This document is a government-issued presentation providing an overview of the Duckabush Estuary Restoration project, a civil works project led by the U.S. Army Corps of Engineers (USACE) and the Washington State Department of Transportation (WSDOT).
The project aims to restore the natural function of the Duckabush Estuary through actions such as removing or modifying existing features to reconnect the Duckabush River with adjacent floodplains and wetlands. Key project components include constructing an elevated 1,613-foot bridge along U.S. Highway 101, replacing two culverts, demolishing existing highway infrastructure, excavating channels, and placing engineered log jams. The project is estimated to cost between $100-$250 million and have a duration of 1,050 calendar days. It will be procured as a competitive, firm-fixed-price design-bid-build contract under FAR Parts 15 and 36. The government is seeking experienced sources, with small business participation encouraged. The solicitation is anticipated in Q1 FY2026, with award in Q3 FY2026.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DUCKABUSH ECOSYSTEM
RESTORATION
INDUSTRY DAY
PROJECT OVERVIEW
U.S. Army Corps of Engineers (USACE) Seattle District
Washington Department of Fish and Wildlife
(WDFW)
Washington State Department of Transportation (WSDOT)
October 9, 2024
2CUI
CUI
Introduction
Scope of the Project
Contracting Discussion
Technical Presentation
Question and Answer Session
AGENDA
Please note that this information is being provided as part of Market Research for this project. No reimbursement will be provided by the Government for participation at today’s industry day or for preparation of any responses to questions posed to industry.
3CUI
The Duckabush River Estuary is located in Jefferson County at approximately Mile 310 of U.S. Highway 101, near Brinnon Washington.
DUCKABUSH ECOSYSTEM RESTORATION
4CUI
PROJECT PURPOSE AND NEED
Puget Sound Nearshore Ecosystem Restoration study authorized in 2016 for implementation
To restore the natural function of the Duckabush Estuary so that it can create and maintain estuarine habitat in a self-sustaining manner.
This is to be accomplished by removing or modifying existing features so that natural habitat forming processes can be restored.
This project will reconnect the Duckabush River with adjacent floodplains and wetlands by removing existing roadway fill.
5CUI
Improved tidal wetland habitat for fish and wildlife, including Hood Canal summer chum and Chinook salmon, a main food source for endangered Southern Resident Killer Whales.
Reduced backwater flooding.
Improved water quality resulting from increased wetland area for natural water filtration and new road run-off treatment areas.
Modernized road and utility infrastructure resulting in improved resiliency to climate change and natural disasters.
Creation of approximately 1,300 jobs throughout construction of the project.
Increased habitat connectivity and reduced wildlife-vehicle collisions by creating a wildlife corridor under U.S. Highway 101.
PROJECT BENEFITS
6CUI
Contract: Duckabush Ecosystem Restoration located at Duckabush Estuary, Brinnon, Washington
Site: Located at Duckabush Estuary
Project Features:
1. Replace Highway with Elevated Bridge
2. Replace Two Culverts
3. Demolish Highway 101
4. Demolish Training Berms
5. Demolish Timber Piles
6. Demolish Remnant Roadbed
7. Excavate Six Channels
8. Two Parking Areas
9. Engineered Log Jams 10.Three Access Paths
Tentative Schedule
• Solicitation: Q1 FY2026
• Award: Q3 FY2026
SCOPE: DESIGN-BID-BUILD CONTRACT
7CUI
Competitive, firm-fixed-price type contract to be procured in accordance with the Federal Acquisition Regulation (FAR) Part 36 (Construction and Architect-Engineer Contracts) and FAR Part 15 (Contracting by Negotiation), using the Tradeoff process.
Estimated construction price range for this project is between $100M and $250M.
Estimated duration of the project is 1050 calendar days from issuance of the Notice to Proceed.
Proposals will be evaluated based on source selection criteria the technical team has deemed relevant and important for confidence in success of the contract. The proposal deemed best value to the government will be selected (not lowest price, technically acceptable).
CONTRACTING PROCESS
8CUI
General Advice:
• Get engaged, EARLY o Understand anticipated SB involvement
a. Small Business Commitment Document
b. Subcontracting Plan – USACE goals are based on historical data, market info o Utilize SAM.gov and FPDS for subcontracting opportunities
• Build relationships, NOW o SBA SubNet – https://subnet.sba.gov/client/dsp_Landing.cfm o FPDS - https://www.fpds.gov/fpdsng_cms/index.php/en/ o Request agency info on recent awards with a subcontracting plan o Request assistance to source SBs (utilize your APEX Accelerators)
• Understand other than small contractor responsibilities under FAR 52.219-9 o Good Faith Efforts (FAR 19.705-7) o eSRS reporting requirements
USACE NWS OFFICE OF SMALL BUSINESS PROGRAMS
9CUI
Construction of an elevated roadway for U.S. Highway 101 (U.S.101) on a 1,613-foot long 36-foot-wide bridge upstream from the existing highway.
Lane width: 12 feet, Shoulder width: 5 feet, 7 Piers, 2 Columns, Longest span: 228 ft, Concrete Spliced
Girder Construction of a new Duckabush Road intersection with left turn lane from northbound U.S.101 to
Duckabush Road.
Replacement of Unnamed tributary crossing with box culvert.
Replacement of Petitjean Creek crossing (north of the new widespan bridge) with a new 81-foot long, 42-foot 10-inch wide bridge.
Removal of 1,700 feet of the U.S.101 causeway and two bridges across the estuary.
Removal of training berms, remnant piles, and roadbed along the Duckabush River.
Excavation of channels at or near their historical configurations.
Construction of parking lots and estuary access trails at each end of the U.S.101 bridge.
Placement of project-generated woody material (engineered logjams and anchored large wood structures).
PROJECT FEATURES
10CUI
PROJECT PLAN OVERVIEW – WSDOT VOLUMES
Culvert Replacement Petitjean Creek Bridge Replacing existing culvert
Proposed Bridge
Existing Alignment
Realignment of Duckabush Rd
New Roadway Approach to Estuary Bridge
Design graphic is preliminary.
South Parking Lot
11CUI
PROJECT PLAN OVERVIEW – USACE VOLUMES
Unique project integration of
USACE/WSDOT design 3 drawing volumes UFGS specs refer to WSDOT standard
12CUI
STAGING AND ACCESS
Staging area: existing south parking lot Construction trailer area TBD Project includes construction of temporary work platforms (next slide) Phase 1 of utility relocation ongoing now, complete prior to advertisement U.S.101: Traffic Flow maintained throughout construction. Reduced speed limits and short duration closures permitted.
Tribal tideland access will be permitted with a shuttle service during construction to a temp parking platform along existing U.S.101
13CUI
BRIDGE TEMPORARY WORK PLATFORMS
14CUI
BRIDGE TEMPORARY WORK PLATFORMS
Temporary work platforms have been preliminarily designed for installation along the existing alignment to stage construction equipment Contractor-designed for final design To be constructed at an elevation of 14.5 to accommodate 100 year flood conditions Work platforms will be removed at the conclusion of the project
15CUI
BRIDGE TEMPORARY WORK AREA
16CUI
ESTUARY BRIDGE
Precast post-tensioned concrete splice girder Epoxy coating on all reinforcement 135 ft longest span length for a girder, 1,613 ft long for the overall bridge Bridge elevation Historic Bridge
17CUI
South U.S. 101: Unnamed Tributary existing culvert
High Tide Imagery @12.8’ MLLW tide (10.18’ NAVD88)
18CUI
UNNAMED TRIB: SPLIT BOX BURIED STRUCTURE
On the south end of the project, an existing culvert needs to be removed and replaced with a split box buried structure per WSDOT Std Plan E-20.10-00
Buried structure has a span length of 43 ft, design span of 19 ft, and a design height of
18.7 ft. The structure has wing walls up and downstream of the culvert down to 2 ft below scour depth
Stream restoration features
19CUI
High Tide Imagery @12.8’ MLLW tide (10.18’ NAVD88)
North U.S. 101: Petitjean Creek existing culvert
20CUI
PETITJEAN BRIDGE
81’ long 42’10” wide Single span, 5 girders, 2 piers Prestressed Concrete Tidally influenced Construction Phasing Scour Countermeasures
Required Stream Restoration Features
Not For Construction
21CUI
PARKING AND PEDESTRIAN ACCESS
22CUI
SOUTH PARKING LOT
Receive fill from removed causeway Access remaining in approximately the same location Adding vault toilet for parking lot for this WDFW wildlife area Incl. bioswale for southern part of U.S.101 treatment and CAVFS for S Parking lot
23CUI
DUCKABUSH INTERSECTION AND NORTH
PARKING LOT
Duckabush Road intersection realigned to the north and elevated Dark Road paving and grading into existing road Guardrail and concrete barrier to protect steep slopes, 2:1 or greater
Lighting installed for the intersection
Wider Shoulder Widths North Parking Lot, 5 vehicle capacity New left turn pocket from
NB U.S.101 to Duckabush Road
24CUI
STORMWATER TREATMENT
Pipes and catch basins for conveyance Media Filter Drains
CAVFS
Flow Spreader Bioswale Bioretention Areas
Bioretention Cross-Section Bioswale Cross Section
Media Filter Drain Cross-Section
25CUI
PEDESTRIAN ACCESS
No dedicated pedestrian/bike access on bridge, just wide shoulders North Parking lot will have a graveled pathway from lot, under the new bridge South Parking lot will have a graveled pathway from the head of the lot to the rivers edge that will be suitable for hand-launched boat access Access to the tidelands from the North and South parking lots, under the bridge
26CUI
ECOSYSTEM RESTORATION COMPONENTS
27CUI
DEMOLITION COMPONENTS
28CUI
DEMOLITION BRIDGES
U.S.101 (South) Bridge 266, looking upstream U.S.101 (North) Bridge 265, looking upstream
29CUI
Construction sequencing considerations Low-impact construction equipment
DEMOLITION PILES
30CUI
CHANNEL AND LWD COMPONENTS
31CUI
LARGE WOODY DEBRIS DETAIL EXAMPLES
BAR
APEX
JAM
EXAMPLE
ANCHORED LARGE WOOD EXAMPLE
32CUI
POST PROJECT CONDITION
Artist Rendering
SPECIAL REQUIREMENTS / CONSIDERATIONS
Work Windows Duckabush River estuary/saltwater areas: 15 July – 15 January in any year Smaller stream crossings/freshwater areas: 15 July – 31 August in any year
Contractor-designed elements Temporary Work Platforms Structural Earth Walls
Geotechnical Geotechnical investigations have been completed for design Contract will contain a Geotechnical Report and Summary of Geotechnical conditions
Staging Limited staging areas
SPECIAL REQUIREMENTS / CONSIDERATIONS
Vehicle Traffic Year-round vehicle traffic
Care and diversion of water Will be contractor’s responsibility
Environmental Considerations Tidal and estuarine work area – sensitive habitat Low-impact methodology and BMPs for environmental compliance NEPA has been completed with the exception of the water quality certification Water quality certification and water quality monitoring plan provided by USACE Letter of Authorization per the Marine Mammal Protection Act provided by USACE
Cultural Resources Inadvertent discovery plan and sensitive area exclusion zone
Tribal and Stakeholder engagement
35CUI
Slides and a summary of questions and answers will be provided on sam.gov following this meeting
Project-Specific Acquisition Questions:
Contracting Specialist Londres Medranda londres.medranda@usace.army.mil
Small Business Questions:
Deputy Office of Small Business Programs Enshane Hill-Nomoto enshane.nomoto@usace.army.mil
Reminder: Industry Day specific questions were posted on sam.gov for this project. Answers from Industry should be received by end of day Wednesday, October 23, 2024. The government will not be commenting further on these questions. The questions can be found at:
• Sam.gov Notice#: W912DW24R0032
• https://sam.gov/opp/0d5a0cbbfb424b03ac0400596e4caf91/view
QUESTIONS
mailto:londres.medranda@usace.army.mil mailto:enshane.nomoto@usace.army.mil https://sam.gov/opp/0d5a0cbbfb424b03ac0400596e4caf91/view
36CUI
WE ARE HERE
Design Phase ~5 years Construction Phase ~4 years
DESIGN
COMPLETION
2019 2025
SECURE
CONSTRUCTION
FUNDING
DUCKABUSH TENTATIVE SCHEDULE
| DUCKABUSH ECOSYSTEM RESTORATION�Industry day�Project overview |
| AGENDA |
| Duckabush Ecosystem restoration |
| PROJECT purpose and need |
| Project benefits |
| Scope: DESIGN-BID-BUILD CONTRACT |
| Contracting process |
| USACE NWS OFFICE OF SMALL BUSINESS PROGRAMS |
| Project features |
| Project Plan Overview – WSDOT Volumes |
| Project Plan Overview – USACE Volumes |
| Staging and access |
| Bridge Temporary work platforms |
| Bridge Temporary work platforms |
| Slide Number 15 |
| Estuary Bridge |
| Slide Number 17 |
| Unnamed trib: Split Box Buried Structure |
| Slide Number 19 |
| Petitjean Bridge |
| Parking and Pedestrian access |
| South Parking Lot |
| Duckabush Intersection and North �Parking Lot |
| Stormwater Treatment |
| Pedestrian access |
| Ecosystem Restoration Components |
| Demolition Components |
| Demolition BRIDGES |
| Demolition PILES |
| Channel and LWD Components |
| Large woody debris detail EXAMPLES |
| Post project condition |
| special requirements / considerations |
| Special requirements / considerations |
| Questions |
| Duckabush Tentative schedule |