This document contains official bid abstracts for a federal construction solicitation. The solicitation seeks bids to reconstruct the toe ditch and install relief wells at three reaches of the Arkabutla Lake Dam in DeSoto County, Mississippi. Work includes removing the existing concrete toe ditch and installing new relief wells, demolishing existing wells, and constructing a new toe ditch with headwalls and reinforced concrete pipe. Bids were received from three contractors for the base work and two option periods to complete additional reaches. The independent government estimate totaled $5.7 million for all work. Bids ranged from $4.1 million to $6.6 million accounting for base work and both option periods. The low bidder was Riverside Construction Co. of Vicksburg, Mississippi. The pre-bid conference was held on-site on January 14, 2020 with site visit to follow. The Army Corps of Engineers Vicksburg District is the contracting agency.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ITEM DESCRIPTION
EST
QTY U/M UNIT PRICE AMOUNT
TOE DITCH RECONSTRUCTION
– REACH 3 1 JOB FOR $1,229,000.00
0002 RELIEF WELLS – REACH 3 26 EA $77,000.00 $2,002,000.00
$3,231,000.00
OPTION 1: TOE DITCH
RECONSTRUCTION - REACH 2 1 JOB FOR $515,000.00
1 807
OPTION 1: RELIEF WELLS -
REACH 2 11 EA $64,000.00 $704,000.00
$1,219,000.00
OPTION 2: TOE DITCH
RECONSTRUCTION - REACH 1 1 JOB FOR $324,000.00
OPTION 2: RELIEF WELLS -
REACH 1 15 EA $64,000.00 $960,000.00
$1,284,000.00
$5,734,000.00
BID ABSTRACT
For Bids Under Solicitation, W912EE20B0003
DESOTO COUNTY, MS, ARKABUTLA LAKE DAM RECONSTRUCTION OF TOE DITCH FC/MR&T,
YAZOO RIVER BASIN COLDWATER RIVER, ARKABUTLA LAKE
TOTAL OPTION 2
TOTAL OPTION 1
TOTAL BASE PLUS ALL OPTIONS
SOUTHERN CONTRACTING, LLC
NEWBERN, TN
QTY U/M UNIT PRICE AMOUNT
TOE DITCH RECONSTRUCTION
– REACH 3 1 JOB FOR $860,000.00
0002 RELIEF WELLS – REACH 3 26 EA $97,000.00 $2,522,000.00
$3,382,000.00
OPTION 1: TOE DITCH
RECONSTRUCTION - REACH 2 1 JOB FOR $415,000.00
OPTION 1: RELIEF WELLS -
REACH 2 11 EA $97,000.00 $1,067,000.00
$1,482,000.00
OPTION 2: TOE DITCH
RECONSTRUCTION - REACH 1 1 JOB FOR $260,000.00
OPTION 2: RELIEF WELLS -
REACH 1 15 EA $97,000.00 $1,455,000.00
$1,715,000.00
$6,579,000.00
TOTAL BASE
BID ABSTRACT
For Bids Under Solicitation, W912EE20B0003
DESOTO COUNTY, MS, ARKABUTLA LAKE DAM RECONSTRUCTION OF TOE DITCH FC/MR&T,
YAZOO RIVER BASIN COLDWATER RIVER, ARKABUTLA LAKE
RIVERSIDE CONSTRUCTION CO
VICKSBURG, MS
TOTAL OPTION 1
TOTAL OPTION 2
TOTAL BASE PLUS ALL OPTIONS
QTY U/M UNIT PRICE AMOUNT
TOE DITCH RECONSTRUCTION
– REACH 3 1 JOB FOR $901,000.00
0002 RELIEF WELLS – REACH 3 26 EA $40,000.00 $1,040,000.00
$1,941,000.00
OPTION 1: TOE DITCH
RECONSTRUCTION - REACH 2 1 JOB FOR $587,400.00
OPTION 1: RELIEF WELLS -
REACH 2 11 EA $39,600.00 $435,600.00
$1,023,000.00
OPTION 2: TOE DITCH
RECONSTRUCTION - REACH 1 1 JOB FOR $498,400.00
OPTION 2: RELIEF WELLS -
REACH 1 15 EA $44,500.00 $667,500.00
$1,165,900.00
$4,129,900.00
I CERTIFY THAT I HAVE OPENED, READ AND RECORDED ON THIS
ABSTRACT,ALL OFFERS RECEIVED IN RESPONSE TO THE
SOLICITATION
SIGNATURE AND DATE
TOTAL OPTION 1
TOTAL OPTION 2
TOTAL BASE PLUS ALL OPTIONS
INDEPENDENT GOVERNMENT ESTIMATE
TOTAL BASE
BID ABSTRACT
For Bids Under Solicitation, W912EE20B0003
DESOTO COUNTY, MS, ARKABUTLA LAKE DAM RECONSTRUCTION OF TOE DITCH FC/MR&T,
YAZOO RIVER BASIN COLDWATER RIVER, ARKABUTLA LAKE
| Official Bid Abstract p1 |
| Table 1 |
| Official Bid Abstract p2 |
| Table 1 |
| Official Bid Abstract p3 |
| Table 1 |
| 2020-02-21T09:29:49-0600 | |
| CANNADA.DUSTIN.1394393777 |
File details come from the government source that posted it. Updated .