Summary of changes in Amendment 4 (R0004).docx

DOCX document 21 KB Posted

Attached to
Three Story Barracks Federal contract opportunity
Solicitation number
W912DW23R2001
Issued by
Department of the Army Corps of Engineers Engineering District Seattle

About this file

This document summarizes the changes made in Amendment 4 to the solicitation for the construction of a three story barracks located at Joint Base Lewis McChord in Washington. The amendment revises 17 drawings related to specifications, demolition plans, site plans, mechanical plans, and panel schedules. It also adds two new specification sections covering requirements for sampling criteria at borrow source pits and subsurface drainage chambers. Responses to the solicitation are due by April 13, 2023 for the construction of the three story barracks at Joint Base Lewis McChord in Washington. The solicitation is issued by the Department of the Army Corps of Engineers Engineering District Seattle.

View the file

Other files for this federal contract opportunity

Other files attached to Three Story Barracks, newest first.
File Type Posted
Amendment 06_Three Story Barracks.pdf PDF
Addtional Inquiries with Government Responses - Barracks.pdf PDF
Amendment 05 -Barracks.pdf PDF
Amendment R0004 - Barracks.pdf PDF
Plans- Amendment R0004.pdf PDF
Attachment A - Index of Drawings- Amendment R0004.docx DOCX document
Specs- Amendment R0004.pdf PDF
00 72 00-A.docx DOCX document
Drawings.pdf PDF
Summary of Changes in Amendment 0003 - Drawings and Specs.pdf PDF
Amendment 03- Barracks.pdf PDF
Specs.pdf PDF
Site Visit Slides - Barracks_sfn.pptx PPTX presentation
signin sheet.pdf PDF
Amendment 0002 - Barracks.pdf PDF
Amendment 0001 - Barracks.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FY23 PN94756 UEPH21010
Joint Base Lewis McChord, WAW912DW23R2001

Summary of Changes in Amendment no. 4 (R0004)

1. SPECIFICATION ATTACHMENT 01 57 19-A – BORROW SOURCE PIT SOP 2022 WITH SAMPLING CRITERIA Changes: Added new attachment in its entirety.

2. SPECIFICATION 33 40 02 – SUBSURFACE DRAINAGE (LEACHING) CHAMBER

Changes: Added new specification section in its entirety.

3. PLAN Drawing C501 TYPICAL PAVEMENT SECTIONS 1 Changes: Revised drawing with clouded area of Revision 1.

4. PLAN Drawing C508 UTILITY DETAILS 4 Changes: Revised drawing with clouded area of Revision 1.

5. PLAN Drawing A-404 FIRST FLOOR ENLARGED CORE RCP Changes: Revised drawing with clouded area of Revision 1.

6. PLAN Drawing IN601 INTERIOR FINISH SCHEDULE Changes: Revised drawing with clouded area of Revision 2.

7. PLAN Drawing M-001 MECHANICAL LEGEND AND ABBREVIATIONS Changes: Revised drawing with clouded area of Revision 2.

8. PLAN Drawing M-402 MECH ROOMS ENLARGED VIEWS Changes: Revised drawing with clouded area of Revision 2.

9. PLAN Drawing ED100 OVERALL PLAN ELECTRICAL DEMOLITION Changes: Revised drawing with clouded area of Revision 3.

10. PLAN Drawing ED101 PLAN 1 ELECTRICAL DEMOLITION Changes: Revised drawing with clouded area of Revision 3.

11. PLAN Drawing ED102 SITE PLAN 2 ELECTRICAL DEMOLITION Changes: Revised drawing with clouded area of Revision 3.

12. PLAN Drawing ED103 SITE PLAN 3 ELECTRICAL DEMOLITION Changes: Revised drawing with clouded area of Revision 3.

13. PLAN Drawing ES100 OVERALL SITE PLAN ELECTRICAL Changes: Revised drawing with clouded area of Revision 3.

14. PLAN Drawing ES101 SITE PLAN 1 ELECTRICAL Changes: Revised drawing with clouded area of Revision 3.

15. PLAN Drawing ES102 SITE PLAN 2 ELECTRICAL Changes: Revised drawing with clouded area of Revision 3.

16. PLAN Drawing ES103 SITE PLAN 3 ELECTRICAL Changes: Revised drawing with clouded area of Revision 3.

17. PLAN Drawing E612 PANEL SCHEDULES 12 Changes: Revised drawing with clouded area of Revision 3.

1 R0004