This solicitation requests bids for water and sewer repairs at three campgrounds located at Saylorville Lake in Polk County, Iowa. The base bid includes work at the Bob Shetler Campground and consists of mobilization, traffic control, demolition, directional drilling, trenching, valve and hydrant installation, water and sewer piping, manholes, a lift station, concrete, asphalt, granular surfacing, flowable fill, and site restoration. Option A is for work at the Cherry Glen Campground and involves mobilization, traffic control, demolition, a water meter vault, sewer lining, piping and manholes, lagoon sludge removal, earthwork, stone slope protection, and trail and site work. Option B covers the Prairie Flower Campground and includes mobilization, demolition, directional drilling, valves, hydrants, meter vaults, sewer piping, manhole repair, a lift station, and site restoration. The solicitation was issued by the U.S. Army Corps of Engineers Rock Island District for water and sewer repairs at three campgrounds located at Saylorville Lake in Polk County, Iowa. Bids are due by the date specified in the solicitation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

96514720404528

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to extend the bid due date to 07 September 2022, update the bid due time 10:00 AM and revise Spec

Section 33 05 23 and a Draw ing.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 30-Aug-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EK22B0011

X 9B. DATED (SEE ITEM 11)

28-Jul-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

30-Aug-2022

CODE

CONTRACTING DIVISION

US ARMY CORPS OF ENGINEERS 1500 ROCK ISLAND D

ROCK ISLAND IL 61201

W912EK 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912EK22B0011

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time has changed from 02-Sep-2022 01:00 PM to 07-Sep-2022 10:00 AM.

SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

The following have been modified:

MVR.13 INSTRUCTIONS TO BIDDERS

INSTRUCTION TO BIDDERS

The Rock Island District has implemented the below procedures for all current bid openings.

Electronic Submission of Bids:

For this IFB Solicitation, the Rock Island District is requesting all electronic bids be submitted via email to the

Contracting Officer and Contract Specialist.

Contracting Officer – Mr. Nicholas M. Moore

Contract Specialist – Mr. Bradley J. Grothus

In the subject of the e-mail – the solicitation and Project Name shall be provided.

The Contracting Officer or Contract Specialist will send an email acknowledging receipt. Please note, the Firewall can cause a delay in receipt of email, so be sure to allow time for the delay.

The Bid Opening is currently scheduled for Wednesday, 07 September 2022 at 11:00 AM CST.

The Contracting Officer and Contract Specialist will begin downloading bids ONE HOUR BEFORE BID

OPENING TIME, which is the bid receipt cutoff time.

All bids received after 10:00 AM CST on Wednesday, 07 September 2022 will be considered late.

Audio Teleconference Bid Opening Information:

Bid Opening will be held on Wednesday, 07 September 2022 at 11:00 AM CST. Please use the following call-in information to attend the meeting:

Toll-Free: 1-844-800-2712

Access Code: 2760 598 3922

Following the conclusion of the bid opening, the Bid Abstract will be uploaded to SAM website under this solicitation, within 24 hours.

Bid Bonds (Offer Guarantee) should be submitted electronically with the Bid Package as per the scheduled Bid

Opening on Amendment.

Per Class Deviation 2020-O0016, Electronic signatures and electronic, mechanically-applied, or printed dates may be used and shall be considered original signatures and dates. In addition, a Corporate Seal is not required, the SF 28 need not be sworn and notarized and a written authorization of the release signed by the surety is acceptable in lieu of the notarized authorization of release by the surety. Original Certified Bonds need not be submitted at time of bid.

W912EK22B0011

HOWEVER, the Rock Island District reserves the right to request the Original Certified Bonds, if deemed necessary to verify their authenticity.

The following deviation clauses now apply, in lieu of the corresponding FAR clauses:

• 52.228-11, Pledges of Assets (DEVIATION 2020-O0016), which removes the requirement for the Standard

Form 28 to be sworn and notarized.

• 52.228-15, Performance and Payment Bonds—Construction (DEVIATION 2020-O0016), which removes the requirements for seals on Standard Forms.

For any Questions please contact:

Contracting Officer – Mr. Nicholas M. Moore

Phone: 309-794-5250

Contracting Specialist – Mr. Bradley J. Grothus

Phone: 309-794-5021

(End of Summary of Changes)

The following modifications are made to the Section 33 05 23 and a Drawing.

SECTION 33 05 23

a. PAGES SECTION 33 05 23 PAGE 1 AND SECTION 33 05 23 PAGE 7. Delete pages SECTION 33 05 23 PAGE 1 and SECTION 33 05 23 PAGE 7, in their entirety, and substitute therefor revised pages SECTION 33 05 23 PAGE 1 and

SECTION 33 05 23 PAGE 7.

DRAWINGS (SUPERCEDED)

b. Revised drawings listed below are being issued with this Amendment. Such revised drawings supersede those of the same sheet identification numbers as listed in the INDEX OF DRAWINGS: C-122.

SOLICITATION NO.: W912EK22B0011

B5SAYLOR202102

SECTION TABLE OF CONTENTS

DIVISION 33 - UTILITIES

SECTION 33 05 23

UTILITY HORIZONTAL DIRECTIONAL DRILLING

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 QUALITY CONTROL

1.3.1 Qualifications

1.3.2 Safety

1.4 REQUIRED DOCUMENTATION

PART 2 PRODUCTS

2.1 POLYETHYLENE PIPE

2.2 DRILLING FLUIDS

PART 3 EXECUTION

3.1 INSTALLATION

3.1.1 Drill Set-Up and Fluids

3.1.2 Drill Entrance and Exit Pits

3.1.3 Drill Entrance and Exit Angle

3.1.4 Pilot Hole

3.1.5 Guidance Systems

3.1.6 Reaming

3.1.7 Pull Back

3.1.8 Drilling Fluids Disposal

3.1.9 Connection of Product Pipe to Pipeline

3.2 FIELD QUALITY CONTROL

3.3 CLOSEOUT ACTIVITIES

-- End of Section Table of Contents --

SECTION 33 05 23 Page 1

AMEND 0003

29 AUG 2022

SECTION 33 05 23

UTILITY HORIZONTAL DIRECTIONAL DRILLING

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1926.652 Safety and Health Regulations for Construction; Subpart P, Excavations;

Requirements for Protective Systems

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 1110-2-2902 Conduits, Culverts, And Pipes

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Statement of Qualifications and Records; G ECG Horizontal Directional Drilling Work Plan; G ECG

SD-03 Product Data

Drill Rod; G ECG Drilling Fluids; G ECG

Submit for all items listed as applicable: manufacturer's descriptive data, performance data, installation instructions, warranty, certificates of compliance, operations and maintenance manual, cleaning instructions in accordance with Section 01 78 00

CLOSEOUT SUBMITTALS.

SD-05 Design Data

Secondary Containment Plan; G ECG

SD-11 Closeout Submittals

Record Drawings; G ECG Complete Work Logs of Guided Directional Drill Operations; G ECG

SECTION 33 05 23 Page 2

1.3 QUALITY CONTROL

1.3.1 Qualifications

Ensure that the field supervisor and workers are experienced in work of this nature and have successfully completed similar projects of similar length, pipe type, pipe size, and soil type using directional drilling in the last 3 years. As part of the bid submission, submit a description of such project(s) which include, at a minimum, a listing of the location(s), date of project(s), owner, pipe type, size installed, length of installation, type, and manufacturer of equipment used, and other information relevant to the successful completion of the project.

1.3.2 Safety

Include in directional drilling equipment machine safety requirements a common grounding system to prevent electrical shock in the event of underground electrical cable strike. Ensure the grounding system connects all pieces of interconnecting machinery; the drill, mud mixing system, drill power unit, drill rod trailer, operators booth, worker grounding mats, and any other interconnected equipment to a common ground. Equip the drill with an "electrical strike" audible and visual warning system that notifies the system operators of an electrical strike.

1.4 REQUIRED DOCUMENTATION

Prior to commencement of the work, submit the following:

a. Statement of Qualifications and Records

b. Horizontal Directional Drilling Work Plan

Provide work plan in accordance with EM 1110-2-2902, include hydraulic fracture restrictions. Provide a description of the drilling procedure and methods. Include size and type of drill tooling, description of locating equipment, type of fluid circulation system, make and model of drilling equipment, anticipated drilling pressures, anticipated fluid flow rates, and cleaning inadvertent fluid returns at the surface.

Submit a complete list of all drilling fluids and mix designs. Include all additives and mixtures used along with Safety Data Sheets. Submit drilling personnel resumes with names, years of experience, and relevant work experience.

For the Des Moines River crossing site, provide a separate work plan to include the items listed previously and the following additional items:

anticipated drilling and pull back advancement rates, maximum limits for pull back forces, limits on fluid pressure, installation methods addressing buoyancy force of the pipe, selection of drill tooling for variable soils, and proposed entry and exit pit's locations and depths within the designed utility alignment. Include prevention of blowouts into the river. Provide analysis for both service and strength limit states in acordance with paragraph "POLYETHYLENE PIPE." If the exit or entry pit is beyond the location of the pump station, describe how the pipe will intercept the sewer pump station. At a minimum, maintain 10 feet of soil cover between the river channel bottom and the top of the pipe. Include details for monitoring, cleaning, and reducing fluid

SECTION 33 05 23 Page 3 release in the river. Soil materials encountered are varied including, but not limited to, clay, sand, shale, and sandstone. Historical Geotechnical data is provided in Section 00 73 05 SPECIAL CONTRACT REQUIREMENTS, paragraph "ADDITIONAL PHYSICAL DATA CLAUSE INFORMATION."

PART 2 PRODUCTS

2.1 POLYETHYLENE PIPE

Select suitable pipe for the Des Moines River crossing, with the indicated diameters. Evaluate both service and strength limit states. The only evaluation needed for service limit state is associated deflection. The strength-based limit stated must be evaluated for thrust, global/localized buckling, and combined strain. Provide thermoplastic pipe in accordance with ER 1110-2-2902 section 4.15.

For all other HDD work, install the indicated diameter polyethylene pipe, with a minimum dimension ratio of 11 in accordance with Section 33 11 00 WATER UTILITY DISTRIBUTION PIPING or as indicated.

2.2 DRILLING FLUIDS

Use a high quality bentonite fluid to ensure hole stability, cuttings transport, bit and electronics cooling, and hole lubrication to reduce drag on the drill pipe and the product pipe. Use only fluid with a composition which complies with all federal, state, and local environmental regulations.

PART 3 EXECUTION

3.1 INSTALLATION

Ensure all utilities are located and clearly marked prior to start of excavation or drilling. Directional drilling is not allowed in the dam embankment, under the dam's stability berm, and/or withing 50 feet of the dam toe or stability berm toe, unless directed by the Contraction Officer.

3.1.1 Drill Set-Up and Fluids

Design and construct the drill entrance and exit pits. Mix the drilling fluid with potable water (of proper pH) to ensure no contamination is introduced into the soil during drilling, reaming, or pipe installation process. Make any required pH adjustments.

3.1.2 Drill Entrance and Exit Pits

Drill entrance and exit pits are required. Maintain at a minimum size to allow only the minimum amount of drilling fluid storage prior to transfer to mud recycling or processing system or removal offsite. Do not allow drilling mud to flow freely on the site or around the entrance or exit pits. Remove spilled mud and restore ground to original condition.

Provide shore pits in accordance with OSHA Standards, 29 CFR 1926.652.

SECTION 33 05 23 Page 4

3.1.3 Drill Entrance and Exit Angle

Ensure entrance and exit angles and elevation profile maintains adequate cover to reduce risk of drilling fluid breakouts and ground exit occurs as specified. Ensure that entrance and exit angles generate pullback forces that do not exceed 5 percent strain on the polyethylene pipe.

3.1.4 Pilot Hole

The type and size of the pilot string cutting head and the diameter of the drill pipe will be at the Contractor's discretion. Drill the pilot hole along the path as shown. Pilot hole tolerances are as follows:

a. Vertical Tolerance: Provide minimum cover below existing ground as specified. Pilot hole may go deeper if necessary to prevent breakout.

b. Horizontal Tolerance: Plus or minus 60-inches from the centerline of the product pipe.

c. Curve Radius: Is prohibited with a radius less than 1,000-feet.

d. Entry Point Location: Make pilot hole entry point within plus or minus 60-inches of the location shown or as directed by the Contracting Officer.

e. Exit Point Location: Make the exit point location within plus or minus 60-inches of the location shown or as directed by the Contracting Officer.

f. Cover mandatory pipeline as shown or specified.

3.1.5 Guidance Systems

Walkover guidance systems are permitted. Refer to paragraph "FIELD QUALITY CONTROL" for additional requirements.

3.1.6 Reaming

Reaming operations and selections of reamer type(s) will be at the Contractor's discretion. Select reamer type(s) and size(s) based on the subsurface conditions and conduit sizes to be installed at each location.

Appropriately size equipment to mitigate surface disturbance. Damages caused by all drilling and reaming operations will be repaired by the Contractor, at no additional cost to the Government.

3.1.7 Pull Back

Fully assemble the entire pipeline and install via directional drilling prior to commencement of pull back operations. Support the pipeline during pullback operations in a manner to enable it to move freely and prevent damage. Install the pipeline in one continuous pull. Minimize torsion stress by using a swivel to connect the pull section to the reaming assembly. Maximum allowable tensile force imposed on the pull section is not to exceed 90 percent of the pipe manufacturer's safe pull (or tensile) strength. If the pull section is made up of multiple pipe size or materials, the lowest safe pull strength value governs and the maximum

SECTION 33 05 23 Page 5 allowable tensile force is not to exceed 90 percent of this value. Minimize external pressure during installation of the pullback section in the reamed hole. Replace damaged pipe resulting from external pressure at no cost to the Government. Buoyancy modification is at the discretion of the Contractor.

3.1.8 Drilling Fluids Disposal

Collect drilling fluid returns in the entrance pit, exit pit, or spoils recovery pit. Immediately clean up any drilling fluid spills or overflows from pits. Dispose of fluids in a manner that is in accordance with all permits and applicable federal, state, and local regulations. Spread the drilling slurry over the Government-approved disposal area and plow into the soil. Conduct disposal in accordance with all relative environmental regulations, right-of-way and work space agreements, and permit requirements.

3.1.9 Connection of Product Pipe to Pipeline

After the product pipe has been successfully installed, allow the product pipe to recover for 24 hours prior to connection of the pipeline. Ensure that a sufficient length of the product pipe has been pulled through the hole so that the pull-nose is not pulled back into bore hole due to stretch recovery of the product pipe.

3.2 FIELD QUALITY CONTROL

Maintain drilling logs that accurately provide drill bit location (both horizontally and vertically) at least every 10 feet along the drill path.

In addition, keep logs that record, as a minimum the following, every 15 minutes throughout each drill pass, back ream pass, or pipe installation pass:

a. Drilling Fluid Pressure

b. Drilling Fluid Flow Rate

c. Drill Thrust Pressure

d. Drill Pullback Pressure

e. Drill Head Torque

Make all instrumentation, readings, and logs available to the Contracting Officer at all times during operation. The Contracting Officer may increase or decrease the time intervals for data recordings, within reasonable scope and notice.

3.3 CLOSEOUT ACTIVITIES

Immediately upon completion of work, remove all rubbish and debris from the job site. Remove all construction equipment and implements of service leaving the entire area involved in a neat condition acceptable of the Contracting Officer.

SECTION 33 05 23 Page 6

Immediately clean "blow holes" or "breakouts" of drilling fluid to the surface and return the surface area to original condition. Dispose of all drilling fluids, soils, and separated materials in compliance with federal, state, and local environmental regulations.

Submit record drawings within 5 days after completing the pull back.

Include in the record drawings a plan, profile, and all information recorded during the progress of the work. Clearly tie the record drawings to the project's survey control. Maintain and submit upon completion signed complete work logs of guided directional drill operations.

-- End of Section --

SECTION 33 05 23 Page 7

A22 - W912EK22B0011 0003 PD2
A22 - SPEC_AMND_0003
33 05 23.pdf
UTILITY HORIZONTAL DIRECTIONAL DRILLING
33 05 23 - UTILITY HORIZONTAL DIRECTIONAL DRILLING
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 QUALITY CONTROL
1.3.1 Qualifications
1.3.2 Safety

1.4 REQUIRED DOCUMENTATION

PART 2 PRODUCTS
2.1 POLYETHYLENE PIPE
2.2 DRILLING FLUIDS
PART 3 EXECUTION
3.1 INSTALLATION
3.1.1 Drill Set-Up and Fluids
3.1.2 Drill Entrance and Exit Pits
3.1.3 Drill Entrance and Exit Angle
3.1.4 Pilot Hole
3.1.5 Guidance Systems
3.1.6 Reaming
3.1.7 Pull Back
3.1.8 Drilling Fluids Disposal
3.1.9 Connection of Product Pipe to Pipeline
3.2 FIELD QUALITY CONTROL
3.3 CLOSEOUT ACTIVITIES