About this file

This solicitation package includes specifications for a subsurface drainage leaching chamber construction project. The project scope involves installing leaching chambers and associated drainage components at a depth of 36 inches with an H-20 load rating. Manufactured polyethylene arch-shaped chambers with a minimum size of 51 by 30 inches and 0.32 square feet of sidewall openings per linear foot are required. The installation must follow manufacturer recommendations and include 12 inches of drain gravel below and at the sides of the chambers. Ballast for the project must meet WSDOT specification 3-01 for Los Angeles Wear and degradation factor, and have the gradation sizes and percentages outlined in the specifications. The solicitation closes on 13 April 2023 for the construction work at Joint Base Lewis McChord, Washington under solicitation number W912DW23R2001 from the Department of the Army Corps of Engineers Engineering District Seattle.

View the file

Other files for this federal contract opportunity

Other files attached to Three Story Barracks, newest first.
File Type Posted
Amendment 06_Three Story Barracks.pdf PDF
Addtional Inquiries with Government Responses - Barracks.pdf PDF
Amendment 05 -Barracks.pdf PDF
Attachment A - Index of Drawings- Amendment R0004.docx DOCX document
Amendment R0004 - Barracks.pdf PDF
Plans- Amendment R0004.pdf PDF
Summary of changes in Amendment 4 (R0004).docx DOCX document
00 72 00-A.docx DOCX document
Drawings.pdf PDF
Summary of Changes in Amendment 0003 - Drawings and Specs.pdf PDF
Amendment 03- Barracks.pdf PDF
Specs.pdf PDF
signin sheet.pdf PDF
Site Visit Slides - Barracks_sfn.pptx PPTX presentation
Amendment 0002 - Barracks.pdf PDF
Amendment 0001 - Barracks.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Borrow Source Pit SOP – signed March 2022

Attachment 01 57 19-A

R0004

2. Contamination Limits Borrow Source Pits

FY23 PN94756 UEPH 21010

Joint Base Lewis McChord, WA W912DW-23-R-2001

SECTION TABLE OF CONTENTS

DIVISION 33 - UTILITIES

SECTION 33 40 02

SUBSURFACE DRAINAGE (LEACHING) CHAMBER

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 DELIVERY, STORAGE AND HANDLING

1.3.1 Delivery and Storage

1.3.2 Handling

1.4 DESIGN REQUIREMENTS

PART 2 PRODUCTS

2.1 Subsurface Drainage (Leaching) Chamber

2.1.1 Provide standard manufactured units for this purpose formed of high density molded polyethylene conforming to the following:

2.2 Permeable Ballast

PART 3 EXECUTION

3.1 INSTALLATION PROCEDURE

3.1.1 Drainage (Leaching) Chambers

-- End of Section Table of Contents --

SECTION 33 40 02 Page 1 R0004

SECTION 33 40 02

SUBSURFACE DRAINAGE (LEACHING) CHAMBER

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS

(AASHTO)

AASHTO T 335 (2009) Standard Method of Test for Determining the Percentage of Fracture in Coarse Aggregate

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Leaching Chamber; G

Data shall consist of manufacturer's descriptive and technical literature for leaching chamber

SD-08 Manufacturer's Instructions

Installation Procedure; G

Where installation procedures or any part thereof are required to be in accordance with the recommendations of the manufacturer of the material being installed, printed copies of these recommendations shall be furnished to the Contracting Officer prior to installation.

1.3 DELIVERY, STORAGE AND HANDLING

1.3.1 Delivery and Storage

Materials delivered to site shall be inspected for damage, unleaded, and stored with a minimum of handling. Materials shall not be stored directly on the ground. The inside of pipes and fittings shall be kept free of dirt and exposure to the direct sunlight over extended periods.

1.3.2 Handling

Materials shall be handled in such a manner as to insure delivery to the trench in sound, undamaged condition.

SECTION 33 40 02 Page 2 R0004

1.4 DESIGN REQUIREMENTS

Installed leaching system with 36 inches minimum backfill cover shall meet H-20 load rating under AASHTO-01

PART 2 PRODUCTS

2.1 Subsurface Drainage (Leaching) Chamber

The subsurface drainage chamber (leaching chamber), is system to receive effluent and allow it to drain or infiltrate into the surrounding soil.

2.1.1 Provide standard manufactured units for this purpose formed of high density molded polyethylene conforming to the following:

a. Units shall be arch shaped, with open-bottom.

b. Nominal size of individual units shall be 51 inches width (min.) by 30 inches (min.) depth in standard manufacturers lengths that shall be interlocked to provide the overall length shown on plans.

c. Each unit shall have a minimum of 0.32 square feet of sidewall opening per linear 12 inches. Openings shall be 0.02 inch wide.

d. Each unit shall have a minimum bearing footprint of 1.5 to 2.0 square feet.

e. Units shall include standard end plates with distribution pipe inlets. Distribution pipe inlets shall be a minimum of 4 inch diameter pipe or as indicated on the plans.

f. Each unit shall be designed with interlocking joints for field installation.

g. Polyethylene used in molded units shall have a minimum density of 6 pcf.

2.2 Permeable Ballast

Ballast shall consist of crushed, partially crushed, or naturally occurring granular material from approved sources manufactured in accordance with the provisions of Washington State Department of Transportation (WSDOT) Specification, Chapter 3, Section 3-01 Production From Quarry and Pit Sites. The material from which ballast is to be manufactured shall meet the following test requirements:

Los Angeles Wear, 500 Rev 40 percent max.

Degradation Factor 15 min.

Ballast shall meet the following requirements for grading and quality when placed in hauling vehicles for delivery to the roadway or during manufacture and placement into a temporary stockpile. The exact point of acceptance will be determined by the Engineer.

Sieve Size Percent Passing 2.5" 99-100 2" 65-100

SECTION 33 40 02 Page 3 R0004

3/4" 40-80 No. 4 5 max.

No. 100 0-2

All percentages are by weight.

The portion of ballast retained on No. 4 sieve shall not contain more than

0.2 percent wood waste.

The fracture requirement shall be at least one fractured face and will apply the combined aggregate retained on the No. 4 sieve in accordance with FOP for AASHTO T 335 .

PART 3 EXECUTION

3.1 INSTALLATION PROCEDURE

3.1.1 Drainage (Leaching) Chambers

Excavation of trenches and backfilling for the subsurface drainage (leaching) chambers shall be in accordance with the applicable portion of Section 31 00 00 EARTHWORK and the installation of the subsurface (leaching) chambers shall be in accordance with the manufacturer's recommendations except provide 12 inches of drain gravel below and at the sidewalls of the chambers.

-- End of Section --

SECTION 33 40 02 Page 4 R0004

Attachment 01 57 19-A Borrow_Source_Pit_SOP_2022 w Sampling Criteria
Borrow Source Pit SOP coversheets
1. Borrow Source Pit SOP - SIgned 2022 MAR
2. Contamination Limits Borrow Source Pits
33 40 02
SUBSURFACE DRAINAGE LEACHING CHAMBER
33 40 02 - SUBSURFACE DRAINAGE LEACHING CHAMBER
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 DELIVERY, STORAGE AND HANDLING
1.3.1 Delivery and Storage
1.3.2 Handling

1.4 DESIGN REQUIREMENTS

PART 2 PRODUCTS
2.1 Subsurface Drainage Leaching Chamber
2.1.1 Provide standard manufactured units for this purpose formed of high

2.2 Permeable Ballast

PART 3 EXECUTION
3.1 INSTALLATION PROCEDURE
3.1.1 Drainage Leaching Chambers