This document is a Department of the Army Permit authorizing the New York City Department of Parks and Recreation to perform construction activities related to an existing dock structure in the Bronx River. The key details are:
The permit authorizes the removal of an existing 102 square foot section of a fixed pier, ramp, and float, and the installation of a new 4-foot by 30-foot ramp and 8-foot by 50-foot float. The work must be completed within 3 years. The permit includes standard conditions as well as special conditions related to coordination with the U.S. Coast Guard, NOAA, and requirements for minimizing turbidity and environmental impacts. The permittee has the right to appeal the permit decision if they object to any of the terms and conditions.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE ARMY
U.S. ARMY CORPS OF ENGINEERS, NEW YORK DISTRICT
JACOB K. JAVITS FEDERAL BUILDING
26 FEDERAL PLAZA
NEW YORK NEW YORK 10278-0090
REGULATORY BRANCH
SUBJECT: Department of the Army Permit Number NAN-2024-00634 Issued to New York City Department of Parks and Recreation
New York City Department of Parks and Recreation Attn: Terence McCormick 117-02 Roosevelt Avenue Flushing Meadows Corona Park Flushing, New York 11368 Terrence.McCormick@parks.nyc.gov
Dear Mr. McCormick:
We have completed our review of Application Number NAN-2024-00634-EMI.
Pursuant to Section 10 of the Rivers and Harbors Act of 1899 (33 USC 403), you are hereby authorized by the Secretary of the Army:
ACTIVITY: Remove an approximately 102 square foot irregularly shaped section of the existing fixed pier, the existing ramp and existing eight-foot-wide by 50-foot-long float and four (4) associated landside steel piles.
Install a new four-foot-wide by 30-foot-long ramp from the existing pier to a new eight-foot-wide by 50-foot-long float located approximately eight (8) feet seaward of the previous. The new 50-foot-long float will be secured using four existing piles.
All work shall be done in accordance with the attached plans, subject to Special Conditions A through E, which are hereby made part of this permit.
WATERWAY: Bronx River
LOCATION: Hunts Point Riverside Park, Borough of The Bronx, Bronx County, City of New York, New York
The activity authorized herein by Letter of Permission must be completed within three years of the date of this permit. This authorization is subject to the enclosed conditions. Please find enclosed two forms to be used to submit to this office, as required, the dates of commencement and completion for the authorized activity.
This letter contains an initial proffered permit for your activity. If you object to this permit decision because of certain terms and conditions therein, you may request that the permit be modified accordingly under Corps regulations at 33 CFR 331. Enclosed you will mailto:Terrence.McCormick@parks.nyc.gov
REGULATORY BRANCH
SUBJECT: Department of the Army Permit Number NAN-2024-00634
Issued to New York City Department of Parks and Recreation for Installation of Dock Structures
- 2 -find a combined Notification of Appeal Process (NAP) and Request for Appeal (RFA) form. If you object to this permit decision you must submit a completed RFA form to the New York District Office at:
Stephan A. Ryba Chief, Regulatory Branch
New York District Corps of Engineers 26 Federal Plaza, Room 16-406
New York, New York 10278-0090
In order for a RFA to be accepted by the Corps, the Corps must determine that it is complete, that it meets the criteria for appeal under 33 CFR Part 331.5, and that it has been received by the District Office within 60 days of the date of the NAP. Should you decide to submit a RFA form, it must be received at the above address by _________________________. Additionally, send an electronic copy of the RFA form to Christopher.W.Minck@usace.army.mil. It is not necessary to submit a RFA form to the District Office if you do not object to the permit decision in this letter.
The authorized activity must be performed in accordance with the enclosed plans.
If any material changes in the location or plans of the subject work are found necessary, revised plans should be submitted to the District Engineer. These plans must receive the approval required by law before work begins.
Notice is hereby given that the permittee should recognize that a possibility exists that the structures permitted herein may be subject to wavewash from passing vessels.
The issuance of this permit does not relieve the permittee from taking all proper steps to insure the integrity of the structures permitted herein and the safety of boats moored thereto from damage by wavewash and the permittee shall not hold the United States liable for any such damage.
In order for us to better serve you, please complete our Customer Service Survey located at: http://www.nan.usace.army.mil/Missions/Regulatory/CustomerSurvey.aspx.
If any questions should arise concerning this matter, please contact Christopher Minck, of my staff, at Christopher.W.Minck@usace.army.mil.
Sincerely, FOR AND IN BEHALF OF
Alexander L. Young Colonel, U.S. Army
Enclosures Commander and District Engineer mailto:Christopher.W.Minck@usace.army.mil http://www.nan.usace.army.mil/Missions/Regulatory/CustomerSurvey.aspx mailto:Christopher.W.Minck@usace.army.mil
PERMITTEE: New York City Department of Parks and Recreation
PERMIT NO.: NAN-2024-00634
- 3 -
PERMIT CONDITIONS:
NOTE: The term "you" and its derivatives, as used in this permit means the permittee or any future transferee. The term "this office" refers to the appropriate district or division office of the Corps of Engineers having jurisdiction over the permitted activity or appropriate official of that office acting under the authority of the commanding officer.
GENERAL CONDITIONS:
1. The time limit for completing the work authorized ends within three years of the date of this permit. If you find that you need more time to complete the authorized activity, submit your request for a time extension to this office for consideration at least four months before the date is reached.
2. You must maintain the activity authorized by this permit in good condition and in conformance with the terms and conditions of this permit. You are not relieved of this requirement if you abandon the permitted activity, although you may make a good faith transfer to a third party upon written notification to this office. Should you wish to cease to maintain the authorized activity or should you desire to abandon it without a good faith transfer, you must obtain a modification of this permit from this office, which may require restoration of the area.
3. If you discover any previously unknown historic or archeological remains while accomplishing the activity authorized by this permit, you must immediately notify this office of what you have found. We will initiate the Federal and state coordination required to determine if the remains warrant a recovery effort or if the site is eligible for listing in the National Register of Historic Places.
4. You must allow representatives from this office to inspect the authorized activity at any time deemed necessary to ensure that it is being or has been accomplished in accordance with the terms and conditions of your permit.
Special Conditions:
A. The permittee understands and agrees that, if future operations by the United States require the removal, relocation, or other alteration, of the structure or work herein authorized, or if, in the opinion of the Secretary of the Army or his authorized representative, said structure or work shall cause unreasonable obstruction to the free navigation of the navigable waters, the permittee will be required, upon due notice from the Corps of Engineers, to remove, relocate, or alter the structural work or obstructions caused thereby, without expense to the United States. No claim shall be made against the United States on account of any such removal or alteration.
- 4 -
B. The permittee shall utilize best management practices to minimize turbidity during all in-water work activities as well as prevent construction materials, including debris, from entering any waterway to become drift or pollution hazards.
C. The permit shall submit the following information for any in-water work, at a minimum, to the First Coast Guard District and Sector New York at D01-SMB- LNM@uscg.mil and D01-SMB-SecNY-Waterways@uscg.mil, a minimum of 14 days before starting operations for publication in the Local Notice to Mariners:
Date of submission Name, phone number, and email address of project point of contact Company Name Type of Work Waterway and location where work will be done Latitude & Longitude of work area (Degrees, Minutes, Thousandths of seconds) Work Start & Stop dates and Hours of Operation Equipment on scene Passing Arrangements / Time to move vessels to not impede navigation VHF Radio Channel monitored Disposal Site (if used) NOAA Chart Number for the area
D. The permittee shall email a copy of the USACE Permit; as-built drawings; and NOAA Permit/Public Notice Status Report from https://www.nauticalcharts.noaa.gov/charts/docs/charts-updates/USACE+Permit+Status+Report.pdf to ocs.ndb@noaa.gov so they may initiate the appropriate chart and Coast Pilot corrections.
E. The permittee shall ensure any current, or future, outdoor lighting is located or shielded so that it is not confused with any aids to navigation and does not interfere with navigation on the adjacent waterway. If installed, the lights must be white and non-flashing.
Further Information:
1. Limits of authorization.
a. This permit does not obviate the need to obtain other Federal, state, or local authorizations required by law.
b. This permit does not grant any property rights or exclusive privileges.
c. This permit does not authorize any injury to the property or rights of others.
d. This permit does not authorize interference with any existing or proposed Federal project.
mailto:D01-SMB-LNM@uscg.mil mailto:D01-SMB-LNM@uscg.mil mailto:D01-SMB-SecNY-Waterways@uscg.mil https://www.nauticalcharts.noaa.gov/charts/docs/charts-updates/USACE+Permit+Status+Report.pdf https://www.nauticalcharts.noaa.gov/charts/docs/charts-updates/USACE+Permit+Status+Report.pdf mailto:ocs.ndb@noaa.gov
- 5 -
2. Limits to Federal Liability. In issuing this permit, the Federal Government does not assume any liability for the following:
a. Damages to the permitted project or uses thereof as a result of other permitted or unpermitted activities or from natural causes.
b. Damages to the permitted project or uses thereof as result of current or future activities undertaken by or on behalf of the United States in the public interest.
c. Damages to persons, property, or to other permitted or unpermitted activities or structures caused by the activity authorized by this permit.
d. Design or construction deficiencies associated with the permitted work.
e. Damage claims associated with any future modification, suspension, or revocation of this permit.
3. Reliance on Applicant's Data: The determination of this office that issuance of this permit is not contrary to the public interest was made in reliance on the information you provided.
4. Reevaluation of Permit Decision: This office may reevaluate its decision on this permit at any time the circumstances warrant. Circumstances that could require a reevaluation include, but are not limited to, the following:
a. You fail to comply with the terms and conditions of the permit.
b. The information provided by you in support of your permit application proves to have been false, incomplete, or inaccurate (See 3 above).
c. Significant new information surfaces which this office did not consider in reaching the original public interest decision.
Such a reevaluation may result in a determination that it is appropriate to use the suspension, modification, and revocation procedures contained in 33 CFR 325.7 or enforcement procedures such as those contained in 33 CFR 326.4 and 326.5.
The referenced enforcement procedures provide for the issuance of an administrative order requiring you to comply with the terms and conditions of your permit and for the initiation of legal action where appropriate. You will be required to pay for any corrective measures ordered by this office, and if you fail to comply with such directive, this office may in certain situations (such as those specified in 33 CFR 209.170) accomplish the corrective measures by contract or otherwise and bill you for the cost.
5. Extensions. General Condition 1 establishes a time limit for the completion of the activity authorized by this permit. Unless there are circumstances requiring either a
- 6 -prompt completion of the authorized activity or a reevaluation of the public interest decision, the Corps will normally give favorable consideration to a request for an extension of this time limit.
TC 10TC 10 . 4444
9 .71
TCTC9
C 6 7
TC
7.3.3
TCTC
TC 8 .6 6
TC 9 .1 6
T CC 9 .3 8
TC 9.
TC
89 7
2 3
C 7 .5
T C 7 .0 1
W OO D D O CK
FL OA T IN G D OC K
.94
HUNTS POINT RIVERSIDE - DOCK
OLMSTED CENTER
FLUSHING MEADOWS CORONA PARK
FLUSHING, NEW YORK, NY 11368
X3
-1
M
X336-119M
CITY OF NEW YORK PARKS & RECREATION
COMMISSIONER
DEPUTY COMMISSIONER, CAPITAL PROJECTS
LANDSCAPE ARCHITECTURE
VINCENT CIRRITO, PLA
NANCY PRINCE, PLA, ASLA
MEREDITH GRIFFIN
ANDREW PENZI, PLA
, PLA
TEAM LEADER, BROOKLYN
CHRISTOPHER SYRETT, PLA
DESIGN DIRECTOR, BROOKLYN
TEAM LEADER, MANHATTAN
DESMOND SPILLANE, PLA
DESIGN DIRECTOR, MANHATTAN
ERIC MATTES, PLA
DESIGN DIRECTOR, QUEENS
TEAM LEADER, STATEN ISLAND
ADRIAN SMITH, PLA
ARCHITECTURE AND ENGINEERING
ASSISTANT COMMISSIONER FOR ARCHITECTURE AND
ENGINEERING PROGRAM MANAGEMENT
TERENCE MCCORMICK, PE
ALLAIRE O'CONNOR, PE
CONSTRUCTION
PHILIP GRANITTO
Hunts Point Riverside Dock 6 21 24
USACE FILE: NAN-2024-00634-EMI
-2.58
WWWWWWW
BOULDER
"RIP-RAP"
1.26
1.41
6.0
RASS
6.23
4.42
3.72
3.98
4.36
4.42
3.37
3.54
4.34
5.78
5.39
5.60
5.74
5.05
4.26
5.09
6.47
6.15
6.21
6.17
3.66
3.45
2.81
2.87 3.62
-5.33
-6.08
-5.93 -5.86
-5.62
-7.55
-7.56
-3.72
-4.19
-4.48
-4.62
-4.11-3.50
-1.50
-1.37
-1.48
-0.98
-0.89
1.52
1.10
2.75
3.87
4.23
3.76
5.39
5.47
5.71
5.70
-1.04
-1.03
-1.07
3.82
3.04
2.24
2.62
5.79
5.46
5.41
-2.0
-1.0
3.0
4.0
0.0
2.0
1.0
3.5
6.35
0.68
S
-1.0
0.0
1.0
-5.0
-5.0
-6.0
-4.0
2.0
2.0 1.0
0.0
3.0
-2.0
DISCIPLINE LEAD:
DESIGNER:
DRAFTED BY:
CHECKED BY:
CONTRACT NO.: DATE:
PROJECT TITLE:
ADDRESS:
NO. DATE REVISION
LOT:BLOCK:
DRAWING TITLE:
DRAWING NO.:
SHEETS IN
CONTRACT SET:
SHEET OF
RESERVED FOR PLAN EXAMINER'S STAMPS
PROJECT MANAGER
X336-199M
Hunts Point Dock
N/A N/A 1409 Lafayette Ave Bronx, NY 10474
CONSULTANTS:
BLUESHORE ENGINEERING LLC
NYC PARKS PROJECT MANAGER:
COMMISSIONER
DEPUTY COMMISSIONER, CAPITAL PROJECTS
LANDSCAPE ARCHITECTURE
VINCENT CIRRITO, PLA
ASSISTANT COMMISSIONER
NANCY PRINCE, PLA, FASLA
CHIEF OF LANDSCAPE ARCHITECTURE
MEREDITH GRIFFIN
CHIEF OF LANDSCAPE PROGRAM MANAGEMENT
ARCHITECTURE AND ENGINEERING
TERENCE MCCORMICK, PE
ASSISTANT COMMISSIONER FOR ARCHITECTURE
AND ENGINEERING PROGRAM MANAGEMENT
REBECCA BYRNES, RA
CHIEF OF ARCHITECTURE AND ENGINEERING
MARLISA WISE, RA
TEAM LEADER OF ARCHITECTURE
ALLAIRE O'CONNOR, PE
TEAM LEADER OF ENGINEERING
RICHARD GILBERT
JOSEPH ANGELI, MIGUEL SANCHEZ
JOSEPH ANGELI, MIGUEL SANCHEZ
RICHARD GILBERT
04/23/2024
REMOVALS PLAN
S-201.00
NORTH
00 8' 16'4'
BRONX RIVER
CUT AND REMOVE AT MUDLINE,
LANDSIDE STEEL PILES
TYP. FOR (4)
REMOVE
FLOATING
DOCK
PROPERTY LINE
REMOVE
ALUMINUM
GANGWAY
PROPERTYLINE
MLW EL.
-3.26'
S-501
REMOVE TIMBER
JOISTS, TYP. OF (4)
REMOVE TIMBER
PILE
REMOVE PILE
CAP
CUT AND REMOVE COMPOSITE
DECK APPROX. 102 SF
CUT & REMOVE PIER
EDGE BEAM
TIMBER PILE
CAP TO
REMAIN
CUT TIMBER
JOISTS, TYP. OF (4)
INSTALL SHORING AS
REQUIRED
MHW EL. +2.98'
SHW EL. +3.66'
PROPERTY LINE
PROPERTY LINE
REMOVALS WORK
AREAS, SEE 1/S-201
LEGEND
CONTOUR LINE
Hunts Point Riverside Dock 6 21 24
S
S
BOULDER
"RIP-RAP"
1.26
1.47
1.41
6.23
4.42
3.72
3.98
4.364
4.42
3.37
3.54
4.34
5.78
5.39339
5.60
5.74
5.055 5
4.26644
6.47
6.15
6.21
6.177
TB
6 65
3.66
3.45 2.87 3.62
2 70
-5.33
-6.08
-5.93 -5.86
-5.62
-7.55
-7.56
-3.72
-4.19
-4.48
-4.62
-4.11-3.50
-1.50
-1.37
-1.48
-0.98
-0.89
1.52
1.10
0.68
2.75
3.87
4.234
3.76
5.47
5.71
5.70
-1.04
-1.03
-1.07
3.82
3.04
2.24
2.62
5.7975
5.46
5.41
3.50
2 7
-1.0
0.0
1.0
2.0
2.0
2.0
1.0
0.0
-1.0
3.0
3.0
4.0
-4.0
-5.0
-5.0
-6.06 0-6 0-66
-7.00-7.0-7
3.0
0.0
2.0
1.0 -1.0
-5.0
3.5
3.5
-55 00
-55 0
-55 0
-0.
-1 00
-00.9 -1 0
-1 00
00 0
00.0
0.00
1.00
1.1 1 00
1 00
22.00
22 0
33.0
A
22.00
2 0
3 04
3 00
22 662
1.41
-2.58585888
6.35
-44 00
3.03.3 003 0-3 0-333 00
DISCIPLINE LEAD:
DESIGNER:
DRAFTED BY:
CHECKED BY:
CONTRACT NO.: DATE:
PROJECT TITLE:
ADDRESS:
NO. DATE REVISION
LOT:BLOCK:
DRAWING TITLE:
DRAWING NO.:
SHEETS IN
CONTRACT SET:
SHEET OF
RESERVED FOR PLAN EXAMINER'S STAMPS
PROJECT MANAGER
X336-199M
Hunts Point Dock
N/A N/A 1409 Lafayette Ave Bronx, NY 10474
CONSULTANTS:
BLUESHORE ENGINEERING LLC
NYC PARKS PROJECT MANAGER:
COMMISSIONER
DEPUTY COMMISSIONER, CAPITAL PROJECTS
LANDSCAPE ARCHITECTURE
VINCENT CIRRITO, PLA
ASSISTANT COMMISSIONER
NANCY PRINCE, PLA, FASLA
CHIEF OF LANDSCAPE ARCHITECTURE
MEREDITH GRIFFIN
CHIEF OF LANDSCAPE PROGRAM MANAGEMENT
ARCHITECTURE AND ENGINEERING
TERENCE MCCORMICK, PE
ASSISTANT COMMISSIONER FOR ARCHITECTURE
AND ENGINEERING PROGRAM MANAGEMENT
REBECCA BYRNES, RA
CHIEF OF ARCHITECTURE AND ENGINEERING
MARLISA WISE, RA
TEAM LEADER OF ARCHITECTURE
ALLAIRE O'CONNOR, PE
TEAM LEADER OF ENGINEERING
RICHARD GILBERT
JOSEPH ANGELI, MIGUEL SANCHEZ
JOSEPH ANGELI, MIGUEL SANCHEZ
RICHARD GILBERT
04/23/2024
PROPOSED SITE PLAN
S-202.00
NORTH
LEGEND
BLOCK 2770
LOT 316
PROPOSED 30'X4' ALUMINUM
GANGWAY TO BE INSTALLED AT
MODIFIED PIER CORNER
BRONX RIVER
EXISTING OUTBOARD PILES TO REMAIN
AS INBOARD PILES, TYP. OF (4).
REINFORCE PER 1/S-501
50'X8' PROPOSED FLOATING DOCK
W/ STEEL FRAME AND COMPOSITE
TIMBER DECKING, 400 SQFT
4'-0"
1"
S-301
PROPERTY LINE
TYP.
MLW EL. -3.26'
60" MIN
CLEAR SPACE
AT LANDING
FLOATING DOCK EXTENSION AREA
TO SUPPORT GANGWAY. APPROX
7.65 SF.
3'-0"
PROPERTY LINE
S-301
3' TRANSITION PLATE
MHW EL. +2.98'
SHW EL. +3.66'
7"
12"X12" GANGWAY SUPPORT
BEAM TO BE
ATTACHED TO EXISTING PIER
FRAME
2'-4"
6'-9" 12'-0"
INSTALL IN-KIND RAILING TO MATCH
EXISTING APPROX. 25' LF.
REPAIR DECKING AT
NEW GANGWAY
CONNECTION
S-501
S-301
PROPOSED PIER
AREA 465 SQFT
S-301
PROPERTY LINE
EXISTING SIGNAGE
00 8' 16'4'
6"
1'-10"
Hunts Point Riverside Dock 6 21 24
DISCIPLINE LEAD:
DESIGNER:
DRAFTED BY:
CHECKED BY:
CONTRACT NO.: DATE:
PROJECT TITLE:
ADDRESS:
NO. DATE REVISION
LOT:BLOCK:
DRAWING TITLE:
DRAWING NO.:
SHEETS IN
CONTRACT SET:
SHEET OF
RESERVED FOR PLAN EXAMINER'S STAMPS
PROJECT MANAGER
X336-199M
Hunts Point Dock
N/A N/A 1409 Lafayette Ave Bronx, NY 10474
CONSULTANTS:
BLUESHORE ENGINEERING LLC
NYC PARKS PROJECT MANAGER:
COMMISSIONER
DEPUTY COMMISSIONER, CAPITAL PROJECTS
LANDSCAPE ARCHITECTURE
VINCENT CIRRITO, PLA
ASSISTANT COMMISSIONER
NANCY PRINCE, PLA, FASLA
CHIEF OF LANDSCAPE ARCHITECTURE
MEREDITH GRIFFIN
CHIEF OF LANDSCAPE PROGRAM MANAGEMENT
ARCHITECTURE AND ENGINEERING
TERENCE MCCORMICK, PE
ASSISTANT COMMISSIONER FOR ARCHITECTURE
AND ENGINEERING PROGRAM MANAGEMENT
REBECCA BYRNES, RA
CHIEF OF ARCHITECTURE AND ENGINEERING
MARLISA WISE, RA
TEAM LEADER OF ARCHITECTURE
ALLAIRE O'CONNOR, PE
TEAM LEADER OF ENGINEERING
RICHARD GILBERT
JOSEPH ANGELI, MIGUEL SANCHEZ
JOSEPH ANGELI, MIGUEL SANCHEZ
RICHARD GILBERT
04/23/2024
SECTIONS & ELEVATIONS
S-301.00
FLOATING DOCK
PER PLAN
ALUMINUM
GANGWAY PER
PLAN
DECK EL.
+6.80'
STEEL PILES PER
STEEL 4-PILE
CLUSTER PER
PLAN, TYP.
TYP.
50'-0"
SHW EL. +3.69'
4.25"X12.5"
TIMBER BRACING, TYP.
MHW EL. +2.98'
MLW EL. -3.26'
MUDLINE EL.
ALUMINUM GANGWAY
PER PLAN
DECK EL. +6.8'
REINFORCED STEEL PILES PER PLAN.
SEE 1/S-501
TYP.
TIMBER FRAME
SEE 7/S-501
MAX. DESIGN WATER EL. +15'
DOCK PER PLAN
50'-0"
MUDLINE EL.
MHW EL. +2.98'
MLW EL. -3.26'
SHW EL. +3.69'
NOTE: 4-PILE CLUSTERS NOT SHOWN FOR CLARITY
NEW CAP EL. +20.5'
6'-9" PILE
EXTENSION
FLOATING DOCK
PER PLAN
3.55
MHW EL. +2.98'
MLW EL. -3.26'
SHW EL. +3.69'
FREEBOARD
FLOATING DOCK
EXTENSION AREA
PER PLAN
ALUMINUM
GANGWAY
PER PLAN
STEEL PILES
PER PLAN
GANGWAY SUPPORT
BEAM PER PLAN
MUDLINE
EL. +6.8'
60" MIN. CLEAR
SPACE AT LANDING
TUBE PICKETS @ 4"
O.C. ALONG FULL
LENGTH OF
GANGWAY
NOTES:
1. CONTRACTOR AND GANGWAY MANUFACTURER SHALL DETERMINE FINAL GANGWAY MEMBER SIZES AND
SUBMIT TO ENGINEER FOR REVIEW AND APPROVAL.
2. ALUMINUM GRATING SHALL MEET ADA REQUIREMENTS.
NOTE:
1. CONTRACTOR AND DOCK MANUFACTURER SHALL DETERMINE FINAL DOCK MEMBER
SIZES, FLOAT SIZES, FLOAT MATERIAL, AND CONSTRUCTION, AND SUBMIT TO ENGINEER
FOR REVIEW AND APPROVAL.
STEEL CROSS
BRACE
DOCK FLOAT,
TYP.
8"-12"
COMPOSITE
TIMBER DOCK
DECKING
2X8 TIMBER
(2) 2X6 TIMBER
TYP.
LAG BOLT,
TYP.
2" HEX THROUGH
BOLT TO FASTEN FLOAT
TO DOCK FRAME
EXISTING PIER
FRAME PER PLAN
STEEL INFILL TO
MATCH EXISTING,
TYP.
TIMBER TOP
RAIL
DECKING PER
PLAN
42"
6'-6" TYP.
STEEL POSTS
TO MATCH
EXISTING
2"
16"
9" FREEBOARD
MLW EL. -3.26'
2" CLEARANCE AT MLW
NOTE: SPECIAL CARE SHOULD BE TAKEN IN THE FIELD WHEN POSITIONING THE
GANGWAY SUPPORT BEAM SUCH THAT THE GANGWAY WILL NOT INTERSECT WITH
THE EXISTING STRUCTURE.
EXST PIER (PILES NOT
SHOWN FOR CLARITY)
8'-11"
4"
S-301
S-501
00 4' 6'2'
00 8' 16'4'
00 2' 3'1' 00 2' 3'1'
00 8' 16'4' 00 10' 20'5'
00 8' 16'4'
S-501
Hunts Point Riverside Dock 6 21 24
DISCIPLINE LEAD:
DESIGNER:
DRAFTED BY:
CHECKED BY:
CONTRACT NO.: DATE:
PROJECT TITLE:
ADDRESS:
NO. DATE REVISION
LOT:BLOCK:
DRAWING TITLE:
DRAWING NO.:
SHEETS IN
CONTRACT SET:
SHEET OF
RESERVED FOR PLAN EXAMINER'S STAMPS
PROJECT MANAGER
X336-199M
Hunts Point Dock
N/A N/A 1409 Lafayette Ave Bronx, NY 10474
CONSULTANTS:
BLUESHORE ENGINEERING LLC
NYC PARKS PROJECT MANAGER:
COMMISSIONER
DEPUTY COMMISSIONER, CAPITAL PROJECTS
LANDSCAPE ARCHITECTURE
VINCENT CIRRITO, PLA
ASSISTANT COMMISSIONER
NANCY PRINCE, PLA, FASLA
CHIEF OF LANDSCAPE ARCHITECTURE
MEREDITH GRIFFIN
CHIEF OF LANDSCAPE PROGRAM MANAGEMENT
ARCHITECTURE AND ENGINEERING
TERENCE MCCORMICK, PE
ASSISTANT COMMISSIONER FOR ARCHITECTURE
AND ENGINEERING PROGRAM MANAGEMENT
REBECCA BYRNES, RA
CHIEF OF ARCHITECTURE AND ENGINEERING
MARLISA WISE, RA
TEAM LEADER OF ARCHITECTURE
ALLAIRE O'CONNOR, PE
TEAM LEADER OF ENGINEERING
RICHARD GILBERT
JOSEPH ANGELI, MIGUEL SANCHEZ
JOSEPH ANGELI, MIGUEL SANCHEZ
RICHARD GILBERT
04/23/2024
DETAILS
S-501.00
TIES PER
2/S-501
S-501 1" DOMED
CONCRETE
STEEL PIPE
PILE
PER PLAN
2"
10"
TYP.
MIN 1"
CLR
#3 TIES,
TYP.
(5) #5 VERT.
BARS, TYP.
MHW EL. +2.98'
MLW EL. -3.26'
SHW EL. +3.69'
MUDLINE EL. -5.0'
TOP OF ROCK, APPROX
EL. -27.50'
STEEL PIPE
PILE
PER PLAN
CONCRETE
FILL
F'C=4000 PSI
MIN 1"CLR
VERT. BARS
PER 2/S-501
REMOVE DOCK
SUPPORT SYSTEM
CUT OFF AND GRIND SMOOTH
EXSTING INBOARD
PILES TO BE REMOVED.
SEE 1/S-201
EXISTING OUTBOARD PILES TO REMAIN
SEE 1/S-202 & 1/S-501
S-501
16"6"
1-1
ROLLER, TYP. OF
(4) PER PILE
HDG STEEL
PILE COLLAR
BRACE,
BOLTED TO
DOCK
EXISTING STEEL
PILE PER PLAN
DOCK PER
PLAN
PILE
MHW EL. +2.98'
SHW EL. +3.69'
6'-9"
EXISTING PIER EDGE BEAM
PER PLAN, TYP.
EXISTING JOISTS PER PLAN, TYP.DECK PER
PLAN
GANGWAY SUPPORT BEAM
PER PLAN
TIMBER PILE CAP PER
PLAN
NOTE: ALUMINUM GANGWAY NOT SHOWN FOR CLARITY
PILE
PILE
PILE
00 1' 2'6"
00 1' 2'6"
00 2' 3'1'
00 1' 2'6"
000 2' 4'1'
000 2' 4'1'
000 2' 4'1'
00 3" 6" 9" 12"
OR ENGINEER APPROVED
EQUIVALENT
3/8"
Hunts Point Riverside Dock 6 21 24
JACOB K. JAVITS FEDERAL BUILDING
26 FEDERAL PLAZA
NEW YORK NEW YORK 10278-0090
CENAN-OP-R
IMPORTANT
This letter must be completed and mailed to the Regulatory Branch at the above address prior to commencement of any work authorized under the permit.
Permittee: ______________________________ Permit No. ___________________________
Date Permit Issued: ______________________ Expiration Date: ______________________
Waterway: ____________________________________________________________________
Project Location: _______________________________________________________________
Work will commence on or about: _________________________
Name, Address & Telephone Number of Contractor:
Signature of Permittee Date
Fold this form into thirds, with the bottom third facing outward. Tape it together and mail to the address below or FAX to (212) 264-4260.
___________________ Place Stamp
___________________ Here
USACE Operations/Regulatory 16-406 c/o PSC Mail Center 26 Federal Plaza New York, New York 10278
JACOB K. JAVITS FEDERAL BUILDING
26 FEDERAL PLAZA
NEW YORK NEW YORK 10278-0090
CENAN-OP-R
IMPORTANT
This letter must be completed and mailed to the Regulatory Branch at the above address following completion or cancellation of work authorized under the permit.
Permittee: _ Permit No. __ __ _
Date Permit Issued: __________ _ Expiration Date: _______ ___
Waterway: __ ___ _
Project Location: ____ ___ __
Check and complete applicable item(s) listed below:
____ Work was completed on _________________________
____ Work will not be performed on the project.
____ Deviation from work authorized in permit is explained below.
____ Other (explain) _______________________________________ __________
____ For dredging projects, list the volume of material dredged, and the amount placed at each disposal location (if more than one).
________ cubic yards placed at ____________________________
________ cubic yards placed at ____________________________
________ cubic yards placed at ____________________________
Signature of Permittee Date
Fold this form into thirds, with the bottom third facing outward. Tape it together and mail to the address below or FAX to (212) 264-4260.
___________________ Place Stamp
___________________ Here
USACE Operations/Regulatory 16-406 c/o PSC Mail Center 26 Federal Plaza New York, New York 10278
-1-
NOTIFICATION OF ADMINISTRATIVE APPEAL OPTIONS AND PROCESS AND
REQUEST FOR APPEAL
Applicant: File Number: Date:
Attached is: See Section below
INITIAL PROFFERED PERMIT (Standard Permit or Letter of permission) A PROFFERED PERMIT (Standard Permit or Letter of permission) B
PERMIT DENIAL WITHOUT PREJUDICE C
PERMIT DENIAL WITH PREJUDICE D
APPROVED JURISDICTIONAL DETERMINATION E
PRELIMINARY JURISDICTIONAL DETERMINATION F
SECTION I
The following identifies your rights and options regarding an administrative appeal of the above decision. Additional information may be found at https://www.usace.army.mil/Missions/Civil- Works/Regulatory-Program-and-Permits/appeals/ or Corps regulations at 33 CFR Part 331.
A: INITIAL PROFFERED PERMIT: You may accept or object to the permit
• ACCEPT: If you received a Standard Permit, you may sign the permit document and return it to the district engineer for final authorization. If you received a Letter of Permission (LOP), you may accept the LOP and your work is authorized. Your signature on the Standard Permit or acceptance of the LOP means that you accept the permit in its entirety, and waive all rights to appeal the permit, including its terms and conditions, and approved jurisdictional determinations associated with the permit.
• OBJECT: If you object to the permit (Standard or LOP) because of certain terms and conditions therein, you may request that the permit be modified accordingly. You must complete Section II of this form and return the form to the district engineer. Upon receipt of your letter, the district engineer will evaluate your objections and may: (a) modify the permit to address all of your concerns, (b) modify the permit to address some of your objections, or (c) not modify the permit having determined that the permit should be issued as previously written. After evaluating your objections, the district engineer will send you a proffered permit for your reconsideration, as indicated in Section B below.
B: PROFFERED PERMIT: You may accept or appeal the permit
• ACCEPT: If you received a Standard Permit, you may sign the permit document and return it to the district engineer for final authorization. If you received a Letter of Permission (LOP), you may accept the LOP and your work is authorized. Your signature on the Standard Permit or acceptance of the LOP means that you accept the permit in its entirety, and waive all rights to appeal the permit, including its terms and conditions, and approved jurisdictional determinations associated with the permit.
• APPEAL: If you choose to decline the proffered permit (Standard or LOP) because of certain terms and conditions therein, you may appeal the declined permit under the Corps of Engineers Administrative Appeal Process by completing Section II of this form and sending the form to the division engineer. This form must be received by the division engineer within 60 days of the date of this notice.
https://www.usace.army.mil/Missions/Civil-Works/Regulatory-Program-and-Permits/appeals/ https://www.usace.army.mil/Missions/Civil-Works/Regulatory-Program-and-Permits/appeals/
-2-
C. PERMIT DENIAL WITHOUT PREJUDICE: Not appealable You received a permit denial without prejudice because a required Federal, state, and/or local authorization and/or certification has been denied for activities which also require a Department of the Army permit before final action has been taken on the Army permit application. The permit denial without prejudice is not appealable. There is no prejudice to the right of the applicant to reinstate processing of the Army permit application if subsequent approval is received from the appropriate Federal, state, and/or local agency on a previously denied authorization and/or certification.
D: PERMIT DENIAL WITH PREJUDICE: You may appeal the permit denial You may appeal the denial of a permit under the Corps of Engineers Administrative Appeal Process by completing Section II of this form and sending the form to the division engineer. This form must be received by the division engineer within 60 days of the date of this notice.
E: APPROVED JURISDICTIONAL DETERMINATION: You may accept or appeal the approved JD or provide new information for reconsideration
• ACCEPT: You do not need to notify the Corps to accept an approved JD. Failure to notify the
Corps within 60 days of the date of this notice means that you accept the approved JD in its entirety and waive all rights to appeal the approved JD.
• APPEAL: If you disagree with the approved JD, you may appeal the approved JD under the
Corps of Engineers Administrative Appeal Process by completing Section II of this form and sending the form to the division engineer. This form must be received by the division engineer within 60 days of the date of this notice.
• RECONSIDERATION: You may request that the district engineer reconsider the approved JD by submitting new information or data to the district engineer within 60 days of the date of this notice.
The district will determine whether the information submitted qualifies as new information or data that justifies reconsideration of the approved JD. A reconsideration request does not initiate the appeal process. You may submit a request for appeal to the division engineer to preserve your appeal rights while the district is determining whether the submitted information qualifies for a reconsideration.
F: PRELIMINARY JURISDICTIONAL DETERMINATION: Not appealable You do not need to respond to the Corps regarding the preliminary JD. The Preliminary JD is not appealable. If you wish, you may request an approved JD (which may be appealed), by contacting the Corps district for further instruction. Also, you may provide new information for further consideration by the Corps to reevaluate the JD.
POINT OF CONTACT FOR QUESTIONS OR INFORMATION:
If you have questions regarding this decision you may contact:
Stephan A. Ryba Chief, Regulatory Branch (CENAN-OP-R) USACE Operations/Regulatory 16-406 c/o PSC Mail Center 26 Federal Plaza New York, New York 10278
If you have questions regarding the appeal process, or to submit your request for appeal, you may contact:
Andrew Dangler Regulatory Appeals Review Officer North Atlantic Division – Fort Hamilton 301 John Warren Avenue – First Floor Brooklyn, NY 11252-6700
(518) 487-0215
-3-
SECTION II – REQUEST FOR APPEAL or OBJECTIONS TO AN INITIAL PROFFERED PERMIT
REASONS FOR APPEAL OR OBJECTIONS: (Describe your reasons for appealing the decision or your objections to an initial proffered permit in clear concise statements. Use additional pages as necessary. You may attach additional information to this form to clarify where your reasons or objections are addressed in the administrative record.)
ADDITIONAL INFORMATION: The appeal is limited to a review of the administrative record, the Corps memorandum for the record of the appeal conference or meeting, and any supplemental information that the review officer has determined is needed to clarify the administrative record.
Neither the appellant nor the Corps may add new information or analyses to the record. However, you may provide additional information to clarify the location of information that is already in the administrative record.
RIGHT OF ENTRY: Your signature below grants the right of entry to Corps of Engineers personnel, and any government consultants, to conduct investigations of the project site during the course of the appeal process. You will be provided a 15-day notice of any site investigation and will have the opportunity to participate in all site investigations.
Signature of appellant or agent.
Date:
Email address of appellant and/or agent: Telephone number:
| We have completed our review of Application Number NAN-2024-00634-EMI. |
| PERMIT CONDITIONS: |
| GENERAL CONDITIONS: |
| Special Conditions: |
| Further Information: |
| CENAN-OP-RE |
| MEMORANDUM FOR RECORD |
| Date1_af_date: August 13, 2024 | |
| Date2: October 11, 2024 | |
| Work will commence on or about: | |
| Text2: | |
| Check and complete applicable items listed below: | |
| undefined_2: | |
| undefined_3: | |
| amount placed at each disposal location if more than one: | |
| cubic yards placed at: | |
| cubic yards placed at_2: | |
| cubic yards placed at_3: | |
| 1: | |
| 2: | |
| 1_2: | |
| 2_2: | |
| 3: | |
| Check Box7: Off | |
| Check Box8: Off | |
| Check Box9: Off | |
| Check Box10: Off | |
| Waterway: Bronx River | |
| Project Location: Hunts Point Riverside Park, Borough of The Bronx, Bronx County, City of New York, New York | |
| Expiration Date: August 13, 2027 | |
| Applicant: New York City Dept. of Parks and Recreation | |
| Date: August 13, 2024 | |
| File Number: NAN-2024-00634 | |
| Check Box6: Off | |
| Check Box1: Yes | |
| Check Box2: Off | |
| Check Box3: Off | |
| Check Box4: Off | |
| Check Box5: Off | |
| Reason for Appeal or Objection: | |
| Date6_af_date: | |
| Email Address: | |
| Telephone Number: | |
| 2024-08-13T08:34:52-0400 | |
| Rosita Miranda |
File details come from the government source that posted it. Updated .