AMENDMENT 01 DRAFT SOL. ATTACH. 7 PERFORMANCE WORK STATEMENT.pdf

PDF 319 KB Posted

Attached to
W912DY26RA030 OFFICIAL SOLICITATION_ AMENDMENT 2 FOR UTILITY MONITORING AND CONTROL SYSTEMS VI
Solicitation number
W912DY26RA030
Issued by

About this file

This is a Performance Work Statement (PWS) for Utility Monitoring and Control Systems (UMCS) Sixth Generation (VI), establishing requirements for a Multiple Award Task Order Contract (MATOC) under the U.S. Army Corps of Engineers (USACE), Engineering & Support Center, Huntsville (CEHNC).

The contractor shall provide procurement, installation, maintenance, and service for facility-related control systems including UMCS, HVAC systems, SCADA systems, fire alarm systems, life safety systems, electronic security systems (ESS), and security/force protection measures such as barriers, fencing, gates, and lighting. Services encompass preventive maintenance, corrective maintenance, condition assessments, engineering surveys, equipment installation, system testing, training, cybersecurity implementation, and central monitoring services. Individual task orders will be firm-fixed-price and may include services, construction, and supply elements. The base contract has a 36-month base period with two 24-month option periods, for a total seven-year ordering period. Work will be performed at DoD installations and other Government facilities throughout the Continental United States, Alaska, Hawaii, and specified foreign locations including Iraq, Japan, Germany, and others. The contractor must maintain a Quality Control Program, develop corporate and site-specific quality control plans, comply with Service Contract Labor Standards where applicable, meet security and clearance requirements (including SECRET-level facility clearance), complete antiterrorism and information security training, and maintain cybersecurity compliance per DoD standards. Key personnel requirements include a Program Manager, Project Manager, Contracts Manager, Quality Control Manager, engineers, technicians, and security specialists with specified experience levels and certifications. Performance measures focus on zero safety incidents, timely deliverables, schedule adherence, and successful system verification testing.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT

Utility Monitoring and Control Systems (UMCS) Sixth Generation (VI)

(Revision Date: 18 June 2026)

PART 1

GENERAL INFORMATION

1.1 Description of Services. The contractor shall provide all personnel, equipment tools, materials supervision, and other items and non-personal services necessary to provide the Procurement and Installation (P&I) of and/or the Maintenance and Service (M&S) of Facility Related Control Systems (FRCS) including but not limited to: Utility Monitoring and Control Systems (UMCS), Heating, Ventilation and Air Conditioning (HVAC) systems to include chiller/boiler systems installation and/or integration, Supervisory Control and Data Acquisition (SCADA) Systems, Fire Alarm Systems (FAS), life safety systems, other automated control systems including chemical / biological / radiological contaminant detection / filtration / response, utilities (electric/ gas/ water/ steam) metering, power/electrical distribution/power generation systems (include but not limited to photovoltaic, backup generator, microgrid, uninterruptible power supplies), other utility systems (central plant, water distribution, electrical distribution, sewer systems) and Electronic Security Systems (ESS), and security and/or force protection measures such as, but not limited to, barriers, fencing, gates, window treatments, hardening, and lighting.

1.2 Background. The U. S. Army Corps of Engineers Engineering & Support Center, Huntsville (CEHNC) maintains Centers of Expertise in UMCS and ESS. As Centers of Expertise, CEHNC provides direct support to Government agencies for the P&I and M&S of UMCS and related systems as described above.

1.3 Objectives. The Contractor shall provide technical support, procurement, installation, monitoring, and M&S for UMCS, ESS and related systems. These services include those actions required to preserve and maintain the systems in such a condition that they may be effectively used for their designated functional purpose.

1.4 Scope. This contract will require the Contractor to have the capability to respond to multiple requests simultaneously and to work at diverse locations. The Contractor shall provide all engineering and services necessary for the P&I of new and/or upgrades to Direct Digital Control (DDC) systems, existing HVAC systems, SCADA systems, or other automated control systems on Government facilities. This contract will require monitoring and control and M&S of control systems at Government facilities, municipalities and educational institutions to meet specific installation requirements. The Multiple Award Task Order Contract (MATOC) will predominantly be services contracts, but some task orders may have construction and supply elements. The task orders will include the necessary clauses, terms, conditions, instructions, and references for each of these work elements as applicable (services, construction, and supply).

1.4.1 These services also include Preventive Maintenance (PM), Corrective Maintenance (CM), repair/ replacement/modernization, equipment inventories, condition assessments, identification and/or validation of problems and deficiencies, preparation of work plans describing method of correction/repair, actual execution of work plan to repair failed or failing systems and associated equipment, facility management support, project management, central monitoring services, minor construction work within or exterior to a facility, development of PM plans, development of recommended spare parts lists, and other activities associated with operation, maintenance, and repair. Facility maintenance/repair/renovation shall conform to the requirements of the Unified Facilities Guide Specifications (UFGS) and Unified Facilities Criteria (UFC) as per the Performance Work Statement (PWS) issued with each Task Order (TO) award, and/or other applicable codes and standards.

1.4.2 Services will include, but are not limited to, developing of equipment installation engineering plans, providing hardware and software, providing system cybersecurity engineering and implementation, system testing and check-out, performing facility modification and minor construction required to support equipment installation, providing technical solutions that incorporate applicable force protection measures, interfacing with and installing new data transmission equipment, determining compatibility of new equipment with existing systems and integrating them, preparing system and component documentation, providing operation and maintenance manuals, providing training, warranting systems, maintaining and servicing systems, retro-commissioning systems, operating and monitoring systems, preparing after action and other reports, providing as-built installation drawings, system evaluations, configuring/programming systems, system administration systems, provide inspections/functional tests/recommendations on control systems, and other technical and programmatic support services.

1.5 Ordering Period. This effort will be accomplished via individual TOs awarded under multiple Indefinite Delivery/Indefinite Quantity (ID/IQ) contracts that have an ordering period of seven years (36 month base period and two, 24 months option periods). The Period of Performance (PoP) will be specified in each TO award.

1.6 Service Contract Labor Standards. TOs from this contract may be issued which are subject to Service Contract Labor Standards (see Revolutionary FAR Overhaul (RFO) 52.222-41). In the event that individual service task orders contain minor incidental work subject to the Construction Wage Rate Requirement (formerly known as the Davis-Bacon Act), Construction Wage Rate Requirements (RFO 52.222-6) will apply. The latest version of the wage determinations for the geographical areas in which the work is to be performed will be incorporated with the issuance of the TO solicitation. Wage determinations may also be found at www.wdol.gov. TOs with performance in foreign countries will not be subject to either Service Contract Labor Standards or Construction Wage Rate Requirements. For work overseas not subject to Service Contract Labor Standards and Construction Wage Rate Requirements, the contractor shall comply with local labor laws in accordance with Defense Federal Acquisition Regulation Supplement (DFARS) 252.222-7002, Compliance with Local Labor Laws (Overseas) (DEVIATION 2026-O0040). Additionally, Defense Base Act (DBA) insurance requirements will be included in TOs performed overseas, when required.

1.7 General Requirements

1.7.1 Quality Control Program (QCP). The Contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS. The Contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The Contractor’s QCP is how he assures himself that his work complies with the requirements of the contract. At a minimum, the contractor shall develop quality control procedures that address the areas identified in Appendix A, Performance Requirements Summary (PRS).

1.7.1.1 Corporate Quality Control and Surveillance Plan. Contractor shall develop, document, and implement an effective quality control and surveillance program for this contract and document in a plan. The QC Plan shall be submitted within 30 calendar days after MATOC award and shall include at a minimum the following documents:

Corporate QC Manager appointment letter, QC organizational structure (organization chart), inspection procedures, recordkeeping procedures, report templates, and any other information as required to describe the QC program. At a minimum, the Contractor shall follow an inspection process (e.g. three phase inspection process (preparatory, initial, and follow-up) or other Government approved inspection methodology) and include sample forms to be filled out for each definable feature at the TO level. After acceptance of the QC Plan, the Contractor shall submit any proposed changes to the Government, tracked through CMP/Quality Control System (QCS) for approval by the UMCS Program Manager or COR on the MATOC.

1.7.1.2 Site Specific Quality Control Plan and Surveillance Plan. A task/site specific quality control plan shall be developed/adapted to the services specified in individual TOs and submitted as required per TO. The site-specific QC Plan shall include the following documents at a minimum: The QC Manager appointment letter (include duties and authorities at a minimum), summary of inspection procedures to be followed, sample inspection forms (preparatory, initial, follow-up) or other Government approved inspection methodology forms, and the list of definable features of work that the inspections will be based off. The Government shall be provided a minimum of 48-hour notification (based on workdays), unless otherwise specified at the TO level, of any inspection meetings.

The Government is not required to be present but must be notified and given the opportunity to attend. It is the responsibility of the Contractor to maintain the inspection reports and to submit them to the Government via email within 5 days of completion. Additional details may be included at the TO level. After acceptance of the QC Plan, the Contractor shall submit any proposed changes to the Government, tracked through CMP/QCS for approval by the COR on the TO.

1.7.2 Quality Assurance (QA). The Government will evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP) and will include an evaluation of the Contractor’s http://www.wdol.gov/ performance. This plan is primarily focused on what the Government must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s). The Government may conduct QA inspections at any time on all phases and types of work performed. If any Government QA review identifies a process/work product failure or identifies noncompliance with safety practices, the Contractor will be issued a Corrective Action Request (CAR). Each CAR will be annotated as a critical nonconformance, major nonconformance, or minor nonconformance. Definitions and required contractor response times are:

* Critical Nonconformance: a nonconformance that is likely to result in hazardous or unsafe conditions for individuals using, maintaining, or depending upon the supplies or services, or is likely to prevent performance of a vital agency mission. Contractor is provided 24 hours (one business day) to provide written response to the CAR.

* Major Nonconformance: a nonconformance, other than critical, that is likely to result in failure of the supplies or services, or to materially reduce the usability of the supplies or services for their intended purpose. Contractor is provided 72 hours (three business days) to provide written response to the CAR.

* Minor Nonconformance: a nonconformance that is not likely to materially reduce the usability of the supplies or services for their intended purpose or is a departure from established standards having little bearing on the effective use or operation of the supplies or services. Contractor is provided up to 15 business days to provide written response to the CAR.

1.7.3 Government Remedies. The KO shall follow 52.246-4, “Inspection of Services-Fixed Price” for contractor’s failure to perform satisfactory services or failure to correct non-conforming services.

1.7.4 Place of Performance. The Contractor is responsible for performing the services required under this contract at the location as specified in the individual TOs. These UMCS services are required to support Department of Defense (DoD) installations or other Government facilities throughout the Continental United States, Alaska, Hawaii, and Outlying areas, as well as outside the Contiguous United States to include: Bahrain, Belgium, Brazil, Costa Rica, Ecuador, Gabon, Germany, Georgia, Greece, Haiti, India, Indonesia, Italy, Iraq, Jamaica, Japan, Kazakhstan, Kuwait, Malaysia, Mali, Montenegro, Norway, Poland, Republic of Korea, Romania, Saudi Arabia, Serbia, Suriname, Tanzania, United Arab Emirates, and United Kingdom where controls systems are installed.

Other foreign jurisdictions may be added to the geographic scope of the base MATOC contracts after preparing a Justification and Approval for an out-of-scope modification to add a country in accordance with RFO Part 6, Competition Requirements, for approval by the appropriate approving authority. This will include verification that all contractors within the MATOC award pool can comply with the applicable requirements for the country to be added.

Work performed by the Contractor may be subject to other requirements or restrictions such as those issued by a U.S. Department of Defense theater-level Unified Combatant Commander (COCOM), e.g., U.S. Central Command (CENTCOM) requirements, which are provided under this contract. .

Entry and exit requirements to countries within the CENTCOM AOR, including Iraq, are contained within DFARS 252.225-7995, Contractor Personnel Performing in the United States Central Command Area of Responsibility (DEVIATION 2017-O0004), available at https://www.acq.osd.mil/dpap/policy/policyvault/Class_Deviation_2017- O0004.pdf .

Predeployment training requirements for Contractor personnel deploying to Iraq (and other countries as applicable) will be specified at the task order level.

Access to bases and installations within Iraq (and other countries as applicable) will be subject to varying operational, security, and force protection conditions. The Contractor shall coordinate with the CENTCOM (or other COCOM as applicable) Liaison Officer (LNO) for the status of such conditions for the bases and installations of interest. Granting access to bases and installations within Iraq may take up to 30 calendar days following request or notification of intent to enter.

1.7.5 Type of Contract. TOs will be firm-fixed price.

https://www.acq.osd.mil/dpap/policy/policyvault/Class_Deviation_2017-O0004.pdf https://www.acq.osd.mil/dpap/policy/policyvault/Class_Deviation_2017-O0004.pdf

1.7.6 Security Requirements. This contract may require the handling and generation of classified information.

Security requirements appropriate for each TO will be delineated in the individual TOs. Some TOs issued may require a security level of SECRET and some may require a higher level than SECRET. The Contractor shall meet the Industrial Security requirements of the National Industrial Security Program Operating Manual (NISPOM) for Safeguarding Classified Information (DoD 5220.22-M), which is now Part 117 of Title 32, Code of Federal Regulations. The clearance level will be determined by the User Agency. A DD Form 254 (DD 254), Contract Security Classification Specification, shall be provided. No classified work is authorized without an approved DD 254 and the appropriate personnel and facility security clearance. Personnel security clearances will be obtained by the contractor in accordance with the NISPOM. Facility security clearances will be obtained by the User Agency Security Office.

1.7.6.1 Physical Security. Reserved

1.7.6.2 Information Security. The Contractor shall provide adequate security for all unclassified DoD information passing through non-DoD information systems including all subcontractor information systems utilized on contract.

Unclassified DoD information shall only be disseminated within the scope of assigned duties and with a clear expectation that confidentiality will be preserved. Examples of such information include the following: non-public information provided to the Contractor, information developed during the contract, and privileged contract information (for ex: program schedules, contract-related tracking). Below are safeguards the Contractor, and all subcontractors, shall abide by to protect Government information.

a) Do not process DoD information on public computers (e.g., those available for use by the public in kiosks or hotel business centers) or computers that do not have access control.

b) Protect information by at least one physical or electronic barrier (e.g., locked room, login and password) when not under direct individual control.

c) Sanitize media (e.g., overwrite) before external release or disposal.

d) Encrypt all information that has been identified as controlled unclassified information (CUI) when it is stored on mobile computing devices such as laptops and personal digital assistants, or removable storage media such as thumb drives and compact disks, using the best available encryption technology.

e) Limit information transfer to subcontractors or teaming partners with a need to know and commitment to at least the same level of protection.

f) Transmit email and similar communications using technology and processes that provide the best level of privacy available, given facilities, conditions, and environment.

g) Do not post DoD information to Web site pages that are publicly available or have access limited only by domain or Internet protocol restriction.

h) Provide protection against computer network intrusions and data exfiltration, minimally including the following: updated malware protection devices, prompt application of security-relevant software patches/service packs/hot fixes, and monitoring and control of inbound and outbound network traffic as appropriate.

i) Report loss or unauthorized disclosure of information in accordance with contract or agreement requirements and mechanisms.

j) The Contractor shall not release any information to the public without prior approval by the CEHNC Office of Public Affairs (i.e. trade publications and marketing information).

1.7.6.3 Site Specific Security Requirements. When Contractor personnel are at any Government site, installation or facility, they shall follow all security procedures and processes of the installation as stated and directed by the Government personnel at the site. The Contractor’s security requirements for work in foreign countries will be based on the requirements set by the combatant commander of the Area of Responsibility (AOR) in which the work will be performed. The items that will be covered on a TO basis will include but are not limited to transportation into and out of the operating area, required clothing and equipment, transportation security while moving in the operating area, specific employee training prior to entering the operating area, etc. All security requirements will be further detailed at the time of TO awards.

1.7.6.4 Information Technology Systems. For TOs requiring access to Government Information Technology (IT) Systems, but not to classified information, the following requirements apply:

1.7.6.4.1 All contractor employees who are U.S. citizens working under this contract who require access to IT systems (stand-alone computers, network computers/systems, e-mail, etc.) shall, at a minimum, be designated into an IT I, II or III position in accordance with Army Regulation (AR) 25-2, Army Cybersecurity. The investigative requirement for an IT I position is a favorable Single Scope Background Investigation (SSBI); IT II and IT III positions require a favorable National Agency Check and written Inquires (NACI).

1.7.6.4.2 A Common Access Card (CAC) is also required for access to Government IT systems. Proof of the appropriate investigative requirement/background check will be verified through the Joint Personnel Adjudication System (JPAS) by the CEHNC security personnel.

1.7.6.4.3 Non-U.S. Citizens. Foreign nationals who work on a Corps of Engineers' contract or TO in the United States shall be approved by the Headquarters U.S. Army Corps of Engineers (HQUSACE) Foreign Disclosure Officer before beginning work on the contract or TO. This approval requirement also includes subcontractor employees. The Contractor shall submit to the KO the names of all foreign nationals proposed for performance under this contract or individual TOs, along with documentation to verify that he or she is legally admitted into the United States and has authority to work. This information will be forwarded to the CEHNC Security Officer for approval.

1.7.7 Contractor Management Platform (CMP). The Contractor must be prepared to transition from the Resident Management System (RMS) to the new CMP at any time during the period of performance of this contract, once the USACE enterprise implements this change. The Government will use CMP for Windows to assist in its monitoring and administration of TOs. The Government will use the CMP to assist in its monitoring and administration of TOs.

The Contractor uses the Contractor Mode of CMP, to record, maintain, and submit various information throughout the contract period. The Contractor mode user manuals, updates, and training information can be downloaded from the CMP web site. The joint Government-Contractor use of CMP facilitates electronic exchange of information and overall management of TOs. CMP provides the means for the Contractor to input, track, and electronically share information with the Government in the following areas: Administration, Finances, Quality Control, Submittal Monitoring, Scheduling, and Import/Export of Data.

1.7.8 Safety Requirements

1.7.8.1 Corporate Safety and Health Program. The Contractor is required by regulation to develop and maintain a written Corporate Safety and Health Program (SHP) in compliance with the requirements of the Occupational Safety and Health Administration (OSHA), EM 385-1-1, 29 CFR 1910, 29 CFR 1926, 29 CFR 1960, and RFO 52.236-13.

1.7.8.2. All Safety submittals must be input into Construction Management Platform (CMP) and email sent to, at a minimum, the HNC PM, HNC Engineer, and UMCS Safety inbox (CEHNC-UMCS-Safety@usace.army.mil).

1.7.8.3. Site Visit Abbreviated Accident Prevention Plan (SVAAPP). A SVAPP is required if an Accident Prevention Plan with a site/survey activity hazard analysis (AHA) has not been previously provided and accepted by the CEHNC KO/COR in coordination with (ICW) CEHNC Safety and Occupational Health Office (SOHO). The SVAPP is necessary for any site visit where physical work will not be occurring. It shall be for visual inspection/observation or office type work only. The SVAAPP shall be approved prior to the Contractor performing any surveys on-site. An example of an SVAAPP can be obtained by contacting the CEHNC Safety Office.

SVAAPP’s shall be submitted electronically to the CEHNC Safety Office and Project Manager (Adobe PDF format) and uploaded to CMP for acceptance. Submission or acceptance requirements may be updated at the TO level.

1.7.8.4. Accident Prevention Plan (APP). The Contractor shall submit a site-specific prior to any installation/maintenance activities beginning at the site. The APP shall follow the minimum requirements of the 2024 version of Engineering Manual (EM) 385-1-1, Safety and Health Requirements Manual, Chapters 2-7 and submitted on the mandatory ENG Form 6293 (Accident Prevention Plan Worksheet). The Contractor shall coordinate with the facility representatives or facility contractor, on first aid, emergency phone numbers & response plans, site evacuation plans, lock out tag out procedures, any permit required procedures, obtaining a list of previously identified confined spaces, evacuation drills, hazardous/toxic environments/agents etc. This information shall be included in the APP. The APP shall also include site specific AHAs for the project. The APP must be submitted and accepted by the CEHNC KO/COR ICW CEHNC SOHO prior to starting any service/construction work at the site. It should be readily available to all tiers of contractors (and their employees) on the jobsite. Safety submittals shall be written ICW the subcontractor when applicable; however, the prime contractor must review, concur, and ensure submittals meet EM 385-1-1 requirements PRIOR to uploading into CMP. Safety resubmittals shall include the original comments with detailed responses and highlight all changes in the resubmission. The APP shall be approved prior to the Contractor mobilizing on-site to perform work. Submission or acceptance requirements may be updated at the TO level.

1.7.8.5. Addendums to the APP - The Contractor is responsible to verify that any Proposals, Service Orders, Change Orders, and Contract Modifications are covered under the current accepted APP. If the pending work effort is NOT covered under the initial task order APP, the contractor shall submit, for Government review and acceptance, an addendum to the APP.

1.7.8.6. Activity Hazard Analysis (AHA) - Before beginning each activity, task or Definable Feature of Work (DFOW) involving a type of work presenting hazards not experienced in previous project operations, or where a new work crew or subcontractor is to perform the work, the Contractor(s) performing that work activity must prepare an AHA. AHAs shall be provided to the Prime Contractor for review and approval before submitting into CMP for review and acceptance by USACE. The Prime Contractor shall review the accepted AHAs periodically (at least annually in conjunction with an APP review) and update as necessary when procedures, scheduling, or hazards change.

1.7.9. Safety Officials

1.7.9.1. Prime Contractor Corporate Safety Official. This contract requires a minimum of one Corporate Safety Official to manage and oversee the implementation of the Prime Contractor’s Safety Program. The Corporate Safety Official shall follow the roles and responsibilities listed in EM 385-1-1 (2024) Chapter 2-4.f. This individual is not required to physically be on the project site.

1.7.9.2. Site and Safety Health Officer (SSHO). No work shall be conducted onsite unless a SSHO is present as described and EM 385-1-1 (2024) Chapter 2-8.b. SSHOs shall be designated on the required ENG Form 6282 found in Chapter 2 of EM 385-1-1. High risk activities require a L1 SSHO. L1/L2 SSHOs are allowed to dual hat with a competent person other than the project manager/onsite manager. He/She cannot manage non-safety individuals on the jobsite. Triple hatting is not allowed. L3s can be a subcontractor dual-hat employee if it is explained in the APP how the prime contractor will exhibit stringent direction and control over the L3’s and overall jobsite safety.

1.7.9.3. SSHO Coverage on projects is determined by the type of work that is occurring. Please refer to the SSHO Chart in the task order level PWS for the minimum acceptable SSHO coverage for UMCS work. If an activity is not listed, it is the prime contractor’s responsibility to ensure that SSHO coverage is adequate for the activities occurring onsite. During high-risk activities, the functions and roles of the L1SSHO shall be a singular, full-time responsibility (no other collateral duties). Such activities include, but are not limited to: crane operations, excavations greater than 5-feet, permit required confined space entry, asbestos/lead abatement, and any other high hazard activity listed in the PWS for each task order. The Contractor must demonstrate that the L1SSHOs non-safety duties are transferred to another employee when full-time SSHO responsibilities are warranted per the risk activities. The SSHO must be at the location of the high hazard activities while they are being conducted.

1.7.10. Exposure Hour and Mishap Reporting

1.7.10.1. Exposure Hour Reporting (Monthly Man-hour reporting) - In accordance with EM 385-1-1, the Contractor shall complete a monthly summary report of accident experience, exposure, Restricted Duty (RD) and Lost Workdays (LWD) prior to the 10th of the following month. Exposure data consists of man-hours (prime and subcontractors) expended in direct performance of the work performed on the jobsite. Hours associated with administrative activities such as payroll, human resource, service order managers, etc., are not counted. The information cut-off date will be the last day of each month. If no hours are worked on the project/task, a report showing zero (0) is required.

1.7.10.2. Mishap Reporting – Mishaps shall be reported in accordance with the EM 385-1, 2-8(d) and Table 2-1.

The Huntsville Center Contracting Officer, Project Manager and Safety Office shall be notified as soon as practical, but no more than twenty-four hours, after any mishaps, including recordable accidents, incidents, and near misses.

All mishap notifications will be submitted in accordance with the task order.

1.7.10.3. Post Award Conference/Periodic Progress Meetings. The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office. The KO, Contracting Officers Representative (COR), and other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance. At these meetings the Government will apprise the Contractor of how the Government views the contractor's performance and the Contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the Government.

1.7.10.4. Program Manager. The Contractor shall provide a program manager who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the contractor when the manager is absent shall be designated in writing to the KO. The program manager or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract.

1.7.10.5. Identification of Contractor Employees. All contract personnel attending meetings and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials. They must also ensure that all documents or reports produced by contractors are suitably marked as contractor products or that contractor participation is appropriately disclosed.

1.7.11 Travel

1.7.11.1 Locations: In support of various tasks and specified on TOs, the Contractor shall be required to travel to DoD facilities located worldwide. Travel shall be performed in accordance with RFO 31.205-46.

1.7.11.2 Travel Outside the Continental United States Immunization Requirements: As specified in each TO, the Contractor shall be required to travel to locations both shore and afloat. Contractor employees who deploy to locations that require immunizations shall do so in accordance with DoD Foreign Clearance Guide or other agreements that the United States may have with the country.

1.7.11.3 Letter of Authorization. Some travel shall require a Letter of Authorization (LOA). As noted in DFARS 225.771-3(e), a LOA is necessary to enable a contractor employee to process through a deployment processing center; to travel to, from, and within a theater of operations; and to identify any additional authorizations and privileges. As required by TO, the Contractor shall initiate a LOA for each prospective traveler. If required at the TO level, the Contractor shall use the Synchronized Pre-deployment & Operational Tracker (SPOT) web-based system to enter and maintain data with respect to traveling/deployed personnel, and to generate LOAs.

If it is in the Government’s interest, the Contractor may also initiate a LOA request to provide an official traveler access to Government facilities and to take advantage of travel discount rates in accordance with Government contracts and/or agreements. All privileges, services, and travel rate discount access are subject to availability and vendor acceptance. LOAs shall be signed/approved by the Contracting Officer for the TO who is registered in the SPOT system.

1.7.12. Base Contract Submittals. The Contractor shall submit the following documents (following format in the table below), tracked through CMP/QCS within thirty (30) days of base contract award to the UMCS Program Manager. The documents shall be submitted under TO #0001, minimum obligation. After approval, all proposed changes by the Contractor shall be submitted under TO #0001

Submittals Tracked in

CMP/QCS

Form

Required

CD/DVD

E-mail

PgM Safety Office

Corporate Safety and Health Program Yes Yes √ √ √ Corporate Quality Control and Surveillance Plan Yes Yes √ Corporate Management Plan Yes Yes √ Unless otherwise specified, all report formats shall be Microsoft Office (Word and Excel) and /or Adobe PDF

PART 2

DEFINITIONS & ACRONYMS

A&A – Assess and Authorize

AAPP – Abbreviated Accident Prevention Plan

ACA – Agent for the Certification Authority

ACE-IT – Army Corps of Engineers Information Technology

AHA – Activity Hazard Analysis

AO – Authorizing Official

AODR – Authorizing Official Designated Representative

AOR – Area of Responsibility

APMS – Army Portfolio Management System

APP – Accident Prevention Plan

AR – Army Regulation

ATC – Authority to Connect

ATO – Authority to Operate

C&A – Certification and Accreditation

CAC – Common Access Card

CAL – Category Assurance List

CAR – Corrective Action Request

CAT - Category

CBT – Computer Based Training

CDRL – Contract Data Requirements List

CIA – Confidentiality, Integrity and Availability

CIO – Chief Information Officer

CM – Corrective Maintenance

CMP – Construction Management Platform

CND – Computer Network Defense

COB – Close of Business

COR – Contracting Officer Representative

CPAR – Contractor Performance Assessment Reporting System

CR – Cost Reimbursement

CS – Control Systems

CUI – Controlled Unclassified Information

CEHNC – U.S. Army Corps of Engineers, Engineering and Support Center, Huntsville

DA – Department of the Army

DBA – Defense Base Act

DFARS – Defense Federal Acquisition Regulation Supplement

DHS – Department of Homeland Security

DID – Data Item Description

DISA – Defense Information Systems Assurance

DoD – Department of Defense

DoDD – Department of Defense Directives

DoDI – Department of Defense Instructions

DDC – Direct Digital Controls

EM – Engineering Manual eMASS – Enterprise Mission Assurance Support Service

ER – Engineering Regulation

ESS - Electronic Security System

FAS - Fire Alarm System

FRCS- Facility Related Control Systems

FSC –Federal Service Code

GDA – Government Designated Authority

HVAC – Heating, Ventilation, and Air Conditioning

HQUSACE – Headquarters, U.S. Army Corps of Engineers

IA – Information Assurance

IAM – Information Assurance Manager

IASAE – Information Assurance System Architect and Engineer

IAT – Information Assurance Technical

IAVA – Information Assurance Vulnerability Alerts

IAVM - Information Assurance Vulnerability Management

IAW – In Accordance With

ID/IQ – Indefinite Delivery / Indefinite Quantity

IO – Information Owner

ISO – Information System Owner

ISSM – Information System Security Manager

ISSO – Information System Security Officer

IT – Information Technology

JPAS – Joint Personnel Adjudication System

JTR – Joint Travel Regulations

KO – Contracting Officer

LHE – Load Handling Equipment

LOA – Letter of Authorization

LWD – Lost Workday

M&S – Maintenance and Service

MATOC – Multiple Award Task Order Contract

NACLC – National Agency Check with Law and Credit

NEC – Network Enterprise Center

NISPOM – National Industrial Security Program Operating Manual

NIST – National Institute of Standards and Technology

O&A – Over and Above

O&M – Operation and Maintenance

OEM – Original Equipment Manufacturer

OND – Operational Need Date

OO – Ordering Officer

OSHA - Occupational Safety and Health Administration

P&I – Procurement and Installation

PAC – Package Approval Chain

PIT – Platform IT

PGI – Procedures, Guidance and Information

PgM – Program Manager

POA&M – Plan of Actions and Milestones

PM – Preventive Maintenance

PoP – Period of Performance

PPS – Ports, Protocols, and Services

PRS – Performance Requirement Summary

PVT – Performance Verification Test

PWS – Performance Work Statement QA - Quality Assurance

QASP – Quality Assurance Surveillance Plan

QC - Quality Control

QCP – Quality Control Program

QCS – Quality Control System

RD - Restricted Duty

RFO – Revolutionary FAR Overhaul

RFP – Request for Proposal

RMF – Risk Management Framework

RMS – Resident Management System

SAP – Security Authorization Package

SCA – Security Control Assessor

SCA-R – Security Control Assessor Representative

SCADA - Supervisory Control and Data Acquisition Systems

SHP – Safety Health Program

SISO – Senior Information Security Officer

SO – Service Order

SSBI – Single Scope Background Investigation

SPOT – Synchronized Pre-Deployment & Operational Tracker

SSHO – Site Safety Health Officer

STIG – Security Technical Implementation Guides

TO – Task Order

UC APL – Unified Capabilities Approved Products List

UFC – Unified Facilities Criteria

UFGS – Unified Facilities Guide Specification

UIC – Unit Identification Code

UMCS - Utility Monitoring and Control System

UR – User Representative

USACE – United States Army Corps of Engineers

PART 3

GOVERNMENT PROPERTY AND SERVICES

RESERVED

PART 4

CONTRACTOR FURNISHED ITEMS AND SERVICES

4.1 General: The Contractor shall furnish all labor, supervision, travel, equipment and materials as required to perform the work under the individual TO PWS.

4.2 Reserve.

4.3 Security Clearances: Security requirements appropriate for each TO will be delineated in the individual TOs.

The Contractor shall have or be capable of obtaining a facility clearance through SECRET. All key personnel designated shall have or be able to obtain a security clearance of SECRET. The Contractor shall comply with the security requirements of the Department of Defense Contract Security Classification Specification, DD Form 254.

PART 5

SPECIFIC TASKS

5.1 Basic Services. The following requirements and deliverables will be required under the base contract and shall therefore be applied to subsequent TOs. Additional requirements described in each TO, once awarded, may complement, emphasize, or add to any requirements or processes mentioned in this paragraph. The Government reserves the right to expand the requirements of any TO so long as the requirement does not force the Contractor to perform outside the scope of what would be considered reasonably within the bounds of this contract. Each TO will identify the nature and scope of the work required.

5.1.1 Contractor shall participate in a post-award orientation conference at the site prior to installation work. The work will be associated with P&I of and/or the M&S of FRCS including but not limited to: UMCS, HVAC systems installation and/or integration, SCADA systems, FAS, life safety systems, other automated control systems including chemical / biological / radiological contaminant detection / filtration / response, utilities (electric/ gas/ water/ steam) metering, ESS, and security and/or force protection measures such as, but not limited to, barriers, fencing, gates, window treatments, hardening, and lighting. HVAC systems may include central plant equipment and systems (e.g., chillers, boilers, cooling towers), distribution systems (e.g., duct work, chilled water piping, hot water piping, drain piping), and unitary heating and cooling equipment (e.g., unitary heat pumps, unitary air conditioners). The work may include design of systems (such as defined above) and will be further clarified in each

TO.

5.2 Specific task areas or functions to be performed at the TO level are listed below. All tasks are to be performed in accordance with criteria, specifications, drawings, original manufacturer’s published procedures (if applicable), and Contract Data Requirements List (CDRL), Form DD 1423 (See Section J, Exhibits C, D, E, & F). As applicable to specific tasks, the Contractor shall:

5.2.1 Participate in a post-award orientation meeting at the site prior to commencing work. Provide a QCP, a Project Schedule and an APP.

5.2.2 Perform an existing site conditions survey to validate the quantities of system equipment and verify existing site conditions. Provide a written report noting all identified discrepancies.

5.2.3 Perform engineering surveys or assessments to develop or verify design drawings and equipment lists. Provide a report identifying equipment incompatibility concerns between the existing and new systems.

5.2.4 Prepare and provide mechanical equipment installation engineering plans.

5.2.5 Prepare and provide electronic equipment installation engineering drawings to include drawings related to installation and assembly of the computers, field equipment panels, data transmission equipment, interfaces, instrumentation and all other equipment.

5.2.6 Prepare and provide system installation engineering drawings, instrumentation installation drawings, wiring diagrams, procedures for field installation of all equipment, and system testing procedures, as defined in UFC 3-470- 01 and UFC 3-410-02, or latest Corps of Engineers technical guidance.

5.2.7 Provide Mechanical Equipment. Install equipment IAW original manufacturer’s published procedures and documentation and as required by the specifications.

5.2.8 Provide Hardware and Software. Install hardware and software IAW original software developer’s published procedures and documentation and as required by the specifications. Resolve compatibility issues and establish an interface between existing and new systems. All software and software updates shall be approved by the Government prior to installation. Provide graphics for the system IAW criteria and specifications using data from drawings, engineering surveys and manufacturer’s data.

5.2.9 Perform factory testing, Performance Verification Testing (PVT), endurance testing, and commissioning IAW the applicable and referenced sections of criteria and specifications in this TO. For PVT and at his/her sole discretion, the KO may require consideration from the contractor equivalent to reimbursing the cost of the Project Engineer and/or other Government PVT witness (including, but not limited to the labor and travel of personnel conducting the subsequent PVT reassessment) in the form of a credit to the contract price if the contractor does not pass the initial PVT attempt.

5.2.10 Perform minor ancillary work required to support equipment installation.

5.2.11 Provide all data transmission equipment IAW specifications, drawings and manufacturer’s published documentation. Install in compliance with Network Enterprise Center (NEC) or its equivalent authority, Department of Defense (DOD) and Component Specific applicable certification and accreditation requirements, policies and procedures.

5.2.12 Interface to all existing data transmission equipment IAW specifications, drawings and manufacturer’s published documentation. Comply with all requirements of the DOD, Component, NEC, or its equivalent authority related to interfacing with the existing communication system. Provide technical data, equipment and software in compliance with Cybersecurity policy and requirements.

5.2.13 Provide all required Operation and Maintenance (O&M) Manuals.

5.2.14 Provide training as required by the applicable sections of the specifications listed in Section H, Exhibit F.

5.2.15 Provide a System Warranty. Provide an unconditional (excluding acts of God and negligence of Government personnel), one-year parts and labor warranty from time of Government acceptance (i.e. successful PVT) for the new components of the entire system: mechanical equipment, ancillary components, subsystems, data transmission system, and all Contractor furnished software.

5.2.16 Provide after-action reports, accident reports, minutes of each meeting, confirmation notices of communications, field inspection reports, calibration reports, and installation progress reports. Copies shall be furnished to the Government within 5 working days or sooner, if required, after each specific action.

5.2.17 Provide final As-Built Drawings. All drawings shall be generated in electronic media compatible with the latest version of Microstation, AutoCAD, or as defined in individual TOs. Drawings shall be delivered within 30 calendar days after the written acceptance of the system by the Government.

5.2.18 Provide software licensing and configuration tools related to UMCS, ESS, SCADA, other control and monitoring systems and HVAC systems as further clarified by individual TO.

5.2.19 Perform special engineering services and studies related to UMCS, ESS, SCADA, other control and monitoring systems and HVAC systems as further clarified by individual TO.

5.2.20 Provide all M&S and/or operation of systems as specified.

5.2.21 Comply with Cybersecurity Requirements. Prepare and provide system cybersecurity design deliverables, specifications, and construction submittals/technical artifacts as defined in UFC 4-010-06, UFGS 25-05-11, and / or latest Corps of Engineers, DoD, and / or Federal agency technical guidance. Provide system, security, and network engineering services, RMF (Risk Management Framework) process services, project specifications, and deliverables to support system owner required cybersecurity activities to obtain operational, accreditation, and / or connection approvals. Provide cybersecurity maintenance services, vulnerability identification and mitigation, and continuous monitoring services required to maintain secure baselines and accreditations. Cybersecurity requirements will be further clarified by individual Task Order level Performance Work Statements.

5.3 TO Requirements

5.3.1 The Contractor shall perform the work under individual TOs. Each TO will identify the specific work to be performed. Individual TOs may add additional technical requirements as necessary to define the work, including Specifications, Technical Manuals, Engineer Instructions, and EMs. The performance period will be negotiated and determined for each individual TO. Contractor shall prepare and submit a detailed project schedule in Primavera (unless otherwise specified at the TO level) that shows an appropriate breakout of activities and includes any key milestones that may be stated in individual TOs. Contractor shall submit a technical solution meeting all the requirements in the PWS, including sufficient detail for the Government to evaluate the Contractor’s technical solution versus the requirements in Adobe PDF format. The Contractor shall submit cost and pricing data associated with the technical solution, to include labor rates, markups, material costs, and detailed subcontractor pricing in an unlocked MS Excel format (cost narratives may be submitted in Adobe PDF format). Cost and pricing data details shall be in enough detail to substantiate any proposed costs, and so that the Government can determine whether the pricing proposed is fair and reasonable.

5.3.2 Awards will be determined based on best value to the Government unless stated otherwise in the Request for Proposal (RFP).

5.4 Information Support and Documentation.

5.4.1 All required technical information, and data shall be delivered in accordance with the requirements, quantities, and schedules set forth in Section J, Exhibit C, CDRL DD Form 1423, Data Item Description (DID) DD Form 1664, or as otherwise specified or required. The requirements for contents and detail of operation and maintenance manuals, testing documentation (including level and detail) shall be as described in applicable UFGS and shall be further clarified in the individual TO PWS.

5.4.2 Contractor shall be responsible for preparing after-action and other reports to include progress reports, minutes of all meetings, confirmation notice for telephone calls, field inspection reports, calibration reports and installation reports. Copies of all such documents shall be furnished, within five working days, to the points of contact identified in the TO after each specific action. Project status shall be formally reported monthly.

5.5 Continuation and Completion of Work.

5.5.1 The Contractor shall conduct all work under the direction of a COR appointed by the KO. This representative shall be responsible for the coordination of all work under each individual TO. The Contractor’s company officer or representative designated as Program Manager shall be responsible for the complete coordination of all work under this contract. All work shall be accomplished in accordance with the contractor’s approved QC Plan. The Government may elect to provide third party technical inspection.

5.5.2 Warranty: The systems, all its components, subsystems, data transmission system, and all Contractor-furnished software shall be covered by warranty. The Contractor shall warrant all products and services provided under each TO (material and labor) for a period of one year from the date of Government acceptance (i.e. successful PVT), or the offeror's standard commercial warranty period, whichever is greater. The Contractor shall provide the necessary support required to maintain the warranty. Upon any product/service failure during the warranty period, Contractor’s response time to restore system service shall be within the timeframes indicated herein. “Mission Critical Outages” will require a maximum of 4-hour response time during normal working hours and maximum of 16-hour response time for after hours (defined as outside “normal” 0700-1600 working hours) and one (1) day to restore system operation. All other outages will require a maximum of three (3) working days response time and seven (7) working days to restore system operation. System outages assessed as “Mission Critical” will be at the discretion of the KO or COR.

5.5.3 Contractor’s warranty letter shall be submitted after successful completion of PVT. Warranty letter shall indicate at a minimum: standard project warranty dates and points of contact, equipment warranties and points of contact, list of equipment (make/model/serial number of equipment) with Original Equipment Manufacturer (OEM) warranties that extend beyond the project warranty…