Soliciation_QandA_19APR18.pdf
PDF 65 KB Posted
- Solicitation number
- W912EP-18-R-0032
About this file
Questions and Answers
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Soliciation_QandA_2_19APR_2018.pdf | ||
| Soliciation_QandA_13APR18.pdf | ||
| Roll_Call.pdf | ||
| PreProposal_Slides.pdf | ||
| Q&A_2018-04-04.pdf | ||
| Soliciation_Q&A's_3.29.18.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912EP‐18‐R‐0032
Topographic and Hydrographic Surveying and Mapping to Support the Jacksonville District
QUESTIONS AND ANSWERS
19 April 2018
QUESTION #1: We have our Joint Venture submitting as a sub‐consultant on the solicitation below. Will a Part II be required from both firms in the JV?
GOVERNMENT RESPONSE: No, a JV is considered one entity, so the submission for Part II should be for the combined team.
QUESTION#2: During the conference call the Corps stated that a resume "Section E" can be more than one page. Can a project "Section F" be more than one page also? Please let me know.
GOVERNMENT RESPONSE: Yes.
QUESTION #3: Related to W912EP‐18‐R‐0032, just a quick point of clarification, do you want two separate volumes bound for both the Part I and Part II? (3 for each – for a total of 6 bound volumes) or is it okay to bind the Part IIs with the Part I for a total of 3?
GOVERNMENT RESPONSE: We require separate volumes for both Part I and Part, 3 copies of each.
QUESTION#4: Is it acceptable for the RFQ below to submit as a prime and be a sub on two different teams?
GOVERNMENT RESPONSE: Yes.
QUESTION #5: We have our Joint Venture submitting as a sub‐consultant on the solicitation below. Will a Part II be required from both firms in the JV?
GOVERNMENT RESPONSE: No, a JV is considered one entity, so the submission for Part II should be for the combined team.