Text version
SHEET
IDENTIFICATION
1 2 3 5
D R
AW
N
B Y:
D
ES
I G N
B Y:
SB
M
T
BY
S
IZ
E :
D
FI
LE
N A
M E:
D
AT
E :
C O
N
TR
AC
T
N O
S O
LI
C
IT
AT
IO
N
N O
C
KD
B
Y:
US Army Corps of Engineers ®
" x
4"
D
C
B
A
FI
LE
N U
M
BE
R
P
LO
T D
AT
E:
SHEET
U .S
. A R
M Y
E N G
IN
EE
R D
IS
TR
IC
T
C O
R
PS
O F
EN
G
IN
EE
R S
SE
AT
T L E
D
IS
T R
IC
T
J U
N E
BR
IA
N C
. N
EL
SO
N
OF 24
FY
P N
L
W C
R
EC
S C
R
AN
E R
EP
LA
C
EM
EN
T
LA
KE
W
AS
H
IN
G
TO
N S
H
IP
C
AN
AL
, W
AS
H
IN
G
TO
N
E- 2-
3-
8/
2/
2:
:0
PM
SN
YD
ER
SN
YD
ER
S-001
G
EN
E R A
L N O
TE
S
H
EN
IN
G
ER
GENERAL:
METHODS, PROCEDURES, AND SEQUENCES OF CONSTRUCTION ARE THE RESPONSIBILITY OF THE
CONTRACTOR. THE CONTRACTOR IS RESPONSIBLE FOR IDENTIFYING AND IMPLEMENTING THE
NECESSARY PRECAUTIONS TO MAINTAIN AND ENSURE THE INTEGRITY OF THE STRUCTURE AT ALL
STAGES OF THE CONSTRUCTION.
TEMPORARY BRACING, SHEETING, SHORING, ETC., REQUIRED TO ENSURE THE STRUCTURAL
INTEGRITY/STABILITY OF THE EXISTING BUILDINGS, SIDEWALKS, UTILITIES, ETC., DURING
CONSTRUCTION AND DEMOLITION IS THE RESPONSIBILITY OF THE CONTRACTOR AND SHALL BE
DESIGNED BY A REGISTERED PROFESSIONAL ENGINEER EMPLOYED BY THE CONTRACTOR.
IMPLEMENTATION OF JOB SITE SAFETY IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR.
DIMENSIONS AND INSTALLATION DETAILS OF EQUIPMENT MUST BE VERIFIED AND COORDINATED WITH
THE SUPPORTING STRUCTURE. THE CONTRACTOR IS RESPONSIBLE FOR DETERMINING SUCH
REQUIREMENTS FROM SUBCONTRACTORS AND EQUIPMENT SUPPLIERS ALONG WITH COORDINATING
THE LOCATIONS AND DETAILS FOR THESE ITEMS PRIOR TO FABRICATION OR ERECTION OF THE
SUPPORTING STRUCTURE. ANY CONFLICTS BETWEEN THESE ITEMS AND THE SUPPORTING
STRUCTURE IS TO BE BROUGHT TO THE ATTENTION OF THE CONTRACTING OFFICER FOR RESOLUTION.
THE STRUCTURAL DRAWINGS GOVERN THE WORK FOR STRUCTURAL FEATURES, UNLESS OTHERWISE
NOTED. DIMENSIONS SHOWN ON PLANS AND DETAILS ARE TO GOVERN THE STRUCTURAL WORK.
IN CASE OF CONFLICT BETWEEN THE GENERAL NOTES, SPECIFICATIONS, AND DRAWINGS, NOTIFY THE COR. THE MOST STRINGENT REQUIREMENTS SHALL GOVERN UNLESS OTHERWISE DIRECTED BY THE
COR.
THE CONTRACTOR IS RESPONSIBLE FOR THE DESIGN AND CONSTRUCTION OF THE CRANE
FOUNDATION AS PART OF THE INSTALLATION OF THE CRANE. STRUCTURAL CALCULATIONS STAMPED
BY A PROFESSIONAL ENGINEER SHALL BE SUBMITTED TO THE COR FOR REVIEW. FOUNDATION
ENGINEER SHALL ASSUME LOCK MONOLITH CONSISTS OF CONCRETE WITH A COMPRESSIVE
STRENGTH OF 5000 PSI.
G-1
G-2
G-3
G-4
G-5
G-6
G-7
STRUCTURAL STEEL:
DESIGN CODE: AISC 360-10 SPECIFICATION FOR STRUCTURAL STEEL BUILDINGS.
MATERIAL STRENGTHS:
1) STEEL ANGLES AND PLATES: ASTM A36.
STRUCTURAL STEEL SHALL BE FABRICATED IN ACCORDANCE WITH THE REQUIREMENTS OF THE
AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC). STEEL ERECTION SHALL BE IN ACCORDANCE WITH THE REQUIREMENTS OF AISC AND THE OSHA STEEL ERECTION STANDARD 29 CFR ART 1926, SUBPART R-STEEL ERECTION, EFFECTIVE DATE JANUARY 18, 2002.
STRUCTURAL STEEL, UNO, TO BE NEW STEEL CONFORMING TO THE REQUIREMENTS OF ASTM
A6/A6M.
THE STRUCTURAL STEEL FABRICATOR AND/OR GENERAL CONTRACTOR MUST VERIFY ALL
DIMENSIONS AND CONDITIONS AT THE SITE. ALL DISCREPANCIES FOUND ARE TO BE REPORTED TO THE ENGINEER PRIOR TO PREPARATION OF SHOP DRAWINGS. SHOP DRAWINGS ARE TO INCLUDE ALL
FIELD MEASUREMENTS AND CONDITIONS.
MANUFACTURE STEEL GRATING IN ACCORDANCE WITH THE "METAL BAR GRATING MANUAL" AS
PUBLISHED BY THE NATIONAL ASSOCIATION OF ARCHITECTURAL METAL MANUFACTURERS, LATEST
EDITION. STEEL FOR GRATING TO CONFORM TO ASTM A1011/A1011M.
STRUCTURAL STEEL SHALL BE SHOP PRIMED AND PAINTED PER SPECIFICATIONS, UNO.
S-1
S-2
S-3
S-4
S-5
S-6
S-7
ABBREVIATIONS:
BLDG BUILDING
BOT BOTTOM
BRG BEARING
CL CENTERLINE
CLR CLEAR
COE CORPS OF ENGINEERS
COL COLUMN
CONC CONCRETE
CONN CONNECTION
CONT CONTINUOUS
COR CONTRACT OFFICER'S REPRSENTATIVE
DEMO DEMOLITION
DIA DIAMETER
DWG DRAWING
EA EACH
EF EACH FACE
ELEC ELECTRICAL
ELEV ELEVATION
EQ EQUAL
ES EACH SIDE
EW EACH WAY
EXP EXPANSION
EXT EXTERIOR
FF FINISHED FLOOR
FDN FOUNDATION
FTG FOOTING
GA GAGE
HORIZ HORIZONTAL
INFO INFORMATION
INSTALL INSTALLATION
INT INTERIOR
LLH LONG LEG HORIZONTAL
LLV LONG LEG VERTICAL
LONGIT LONGITUDINAL
MAX MAXIMUM
MFR MANUFACTURER
MIN MINIMUM
NO NUMBER
NTS NOT TO SCALE
OC ON CENTER
OH OPPOSITE HAND
OPP OPPOSITE
PCF POUNDS PER CUBIC FOOT
PSF POUNDS PER SQUARE FOOT
PEMB PRE-ENGINEERED METAL BUILDING
PL PLATE
REF REFERENCE
REINF REINFORCING
REPL REPLACEMENT
REQ'D REQUIRED
SCHED SCHEDULE
SEC SECTION
SIM SIMILAR
SOG SLAB ON GRADE
SPECS SPECIFICATIONS
SQ SQUARE
SS STAINLESS STEEL
STD STANDARD
STL STEEL
THK THICKNESS
TRANSV TRANSVERSE
TYP TYPICAL
T&B TOP AND BOTTOM
UNO UNLESS NOTED OTHERWISE
VERT VERTICAL
W/ WITH
DESIGN CRITERIA:
REFERENCES:
ER 1110-2-1150 ENGINEERING AND DESIGN FOR CIVIL WORKS PROJECTS (31 AUG 1999)
ER 1110-2-1806 EARTHQUAKE DESIGN AND EVALUATION FOR CIVIL WORKS PROJECTS (31 JUL 1995)
EM 1110-2-2000 STANDARD PRACTICE FOR CONCRETE FOR CIVIL WORKS STRUCTURES (31 MAR 2001)
EM 1110-2-2100 STABILITY ANALYSIS OF CONCRETE STRUCTURES (1 DEC 2005)
EM 1110-2-2104 STRENGTH DESIGN FOR REINFORCED-CONCRETE HYDRAULIC STRUCTURES (20 AUG 2003)
IBC 2012 INTERNATIONAL BUILDING CODE 2012
ASCE 7-10 MINIMUM DESIGN LOADS FOR BUILDINGS AND OTHER STRUCTURES
AISC 360-10 SPECIFICATIONS FOR STRUCTURAL STEEL BUILDINGS
ACI 318-11 BUILDING CODE REQUIREMENTS FOR STRUCTURAL CONCRETE
LATERAL LOAD DESIGN CRITERIA:
DC-1
DC-2
A.
B.
WIND DESIGN CRITERIA
1. RISK CATEGORY IV
2. BASIC WIND SPEED (3 SECOND GUST) 110 MPH
3. EXPOSURE CATEGORY D
SEISMIC DESIGN CRITERIA
1. RISK CATEGORY IV
2. SEISMIC IMPORTANCE FACTOR 1.5
3. SHORT PERIOD DESIGN SPECTRAL RESPONSE COEFFICIENT 0.874
4. ONE SECOND DESIGN SPECTRAL RESPONSE COEFFICIENT 0.510
5. SITE CLASS D
6. SEISMIC DESIGN CATEGORY D
EPOXY:
EPOXY SHALL BE HILTI HIT-RE 500 V3 INJECTABLE TWO-COMPONENT EPOXY ADHESIVE OR EQUAL.
EPOXY SHALL BE SEISMICALLY QUALIFIED PER IBC FOR SEISMIC DESIGN CATEGORY D AND SHALL MEET THE REQUIREMENTS OF ASTM C881-90, TYPE IV, GRADE 2 AND 3, CLASS A, B, AND C EXCEPT GEL TIMES.
MATERIAL PROPERTIES OF FULLY CURED EPOXY SHALL MEET OR EXCEED THE FOLLOWING CRITERIA:
BOND STRENGTH ASTM C882-13A 2 DAY CURE 1560 PSI
BOND STRENGTH ASTM C882-13A 7 DAY CURE 1690 PSI
COMPRESSIVE STRENGTH ASTM D695-10 12,000 PSI
COMPRESSIVE MODULUS ASTM D695-10 0.38X10 PSI
TENSILE STRENGTH 7 DAY ASTM D638-14 7150 PSI
ELONGATION AT BREAK ASTM D638-14 1.1%
HEAT DEFLECTION TEMPERATURE ASTM D648-07 122 DEG F
ABSORPTION ASTM D570-98 0.18%
LINEAR COEFFICIENT OF SHRINKAGE ON CURE ASTM D2566-86 0.008
E-1
E-2
SY
M
BO
L
D
ES
C R
IP
TI
O N
D
AT
E
BY
A A
D D
C O
N C
S
TR
EN
G
TH
AU
G
A
R0002
E-101
S U
S
IN
S U
S
IN
4' 2' 4'0
''= 1'-0"4
1SCALE:
P N
L
W C
R -E -1
.d g n
GENERATOR
CRANE LOCATION
COMPRESSORS
EXISTING AIR
EDH-LTG
EXISTING PANEL
WITH GOVERNMENT PERSONEL.
1. CONTRACTOR TO DETERMINE FINAL LOCATION OF EQUIPMENT
GENERAL NOTES:
TRENCH.
ROUTE USING EXISTING
AUXILLARY POWER.
CRANE AND CRANE
E L E
C T
R
IC
A L P
L
N
M
S T
E N
J
NOTE 1
NOTE 1
NOTE 3
NOTE 4
4. JUNCTION BOX FOR POWER CONNECTION TO CRANE.
3. 750KW, 480V, 3PH GENERATOR SET WITH MCC.
2. PROVIDE NEW 240V CIRCUIT FOR THE CRANE AUXILLARY LOADS.
FROM A 240V SYSTEM TO A 480V SYSTEM.
1. REUSE EXISTING CONDUCTORS FOR HYDRAULIC PUMPS. REWIRE PUMPS
NOTES:
R E
V
IS
E D N
O T
E S
/2 /2
P S
A
R0002
F
IL
E N
A M
E
D W
N B
Y
C K
D B
Y
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
D
2 3
C
4 5
A
B
M A
R K
A P
P R
D A
T E
F
IL
E N
U M
B E
R
S
IZ
E
S U
B M
IT
T E
D B
Y
D A
T E
M A
R K
D E
S C
R
IP
T
IO
N
IDENTIFICATION
SHEET
D A
T E
A P
P R
®of Engineers
US Army Corps of Engineers
US Army Corps
S I
D
U .S
A R
M Y C
O R
P S O
F E
N G
IN
E E
R S
S E
A T
T L E
W A
S H
IN
G T
O N
S E
A T
T L E D
IS
T R
IC
T
SEATTLE DISTRICT
:2
:3
A
M
OF
P L
O T D
A T
E
P L
O T T
IM
E
/2 /2
DESIGN FILE: pw:\\COE-NWSPW001SEA.nws.ds.usace.army.mil:cenws01\Documents\Civil Works\Lake Washington Ship Canal, WA\FY16_PN444974_LWCR\Current_Phase\Con_Docs\CAD_Sheets\Electrical\E-101 - EMERGENCY DAM HOIST HOUSE PLAN AND SECTIONS
E -2 -3 -2
E C
S C
R A
N E R
E P
L A
C E
M E
N T
F Y P
N L
W C
R
L A
K E W
A S
H
IN
G T
O N S
H
IP
C
A N
A L
W A
S H
IN
G T
O N
24SHEET
J
U N
E
B R
IA
N C
N E
L S
O N
EDGE OF WALL N-90
EDGE OF WALL N-40
CHANNEL FLOW
" = 1'-0"4
1SCALE:
E E
E
E
E
OF CONTROL HOUSE #1
SEE SHEET E-401 FOR ENLARGED PLAN
HYDRAULIC PUMP
LANDSIDE
HYDRAULIC PUMP
RIVERSIDE
ELECTRICAL PLAN
2-4"
CABLE T
RAYS (E
XISTING)
P
L
W C
R -E -6
.d g n
O
E -L
IN
E D
IA
G R
A M
E-601
200A
TRANSFORMER HOUSE
(3) 350 KCM
VC-1
400A
100100
VC-3 VC-2
VISITOR CENTER
300HP
250A
TLTP
600A
100200225
225 175
TL-2
YSD MOCKING
(3)#I/O
TL-6
MACHINE
SHOP
(3)#2/0
WAREHOUSE NO.2
TL-8
(3)#1/0
FISH LADDER
3/C #4 & (1) #6
2"C-(3)#2/0 & 1#6
(3)-75 KVA,10
2400-120/240V
IZ-6.3%
CONTROL HOUSE #4
100A
80A
PP-A PP-1 PP-2 PP-3 PP-4
MCC
CH 3
MDP
CONTROL HOUSE #3
(3)-75 KVA, 10
2400-120/240V
IZ-6.3%
3#2/0 & 1#6
MDP
3#2/0 & 1#6
MCC
60HP
4/C #6
MCC
MDP
CONTROL HOUSE #2
(3)-75 KVA, 10
2400-120/240V
IZ-6.3%
CH-2
2#C-(3) #3/0 & 1#6
3/C#2
EXISTING
CARPENTER
SHOP
NO.2
(3)#2/0
(3)#2
(3)#1/0
(3)#2/0
CH#1
3#2/0-1"6
TRANSFORMER
HOUSE
LAV-LTG
LAVATORY &
STORAGE ROOM
TO WELDING
RECEPTS
MDP
MCC
(3) 500 MCM
200A
SEATTLE CITY
LIGHT
ISC = 3550A
METERING PP-T PP-P PP-S
IZ-4.3%
208-240V
75 KVA 30
STEEL SHOP
2400-208/120V
IZ-4.7%
MACH RECESS #2 60
BOAT HOUSE
BH-LTG.
3#2/0 & 1#6
4/C#4
2"C(3)#3/0 & 1#6
300HP 75HP
ADMINISTRATION BLDG.
DEWATERING PUMPS
150 KVA, 30
2400V-208/120V
(2) SETS OF 3#3 &
1#1/0 IN 2"C
IN 3" C.
(3) 1/C #4, 5KV-SH.
TP-6
WAREHOUSE
(3)#3/0
(3)#1/0
TP-4 TL-1
TL-1
GARAGE
NO. END
SO. END
GARAGE
TL-4
WAREHOUSE
NO.1
SPLICE
BOX
(4)#3/0 2"C
SHORE
POWER
A3
GARAGE
NO. END
SO. END
GARAGE
(3)#4/0
TP-1
TPIN
TP-5
(3)#3/0 & (1) #4
MACH. SHOP
TP-3
SEC. I SEC. II
MACHINE
SHOP
TP-3A
(MLO)
(3)#1/0
J
SHOP
CARPENTER WAREHOUSE #1
2ND FLOOR
TL-4A TL-4D
(EXIST'G-
(3)#2 (3)#4 (3)#4 (3)#1/0
(3)-75KVA, 10
2400V-120/240V
IZ = 6.3%
COMPRESSOR
EDH-LTG.
HOUSE
2"C-(3)#2/0 & 1#6
1P
1P
GUARD HOUSE
(4)#2-IN EXIST.
(3)#1 IN
PNL.)
J J
ELECTRICAL SHOP
(WAREHOUSE #1)
CARPENTER
SHOP ADD
(WHSE #1) (3)#3/0
(3)#3/0
TL-7
TL-7A
2060A
GH-LTG.
GREENHOUSE
GHS-LTG.
FUEL STOR.
LTG SW.
(3)#2
TL-12
STEEL SHOP
PDL GP
AMP
208/120
(4)#2-(1)#8
CONTROL HOUSE #1
GARDNERS STORAGE
(WAREHOUSE NO.1)
TL-4C TL-4B
(4)#1 IN
3#4/0-5KV, 1#4GND
3#4/0-5KV, 1#4GND
LOAD BANK
400KW
J
MANUAL XFER SWITCH
800A-3P-600V,S/N
GFI
800A
2(4#500KCMIL, 1#1/0GND)
G
2(3#500KCMIL, 1#1/0GND)
2(4#500KCMIL, 1#1/0GND)
d
2400V, 30, 3W
TRANSFORMER HOUSE
1‚"C-3#1 1‚"C(3)#1
(3)#1, 1•"C
(4)#4/0 IN 2•"C
(4)#2, 1•"C
1‚"C 1•"C
1•"C (4)#2 IN 1•"C
1•"C-(4)#8
1•"C
Z=5.4%
480Y/277V-2400V
500 KVA, 30
d
200A 200A 200A
175A
300KVA, 30
2400-480/277V
100A
400A
3 #2/0 - 5KV
AP-11 AL-7 AL-8 AL-9
225A
150 KVA, 30
2400-208/120V
IZ = 4.2%
AP AL
225A
BASEMENT
75KVA, 30
208V-240V
(3)#250
(3)#4 (3)#4
ADMINISTRATION
ADMINISTRATION BUILDING
P1
& 1#6
2"C-(3)#2/0
& 1#6
2"C-(3)#2/0
P1
P1
SALT WATER
RETURN VALVE
SPILLWAY
GATES
TRIDENT CRANE
100A 100A
AIR COMP'R IN
x "=0.167 P.U.
480Y/277V
400 KW @ 0.8PF
2"C-(3)#2/0 & 1#6
HMR
HML
(4)#1
(4)#3
PANEL 'MP' PANEL AC
LAV-LTG
(2) CAPSTAN (25HP)
(2) STONEY GATE VALVE (50HP)
TYPICAL CONTROL HOUSE
(2) CAPSTAN (25HP)
(2) STONEY GATE VALVE (50HP)
TYPICAL CONTROLHOUSE
10.27 X/R @1/2cyc
14404 SCA Asym @ 1/2cyc
9976 SCA Sym @ 1/2cyc
441719 SCKVA
25.564 KV-Nom
UTILITY XFMR PRI
XFMR-UTP
29 X/R @1/2cyc
5808 SCA Asym @1/2cyc
3595 SCA Sym @1/2cyc
500 KVA
480 V-Nom
GENERATOR
PUMP UNITS
(2) HYDRAULIC
CENTRAL CONTROL TOWER
ID TOFROM VOLTAGE CONFIGURATION PHASES CONDUCTORS
NUMBER OF
CONDUCTOR SIZE LENGTH, FT. RACEWAY TYPE FEEDER PROTECTION
SEATTLE CITY LIGHT (SCL) SERVICE
A
B
C
D
E
F
G
H
I
J
K
L
M
MAIN PP NORMAL
EMERGENCY PP
SCL POLE
PP-T
PP-T TAP
PP-P
PP-S
TRANSFER SWITCH
EPP-A
EPP-1
EPP-2
EPP-3
EPP-4
SPLICE NEAR CHANNEL 4
SPLICE NEAR CHANNEL 4
MAIN PP-NORMAL
TL TX IN TX HOUSE
VC TX IN VISITOR CENTER
DEWATERING PUMPS
TRANSFER SWITCH
EMERGENCY-EPP
AL IN ADMIN BLDG
CONTROL HOUSE-1 TX
CONTROL HOUSE-2 TX
CONTROL HOUSE-3 TX
SPLICE NEAR CONTROL HOUSE 4
CONTROL HOUSE-4 TX
CONTROL TOWER TX
DELTA
DELTA
DELTA
DELTA
DELTA
DELTA
DELTA
DELTA
DELTA
DELTA
DELTA
DELTA
DELTA
350 KCMA CU
2 AWG CU
4 AWG CU
2/0 AWG CU
4/0 AWG CU
3-4/0 CU, 1-4 CU
4 AWG CU
2 AWG CU
4 AWG CU
4 AWG CU
1/0 AWG CU
1/0 AWG CU
1/0 AWG CU
DUCT BANK
DUCT BANK
DUCT BANK
3" CONDUIT
AGS
AGS
DUCT BANK
DUCT BANK
DUCT BANK
DUCT BANK
DUCT BANK
AGS
AGS
UNKNOWN
3-120 A FUSE
2-120 A FUSE
3-200 A FUSE
3-200 A FUSE
1-800 A CB AT 480 V
3-60 A FUSE
3-80 A FUSE
3-80 A FUSE
3-80 A FUSE
3-80 A FUSE
NONE
NONE
2400 VOLT CABLE AND CONDUIT SCHEDULE
CU = COPPER
CH = CONTROL HOUSE
EPP = EMERGENCY POWER PANEL
225KVA, 30
400A-3P-2.4KV
5.061 X/R @1/2cyc
5627 SCA Asym @1/2cyc
4480 SCA Sym @1/2cyc
2.4 KV-Nom
FEDERAL PACIFIC AUTO XFER SW
IZ-4.2%
208Y/120V-2400V
30 KVA-XFER, 30
120A
AL-10
NORTH RESTROOM
MCC
PNL-R
PNL-S
KVA 5
240/120/240
120/208V/240
45 KVA, 30 LTG PNL
PP = POWER PANEL
AGS = ACID GALVANIZED STEEL
TX = TRANSFORMER
GP
IZ-3.0%
HYD. PUMP
345KW
CRANE
(2) CAPSTAN (25HP)
(2) STONEY GATE VALVE (50HP)
CONTROL HOUSE
TYPICAL LAND WALL
60HP 60HP
G
ONE-LINE
3#1, 1 #6 GND
2(3#350), 1#3 GND
4#1/0, 1 #8 GND
S U
S
IN
S U
S
IN
CR
GN-CR
1000A MCC
240V
CRANE AUX LOAD
240V
CRANE AUX LOAD
240V
CRANE AUX LOAD
750 KW
GENERATOR
CRANE OPERATING
GENERATOR BATTERY CHARGER
GENERATOR JACKET-COOLANT HEATER
GENERATOR ENGINE OIL HEATER
GENERATOR ANTI-CONDENSATION HEATER
CRANE LIGHTING
CRANE RECEPTACLES
PEDESTAL HEATER
M A
S T
E N
HIGH LEG APPROPRIATELY.
6. PANEL CR IS FED BY A 3 PHASE 240V DELTA SYSTEM FROM PANEL MDP. USE
OPERATE PROPERLY.
EQUIPMENT PER NEC AND CRANE LOAD REQUIREMENTS TO HAVE SYSTEM
SIZES ARE FOR BIDDING PURPOSES ONLY. CONTRACTOR TO SIZE
5. MOTOR CONTROL CENTER, STARTERS, CONDUCTORS, AND BREAKER
GENERATOR SET AND THROUGH OPERATING HOUSE.
4. ROUTE NEW CONDUCTORS TO CRANE USING EXISTING TRENCH NEXT TO
REWIRED TO 480V SYSTEM.
USING EXISTING TRENCHES WHERE POSSIBLE. HYDRAULIC PUMPS TO BE
3. ROUTE NEW CONDUCTORS TO EXISTING HYRDAULIC PUMPS AND ROUTE
INTERNAL BREAKERS, AND STARTERS. .
2. PROVIDE 1000A MOTOR CONTROL CENTER WITH ASSO. BUCKETS,
1. PROVIDE 750KW GENERATOR SET.
NOTES:
R E
V
IS
E D N
O T
E S
A
/2 /2
P S
R0002
F
IL
E N
A M
E
D W
N B
Y
C K
D B
Y
D E
S
IG
N E
D B
Y
D E
S C
R
IP
T
IO
N
D
2 3
C
4 5
A
B
M A
R K
A P
P R
D A
T E
F
IL
E N
U M
B E
R
S
IZ
E
S U
B M
IT
T E
D B
Y
D A
T E
M A
R K
D E
S C
R
IP
T
IO
N
IDENTIFICATION
SHEET
D A
T E
A P
P R
®of Engineers
US Army Corps of Engineers
US Army Corps
S I
D
U .S
A R
M Y C
O R
P S O
F E
N G
IN
E E
R S
S E
A T
T L E
W A
S H
IN
G T
O N
S E
A T
T L E D
IS
T R
IC
T
SEATTLE DISTRICT
:2
:4
A
M
OF
P L
O T D
A T
E
P L
O T T
IM
E
/2 /2
DESIGN FILE: pw:\\COE-NWSPW001SEA.nws.ds.usace.army.mil:cenws01\Documents\Civil Works\Lake Washington Ship Canal, WA\FY16_PN444974_LWCR\Current_Phase\Con_Docs\CAD_Sheets\Electrical\E-601 - ONE-LINE DIAGRAM
E -2 -3 -2
E C
S C
R A
N E R
E P
L A
C E
M E
N T
F Y P
N L
W C
R
L A
K E W
A S
H
IN
G T
O N S
H
IP
C
A N
A L
W A
S H
IN
G T
O N
24SHEET
J
U N
E
B R
IA
N C
N E
L S
O
REFERENCE DRAWING 42
| Plan Revisions - R0002 |
| LWCR-G-002IND-R2 |
| PN444974_LWCR-S-001-R2 |
| PN444974_LWCR-E-101-R2 |
| PN444974_LWCR-E-601-R2 |
| Reference Drawing Revisions - R0002 |
| REF DWG 42.pdf |
File details come from the government source that posted it. Updated .