AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The reason for this Amendment is to make changes to the SCHEDULE OF PRICES, SECTION 00 73 05, SECTION 01 22 00, SECTION 01 32 01, SECTION 01 33 00, SECTION 02 10 05, SECTION 02 21 00, SECTION 02 95 00, SECTION 03 31 00 & DRAWINGS.
In addition, the Contract Specialist is changed to Katelyn Nelson for proposal submissions. The Offeror’s proposal shall be submitted in electronic version to katelyn.t.nelson@usace.army.mil.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 6
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 22-Aug-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EK19R0016
X 9B. DATED (SEE ITEM 11)
01-Aug-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
22-Aug-2019
CODE
CONTRACTING DIVISION
US ARMY CORPS OF ENGINEERS
1500 ROCK ISLAND DRIVE
ROCK ISLAND IL 61201
W912EK 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
19R0016
AMEND. 0002
The following modifications have been made to the Solicitation:
SCHEDULE OF PRICES
a. ALL PAGES. Delete the SCHEDULE OF PRICES in its entirety and substitute therefor revised SCHEDULE OF PRICES, Amendment 0002.
SECTION 00 73 05
b. PAGES 4, 5, 6, 7, 21, 23, and 25. Delete SECTION 00 73 05 Pages 4, 5, 6, 7, 21, 23, and 25 in their entirety, and substitute therefor revised and new SECTION 00 73 05 Pages 4, 5, 5a, 6, 6a, 7, 7a, 21, 23, 23a, and 25, Amendment 0002, dated August 15, 2019.
SECTION 01 22 00
c. ALL PAGES. Delete SECTION 01 22 00 in its entirety and substitute therefor revised SECTION 01 22 00 Pages 1 through 13, Amendment 0002, dated August 15, 2019.
SECTION 01 32 01
d. PAGES 1, 2, 5, 6, and 7. Delete SECTION 01 32 01 Pages 1, 2, 5, 6, and 7 in their entirety, and substitute therefor revised and new SECTION 01 32 01 Pages 1, 2, 5, 5a, 6, and 7, Amendment 0002, dated
SECTION 01 33 00
e. ALL PAGES. Delete the SUBMITTAL REGISTER in its entirety and substitute therefor revised SUBMITTAL REGISTER Pages 1 through 13, Amendment 0002, dated August 15, 2019.
SECTION 02 10 05
f. PAGE 2. Delete SECTION 02 10 05 Page 2 in its entirety, and substitute therefor revised SECTION 02 10 05 Page 2, Amendment 0002, dated
SECTION 02 21 00
g. PAGE 3. Delete SECTION 02 21 00 Page 3 in its entirety, and substitute therefor revised and new SECTION 02 21 00 Pages 3 and 3a, 19R0016
SECTION 02 95 00
h. PAGE 4. Delete SECTION 02 95 00 Page 4 in its entirety, and substitute therefor revised and new SECTION 02 95 00 Pages 4 and 4a, SECTION 03 31 00
i. PAGES 1, 2, 3, 7, 9, 14, 19, and 31. Delete SECTION 03 31 00 Pages 1, 2, 3, 7, 9, 14, 19, and 31 in their entirety, and substitute therefor revised and new SECTION 03 31 00 Pages 1, 2, 3, 7, 7a, 9, 14, 14a, 19, and 31, DRAWINGS (SUPERCEDED)
j. Revised drawings listed below are being issued with this Amendment.
Such revised drawings supersede those of the same sheet identification numbers listed in the INDEX OF DRAWINGS included in the set of drawings furnished with Solicitation No. W912EK19R0016, dated August 1, 2019:
G-001; G-002; G-003; G-004; C-101; V-102; Volume I G-001; Volume I-A SD101;
Volume I-A SD110; Volume I-A SD120; Volume I-A SD210; Volume I-A SD220;
Volume I-A SD301; Volume I-A SD330; Volume I-A S-101; Volume I-A S-110;
Volume I-A S-120; Volume I-A S-130; Volume I-A S-211; Volume I-A S-212;
Volume I-A S-221; Volume I-A S-222; Volume I-A S-240; Volume I-A S-301;
Volume I-A S-310; Volume I-A S-311; Volume I-A S-312; Volume I-A S-320;
Volume I-A S-321; Volume I-A S-322; Volume I-A S-501; Volume I-A S-502;
Volume I-A S-504; Volume I-A S-540; Volume I-B S-001; Volume I-B S-501;
Volume I-B S-502; Volume I-B S-503; Volume I-B S-504; Volume I-C S-301;
Volume I-C S-501; Volume I-C S-502; Volume I-C S-503; Volume I-D S-001;
Volume I-D S-050; Volume I-D S-301; Volume I-D S-351; Volume I-D S-505;
Volume I-D S-550; Volume I-D S-553; Volume I-E S-201; Volume I-E S-301;
Volume I-E S-501; Volume II G-001; Volume II-A SD302; Volume II-A S-102;
Volume II-A S-103; Volume II-A S-104; Volume II-A M-301; Volume II-A M-302;
Volume II-A M-303; Volume II-A E-601; Volume II-B S-301; Volume II-B M-505;
Volume III G-001; Volume III SD901; and Volume III SD921.
W912EK19R0016
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00010 - SOLICITATION CONTRACT FORM
The following have been modified:
SCHEDULE OF PRICES
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
BASE BID
0001 Mobilization and Demobilization 1 JOB XXXXXXXX $ 0002 Temporary Field Office
0002AA First 6 Months 6 MO ____________ $
0002AB Over 6 Months 1 MO ____________ $
0003 Dive Inspections 1 JOB XXXXXXXX $
0004 Emergency Miter Gate Disposal 1 JOB XXXXXXXX $
0005 Emergency Miter Gate Anchorage Removal
1 JOB XXXXXXXX $
0006 Bulkhead Recess Installation
0006AA Concrete Removal 1 JOB XXXXXXXX $
0006AB Deadman Anchors Installation 1 JOB XXXXXXXX $
0006AC Precast Panel Fabrication and Delivery 1 JOB XXXXXXXX $
0006AD Precast Panel Installation 1 JOB XXXXXXXX $
0006AE Bulkhead Recess 1 JOB XXXXXXXX $
0006AF Bulkhead Slot Protection Plate 1 JOB XXXXXXXX $
0007 Sill Concrete Formwork 1 JOB XXXXXXXX $
0008 Sill Concrete Placement 1 JOB XXXXXXXX $
0009 Sill Anchors 1 JOB XXXXXXXX $
0010 Weep Holes 1 JOB XXXXXXXX $
0011 Handrailing 215 LF ____________ $ 0012 Valve Grating Support 1 JOB XXXXXXXX $ 0013 Electrical Work 1 JOB XXXXXXXX $
0014 Sill Concrete Removal 1 JOB XXXXXXXX $
TOTAL OF ESTIMATED AMOUNTS OF BASE BID
(ITEM NOS. 0001 THROUGH 0014, INCL.)
OPTION A - FABRICATION AND DELIVERY
0101 Bull Gear Components Fabrication and Delivery
1 JOB XXXXXXXX $
0102 Bull Gear Roller Components Fabrication and Delivery
1 JOB XXXXXXXX $
0103 Support Frame and Handrailing 1 JOB XXXXXXXX $ 0104 Cover Plate Fabrication and Delivery 1 JOB XXXXXXXX $
TOTAL OF ESTIMATED AMOUNTS OF OPTION A
(ITEM NOS. 0101 THROUGH 0104, INCL.)
OPTION B - UPPER LAND WALL PIT
0201 Sole Plate and Machinery - Remove and
Reinstall
1 JOB XXXXXXXX $
0202 Bull Gear Components Installation 1 JOB XXXXXXXX $
0203 Bull Gear Roller Components Installation 1 JOB XXXXXXXX $
0204 Vertical Concrete Removal 0204AA First 7 Cubic Yards 7 CY ____________ $
0204AB Over 7 Cubic Yards 2 CY ____________ $
0205 Horizontal Concrete Removal 0205AA First 8 Cubic Yards 8 CY ____________ $
0205AB Over 8 Cubic Yards 2 CY ____________ $
0206 Vertical Concrete Placement 0206AA First 7 Cubic Yards 7 CY ____________ $
0206AB Over 7 Cubic Yards 2 CY ____________ $
0207 Horizontal Concrete Placement 0207AA First 8 Cubic Yards 8 CY ____________ $
0207AB Over 8 Cubic Yards 2 CY ____________ $
0208 Framing Installation 1 JOB XXXXXXXX $ 0209 Cover Plate Installation 1 JOB XXXXXXXX $ 0210 Electrical Work 1 JOB XXXXXXXX $
TOTAL OF ESTIMATED AMOUNTS OF OPTION B
(ITEM NOS. 0201 THROUGH 0210, INCL.)
OPTION C - LOWER LAND WALL PIT
0301 Sole Plate and Machinery - Remove and Reinstall
1 JOB XXXXXXXX $
0302 Bull Gear Components Installation 1 JOB XXXXXXXX $
0303 Bull Gear Roller Components Installation 1 JOB XXXXXXXX $
0304 Vertical Concrete Removal 0304AA First 7 Cubic Yards 7 CY ____________ $
0304AB Over 7 Cubic Yards 2 CY ____________ $
0305 Horizontal Concrete Removal 0305AA First 8 Cubic Yards 8 CY ____________ $
0305AB Over 8 Cubic Yards 2 CY ____________ $
0306 Vertical Concrete Placement 0306AA First 7 Cubic Yards 7 CY ____________ $
0306AB Over 7 Cubic Yards 2 CY ____________ $
0307 Horizontal Concrete Placement 0307AA First 8 Cubic Yards 8 CY ____________ $
0307AB Over 8 Cubic Yards 2 CY ____________ $
0308 Framing Installation 1 JOB XXXXXXXX $ 0309 Cover Plate Installation 1 JOB XXXXXXXX $ 0310 Electrical Work 1 JOB XXXXXXXX $
TOTAL OF ESTIMATED AMOUNTS OF OPTION C
(ITEM NOS. 0301 THROUGH 0310, INCL.)
OPTION D - UPPER I-WALL PIT
0401 Sole Plate and Machinery - Remove and Reinstall
1 JOB XXXXXXXX $
0402 Bull Gear Components Installation 1 JOB XXXXXXXX $
0403 Bull Gear Roller Components Installation 1 JOB XXXXXXXX $
0404 Vertical Concrete Removal 0404AA First 7 Cubic Yards 7 CY ____________ $
0404AB Over 7 Cubic Yards 2 CY ____________ $
0405 Horizontal Concrete Removal 0405AA First 8 Cubic Yards 8 CY ____________ $
0405AB Over 8 Cubic Yards 2 CY ____________ $
0406 Vertical Concrete Placement 0406AA First 7 Cubic Yards 7 CY ____________ $
0406AB Over 7 Cubic Yards 2 CY ____________ $
0407 Horizontal Concrete Placement 0407AA First 8 Cubic Yards 8 CY ____________ $
0407AB Over 8 Cubic Yards 2 CY ____________ $
0408 Framing Installation 1 JOB XXXXXXXX $ 0409 Cover Plate Installation 1 JOB XXXXXXXX $ 0410 Electrical Work 1 JOB XXXXXXXX $
TOTAL OF ESTIMATED AMOUNTS OF OPTION D
(ITEM NOS. 0401 THROUGH 0410, INCL.)
OPTION E - LOWER I-WALL PIT
0501 Sole Plate and Machinery - Remove and
Reinstall
1 JOB XXXXXXXX $
0502 Bull Gear Components Installation 1 JOB XXXXXXXX $
0503 Bull Gear Roller Components Installation 1 JOB XXXXXXXX $
0504 Vertical Concrete Removal 0504AA First 7 Cubic Yards 7 CY ____________ $
0504AB Over 7 Cubic Yards 2 CY ____________ $
0505 Horizontal Concrete Removal 0505AA First 8 Cubic Yards 8 CY ____________ $
0505AB Over 8 Cubic Yards 2 CY ____________ $
0506 Vertical Concrete Placement 0506AA First 7 Cubic Yards 7 CY ____________ $
0506AB Over 7 Cubic Yards 2 CY ____________ $
0507 Horizontal Concrete Placement 0507AA First 8 Cubic Yards 8 CY ____________ $
0507AB Over 8 Cubic Yards 2 CY ____________ $
0508 Framing Installation 1 JOB XXXXXXXX $ 0509 Cover Plate Installation 1 JOB XXXXXXXX $ 0510 Electrical Work 1 JOB XXXXXXXX $
TOTAL OF ESTIMATED AMOUNTS OF OPTION E
(ITEM NOS. 0501 THROUGH 0510, INCL.)
OPTION F - UPPER GUIDE WALL
0601 Bullnose Surface Replacement 1 JOB XXXXXXXX $ 0602 Horizontal Concrete Removal
0602AA First 12 Cubic Yards 12 CY ____________ $ 0602AB Over 12 Cubic Yards 3 CY ____________ $ 0603 Horizontal Concrete Placement 0603AA First 12 Cubic Yards 12 CY ____________ $ 0603AB Over 12 Cubic Yards 3 CY ____________ $ 0604 Electrical Work 1 JOB XXXXXXXX $
0605 Reinforcing Plate 1 JOB XXXXXXXX $
TOTAL OF ESTIMATED AMOUNTS OF OPTION F
(ITEM NOS. 0601 THROUGH 0605, INCL.)
TOTAL OF ESTIMATED AMOUNTS OF BASE BID AND OPTIONS A THROUGH F
(ITEM NOS. 0001 THROUGH 0605, INCL.)
CY = CUBIC YARD JOB = LUMP SUM LF = LINEAR FOOT MO = MONTH
THE GOVERNMENT RESERVES THE RIGHT TO AWARD OPTION A
BY 30 OCTOBER 2019.
IF OPTION A IS EXERCISED, THE CONTRACT WILL NOT BE
EXTENDED.
THE GOVERNMENT RESERVES THE RIGHT TO AWARD OPTIONS B
THROUGH F
BY 15 DECEMBER 2019.
IF OPTIONS B THROUGH F ARE EXERCISED, THE CONTRACT
WILL NOT BE EXTENDED.
(End of Summary of Changes)
The following items are applicable to this modification:
POC INFORMATION
All proposal submittals shall be to the following POC:
Katelyn Nelson
(309) 794-5340 Katelyn.t.nelson@usace.army.mil
Solicitation No.: W912EK19R0016
Rock Island District 1500 Rock Island Drive Rock Island, Illinois 61201
Insurance; G, CT
Superintendence of Subcontractors; G
Pre-Construction Condition Survey; G
High Water Action Plan; G
Diving Plan; G
Sequencing of Work;G
SD-05 Design Data
Plan And Design Calculations; G
SD-11 Closeout Submittals
Post-Construction Condition Survey; G
1.3 ADDITIONAL COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
In addition to the requirements of Contract Clause 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK, comply with the following requirements:
1.3.1 Sequencing of Work
a. All work to occur between 7:00am on 6 July 2020, and 5:30pm on 24 October 2020, excluding "Emergency Miter Gate Removal and Disposal".
b. The construction period is comprised of a navigation restriction period (barge traffic reduced to 70 foot width and only passing at night) and a 14 calendar day navigation closure period of the lock (no barge traffic).
c. The 14 calendar day navigation closure period to commence at 7:00am on 7 October 2020, and be complete by 5:30pm on 20 October 2020. The Contractor will be allowed to work 24 hours a day during the navigation closure period.
d. The navigation restricted period will be in effect the remaining work period. The first navigation restriction period begins on 6 July 2020 and ends on 6 October 2020. The final navigation restriction period begins on 21 October 2020 and ends on 24 October 2020. The Contractor's working hours are 7:00am to 5:30pm, during the navigation restriction period.
Outside of those hours, the Contractor is prohibited to have personnel within the work area, unless approved by the Contracting Officer.
Navigation traffic is prohibited to pass through the lock during the Contractor's working hours. Each night lock operators will navigate traffic through the lock. The lock will open to navigation traffic with a width restriction from 6:00pm to 6:00am.
e. The Contractor will be allowed two 8 hour lock closures prior to the commencement of the navigation restriction period to perform an initial dive inspection in accordance with the approved diving plan, paragraph "DIVING PLAN" and "Dive Operations" for additional information and perform minor preparatory work, as described. Provide the Government a minimum 30
DOCUMENT 00 73 05 Page AMEND. 0002
15-AUG-2019
calendar days' notice prior to the requested closure date.
The Contractor may perform minor preparatory work, such as installing temporary wiring and line drilling for concrete removal prior to the navigation restriction period as long as work does not affect navigation, operation of the lock, access and work safety of lock personnel, or reduce lock component strengths or performance. Submit the required work along with a detailed work plan, schedule, location of equipment, computations, and other required information for Governmental approval. The work plan will require approval by the Contracting Officer prior to commencement of work. A detailed work plan will be required when the Contractor requests to do work outside of the navigation restriction period. The Government reserves the right to disallow any work outside of the navigation restriction period, and not account for any days outside of the navigation restriction period when preparing bid documents and project schedule. Any damage to lock components outside of the navigation restriction period will be the responsibility of the Contractor to repair immediately at the Contractor's expense. Any damages which cause closure to the lock by the Contractor operations shall require the Contractor to cease all operation and initiate repairs to damaged components. Repair work shall be continuous until components have been replaced and the Lock returned to service.
1.3.2 Upper Bulkhead Recesses
1.3.2.1 Emergency Miter Gate Removal and Disposal
Prior to 1 June 2020, deliver one hopper or deck barge, 35 feet by 200 feet and leave in mooring area as indicated.
Between 1 June 2020, and 14 June 2020, the following to occur:
a. The Government will remove and place the emergency miter gate leaves and pintle balls on the Contractor provided barge for disposal by the Contractor. The pintle ball base to be removed and disposed by the Contractor. Equip barge with a support system adequate to safely hold and transport the miter gates leaves in an upright position on the barge. Submit the plan and design calculations, signed and sealed by an Illinois Licensed Structural Engineer. The plan to be approved prior to the barge arriving on site.
b. The Government will install a temporary fender system in the empty recesses to provide short-term protection from barge impact. The Contractor to remove temporary fender system from the first recess to be worked on at the start of the navigation restriction period and place in the staging area. The temporary fender system in the opposite recess to stay in place until the Contractor has completed work on the first recess. Each emergency miter gate leaf is estimated to weigh 160 tons.
1.3.2.2 Bulkhead Recess Construction
Bulkhead recess construction on both sides of the chamber will take place during the navigation restriction period. The lock will remain fully operational and functional throughout the navigation restriction period, with a 70 foot width restriction in place; therefore, the Contractor will only be allowed to perform work on one wall at a time.
All precast panels for the bulkhead recess construction to be fabricated
DOCUMENT 00 73 05 Page AMEND. 0002
15-AUG-2019
and delivered on site prior to the commencement of the first navigation
DOCUMENT 00 73 05 Page AMEND. 0002
15-AUG-2019
restriction period, 6 July 2020.
During the first navigation restriction period, the work at each lockwall includes, but is not limited to:
a. Concrete removal.
b. Dive operations to assist in concrete removal, prepare rock surface in recess area, install anchors in existing lockwall, install Contractor designed concrete formwork, and underwater concrete placement in recess area.
c. Precast panel installation.
d. Remaining concrete placement in recess and curing.
Work on one lockwall cannot be started until work on the other lockwall is completed. During the final navigation restriction period, the work includes, but is not limited to:
a. Installing Government provided bulkhead for Contractor's Quality Control Dive Inspection and the Government's Quality Assurance Dive Inspection. See paragraph "Dive Operations" for more information.
b. Final Dive Inspection. See paragraph "Dive Operations" for more information.
1.3.2.3 Sill Construction
Sill construction, between the lock walls, to take place during the 14 day navigation closure period. This work includes, but is not limited to:
a. Dive operation to prepare rock surface in the footprint of the proposed sill concrete.
b. Installing the Contractor designed sill concrete formwork.
c. Install weep holes and rock dowels (may be completed after sill concrete pour).
d. Concrete placement in sill area. Allow for concrete cure time.
1.3.3 Bull Gear Machinery Pit Repairs
a. Options B through E will only be awarded if Option A is awarded.
b. If any or all of Options B through E are awarded, the Government will provide boats and operators to manually operate the gates during the navigation restriction period.
c. Construction means and methods must not interfere with the miter gate leaves full range of motion, the recessed position in particular.
1.3.4 Upper Guidewall Repairs
a. If Option F is awarded, complete this work concurrently with landwall bulkhead slot work. Provide 14 days of concrete cure time prior to navigation traffic shifting to the landwall.
DOCUMENT 00 73 05 Page AMEND. 0002
15-AUG-2019
1.3.5 Miscellaneous Work Requirements
a. Provide all necessary protection, appurtenant equipment, and supplies including, but not limited to, enclosures, heating, lighting, DOCUMENT 00 73 05 Page AMEND. 0002 and sufficient labor to accomplish the work required to be completed during the aforementioned periods, taking into account low and high temperatures, high humidity, and heat index factors that may be encountered at the site and working adjacent to water. This may require additional labor or shifts and special equipment or special equipment maintenance to compensate for lost productivity caused by low and high temperatures or other associated environmental factors.
b. Work involving open flames, sparks, or other operations deemed dangerous by the Lockmaster is prohibited during lockage's of tows containing flammable products. It is estimated that 10 percent to 25 percent of the tows being locked through contain flammable products.
Additionally, during all lockage's, not just tows containing flammable products, conduct operations such that no loud noises occur during the lockage that would interfere with barge personnel's ability to hear radio communications.
1.3.6 Lock Operations
All lock operations will be conducted by the Government. Lock operations may occur within the following parameters:
a. To perform lock operations between 8:00am and 4:00pm, Monday through Friday, excluding Government holidays.
b. Provide a minimum of 1 working day, excluding Government holidays, advance notice to the Contracting Officer for all lock operations.
c. Allow 4 hours for the Government to complete operation.
1.3.7 Dive Operations
This is not a complete list of all dive operations required by the Contract, only a description of special dive operations required. Perform a preconstruction dive investigation, a sill construction quality control dive inspection, and a post-construction dive inspection. The preconstruction dive investigation to be used to determine existing conditions underwater, including, but not limited to, a general investigation of existing conditions and investigate distance between wall faces as required for recess fabrication, as noted. Videotape the preconstruction dive investigation and submit a copy to the Contracting Officer within three days. Sill Construction Quality Control dive inspection to include:
a. Perform during the second navigation restriction period.
Survey of newly constructed sill, including but not limited to, the upstream seal plate and the individual downstream bearing plates (embedded sill plates).
b. Setting Government provided bulkhead in newly constructed bulkhead recesses to verify seal and bearing on embedded sill plates.
c. Measure gaps between bulkhead and embedded sill plates.
d. Videotape dive inspection and submit a copy to the Contracting Officer within 3 days.
The Government will conduct a Quality Assurance Dive Inspection concurrent
DOCUMENT 00 73 05 Page AMEND. 0002 with the Contractor's Quality Control Dive Inspection. The bulkhead picking strongback will not be provided. The bulkhead has padeyes to attach a sling. See the reference drawings for the bulkhead lift angle and height of the picking point. The post construction dive investigation to be used to verify the complete
DOCUMENT 00 73 05 Page AMEND. 0002
15-AUG-2019
"Diving Superintendent" will be responsible for scheduling and coordinating all diving operations with other project superintendents, implementing and enforcing the Safe Practice Manual, and preparing all dive plans. This individual will be responsible for ensuring that all divers employed on the project possess current and valid physicals, first-aid/CPR/O2 cards, and proper experience credentials in accordance with EM 385-1-1, Section 30.A.05. This person is in addition to the required 4-man dive crew in accordance with EM 385-1-1, Appendix G. The approved plan to be kept at the dive location(s) at all times.
1.26.1 Safe Practices Manual
Submit for approval a safe practices manual which depicts the Contractor's general plan for accomplishing the diving operations. The manual will be approved prior to commencement of any diving operation. The manual to include the minimum requirements in accordance with EM 385-1-1, Section 30.A.15.
1.26.2 Dive Operations Plan
Submit for approval a dive operations plan to cover all aspects of the diving operations. The dive operations plan will be approved prior to commencement of any diving operation. The plan to include the minimum content in accordance with EM 385-1-1, Section 30.A.16. The plan to include general overview of all tasks to be performed, dive modes and equipment, site access, etc. Complex projects involving more than one work task, location, and/or dive team will require task-specific dive plans as part of the overall dive operations plan.
1.26.3 Activity Hazardous Analysis
Submit for approval an activity hazardous analysis to cover all aspects of the hazards of and activities to include diving, equipment failures, environmental conditions weather and other hazardous/unexpected situations in accordance with EM 385-1-1, Section 30.A.17.
1.26.4 Emergency Management Plan
Submit for approval an emergency management plan to be prepared for each dive operation. The emergency management plan to include the minimum requirements in accordance with EM 385-1-1, Section 30.A.18. The plan will be approved prior to commencement of any diving operations.
1.26.5 Diving Personnel Qualifications
As a minimum, each dive team personnel, dive supervisor, diver and back up diver, to have at a minimum at least 1 year of commercial experience in the applicable position. Dive tenders are required to have previous experience and training as a dive tender. Provide all team personnel the required training documentation, medical documentation, and experience documentation in accordance with EM 385-1-1, Section 30.A.05 through 30.A.09. The plan will be approved prior to commencement of any diving operation for the dive team personnel's permission to perform any diving operation.
1.26.6 Diving Supervisor
Provide a qualified diving supervisor, responsible for supervising all diving operations, implementing and enforcing the Diving Manual, preparing and implementing all diving plans, and enforcing all diving requirements.
DOCUMENT 00 73 05 Page 2 AMEND. 0002
1.28 HIGH WATER ACTION PLAN
Provide a plan detailing the activities to minimize the adverse effects of high water. Include protection of accomplished work and Contractor's equipment and personnel. Include emergency measures to restore any damaged sections of the project. Emergency measures to provide sound engineering methods that provide protection at or greater than the height of the existing feature should high water occur.
1.29 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
a. Provision ER 415-1-15 specifies the procedure for determination of time extensions for unusually severe weather in accordance with the Contract Clause 52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION). In order for the Contracting Officer to award a time extension under this clause, the following conditions to occur:
(1) The weather experienced at the project site during the Contract period to be found unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
(2) The unusually severe weather to actually cause a delay to the completion of the project. The delay is beyond the control and without the fault or negligence of the Contractor.
b. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and constitutes the base line for monthly weather time evaluations. Include in the progress schedule to reflect these anticipated adverse weather delays in all weather dependent activities.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY
WORK DAYS BASED ON (7) DAY WORK WEEK
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
(31) (28) (26) (12) (08) (07) (06) (06) (05) (10) (19) (31)
c. Upon mobilization and continuing throughout the Contract, record on the daily Contractor's quality control report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days that prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day. The number of actual adverse weather delay days to include days impacted by actual adverse weather (even if adverse weather occurred in the previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in list item (b.) above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the Contract Clause 52.249-10 DEFAULT (FIXED-PRICE
CONSTRUCTION).
d. The navigation restriction period and closure period are excluded from this provision. This period (6 July 2020 - 24 October 2020) will not be extended for unusually severe weather.
DOCUMENT 00 73 05 Page 2 AMEND. 0002
15-AUG-2019
1.30 ILLINOIS RETAILERS' OCCUPATIONAL TAX AND USE TAX EXEMPTION
Materials physically incorporated into real estate owned by the Government are exempt from Illinois Retailers' Occupational Tax and Use Tax. However, DOCUMENT 00 73 05 Page 2 AMEND. 0002 electrical utilities available from existing receptacles and supplies currently in place. The Contractor may not disconnect existing cables/conductors/receptacles and re-route or relocate to accommodate site activities. If the Contractor chooses not to use Government power, then all utility requirements for construction activities associated with the Contract requirements to be provided by the Contractor. The Government does not guarantee the reliability of incoming power and distribution to the site, and may not be held liable for power outages affecting Contractor operations, or schedule, or both. Make provisions for supplying backup power to maintain construction activities and schedule in the case of a power outage, as necessary.
b. Be responsible for damage caused to Government facilities, receptacles, breakers, and other electrical equipment by damage from Contractor's use and/or operations. Immediately notify the Contracting Officer of any damage or outages. The Government requires full replacement of damaged items and immediate repair.
c. The amount of each utility service consumed to be paid by the Contractor based on the following options:
(1) The Contractor may set up a meter(s) between the incoming power source and the Government meter, and pay for power consumed through normal methods required by the utility company. At no additional cost to the Government, and in a workmanlike manner satisfactory to the Contracting Officer, install and maintain all necessary connections and distribution lines. Before final acceptance of the work by the Government, remove all the temporary connections, distribution lines, and associated equipment.
(2) The Contractor may pay the site utility costs above the average monthly costs for each month, while the Contractor is performing work. The determination on when costs start/end is based on when the Contractor is actively using electrical power on-site, as agreed to by the Contractor and the Contracting Officer, but at a minimum when significant Contractor activities are occurring such as coring/sawing/pumping or when three or more Contractor personnel are on-site and using electrical power. If the Contractor is not actively working at the site for an entire month, the utility cost above the amount listed below will be prorated and pay their portion of utility usage.
d. Submit verification of payment to the utility company prior to acceptance of progress payments. Failure to demonstrate payment will result in a retainage held in accordance with Contract Clause 52.232-5
PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS.
e. The following schedule lists the average monthly electrical utility costs for:
Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
$ 7586 5721 2870 4468 1112 1302 1681 1815 1445 1950 2679 8364
f. Government drinking and restroom facilities are prohibited for Contractor use. The Contractor to provide and maintain within the
DOCUMENT 00 73 05 Page AMEND. 0002
15-AUG-2019
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 JOB PAYMENT ITEMS
1.1.1 Mobilization and Demobilization
1.1.1.1 Payment
1.1.1.2 Unit of Measure
1.1.2 Dive Inspections
1.1.2.1 Payment
1.1.2.2 Unit of Measure
1.1.3 Emergency Miter Gate Disposal
1.1.3.1 Payment
1.1.3.2 Unit of Measure
1.1.4 Emergency Miter Gate Anchorage Removal
1.1.4.1 Payment
1.1.4.2 Unit of Measure
1.1.5 Concrete Removal
1.1.5.1 Payment
1.1.5.2 Unit of Measure
1.1.6 Deadman Anchors Installation
1.1.6.1 Payment
1.1.6.2 Unit of Measure
1.1.7 Precast Panel Fabrication and Delivery
1.1.7.1 Payment
1.1.7.2 Unit of Measure
1.1.8 Precast Panel Installation
1.1.8.1 Payment
1.1.8.2 Unit of Measure
1.1.9 Bulkhead Recess
1.1.9.1 Payment
1.1.9.2 Unit of Measure
1.1.10 Bulkhead Slot Protection Plate
1.1.10.1 Payment
1.1.10.2 Unit of Measure
1.1.11 Sill Concrete Formwork
1.1.11.1 Payment
1.1.11.2 Unit of Measure
1.1.12 Sill Concrete Placement
1.1.12.1 Payment
1.1.12.2 Unit of Measure
1.1.13 Sill Anchors
1.1.13.1 Payment
1.1.13.2 Unit of Measure
1.1.14 Weep Holes
1.1.14.1 Payment
1.1.14.2 Unit of Measure
1.1.15 Valve Grating Support
1.1.15.1 Payment
1.1.15.2 Unit of Measure
SECTION 01 22 00 Page 1 AMEND. 0002
15-AUG-2019
1.1.16 Electrical Work
1.1.16.1 Payment
1.1.16.2 Unit of Measure
1.1.17 Bull Gear Components Fabrication and Delivery
1.1.17.1 Payment
1.1.17.2 Unit of Measure
1.1.18 Bull Gear Roller Components Fabrication and Delivery
1.1.18.1 Payment
1.1.18.2 Unit of Measure
1.1.19 Framing
1.1.19.1 Payment
1.1.19.2 Unit of Measure
1.1.20 Cover Plate
1.1.20.1 Payment
1.1.20.2 Unit of Measure
1.1.21 Sole Plate and Machinery - Remove and Reinstall
1.1.21.1 Payment
1.1.21.2 Unit of Measure
1.1.22 Reinforcing Plate
1.1.22.1 Payment
1.1.22.2 Unit of Measure
1.1.23 Bullnose Surface Replacement
1.1.23.1 Payment
1.1.23.2 Unit of Measure
1.2 UNIT PRICE PAYMENT ITEMS
1.2.1 Temporary Field Office
1.2.1.1 Payment
1.2.1.2 Unit of Measure
1.2.2 Handrailing
1.2.2.1 Payment
1.2.2.2 Measurement
1.2.2.3 Unit of Measure
1.2.3 Vertical Concrete Removal
1.2.3.1 Payment
1.2.3.2 Measurement
1.2.3.3 Unit of Measure
1.2.4 Horizontal Concrete Removal
1.2.4.1 Payment
1.2.4.2 Measurement
1.2.4.3 Unit of Measure
1.2.5 Vertical Concrete Placement
1.2.5.1 Payment
1.2.5.2 Measurement
1.2.5.3 Unit of Measure
1.2.6 Horizontal Concrete Placement
1.2.6.1 Payment
1.2.6.2 Measurement
1.2.6.3 Unit of Measure
PART 2 MATERIALS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 22 00 Page 2 AMEND. 0002
15-AUG-2019
SECTION 01 22 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 JOB PAYMENT ITEMS
Payment items for the work of this Contract for which Contract job payments will be made are listed in the SCHEDULE OF PRICES and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job payment item, to be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed to constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.1.1 Mobilization and Demobilization
1.1.1.1 Payment
Mobilization and demobilization for all plant and equipment, materials, tools, and supplies necessary to complete the work, will be made for Base Bid Item No. 0001, "Mobilization and Demobilization." Mobilization consists of all costs required to prepare plant and equipment for shipment, moving plant, equipment, supplies, and incidentals to the work site.
Demobilization consists of all costs required to prepare plant and equipment for removal and for removing all plant, equipment, unused supplies, and incidentals from the work site, including restoration of staging areas used for construction operations. The Contractor will be paid 60 percent of the job price upon completion of mobilization to the work site. The remaining 40 percent will be paid to the Contractor upon completion of demobilization at the end of the Contract. Failure to justify such price to the satisfaction of the Contracting Officer may result in: payment of actual mobilization costs, as determined by the Contracting Officer at the completion of mobilization; actual demobilization costs, as determined by the Contracting Officer at the completion of demobilization; and payment of the remainder of this item in the final payment under this Contract. Construction bonds, with proof of a paid invoice, may be paid under this payment item.
1.1.1.2 Unit of Measure
Unit of measure: job.
1.1.2 Dive Inspections
1.1.2.1 Payment
Payment for all costs associated with the dive operations described in Section 00 73 05 SPECIAL CONTRACT REQUIREMENTS will be made for Base Bid Item No. 0003 "Dive Inspections."
SECTION 01 22 00 Page 3 AMEND. 0002
15-AUG-2019
1.1.2.2 Unit of Measure
Unit of measure: job.
1.1.3 Emergency Miter Gate Disposal
1.1.3.1 Payment
Payment for all costs associated with gate disposal to include, but is not limited to, barge for transport, support system for gate leafs including design and plans, and disposing of emergency miter gates and gate pintles, both coated in lead based paint will be made for Base Bid Item No. 0004, "Emergency Miter Gate Disposal."
1.1.3.2 Unit of Measure
Unit of measure: job.
1.1.4 Emergency Miter Gate Anchorage Removal
1.1.4.1 Payment
Payment for all costs associated with removing concrete and anchorage components, and properly disposing materials will be made for Base Bid Item No. 0005 "Emergency Miter Gate Anchorage Removal."
1.1.4.2 Unit of Measure
Unit of measure: job.
1.1.5 Concrete Removal
1.1.5.1 Payment
Payment for all costs associated with wire sawing, coring recesses, non-wiring sawing removal, concrete removal capture and removal, and disposal will be made for:
Base Bid Item No. 0006AA, "Bulkhead Recess Installation, Concrete Removal;" and
Base Bid Item No. 0014, "Sill Concrete Removal." as applicable.
1.1.5.2 Unit of Measure
Unit of measure: job.
1.1.6 Deadman Anchors Installation
1.1.6.1 Payment
Payment for all costs associated with the anchor installation to include, but is not limited to, drilling, anchoring, grouting, and installing anchors will be made for Base Bid Item No. 0006AB "Bulkhead Recess Installation, Deadman Anchors Installation."
1.1.6.2 Unit of Measure
Unit of measure: job.
SECTION 01 22 00 Page 4 AMEND. 0002
15-AUG-2019
1.1.7 Precast Panel Fabrication and Delivery
1.1.7.1 Payment
Payment for all costs associated with fabricating and delivering the required number of precast panels; and concrete, reinforcement bars, embedded materials, and embedded steel will be made for Base Bid Item No.
0006AC "Bulkhead Recess Installation, Precast Panel Fabrication and Delivery."
1.1.7.2 Unit of Measure
Unit of measure: job.
1.1.8 Precast Panel Installation
1.1.8.1 Payment
Payment for all costs associated with installing panels will be made for Base Bid Item No. 0006AD "Bulkhead Recess Installation, Precast Panel Installation."
1.1.8.2 Unit of Measure
Unit of measure: job.
1.1.9 Bulkhead Recess
1.1.9.1 Payment
Payment for all costs associated with removing, storing, and reinstalling tow haulage unit, providing rebar anchors and grouting as completed by diving operations; providing and installing deadman, angle support and recess grating; placing tremie concrete; installing armor; placing cast-in-place concrete; and installing reinforcement bars will be made for Base Bid Item No. 0006AE "Bulkhead Recess Installation, Bulkhead Recess."
1.1.9.2 Unit of Measure
Unit of measure: job.
1.1.10 Bulkhead Slot Protection Plate
1.1.10.1 Payment
Payment for all costs associated with fabricating, delivering and installing the plate will be made for Base Bid Item No. 0006AF "Bulkhead Recess Installation, Bulkhead Slot Protection Plate."
1.1.10.2 Unit of Measure
Unit of measure: job.
1.1.11 Sill Concrete Formwork
1.1.11.1 Payment
Payment for all costs associated with fabricating, delivering, and
SECTION 01 22 00 Page 5 AMEND. 0002
15-AUG-2019
installing seat steel, and installing and removing formwork will be made for Base Bid Item No. 0007 "Sill Concrete Formwork."
1.1.11.2 Unit of Measure
Unit of measure: job.
1.1.12 Sill Concrete Placement
1.1.12.1 Payment
Payment for all costs associated with providing bulkhead bearing beam and plates, underwater concrete placement, and installing bulkhead and quality control check as completed by diving operations will be made for Base Bid Item No. 0008 "Sill Concrete Placement."
1.1.12.2 Unit of Measure
Unit of measure: job.
1.1.13 Sill Anchors
1.1.13.1 Payment
Payment for all costs associated with drilling holes and providing rods and grouting as completed by diving operations will be made for Base Bid Item No. 0009 "Sill Anchors."
1.1.13.2 Unit of Measure
Unit of measure: job.
1.1.14 Weep Holes
1.1.14.1 Payment
Payment for all costs associated with constructing weep holes including, but not limited to, drilling, providing piping and aggregate will be made for Base Bid Item No. 0010 "Weep Holes."
1.1.14.2 Unit of Measure
Unit of measure: job.
1.1.15 Valve Grating Support
1.1.15.1 Payment
Payment for all costs associated with fabricating, delivering, and installing grating, removing, storing, and reinstalling grating, and concrete removal, fabrication and delivery of grating/coverplates as indicated will be made for Base Bid Item No. 0012 "Valve Grating Support."
1.1.15.2 Unit of Measure
Unit of measure: job.
SECTION 01 22 00 Page 6 AMEND. 0002
15-AUG-2019
1.1.16 Electrical Work
1.1.16.1 Payment
Payment for all costs associated with the electrical work will be made for:
Base Bid Item No. 0013 "Electrical Work;"
Option B Item No. 0210 "Electrical Work;"
Option C Item No. 0310 "Electrical Work;"
Option D Item No. 0410 "Electrical Work;"
Option E Item No. 0510 "Electrical Work;" and
Option F Item No. 0604 "Electrical Work," as applicable.
1.1.16.2 Unit of Measure
Unit of measure: job.
1.1.17 Bull Gear Components Fabrication and Delivery
1.1.17.1 Payment
Payment for all costs associated with fabricating, delivering, and installing, as applicable, the components to include, but not limited to, gear base, pins, bushing, and other required components, and furnishing/providing anchor bolts, nuts, and components will be made for:
Option A Item No. 0101 "Bull Gear Components Fabrication and Delivery;"
Option B Item No. 0202 "Bull Gear Components Fabrication and Delivery;"
Option C Item No. 0302 "Bull Gear Components Fabrication and Delivery;"
Option D Item No. 0402 "Bull Gear Components Fabrication and Delivery;"
and
Option E Item No. 0502 "Bull Gear Components Fabrication and Delivery," as applicable.
1.1.17.2 Unit of Measure
Unit of measure: job.
1.1.18 Bull Gear Roller Components Fabrication and Delivery
1.1.18.1 Payment
Payment for all costs associated with fabricating, delivering, and installation, as applicable, the components to include, but not limited to, roller, pin, bushing, and base and other required components, and furnishing/providing anchor bolts, nuts, and set screws will be made for:
Option A Item No. 0102 "Bull Gear Roller Components Fabrication and Delivery;"
SECTION 01 22 00 Page 7 AMEND. 0002
15-AUG-2019
Option B Item No. 0203 "Bull Gear Roller Components Fabrication and Delivery;"
Option C Item No. 0303 "Bull Gear Roller Components Fabrication and Delivery;"
Option D Item No. 0403 "Bull Gear Roller Components Fabrication and Delivery;" and
Option E Item No. 0503 "Bull Gear Roller Components Fabrication and Delivery," as applicable.
1.1.18.2 Unit of Measure
Unit of measure: job.
1.1.19 Framing
1.1.19.1 Payment
Payment for all costs associated with fabricating and delivering beams and baseplates, furnishing bolts and nuts for assembly, and installing framing;
and removing, storing, and reinstalling handrail, and providing new handrail bolts and nuts will be made for:
Option A Item No. 0103 "Support Frame and Handrailing;"
Option B Item No. 0208 "Framing Installation;
Option C Item No. 0308 "Framing Installation;
Option D Item No. 0408 "Framing Installation;" and
Option E Item No. 0508 "Framing Installation," as applicable.
1.1.19.2 Unit of Measure
Unit of measure: job.
1.1.20 Cover Plate
1.1.20.1 Payment
Payment for all costs associated with fabricating and delivering beams and baseplates, furnishing bolts and nuts for assembly, and installing framing;
and providing handrail will be made for:
Option A Item No. 0104 "Cover Plate Fabrication and Delivery;"
Option B Item No. 0209 "Cover Plate Installation;"
Option C Item No. 0309 "Cover Plate Installation;"
Option D Item No. 0409 "Cover Plate Installation;" and
Option E Item No. 0509 "Cover Plate Installation," as applicable.
SECTION 01 22 00 Page 8 AMEND. 0002
15-AUG-2019
1.1.20.2 Unit of Measure
Unit of measure: job.
1.1.21 Sole Plate and Machinery - Remove and Reinstall
1.1.21.1 Payment
Payment for all costs associated with surveying existing location of platforms; removing, placing in storage, and reinstalling the miter gate bull gear and machinery platforms will be made for:
Option B Item No. 0201 "Sole Plate and Machinery - Remove and Reinstall;"
Option C Item No. 0301 "Sole Plate and Machinery - Remove and Reinstall;"
Option D Item No. 0401 "Sole Plate and Machinery - Remove and Reinstall;" and
Option E Item No. 0501 "Sole Plate and Machinery - Remove and Reinstall," as applicable.
1.1.21.2 Unit of Measure
Unit of measure: job.
1.1.22 Reinforcing Plate
1.1.22.1 Payment
Payment for all costs associated with fabricating, delivering, and installing the plate, providing anchors and grouting, and removing embedded steel will be made for Option F Item No. 0605 "Reinforcing Plate."
1.1.22.2 Unit of Measure
Unit of measure: job.
1.1.23 Bullnose Surface Replacement
1.1.23.1 Payment
Payment for all costs associated with concrete, asphalt, and gravel removal and disposal, chipping around miscellaneous embeds, formwork, cast-in-place concrete, reinforcement, finishing, and curing will be made for Option F Item No. 0601 "Bullnose Surface Replacement."
1.1.23.2 Unit of Measure
Unit of measure: job.
1.2 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this Contract on which the Contract unit price payments will be made are listed in the SCHEDULE OF PRICES and described below. The unit price and payment made for each item listed constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, SECTION 01 22 00 Page 9 AMEND. 0002
15-AUG-2019
surveys, and for performing all costs required for each of the unit price items.
1.2.1 Temporary Field Office
1.2.1.1 Payment
Payment for all costs associated with providing a temporary field office, furnishings, utilities, and paid monthly for trailers will be made for:
Base Bid Item No. 0002AA "Temporary Field Office, First 6 Months;" and
Base Bid Item No. 0002AB "Temporary Field Office, Over 6 Months;" as applicable.
1.2.1.2 Unit of Measure
Unit of measure: month.
1.2.2 Handrailing
1.2.2.1 Payment
Payment for all costs associated with removing, storing, and installation of existing handrail to be reused, fabrication, delivery, and installation of new handrail will be made for Base Bid Item No. 0011 "Handrailing."
1.2.2.2 Measurement
The quantity of handrail to be paid for in linear feet, placed in the completed and accepted construction. Handrail will be measured in place in the field by the Contractor only within the handrail dimensions shown on the plans and approved by the Contracting Officer.
1.2.2.3 Unit of Measure
Unit of measure: linear foot.
1.2.3 Vertical Concrete Removal
1.2.3.1 Payment
Payment for all costs associated with removing and disposing of concrete vertically will be made for:
Option B Item No. 0204AA "Vertical Concrete Removal, First 7 Cubic Yards;"
Option B Item No. 0204AB "Vertical Concrete Removal, Over 7 Cubic Yards;"
Option C Item No. 0304AA "Vertical Concrete Removal, First 7 Cubic Yards;"
Option C Item No. 0304AB "Vertical Concrete Removal, Over 7 Cubic Yards;"
Option D Item No. 0404AA "Vertical Concrete Removal, First 7 Cubic Yards;"
Option D Item No. 0404AB "Vertical Concrete Removal, Over 7 Cubic Yards;"
SECTION 01 22 00 Page 10 AMEND. 0002
15-AUG-2019
Option E Item No. 0504AA "Vertical Concrete Removal, First 7 Cubic Yards;" and
Option E Item No. 0504AB "Vertical Concrete Removal, Over 7 Cubic Yards," as applicable.
1.2.3.2 Measurement
Concrete removal will be measured in place in the field by the Contractor only within and a paid to the lines as shown and as approved.
1.2.3.3 Unit of Measure
Unit of measure: cubic yard.
1.2.4 Horizontal Concrete…