B.08.03_Amendment 0001 - Bronx River 2024 - Solicitation W912DS-24-B-0023 4 Oct 2024.pdf
PDF 291 KB Posted
- Solicitation number
- W912DS24B0023
About this file
This document is Amendment 0001 to Solicitation W912DS-24-B-0023 for the maintenance dredging of the Bronx River, NY, Federal Navigation Project. The amendment responds to questions from potential bidders and provides revisions to the solicitation documents.
The key details are:
- The correct volume of material to be dredged from Dredge Area 2A is 73,910 CY, not 79,910 CY as initially listed.
- Transloading of dredged material is not expressly prohibited, but must conform to requirements in the NYSDEC Water Quality Certificate.
- The contractor will be allowed to commence dredging at the south end of the project and progress to the north.
- The overdepth channel bottom is 100' wide, matching the required channel width.
- The project completion time has been revised from 32 calendar days to approximately 55 days from the Notice to Proceed, allowing for 12 days of mobilization/demobilization.
- Additional information on channel coordinates and utilities has been provided.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
See Continuation Page.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 9
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 04-Oct-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DS24B0023
X 9B. DATED (SEE ITEM 11)
20-Sep-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
04-Oct-2024
CODE
US ARMY CORPS OF ENGINEERS, NEW YORK
26 FEDERAL PLAZA, RM 16-300
NEW YORK NY 10278-0090
W912DS 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DS24B0023
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0001
AMENDMENT 0001
Bronx River, New York Federal Navigation Project
Solicitation No. W912DS-24-B-0023
The purpose of this Amendment 0001 is to 1) respond to the following questions posed by potential bidders and 2) provide additional/necessary revisions to solicitation documents.
1. Questions from potential bidders and USACE responses:
Question 1: The bid schedule lists a quantity of 79,910 CY for Dredge Area 2A, bid item 0003.
Section 01 11 00 (Summary of Work), page 3, lists the volume as 73,910 CY. Section 01 30 00 (Administrative Requirements), page 9, also lists the volume as 73,910 CY. Please clarify the volume of material to be dredged for Dredge Area 2A.
Answer 1: 73,910 cubic yards (CY) is the correct volume for Dredging Area 2A, CLIN 0003. A revised Bid Schedule is included in this amendment.
Question 2: Will transloading of dredged material be allowed for this project? At what location will the contractor be allowed to perform transloading operations?
Answer 2: Means and methods utilized by the contractor for accomplishing the required work must conform with all conditions listed in the NYSDEC Water Quality Certificate (WQC). ‘Transloading’ of dredged material is not expressly described within the project’s WQC, but any ‘transloading’ must conform to relevant/applicable material handling conditions listed within the WQC and within this solicitation’s specifications. The contractor’s proposed means and methods for accomplishing the required work will be reviewed and discussed prior to award and again during the preconstruction conference.
Question 3: Please modify the contract duration to allow for a 12-day mobilization/demobilization period and dredging at a daily production rate of 3,500 cy per day, resulting in a completion date of approximately 55 days from NTP.
Answer 3: A Market Survey detailing the project parameters of concern was published on 24 June 2024. Responses to the Market Survey from multiple potential bidders indicate that the prescribed performance period and production rate are achievable. The means and methods for completing the work in accordance with the contract plans, specifications, and applicable laws/regulations (e.g. NYSDEC WQC) are left to the bidders/contractor.
Question 4: Section 01 11 00, page 3, paragraph 1.3.1 states; “…additional time will be allowed at the rate of one (1) calendar day for each 8,000 cubic yards in excess of the established limit”. As this is a shallow channel requiring tidal work dredging, please modify this to be a minimum average production rate of 3,500 cy per day.
Answer 4: Please see response to question 3.
Question 5: Per the USACE Fact Sheet for Bronx River, this channel was last dredged in 1991.
Please provide the type and quantity of debris that was encountered during the previous dredging contract.
Answer 5: Records of removed debris type and quantity are not available from the 1991 maintenance cycle, all potential bidders should anticipate the potential for encountering debris such as that listed in Section 01 20 00 including, but not limited to – “lumber, tires, scrap metal, car bodies, shopping carts, cables, pilings, line and all objects not included in the definition of natural material or material suitable for HARS placement”.
Question 6: Section 01 11 00, page 4, paragraph 1.3.1 states; “Dredging is prohibited during the seasonal no-dredging window from 15 January through 30 June.”. Given an October 22 bid date, a mid- November award date and a late November NTP are likely. This leaves ~45 days available between NTP and 15 January. As the dredging is tidal work, the completion of dredging may not occur prior to 15 January. Is the 15 January date able to be extended should the dredging need additional time due to a late- October bid date?
Answer 6: The seasonal no-dredging window is from 15 January to 30 September per the WQC dated 23 August 2024. The contractor will be required to conform with all WQC requirements, including no-dredge windows. A revised Section 01 11 00 Summary of Work is included in this amendment.
Question 7: Section 35 20 23, page 6, paragraph 3.2.1 states; “The Contracting Officer will direct the Contractor on the order of work”. As this is a shallow channel, it needs to be dredged from south to north to maximize channel depths between the dredge and the mouth of the river. Please confirm that the contractor will be allowed to commence dredging at the south end of the project and progress to the north.
Answer 7: Yes, the contractor will be allowed to commence dredging at the south end of the project and progress to the north.
Question 8: The typical cross-sections depicted in the plan sheets show an overdepth channel width (94’ at -11 MLLW) that is less than the required channel width (100’ at 10’ MLLW). Please confirm that the overdepth channel bottom is 100’ wide, matching the required channel width.
Answer 8: Yes, the overdepth channel bottom is 100’ wide or otherwise as wide as the channel toe (in the plan view) as shown on the contract plans.
Question 9: We are concerned about the completion time of the project being 32 calendar days. This seems incredibly short for a project that is estimated to be $5,000,000. Can you please confirm that the 32 day completion time frame is accurate?
Answer 9: Please see response to question 3.
Question 10: Please provide the XY coordinates and stationing of the channel vertices. Each has an identifying label (numbers 1 to 29), but we are unable to locate an associated table of points with corresponding coordinates and stationing.
Answer 10: Please find the requested XY coordinates and stationing included in this amendment.
Question 11: Plan sheet VH-107 depicts an area along the green toe that is labelled “ROCKS.” Also, there is an associated dashed line that appears to be drawn for only a portion of the distance of the rock area (assumed to be where there is missing hydrographic data). What is the intent of this rock area? Is the contractor to leave the area undisturbed? Please further delineate/identify the entire rock area in question.
Answer 11: The area of concern on Sheet VH-107 indicates the approximate location of an obstruction encountered during hydrographic surveying. In this case, shallow draft and the presence of rocks prevented the survey crew from obtaining data in this portion of the channel. The USACE intends to restore the entire channel to the depth and width described in the plans and specifications and in accordance with the NYSDEC WQC and contract specifications. However, if as work progresses, the Contractor determines that the stability of piers, bulkheads, or other structures may be jeopardized by dredging operations, the contractor shall immediately notify the Contracting Officer and/or their representative (See Section 35 20 23, 3.2.13 Safety of Structures). In addition, per the WQC dated 23 August 2024, “Where the environmental bucket repeatedly encounters resistance from consolidated materials (e.g. stone, rock) a conventional digging bucket may be used (with a written notice of intent to switch bucket at least 2 business days prior)”.
Question 12: Plan sheet VH-109 shows a small portion of the dredging area terminus ending approximately 30 feet under the Bruckner Boulevard Bridge. Is the contractor required to dredge material from under the low-clearance bridge?
Answer 12: Prior to contract award, the USACE and the apparent low bidder will discuss the low bidder’s plan to complete the project. Safety and any equipment-specific safety buffers will be discussed at this time. Per Section 01 30 00,1.7b – “The contractor shall exercise the utmost caution when dredging in the vicinity of any bridge, pier, abutment, or bulkhead to prevent the collapse, undermining or damage to these structures. In no case shall the contractor moor any plant to or tie any line, cable, chain or anchor line around any part of a bridge structure, pier, abutment or bulkhead connected therewith”. If as work progresses, the Contractor determines that the stability of piers, bulkheads, or other structures may be jeopardized by dredging operations, the contractor shall immediately notify the Contracting Officer and/or their representative (See Section 35 20 23, 3.2.13 Safety of Structures).
Additional/Revised Solicitation documents are attached as follows:
a. Revised Bid Schedule
b. Revised Section 01 11 00 Summary of Work (chg. seasonal window dates)
c. Revised Section 01 30 00 Administration Requirements (chg. utility crossing search results)
d. Additional/Supplemental - Utility/Cable Crossing Search Results
e. Additional/Supplemental - channel XY coordinates
Section 00 10 00 - Solicitation
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job Mobilization and Demobilization
FFP
Mobilization and Demobilization FOB: Destination
PSC CD: Y1KZ
NET AMT
0002 48,760 Cubic
Yard
Basic Work - Dredging Area 1
FFP
Dredging (to -10 feet MLLW + 1 foot allowable overdepth), Transportation and Placement (Sheets 3-6 of the contract drawings).Removal of material (48,760 CY) except ledge rock lying above the plane of 10 feet below mean lower low water (MLLW), plus 1 foot allowable overdepth from Dredging Area 1 of the Bronx River, NY, Federal Navigation Project with placement of the dredged material at the Historic Area Remediation Site (HARS). Estimated Quantities.
0003 73,910 Cubic
Basic Work - Dredging Area 2A
Dredging (to -10 feet MLLW + 1 foot allowable overdepth), Transportation and Placement (Sheets 6-9 of the contract drawings).Removal of material (73,910 CY) except ledge rock lying above the plane of 10 feet below mean lower low water (MLLW), plus 1 foot allowable overdepth from Dredging Area 2A of the Bronx River, NY, Federal Navigation Project with placement of the dredged material at the Historic Area Remediation Site (HARS). Estimated Quantities.
0004 19,945 Cubic
Basic Work - Dredging Area 2B
Dredging (to -10 feet MLLW + 1 foot allowable overdepth), Transportation and Placement (Sheets 9-10 of the contract drawings).Removal of material (19,945 CY) except ledge rock lying above the plane of 10 feet below mean lower low water (MLLW), plus 1 foot allowable overdepth from Dredging Area 2B of the Bronx River, NY, Federal Navigation Project with placement of the dredged material at the Historic Area Remediation Site (HARS). Estimated Quantities.
0005 40 Ton Miles Basic Work - Debris Removal and Disposal
FFP
Basic Work - Debris Removal and Disposal (During dredging)
0006 1 Job Black Box Monitoring
FFP
(See specifications Section 35 20 23.10 18)
0007 20 Ton Miles OPTION Option 1 - Debris Removal and Disposal
FFP
During dredging this is an additional ton beyond the 40 tons in CLIN 0005 and it is from 41 to 60 tons if needed.
0008 20 Ton Miles OPTION Option 2 - Debris Removal and Disposal
FFP
During dredging this is an additional ton beyond the 60 tons in CLIN 0006 and it is from 61 to 80 tons if needed.
TOTALS AND NOTES
TOTAL BASE BID (CLINs 0001 THRU 0006) $____________________________________
TOTAL OPTION BID (CLINs 0007 THRU 0008) $_____________________________________
TOTAL BID (CLINs 0001 THRU 0008) $_____________________________________
NOTES TO BIDDERS:
NOTE 01:Bidders are required to bid on both the Base Bid Items and the Optional Items on the Price Schedule or their bid will be rejected.
NOTE 02:Award of contract will be based on the responsible and responsive bidder with the lowest total price for the total of the CLINs 0001 through 0008.
NOTE 03:Any bid which is materially unbalanced as to the price for the Base Bid Item and Optional Item may be rejected.
An unbalanced bid is one, which is based on price significantly less than the cost for some work and prices are significantly overstated for other work.
NOTE 04:Bidders are reminded that they must bid on the issued plans and specifications as amended. Any deviations, conditions or attachments made by the bidders thereto may render the bid non-responsive and be cause for its rejection.
NOTE 05:Options may be exercised within thirty-two (32) calendar days of receipt by the contractor of the Notice to Proceed.). No Additional time will be added. The Government is under no obligation to exercise any Optional Item. Options will not be exercised if the contract has expired. Option 1 may be exercised only if we exceed the tonnage in CLIN 0005.
Option 2 may be exercised only if we exceed the tonnage in Option 1.
NOTE 06:All bidders are hereby advised that the estimated dredge quantities for placement in the price schedule are estimated and based on the survey data collected on 09-11, 22 January 2024.
NOTE 07:All bidders are hereby advised that the contractor is to complete the entire basic work ready for use, not later than thirty-two (32) calendar days after the date the Contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.
NOTE 08:All Request for Information (RFI) must be submitted fifteen (15) days prior to bid opening. Anything submitted after that will not be addressed. All RFI’s need to be sent to Jo Ann McCue at jo.a.mccue@usace.army.mil and Nicholas Emanual at Nicholas.P.Emanuel@usace.army.mil.
(End of Summary of Changes) mailto:jo.a.mccue@usace.army.mil mailto:Nicholas.P.Emanuel@usace.army.mil