Construction Project: Little Goose Dam Unit #5 Rotor Spider and Upper Bearing Bracket Repair.
The work will be performed at Little Goose Lock and Dam located in Whitman County and
Columbia County, Washington. This will be a firm fixed-price construction contract.
Construction magnitude is estimated to be between $5,000,000.00 and $10,000,000.00.
Performance and payment bonds in the amount of 100 percent of the contract price are required.
A bid bond is required in the amount of 20 percent of the total bid price.
This project is open to both large and small business concerns. The North American Industry
Classification System (NAICS) code for this work is 237990. The small business size standard is $36.5 million in average annual receipts.
This is a pre solicitation and the solicitation is anticipated to be posted in 21 days.
Summary of Scope of Work:
The work consists of the following major elements:
Unit 5 at Little Goose Lock & Dam is currently out of service due to excessive vibrations and cracks on the rotor spider and upper bearing bracket. The work covered in this contract includes inspection of the stator core with optional minor repair, inspecting and testing the stator winding and rotor with optional minor winding repairs, conduct a Finite Element Analysis (FEA) of the rotor structure (including Government proposed strengthening) and providing insight and further recommendations, perform weld repair of cracks in the rotor spider arms and upper bearing bracket, and structural strengthening of the rotor spider.
All rotor spider repair welding is to be done on site, under tightly controlled and monitored pre-heat conditions to avoid damage to or distortion of the rotor rim. To ensure the rotor spider is not under stress due to the rotor rim weight during the spider arm crack repair, the contractor will be required to develop a jacking and cribbing plan to properly support the weight of the rim, without removing the rim from the rotor. In-place machine condition monitoring equipment (air gap, shaft runout) will be installed as part of this work.
This work requires disassembly and reassembly of the hydraulic turbine generator unit. The contractor will be responsible for the inspection and replacement or refurbishment of all major generator and turbine bearings to include the upper generator guide bearing, lower generator guide bearing, thrust bearing, turbine guide bearing, and thrust bearing coolers. The contractor will be responsible for pre-disassembly measurements, as well as post-reassembly measurements and operational testing. The generator is manufactured by General Electric.
All on-site work shall be performed in accordance with the Corps of Engineers Safety and Health
Requirements Manual (EM 385-1-1).
The Contractor will be responsible for establishing and managing an effective on-site Safety and
Health program in accordance with EM 385-1-1 that will require the development and submission of a comprehensive project specific Accident Prevention Plan for Government acceptance. In addition, the Contractor will be required to develop and submit for Government acceptance Activity Hazard Analyses for each phase of work and a project specific Fall
Protection Plan that comply with EM 385-1-1.
A Site Safety and Health Officer (SSHO) employed by the prime contractor shall be required for each shift of the contractor’s on-site operations. The SSHO shall possess a minimum of five years experience in construction safety on similar projects, shall have completed the 30-Hour
OSHA Construction Safety training within the last five years, and shall have completed at least
24-hours of formal safety training each year for the past five years.
A qualified Fall Protection Competent Person shall be provided by the Contractor for each shift of the contractor’s on-site operations that involves work that exposes workers to fall hazards.
The Contractor will be responsible for establishing and managing an effective Contractor Quality
Control (CQC) System that will require the development and submission of a comprehensive project specific CQC Plan for Government acceptance. A CQC System Manager employed by the prime contractor shall be required to be on-site for each shift of the Contractor’s operations.
The CQC System Manager must possess a minimum of five years relevant experience in a supervisory or management position such as Quality Control Manager, Quality Assurance
Manager, or Construction Manager directly involved in the management of construction quality at the project site. In addition, the CQC System Manager shall have completed the course entitled “Construction Quality Management for Contractors” within the last five years.
The Contractor will be required to use the Government-furnished Construction Contractor
Module (referred to as QCS) of the Resident Management System (RMS) to record, maintain, and submit various information throughout the contract period. QCS is a Windows-based program that can be run on a stand-alone personal computer or on a network. The Government will make the QCS software available to the Contractor after contract award.
The project will involve the development and management of Contractor furnished submittals for items such as pre-construction plans, product data, test reports, and contract close-out documentation as required by the technical specifications of the contract.
Miscellaneous work within the project includes the delivery of As-Built Drawings to the USACE prior to final payment and final contract closeout.
Important Note: The FBO response date listed elsewhere in this synopsis is for the FedBizOpps archive purposes only. It has no relationship to the actual bid opening date. The bid opening date will be contained in the solicitation and any solicitation amendments that are issued.
When issued, the solicitation documents for this project will be available via FedBizOpps.gov or https://www.fbo.gov. NO CD's OR HARD COPIES WILL BE AVAILABLE. Bidders are responsible for checking the referenced page for any update(s) to the Notice. The Government is not responsible for any loss of Internet connectivity or for an offeror's inability to access the document(s) posted at the referenced website. To obtain automatic notifications of updates to this solicitation, you MUST log in to FedBizOpps.gov and add the solicitation to your Watchlist. If https://www.fbo.gov/ you would like to list your firm so others can see you are an interested vendor, you must click the
“Add Me To Interested Vendors” button in the listing for this solicitation on FedBizOpps.gov.
ACCESS FOR FOREIGN NATIONALS: Security clearance for foreign nationals to attend a site visit requires approximately four (4) weeks; therefore, clearance should be requested immediately. To request clearance, please submit the names of all foreign nationals proposed for site visit attendance, along with documentation to verify that they were legally admitted into the
United States and have authority to work and/or go to school in the US. Such documentation may include a US passport, Certificate of US citizenship (INS Form N-560 or N-561), Certificate of Naturalization (INS Form N-550 or N-570), foreign passport with I-551 stamp or attached
INS Form I-94 indicating employment authorization, Alien Registration Receipt Card with photograph (INS Form I-151 or I-551), Temporary Resident Card (INS Form I-688), Employment Authorization Card (INS Form I-688A), Reentry Permit (INS Form I-327), Refugee Travel Document (INS Form I-571), Employment Authorization Document issued by the INS which contains a photograph (INS Form I-688B). Send this information by email to
Kent.R.Bernard@usace.army.mil and Jani.C.Long@usace.army.mil. Foreign nationals must have received clearance prior to being granted access to the project site.
mailto:Kent.R.Bernard@usace.army.mil mailto:Jani.C.Long@usace.army.mil
File details come from the government source that posted it. Updated .