W912EP‐18‐R‐0032

Topographic and Hydrographic Surveying and Mapping to Support the Jacksonville District

QUESTIONS AND ANSWERS

19 April 2018

QUESTION #1: We have our Joint Venture submitting as a sub‐consultant on the solicitation below. Will a Part II be required from both firms in the JV?

GOVERNMENT RESPONSE: No, a JV is considered one entity, so the submission for Part II should be for the combined team.

QUESTION#2: During the conference call the Corps stated that a resume "Section E" can be more than one page. Can a project "Section F" be more than one page also? Please let me know.

GOVERNMENT RESPONSE: Yes.

QUESTION #3: Related to W912EP‐18‐R‐0032, just a quick point of clarification, do you want two separate volumes bound for both the Part I and Part II? (3 for each – for a total of 6 bound volumes) or is it okay to bind the Part IIs with the Part I for a total of 3?

GOVERNMENT RESPONSE: We require separate volumes for both Part I and Part, 3 copies of each.

QUESTION#4: Is it acceptable for the RFQ below to submit as a prime and be a sub on two different teams?

GOVERNMENT RESPONSE: Yes.

QUESTION #5: We have our Joint Venture submitting as a sub‐consultant on the solicitation below. Will a Part II be required from both firms in the JV?

GOVERNMENT RESPONSE: No, a JV is considered one entity, so the submission for Part II should be for the combined team.