INDUSTRY DAYS - Duckabush Estuary Restoration, Jefferson County, WA
Solicitation number
W912DW24R0032
Issued by

About this file

This document is a presentation given at a virtual industry day event hosted by the U.S. Army Corps of Engineers (USACE) Seattle District regarding the Duckabush Ecosystem Restoration project located in Jefferson County, Washington.

The project aims to restore the natural function of the Duckabush Estuary by removing or modifying existing features to reconnect the Duckabush River with adjacent floodplains and wetlands. Key project features include constructing an elevated 1,613-foot long 36-foot-wide bridge to replace the existing U.S. Highway 101 causeway, replacing two culverts, demolishing existing highway and training berms, excavating channels, and placing engineered log jams. The estimated construction price range is $100M to $250M, with an estimated duration of 1,050 calendar days. The project will be procured using a competitive, firm-fixed-price design-bid-build contract under FAR Parts 15 and 36. Small business involvement is encouraged, with USACE's small business goals for the project discussed. The solicitation is anticipated to be released in Q1 FY2025 with award in Q3 FY2025.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DUCKABUSH ECOSYSTEM

RESTORATION

INDUSTRY DAY

PROJECT OVERVIEW

U.S. Army Corps of Engineers (USACE) Seattle District

Washington Department of Fish and Wildlife

(WDFW)

Washington State Department of Transportation (WSDOT)

October 9, 2024

2CUI

CUI

Introduction

Scope of the Project

Contracting Discussion

Technical Presentation

Question and Answer Session

AGENDA

Please note that this information is being provided as part of Market Research for this project. No reimbursement will be provided by the Government for participation at today’s industry day or for preparation of any responses to questions posed to industry.

3CUI

The Duckabush River Estuary is located in Jefferson County at approximately Mile 310 of U.S. Highway 101, near Brinnon Washington.

DUCKABUSH ECOSYSTEM RESTORATION

4CUI

PROJECT PURPOSE AND NEED

Puget Sound Nearshore Ecosystem Restoration study authorized in 2016 for implementation

To restore the natural function of the Duckabush Estuary so that it can create and maintain estuarine habitat in a self-sustaining manner.

This is to be accomplished by removing or modifying existing features so that natural habitat forming processes can be restored.

This project will reconnect the Duckabush River with adjacent floodplains and wetlands by removing existing roadway fill.

5CUI

Improved tidal wetland habitat for fish and wildlife, including Hood Canal summer chum and Chinook salmon, a main food source for endangered Southern Resident Killer Whales.

Reduced backwater flooding.

Improved water quality resulting from increased wetland area for natural water filtration and new road run-off treatment areas.

Modernized road and utility infrastructure resulting in improved resiliency to climate change and natural disasters.

Creation of approximately 1,300 jobs throughout construction of the project.

Increased habitat connectivity and reduced wildlife-vehicle collisions by creating a wildlife corridor under U.S. Highway 101.

PROJECT BENEFITS

6CUI

Contract: Duckabush Ecosystem Restoration located at Duckabush Estuary, Brinnon, Washington

Site: Located at Duckabush Estuary

Project Features:

1. Replace Highway with Elevated Bridge

2. Replace Two Culverts

3. Demolish Highway 101

4. Demolish Training Berms

5. Demolish Timber Piles

6. Demolish Remnant Roadbed

7. Excavate Six Channels

8. Two Parking Areas

9. Engineered Log Jams 10.Three Access Paths

Tentative Schedule

• Solicitation: Q1 FY2025

• Award: Q3 FY2025

SCOPE: DESIGN-BID-BUILD CONTRACT

7CUI

Competitive, firm-fixed-price type contract to be procured in accordance with the Federal Acquisition Regulation (FAR) Part 36 (Construction and Architect-Engineer Contracts) and FAR Part 15 (Contracting by Negotiation), using the Tradeoff process.

Estimated construction price range for this project is between $100M and $250M.

Estimated duration of the project is 1050 calendar days from issuance of the Notice to Proceed.

Proposals will be evaluated based on source selection criteria the technical team has deemed relevant and important for confidence in success of the contract. The proposal deemed best value to the government will be selected (not lowest price, technically acceptable).

CONTRACTING PROCESS

8CUI

General Advice:

• Get engaged, EARLY o Understand anticipated SB involvement

a. Small Business Commitment Document

b. Subcontracting Plan – USACE goals are based on historical data, market info o Utilize SAM.gov and FPDS for subcontracting opportunities

• Build relationships, NOW o SBA SubNet – https://subnet.sba.gov/client/dsp_Landing.cfm o FPDS - https://www.fpds.gov/fpdsng_cms/index.php/en/ o Request agency info on recent awards with a subcontracting plan o Request assistance to source SBs (utilize your APEX Accelerators)

• Understand other than small contractor responsibilities under FAR 52.219-9 o Good Faith Efforts (FAR 19.705-7) o eSRS reporting requirements

USACE NWS OFFICE OF SMALL BUSINESS PROGRAMS

9CUI

Construction of an elevated roadway for U.S. Highway 101 (U.S.101) on a 1,613-foot long 36-foot-wide bridge upstream from the existing highway.

Lane width: 12 feet, Shoulder width: 5 feet, 7 Piers, 2 Columns, Longest span: 228 ft, Concrete Spliced

Girder Construction of a new Duckabush Road intersection with left turn lane from northbound U.S.101 to

Duckabush Road.

Replacement of Unnamed tributary crossing with box culvert.

Replacement of Petitjean Creek crossing (north of the new widespan bridge) with a new 81-foot long, 42-foot 10-inch wide bridge.

Removal of 1,700 feet of the U.S.101 causeway and two bridges across the estuary.

Removal of training berms, remnant piles, and roadbed along the Duckabush River.

Excavation of channels at or near their historical configurations.

Construction of parking lots and estuary access trails at each end of the U.S.101 bridge.

Placement of project-generated woody material (engineered logjams and anchored large wood structures).

PROJECT FEATURES

10CUI

PROJECT PLAN OVERVIEW – WSDOT VOLUMES

Culvert Replacement Petitjean Creek Bridge Replacing existing culvert

Proposed Bridge

Existing Alignment

Realignment of Duckabush Rd

New Roadway Approach to Estuary Bridge

Design graphic is preliminary.

South Parking Lot

11CUI

PROJECT PLAN OVERVIEW – USACE VOLUMES

Unique project integration of

USACE/WSDOT design 3 drawing volumes UFGS specs refer to WSDOT standard

12CUI

STAGING AND ACCESS

Staging area: existing south parking lot Construction trailer area TBD Project includes construction of temporary work platforms (next slide) Phase 1 of utility relocation ongoing now, complete prior to advertisement U.S.101: Traffic Flow maintained throughout construction. Reduced speed limits and short duration closures permitted.

Tribal tideland access will be permitted with a shuttle service during construction to a temp parking platform along existing U.S.101

13CUI

BRIDGE TEMPORARY WORK PLATFORMS

14CUI

BRIDGE TEMPORARY WORK PLATFORMS

Temporary work platforms have been preliminarily designed for installation along the existing alignment to stage construction equipment Contractor-designed for final design To be constructed at an elevation of 14.5 to accommodate 100 year flood conditions Work platforms will be removed at the conclusion of the project

15CUI

BRIDGE TEMPORARY WORK AREA

16CUI

ESTUARY BRIDGE

Precast post-tensioned concrete splice girder Epoxy coating on all reinforcement 135 ft longest span length for a girder, 1,613 ft long for the overall bridge Bridge elevation Historic Bridge

17CUI

South U.S. 101: Unnamed Tributary existing culvert

High Tide Imagery @12.8’ MLLW tide (10.18’ NAVD88)

18CUI

UNNAMED TRIB: SPLIT BOX BURIED STRUCTURE

On the south end of the project, an existing culvert needs to be removed and replaced with a split box buried structure per WSDOT Std Plan E-20.10-00

Buried structure has a span length of 43 ft, design span of 19 ft, and a design height of

18.7 ft. The structure has wing walls up and downstream of the culvert down to 2 ft below scour depth

Stream restoration features

19CUI

High Tide Imagery @12.8’ MLLW tide (10.18’ NAVD88)

North U.S. 101: Petitjean Creek existing culvert

20CUI

PETITJEAN BRIDGE

81’ long 42’10” wide Single span, 5 girders, 2 piers Prestressed Concrete Tidally influenced Construction Phasing Scour Countermeasures

Required Stream Restoration Features

Not For Construction

21CUI

PARKING AND PEDESTRIAN ACCESS

22CUI

SOUTH PARKING LOT

Receive fill from removed causeway Access remaining in approximately the same location Adding vault toilet for parking lot for this WDFW wildlife area Incl. bioswale for southern part of U.S.101 treatment and CAVFS for S Parking lot

23CUI

DUCKABUSH INTERSECTION AND NORTH

PARKING LOT

Duckabush Road intersection realigned to the north and elevated Dark Road paving and grading into existing road Guardrail and concrete barrier to protect steep slopes, 2:1 or greater

Lighting installed for the intersection

Wider Shoulder Widths North Parking Lot, 5 vehicle capacity New left turn pocket from

NB U.S.101 to Duckabush Road

24CUI

STORMWATER TREATMENT

Pipes and catch basins for conveyance Media Filter Drains

CAVFS

Flow Spreader Bioswale Bioretention Areas

Bioretention Cross-Section Bioswale Cross Section

Media Filter Drain Cross-Section

25CUI

PEDESTRIAN ACCESS

No dedicated pedestrian/bike access on bridge, just wide shoulders North Parking lot will have a graveled pathway from lot, under the new bridge South Parking lot will have a graveled pathway from the head of the lot to the rivers edge that will be suitable for hand-launched boat access Access to the tidelands from the North and South parking lots, under the bridge

26CUI

ECOSYSTEM RESTORATION COMPONENTS

27CUI

DEMOLITION COMPONENTS

28CUI

DEMOLITION BRIDGES

U.S.101 (South) Bridge 266, looking upstream U.S.101 (North) Bridge 265, looking upstream

29CUI

Construction sequencing considerations Low-impact construction equipment

DEMOLITION PILES

30CUI

CHANNEL AND LWD COMPONENTS

31CUI

LARGE WOODY DEBRIS DETAIL EXAMPLES

BAR

APEX

JAM

EXAMPLE

ANCHORED LARGE WOOD EXAMPLE

32CUI

POST PROJECT CONDITION

Artist Rendering

SPECIAL REQUIREMENTS / CONSIDERATIONS

Work Windows Duckabush River estuary/saltwater areas: 15 July – 15 January in any year Smaller stream crossings/freshwater areas: 15 July – 31 August in any year

Contractor-designed elements Temporary Work Platforms Structural Earth Walls

Geotechnical Geotechnical investigations have been completed for design Contract will contain a Geotechnical Report and Summary of Geotechnical conditions

Staging Limited staging areas

SPECIAL REQUIREMENTS / CONSIDERATIONS

Vehicle Traffic Year-round vehicle traffic

Care and diversion of water Will be contractor’s responsibility

Environmental Considerations Tidal and estuarine work area – sensitive habitat Low-impact methodology and BMPs for environmental compliance NEPA has been completed with the exception of the water quality certification Water quality certification and water quality monitoring plan provided by USACE Letter of Authorization per the Marine Mammal Protection Act provided by USACE

Cultural Resources Inadvertent discovery plan and sensitive area exclusion zone

Tribal and Stakeholder engagement

35CUI

Slides and a summary of questions and answers will be provided on sam.gov following this meeting

Project-Specific Acquisition Questions:

Contracting Specialist Londres Medranda londres.medranda@usace.army.mil

Small Business Questions:

Deputy Office of Small Business Programs Enshane Hill-Nomoto enshane.nomoto@usace.army.mil

Reminder: Industry Day specific questions were posted on sam.gov for this project. Answers from Industry should be received by end of day Wednesday, October 23, 2024. The government will not be commenting further on these questions. The questions can be found at:

• Sam.gov Notice#: W912DW24R0032

• https://sam.gov/opp/0d5a0cbbfb424b03ac0400596e4caf91/view

QUESTIONS

mailto:londres.medranda@usace.army.mil mailto:enshane.nomoto@usace.army.mil https://sam.gov/opp/0d5a0cbbfb424b03ac0400596e4caf91/view

36CUI

WE ARE HERE

Design Phase ~5 years Construction Phase ~4 years

DESIGN

COMPLETION

2019 2025

SECURE

CONSTRUCTION

FUNDING

DUCKABUSH TENTATIVE SCHEDULE

DUCKABUSH ECOSYSTEM RESTORATION�Industry day�Project overview
AGENDA
Duckabush Ecosystem restoration
PROJECT purpose and need
Project benefits
Scope: DESIGN-BID-BUILD CONTRACT
Contracting process
USACE NWS OFFICE OF SMALL BUSINESS PROGRAMS
Project features
Project Plan Overview – WSDOT Volumes
Project Plan Overview – USACE Volumes
Staging and access
Bridge Temporary work platforms
Bridge Temporary work platforms
Slide Number 15
Estuary Bridge
Slide Number 17
Unnamed trib: Split Box Buried Structure
Slide Number 19
Petitjean Bridge
Parking and Pedestrian access
South Parking Lot
Duckabush Intersection and North �Parking Lot
Stormwater Treatment
Pedestrian access
Ecosystem Restoration Components
Demolition Components
Demolition BRIDGES
Demolition PILES
Channel and LWD Components
Large woody debris detail EXAMPLES
Post project condition
special requirements / considerations
Special requirements / considerations
Questions
Duckabush Tentative schedule