Q A - Government Responses

View the file

Other files

File Type Posted
Attachment_1_-_TV_Locations_4-6-16_Rev2.xlsx XLSX spreadsheet
Q A_2__W912DY-16-T-0105.pdf PDF
W912DY-16-T-0105-05.pdf PDF
W912DY-16-T-0105-04.pdf PDF
TV_Floor_Plans.pdf PDF
W912DY-16-T-0105-03.pdf PDF
Attachment_1_-_TV_Locations_3-31-16_Rev2.xlsx XLSX spreadsheet
A07.23_W912DY16T0105-02.pdf PDF
W912DY16T0105-01.pdf PDF
Attachment_1_-_TV_Locations_3-02-16(2).xlsx XLSX spreadsheet
W912DY16T0105.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

W912DY-16-T-0105
RFP Q&A
QUESTIONGOVERNMENT RESPONSEPWS/REF
1Please clarify totals in the TV Locations spreadsheetPlease see revised Attachment 1Revised Attachment 1
2Are the working hours only between 6PM - 6AM when the work starts for the project or can you work between regular business hours 8AM - 5PM?Working hours are only between 6PM and 6AM.Revised PWS 3.0
3Identify data room numbersPlease see the "TV Floor Plans.pdf" in amendment 3 of the solicitationTV Floor Plans.pdf
4Disseminate TV Locations spreadsheet and plan view schematics of first floor main building, second floor main building, third floor main building, Suite 4, Suite 6, and USACE Learning Center (ULC) where installation is to commencePlease see the "TV Floor Plans.pdf" in amendment 3 of the solicitationTV Floor Plans.pdf
5Verify that fire retardant cabling is not requiredFire retardant cabling is not required
6Identify electrical closets/room numbersPlease see the "TV Floor Plans.pdf" in amendment 3 of the solicitationTV Floor Plans.pdf
7Specify articulating mounts for monitorsTV/monitor mounts shall allow units to be viewed by the intended audience and all shall be articulating for flexibility of viewing position.This will vary with location.Revised PWS 2.1.6
8Provide make/model and quantity of all monitors to ensure wall mount compatibilityPlease see revised Attachment 1.Revised Attachment 1
9Specify electrical outlets should be behind monitors, not beside themIntent is for the outlets and cabling to be out of sight as much as physically possible.See 2.1.6 of Revised PWS.
10Verify if flex conduit/cabling should be usedAll electrical work shall be in accordance NFPA 70.See 2.1.12 of Revised PWS
11Confirm that cabling shall not be installed within six (6) feet of area 2GXXX on the main building second floorConfirmed. This includes above and below.See 2.1.2 of Revised PWS.
12Will the floor plans be added to the RFP?Yes. Please see the "TV Floor Plans.pdf" in Amendment 3 of the solicitationTV Floor Plans.pdf
13Please clarify the number of additional monitors needed and brand4 Additional monitors are needed; 3 - 48" and 1 - 65". All existing monitors are "Samsung". Please see revised Attachment 1.Revised Attachment 1
14Can the QC Manager also act as the Site Safety Officer for the project?Yes
15Item No. 3 states that Manpower Reporting Data will need to be provided by the GC. We need to know if this can be a manual (4296) Daily Report or if the data needs to be entered into the QCS(RMS) System?CONTRACTOR MANPOWER REPORTING. "The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the USCE - Huntsville Engineering and Support Center via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: http://www.ecmra.mil/See Revised PWS and solicitation CLIN 3
16Is this a service contract or construction?This solicitation was drafted on a 1449, Service Contract
17Are we required to turn in certified payrollsNo
18Can you provide me with more info on what you are looking for in the “Accident Prevention Plan” as referenced on page 5 of the solicitation?Contractor shall execute all work IAW the latest version of the US Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1. http://www.usace.army.mil/SafetyandOccupationalHealth/SafetyandHealthRequirementsManual.aspxSee 7.0 in revised PWS
19Please clarify the required delivery time. How many days after receipt of order?45 days from date of award.See 3.0 in revised PWS
20Can you provide us with a copy of the pertinent “wage determination”?SCA Wage determination is included in this amendmentAdded with Solicitation Amendment 3
21Will this be a “construction” or service contractThis solicitation was drafted on a 1449, Service Contract
22Several sentences in para 2.1.2 (pg 4) are vague or not very clear as it would pertain to this project. For clarification purposes – please state if the cables need to be PLENUM rated OR NON-PLENUM rated.As stated in the PWS you must follow NFPA 70. All local, state and federal electric codes will be followed.
23Again, referencing para 2.1.2, it calls for ALL cabling within walls to be in conduit. This is NOT standard practice in the AV nor network cabling industries. There is no real need to install AV and/or network cabling within conduit. This only serves to drive up the costThis is for the physical protection of the cables. Installation of various objects on walls have damaged cables previously in this building. This is user's request and only for within walls.
24Again referencing para 2.1.2, it specifies “All’ connectors shall be gold plated’. Please clarify that this is for the network and AV (minus CATV) cabling/connectors and NOT the electrical or CATV connectorsAll cabling within walls shall be in metal conduit.
25Please provide more information on requirements for power surge protection at each TV location (ref para 2.1.6).Minimum requirements are 2 power recptacles, 600 joules. If a power strip is provided it should be mounted behind the TV, out of sight, like the outlets. 60 additional surge protectors are to be provided.
26What are the 60 extra surge protectors…power strips?Strips or individual protectors. At least 2 power receptacles, 600 joules protection.PWS 2.1.6
27Please verify that we can run ac power from any existing non-switched ac power outlet or source, to the new power outlets for the TVsYes, you can run to nonswitched 120 V power source if per code.
28Please provide the make and model info for the GFE TVs so that we can match the 5 TVs we are furnishing to what you have4 Additional monitors are needed; 3 - 48" and 1 - 65". All existing monitors are "Samsung". Please see revised Attachment 1.Revised Attachment 1
29In case of discrepancy as to quantities of the items required – ALL of which are provided on one spreadsheet, WHICH number should prevail?Please see the revised Attachment 1Revised Attachment 1
30Please clarify if the new TV mount are to be STAIONARY, TILT or ARTICULATINGTV/monitor mounts shall allow units to be viewed by the intended audience and all shall be articulating for flexibility of viewing position.This will vary with location.Revised PWS 2.1.6