for all labor, equipment, tools, and incidentals necessary to complete the work specified herein.
1.4.11 Vibration Control and Monitoring (Line Item 0026)
Payment will be made for costs associated with or incidental to inspecting existing structures within 200 feet from the construction limits, State Road 119, State Road 476, and the Bridge over State Road 476 (downstream of the spillway). See Section 02 22 13 VIBRATION MONITORING.
1.4.12 Removal and Reinstallation of Existing Spillway Pipes (Line Item 0027)
Payment will be made for costs associated with or incidental to removing
SECTION 01 22 00 Page 6 and replacing one (1) 8" PVC pipe and one (1) 8" ductile iron pipe before the spillway work beings and to reinstall the pipes after the spillway work is completed.
1.4.13 Demolition (Line Item 0028)
Payment will be made for costs associated with or incidental to demolition and off-site disposal of the slab section 1 and 2 for crack repair, spillway slab section 5, grouted riprap, flowable fill, as indicated on the drawings.
1.4.14 Excavation - Miscellaneous (Line Item 0029)
Payment will be made for costs associated with or incidental to miscellaneous excavation as indicated on the drawings or as required where not incidental to other line items. Such excavation shall include but is not limited to, regrading of the channel, key-in feature under the weir, key-in feature under the siphon, and excavation related to removal of concrete slabs and for construction of grouted riprap. Off-site disposal will be required.
1.4.15 Municipal Taxes (Line Item 0032)
Pursuant to municipality local regulations, taxes may apply with line items under this contract. See Paragraph 999.229-1 in Section 00100 of this solicitation. The contract price will be adjusted to compensate the Contractor for the amount of construction taxes. No mark-ups will be allowed in this line item. The Contractor will be paid on the basis of proof of payment from the appropriate Commonwealth of Puerto Rico or Municipal authorities.
1.5 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the LINE ITEMS AND PRICING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
Each Unit Price CLIN may be a single pay activity item or may be broken down into pay activities with smaller quantities equal to CLIN total.
Contract unit price multiplied by agreed quantity is full compensation.
1.5.1 Spillway Flowable Fill - Low Strength (Line Item 0002)
1.5.1.1 Payment
Payment will be made for costs associated with and incidental to pouring low strength flowable fill within the damaged spillway. Incidental costs include but are not limited to subgrade preparation, compaction, finishing, excavation, etc.
1.5.1.2 Measurement
The total amount of material placed, and to be paid for under this contract, will be measured by the volume-in-place with quantities
SECTION 01 22 00 Page 7 determined by concrete delivery tickets. Payment will only be made for trucks which concrete is determined to meet the required specifications and for which is placed on-site. Payment will not be made prior to submission and approval of delivery tickets. The Contractor shall seek Government approval prior to ordering concrete for quantities placed above the awarded amount.
1.5.1.3 Unit of Measure
Cubic yards.
1.5.2 Spillway Flowable Fill - High Strength (Line Item 0003)
1.5.2.1 Payment
Payment will be made for costs associated with and incidental to pouring high strength flowable fill within the damaged spillway and for grouting the riprap. Incidental costs include but are not limited to subgrade preparation, compaction, finishing, excavation, etc.
1.5.2.2 Measurement
The total amount of material placed, and to be paid for under this contract, will be measured by the volume-in-place with quantities determined by concrete delivery tickets. Payment will only be made for trucks which concrete is determined to meet the required specifications and for which is placed on-site. Payment will not be made prior to submission and approval of delivery tickets. The Contractor shall seek Government approval prior to ordering concrete for quantities placed above the awarded amount.
1.5.2.3 Unit of Measure
Cubic yards.
1.5.3 Intake Structure Slope Stabilization - Shotcrete (Line Item 0004)
1.5.3.1 Payment
Payment will be made for costs associated with and incidental to stabilizing the slope at the intake structure, as depicted in the drawings at the intake structure. Incidental costs include but are not limited to slope preparation, excavation, compacted stone, geocomposite drains, High Density Polyethylene (HDPE) sheet, shotcrete, etc.
1.5.3.2 Measurement
The total amount of material placed, and to be paid for under this contract, will be measured by the finished area of completed work, measured as the area of shotcrete placed.
1.5.3.3 Unit of Measure
Square meters.
SECTION 01 22 00 Page 8
1.5.4 Intake Structure Slope Stabilization - Ground Anchors (Line Item 0005)
1.5.4.1 Payment
Payment will be made for costs associated with and incidental to installing ground anchors as depicted in the drawings. Incidental costs include but are not limited to foundation drilling, excavation, grouting and installation, etc.
1.5.4.2 Measurement
The total amount of material placed, and to be paid for under this contract, will be measured by the total quantity of anchors placed.
1.5.4.3 Unit of Measure
Each.
1.5.5 Sodding/Hydroseeding (Line Item 0006)
1.5.5.1 Payment
Payment will be made for costs associated with or incidental to placement and establishment of sod or hydroseeding.
1.5.5.2 Measurement
Measurement will be made by the area of sod placed or hydroseed spread.
1.5.5.3 Unit of Measure
Square meters.
1.5.6 Structural Cast-in-Place Concrete - Spillway Slab (Line Item 0007)
1.5.6.1 Payment
Payment will be made for costs associated with and incidental to placement and completion of reinforced concrete required for the spillway slabs including: concrete mixture, reinforcement, plate and hex nuts attached to soil nail, waterstops, adhesive anchor, formwork, concrete placing, hooks bars, finishing, curing, joint sealant, joint filler, elastomeric bearing pad, bond breaker, testing, crack repair on the existing spillway, etc.
1.5.6.2 Measurement
The total amount of material placed, and to be paid for under this contract, will be measured by the volume-in-place with quantities determined by neat lines on the drawings. Payment will only be made for concrete placed in compliance with contract specifications and accepted.
The Contractor shall seek Government approval prior to ordering concrete for quantities placed above the awarded amount.
1.5.6.3 Unit of Measure
Cubic yard.
SECTION 01 22 00 Page 9
1.5.7 Structural Cast-in-Place Concrete - Headwall Staircase (Line Item 0008)
1.5.7.1 Payment
Payment will be made for costs associated with and incidental to placement and completion of reinforced concrete required for the headwall staircase including: concrete mixture, reinforcement, formwork, adhesive anchor, concrete placing, finishing, curing, testing, etc.
1.5.7.2 Measurement
The total amount of material placed, and to be paid for under this contract, will be measured by the volume-in-place with quantities determined by neat lines on the drawings. Payment will only be made for concrete placed in compliance with contract specifications and accepted.
The Contractor shall seek Government approval prior to ordering concrete for quantities placed above the awarded amount.
1.5.7.3 Unit of Measure
Cubic yard.
1.5.8 Structural Cast-in-Place Concrete - Cone Valve Headwall (Line Item 0009)
1.5.8.1 Payment
Payment will be made for costs associated with and incidental to placement and completion of reinforced concrete required for the cone valve headwall including concrete mixture, reinforcement, formwork, concrete placing, finishing, curing, testing, etc.
1.5.8.2 Measurement
The total amount of material placed, and to be paid for under this contract, will be measured by the volume-in-place with quantities determined by neat lines on the drawings. Payment will only be made for concrete placed in compliance with contract specifications and accepted.
The Contractor shall seek Government approval prior to ordering concrete for quantities placed above the awarded amount.
1.5.8.3 Unit of Measure
Cubic yard.
1.5.9 Mud Mat (Line Item 0010)
1.5.9.1 Payment
Payment will be made for costs associated with and incidental to placement of the unreinforced concrete mud mat required for a foundation as shown on the drawings, which includes excavation, compaction, mud mat, and backfilling.
1.5.9.2 Measurement
Measurement will be made by the area of mud mat placed.
SECTION 01 22 00 Page 10
1.5.9.3 Unit of Measure
Square meter.
1.5.10 Riprap (Line Item 0013)
1.5.10.1 Payment
Payment will be made for costs associated with and incidental to placement of riprap.
1.5.10.2 Measurement
Measure riprap for payment by the ton (2,000 pounds) by weighing each truckload to the nearest 0.1 ton, and the final quantity of the whole sum is rounded to the nearest whole ton. Weigh the riprap for payment on approved scales before being placed in the work. Quarry weights will not be accepted. Use scales of sufficient length to permit simultaneous weighing all axle loads. Scales must be inspected, tested and sealed as directed to assure accuracy with 0.5 percent throughout the range of the scales. Certify scales located at the site of the work as to accuracy by an acceptable scales company representative prior to weighing any riprap.
Scales will be checked and certified before riprap hauling and rechecked and recertified whenever a variance is suspected. Furnish the scales. If commercial scales are readily available in close proximity, 25 miles of site of work, the Contracting Officer may approve the use of the scales.
Weigh riprap in the presence of the Government representative. The Contracting Officer may elect to accept certified weight certificates furnished by a public weighmaster in lieu of scale weights at the jobsite.
1.5.10.3 Unit of Measure
Ton.
1.5.11 Rock Fill (Line Item 0014)
1.5.11.1 Payment
Payment will be made for costs associated with and incidental to placement of rock fill.
1.5.11.2 Measurement
Measure rock fill for payment by the ton (2,000 pounds) by weighing each truckload to the nearest 0.1 ton, and the final quantity of the whole sum is rounded to the nearest whole ton. Weigh the rock fill for payment on approved scales before being placed in the work. Quarry weights will not be accepted. Use scales of sufficient length to permit simultaneous weighing all axle loads. Scales must be inspected, tested and sealed as directed to assure accuracy with 0.5 percent throughout the range of the scales. Certify scales located at the site of the work as to accuracy by an acceptable scales company representative prior to weighing any rock fill. Scales will be checked and certified before rock fill hauling and rechecked and recertified whenever a variance is suspected. Furnish the scales. If commercial scales are readily available in close proximity, 25 miles of site of work, the Contracting Officer may approve the use of the scales. Weigh rock fill in the presence of the Government representative.
The Contracting Officer may elect to accept certified weight certificates furnished by a public weighmaster in lieu of scale weights at the jobsite.
SECTION 01 22 00 Page 11
1.5.11.3 Unit of Measure
Ton.
1.5.12 Graded Aggregate Base (Line Item 0019)
1.5.12.1 Payment
Payment will be made for costs associated with and incidental to placement of graded aggregate base.
1.5.12.2 Measurement
Measure aggregate for payment by the ton (2,000 pounds) by weighing each truckload to the nearest 0.1 ton, and the final quantity of the whole sum is rounded to the nearest whole ton. Weigh the aggregate for payment on approved scales before being placed in the work. Quarry weights will not be accepted. Use scales of sufficient length to permit simultaneous weighing all axle loads. Scales must be inspected, tested and sealed as directed to assure accuracy with 0.5 percent throughout the range of the scales. Certify scales located at the site of the work as to accuracy by an acceptable scales company representative prior to weighing any aggregate. Scales will be checked and certified before aggregate hauling and rechecked and recertified whenever a variance is suspected. Furnish the scales. If commercial scales are readily available in close proximity, 25 miles of site of work, the Contracting Officer may approve the use of the scales. Weigh aggregate in the presence of the Government representative. The Contracting Officer may elect to accept certified weight certificates furnished by a public weighmaster in lieu of scale weights at the jobsite.
1.5.12.3 Unit of Measure
Ton.
1.5.13 Hot Mix Asphalt (Line Item 0020)
1.5.13.1 Payment
Payment will be made for costs associated with and incidental to placement of hot mix asphalt.
1.5.13.2 Measurement
Measurement will be made by the area of HMA placed, as measured by finished area.
1.5.13.3 Unit of Measure
Square meters.
1.5.14 Contracting Officer's Field Office (Line Item 0021)
1.5.14.1 Payment
Payment will be made for costs associated with or incidental to providing, maintaining, and final disposition of the Contracting Officer's field office including all costs for rent and provision of all services indicated
SECTION 01 22 00 Page 12 in Section 01 52 10 CONTRACTING OFFICER'S FIELD OFFICE. Costs for such provision and maintenance of the Contractor's own field office and other facilities will not be paid for under this line item.
1.5.14.2 Measurement
The basis for payment will be the amount of time that the Contracting Officer's field office is available to the Government within the duration of the contract.
1.5.14.3 Unit of Measure
Month.
1.5.15 PVC Drain Pipe (Line Item 0025)
1.5.15.1 Payment
Payment will be made for costs associated with and incidental to installing PVC drain pipe, including PVC pipes, pipe joints, connection to the existing pipes and between the PVC pipes, installation, etc.
1.5.15.2 Measurement
Length of the PVC line measured in place.
1.5.15.3 Unit of Measure
Linear Feet.
1.5.16 Backfill Stone (Line Item 0030)
1.5.16.1 Payment
Payment will be made for costs associated with and incidental to placement of backfill stone.
1.5.16.2 Measurement
Measure stone for payment by the ton (2,000 pounds) by weighing each truckload to the nearest 0.1 ton, and the final quantity of the whole sum is rounded to the nearest whole ton.