About this file

This document is Amendment 6 to Solicitation W912DS24B0001 for the construction of a new steel sheet pile bulkhead wall along the Passaic River in Newark, New Jersey. The key changes in this amendment include:

  1. Revisions to the bid schedule, including adding an optional item for pumping, testing, storage, and discharge/disposal of contaminated groundwater encountered during construction, with a pre-priced CLIN of $100,000.
  2. Revisions to specifications, including Section 31 41 16 for the metal sheet piling bulkhead system.
  3. Revisions to drawings, including Sheet S-001.
  4. Responses to requests for information, including details on the rock socket grouting requirements and existing bulkhead information.

The solicitation is for a project valued between $10-25 million, with a period of performance of 425 calendar days. The procurement is for unrestricted full and open competition with HUBZone preference. Interested parties must be registered in SAM.gov and the Contract Opportunities website to access the solicitation and amendments.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912DS24B0001

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this Amendment is to:

1. Revise and reissue the bid schedule.

2. Revise and reissue Section 31 41 16 of the Specif ications.

3. Revise and reissue Sheet S-001 Draw ings.

4. Answ er requests for information.

5. Provide Site Prep Plan Draw ings for informational purposes only.

NOTE: Bidders must acknow ledge receipt of this amendment by date specif ied in the bid (or as amended) by one of the follow ing methods:

In the space provided on the SF 1442, by separate letter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENT BY DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH THE LATE BID, LATE MODIFICATION OF BID, OR LATE

WITHDRAWAL OF BID (FAR 14.304).

1. CONTRACT ID CODE PAGE OF PAGES

1 19

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 13-Jun-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DS24B0001

X 9B. DATED (SEE ITEM 11)

16-Apr-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION

NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

13-Jun-2024

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 16-300

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 6

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Construction of Steel Sheet Piles

FFP

See Priced SubCLINs 0001AA, 0001AB, and 0001AC

INFO ONLY

NET AMT

0001AA 913.71 Linear

Foot

Construction of Steel Sheet Piling

Steel for Bulkhead System - Steel Sheet Piling for construction of bulkhead for Stations 0+00 through 9+13.71, complete, in accordance with the drawings and specifications, but not including Items 0002- 0014 on the bid schedule.

[ESTIMATED QUANTITY]

FOB: Destination

PSC CD: Y1KZ

0001AB 1 Job Construction of Cap, Tie-Back & Drainage

FFP

Concrete Cap, and Tie-Back rod system - All work, excluding steel costs stated in SubCLIN 0001AA, for construction of bulkhead, which includes concrete cap and related work, including drainage structures, for Stations 0+00 through 9+13.71, complete, in accordance with the drawings and specifications, but not including Items 0002-0014 on the bid schedule.

0001AC 1 Job Mobilization / Demobilization

FFP

All mobilization and demobilization work for construction of bulkhead, which includes concrete cap and related work, including drainage structures, for Stations 0+00 through 9+13.71, complete, in accordance with the drawings and specifications. The price of this CLIN shall be 5% of the total Base CLIN amount.

0002 1 Job Drawing Set

FFP

Contractor shall complete the Record ("As-Builts") CAD submittal as required by Specification Section 01 78 00 CLOSEOUT SUBMITTALS for Record Drawings (“as-Builts”) Requirements and for CADD standards and compliance. Prepriced CLIN in the amount of $100,000. The amount paid will be actual cost NOT TO

EXCEED THE PREPRICED AMOUNT

$100,000.00

0003 1 Job Report and Drawing Set

Archaeological monitoring for historical structures.

0004 1 Job Report and Drawing set

FFP

Development of Landscape seeding plan with two coordination meetings with DLUR and Development of Tree Survey, Protection, and Restitution plan with two coordination meetings with representatives of State of New Jersey

0005 2,200 Cubic

Yard

Displacement Stone Material

Material for Displacement Stone. [ESTIMATED QUANTITY]

0006 913.71 Linear

OPTION OPTIONAL ITEM 1- Railings

All Work for Installation of Railings. A small amount of railing fabrication is required for bends, change in direction, and point of inflections. [ESTIMATED QUANTITY] Option 1 may be awarded within 120 calendar days of issuance of the Base Bid NTP. No additional time shall be added to the contract performance period.

0007 1,200 Cubic

OPTION OPTIONAL ITEM 2 - Excavation, Transport

All Work for Excavation, Testing, Transport, Treatment and Off-Site Disposal of Upland Material Exceeding NJDEP Non-Residential Soil Cleanup Criteria and classified as Contaminated Non-Hazardous (ID 27 Waste) not suitable for landfill cover, etc. for Stations 0+00 through 9+13.71, complete. [ESTIMATED QUANTITY] Option 2 may be awarded within 210 calendar days of issuance of the Base Bid NTP. No additional time shall be added to the contract performance period.

0008 1,200 Cubic

OPTION OPTIONAL ITEM 3 - Excavation, Transport

All Work for Excavation, Testing, Transport, Treatment and Off-Site Disposal of Upland Material Exceeding NJDEP Non-Residential Soil Cleanup Criteria and classified as Contaminated Hazardous or material not suitable for landfill cover, etc. for Stations 0+00 through 9+13.71, complete. [ESTIMATED QUANTITY] Option 3 may be awarded within 210 calendar days of issuance of the Base Bid NTP. No additional time shall be added to the contract performance period.

0009 1 Job OPTION OPTIONAL ITEM 4 – Implementation Plan

FFP

All work for implementation of landscape and seeding plan. Prepriced CLIN in the amount of $100,000. The amount paid will be actual cost NOT TO EXCEED THE PREPRICED AMOUNT. Option 4 may be awarded within 270 calendar days of issuance of the Base Bid NTP. No additional time shall be added to the contract performance period.

0010 1 Job OPTION OPTIONAL ITEM 5 – Implementation Plan

FFP

All Work for stabilization of historic structures. Prepriced CLIN in the amount of $100,000. The amount paid will be actual cost NOT TO EXCEED THE PREPRICED AMOUNT. may be awarded within 270 calendar days of issuance of the Base Bid NTP. No additional time shall be added to the contract performance period.

0011 100 Linear

OPTION OPTIONAL ITEM 6 – Additional materials

Additional furnishing and placing steel wide flange beams/sheet pile connections.

[ESTIMATED QUANTITY] Option 11 may be awarded within 180 calendar days of issuance of the Base Bid NTP. Additional 90 days will be added to the scheduled.

0012 100 Cubic

OPTION OPTIONAL ITEM 7 – Additional materials

Additional 100 CY material for displacement stone [ESTIMATED QUANTITY] Option 7 may be awarded within 180 calendar days of issuance of the Base Bid NTP. No additional time shall be added to the contract performance period.

0013 1 Job OPTION OPTIONAL ITEM 8 - Gravel Tracking

FFP

All Work and Materials for construction of temporary Gravel Tracking Pad from Access Point 2 to Staging Area while protecting historic structures and bringing back to initial conditions. Option 8 may be awarded within 15 calendar days of issuance of the Base Bid NTP. Additional 30 days will be added to the schedule.

0014 1 Job OPTION OPTIONAL ITEM 9 - Liability Insurance

FFP

Liability insurance for New Jersey Department of Environmental Protection (NJDEP), City of Newark, NJDOT and their officers, employees and agents.

NON-FED FUNDS. The amount bid will be the maximum amount payable. Actual payment will be based on actual costs. Option 9 may be awarded within 60 calendar days of issuance of the Base Bid NTP. No additional time shall be added to the contract performance period.

0015 1 Job OPTIONAL ITEM 10 Groundwater

FFP

All work for pumping, testing, storage, and eventual treatment/discharge/disposal of contaminated groundwater, if encountered, during construction activities. Pre-priced CLIN in the amount of $100,000. The amount paid will be actual cost NOT TO EXCEED THE PREPRICED AMOUNT. Option 10 may be awarded within 300 calendar days of issuance of the Base Bid NTP. No additional time shall be added to the contract performance period.

TOTALS

TOTALS SECTION

BASE TOTAL AMOUNT (CLIN 0001-0005 $__________________________________________

TOTAL OPTIONAL (CLIN 0006-0015) $ _____________________________________________

TOTAL BASE PLUS OPTIONAL (CLINS 0001-0015) $__________________________________

NOTES

BID SCHEDULE NOTES

1. Bidders are required to bid on all items in the Price Schedule or their bid will be rejected.

2. Low bidder for the purpose of award will be the conforming responsible bidder offering the lowest amount for the Grand Total Bid Items.

3. Any bid which is materially unbalanced as to prices for the bid items may be rejected. An unbalanced bid is one which is based on prices significantly less than cost for some work, and prices which are significantly overstated for other work.

4. Bidders are reminded that they must bid on the issued plans and specifications as amended. Any deviations, conditions, or attachments made by the bidders thereto may render the bid non- responsive and may be cause for its rejection.

5. If awarded, the options would be exercised as follows:

Option #1, Bid Item No. 0006, Installation of Railings, and a small amount of railing fabrication required for bends, change in direction, and point of inflections, may be awarded within 120 calendar days of issuance of the Base Bid NTP. No additional time shall be added to the contract performance period.

Option #2, Bid Item No. 0007, Contaminated Non-Hazardous Material (ID27), may be awarded within 210 calendar days of issuance of the Base Bid NTP. No additional time shall be added to the contract performance period.

Option #3, Bid Item No. 0008, Contaminated Hazardous Material, may be awarded within 210 calendar days of issuance of the Base Bid NTP. No additional time shall be added to the contract performance period.

Option #4, Bid Item No. 0009, Implementation of Landscape Plan may be awarded within 270 calendar days of issuance of the Base Bid NTP. No additional time shall be added to the contract performance period.

Option #5, Bid Item No. 0010, Implementation of Treatment Plan, may be awarded within 270 calendar days of issuance of the Base Bid NTP. No additional time shall be added to the contract performance period.

Option #6, Bid Item No. 0011, Additional Materials, may be awarded within 180 calendar days of issuance of the Base Bid NTP. No additional time shall be added to the contract performance period.

Option #7, Bid Item No. 0012, Additional Materials, may be awarded within 180 calendar days of issuance of the Base Bid NTP. No additional time shall be added to the contract performance period.

Option #8, Bid Item No. 0013, Gravel Tracking Pad, may be awarded within 15 calendar days of issuance of the Base Bid NTP. Additional 30 days will be added to the schedule.

Option #9, Bid Item No. 0014, Liability Insurance, may be awarded within 60 calendar days of issuance of the Base Bid NTP. No additional time shall be added to the contract performance period.

Option #10, Bid Item No. 0015, Contaminated Groundwater, may be awarded within 300 calendar days of issuance of the Base Bid NTP. No additional time shall be added to the contract performance period.

Joseph G. Minish Passaic River Waterfront Park and Historic Area Project in Newark New Jersey Contract 3B: Construction of New

Sheet Pile Bulkhead Wall

Amendment 0006

AMENDMENT 0003 to DRAWINGS and SPECIFICATIONS Joseph G. Minish Passaic River Waterfront Park and Historic Area Project in Newark New Jersey Contract 3B: Construction of New Sheet Pile Bulkhead Wall

TO OFFERORS

The following changes shall be made to the drawings and specifications.

DRAWINGS

1. The following DRAWINGS have been REVISED but NOT REISSUED:

- None

2. The following DRAWINGS have been REVISED and REISSUED:

- Structural drawings notes on Sheet S-001

3. The following DRAWINGS have been ADDED:

- None

4. The following DRAWINGS have been DELETED:

SPECIFICATIONS

1. The following SPECIFICATION SECTIONS have been ADDED and are provided in their entirety herein:

- None

2. The following SPECIFICATIONS SECTIONS have been DELETED in their entirety:

- None

3. The following SPECIFICATIONS SECTIONS have been REVISED and REISSUED:

- Bid Schedule – Item No 0015 - Optional Item 10 – Contaminated Groundwater

- Section 31 41 16 Metal Sheet Puling Bulkhead System

4. The following SPECIFICATIONS have been REVISED but NOT REISSUED:

PROPOSER’S QUESTIONS AND GOVERNMENT REPLY

Questions that may be of general interest to all Offerors and/or the Government and that are not readily answered by the proceeding changes will appear below. These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question(s). Questions and answers are issued to the Offerors “for information only” and do not revise the solicitation, plans or specifications.

Rock socket/grouting

• As per our conversation, we have received addendum #4, which has addressed our question concerning the use of a temporary casing. As you know, the response was that a temporary casing is allowed. However, the current means and methods for the bulkhead king pile and sheeting installation indicated in the contract plans, specifications and details are not in alignment with the use of a temporary casing and therefore need to be modified accordingly in order for all contractors to properly bid and execute this option.

As you may know, when using a temporary casing for this type of work, contractors will typically need to auger out soil and a rock socket, set the king pile within the temporary casing, grout the pile in the rock socket, backfill the temporary casing from top of rock to grade, remove the temporary casing and then drive sheeting between king piles. In order to maintain fair and balanced bids we ask that the USACE/Engineer provide additional details on the rock socket, including grout strength and also identify what type of soil, sand or stone can be used to backfill the temporary casing prior to its removal.

Response: The grout shall be 4000 psi (28 days). The contractor can attach a tremie pipe to the wide flange beams, pump and backfill the rock socket with water-cement grout after dropping/placing the wide beam into the cased hole, while extracting the casing.

Depending on the contractor’s means and methods, the grout may contain a retarder to provide a flexibility and allow sheet piles to be installed through the E22 connections.

Another way would be to backfill with ungraded sand and pump grout after installation (no retarder) of the sheet piles that would provide some flexible to allow sheet piles to be installed and locked.

• Regarding the requirement of pressure grouting the piles according to the contract documents and clarifications issued with the addendums… further clarification is required in order to provide a proper bid and maintain balanced bids between contractors. Based on the contract plan notes and available geotechnical data, many of the specialty subs for this work have advised that while grouting through a 1” fixed tremie pipe is possible, there is no way to control, determine and or even estimate the amount of grout that will be necessary in performing this work. The path the grout will take or quantity that will be required is completely undeterminable. Therefore, in order to maintain balanced bids, we request that a line item with a volumetric quantity be provided for pressure grouting bulkhead piles.

Response: The bedrock profile is based on the historic boreholes and is only an estimate.

The contractor can execute additional boreholes to determine/verify the top of bedrock.

Based on the current top of bedrock estimate, the contractor is expected to pump a minimum 650 gallons of grout to for the rock socket.

• One of the Government answers to the rock socket questions, states “ Rock socket can be formed by drilling/coring or by other means…” please indicate what other means are allowed.

Response: “Other means” is the contractor’s means, methods, equipment, and tools.

Existing Bulkhead

• Furthermore, please be advised that the proposed bulkhead may be in direct conflict with the existing bulkhead. However, the contract documents do not include any information or asbuilts on the existing bulkhead/structure, including type, size, or location. Not having this information creates ambiguity and will ultimately cause bid pricing from contractors to be unbalanced. Please provide contractors with existing bulkhead information and details accordingly.

Response: Existing plans will be posted.

Epoxy Coating for A690 Steel

• In Amendment No. 4 issued on June 6, 2024, under the heading “PROPOSER’S QUESTIONS AND GOVERNMENT REPLY” the Government states in the last sentence “Questions and answers are issued to the Offerors “for information only” and do not revise the solicitation, plans or specifications.” However, the Government answers have changed the plans and specifications, for example: The plans and specifications call for the bulkhead sheeting and king piles to be ASTM A690, with 25 Mil Coal Tar Epoxy Coating, but answers indicate no coating required if A690 is used. Will the Government change the plans and specifications to match the answers to the questions?

Response: Either A690 or A572 grade steel can be used. When using A690 steel, no coating is required – this is a high grade of steel. If using a standard steel grade A572, coating is required. Specifications and structural notes will be updated to clarify.

Contaminated Groundwater

• Government response to question No. 4 states “Please see revised bid schedule.” Revised Bid Schedule does not include and Optional Bid Item to account for the potential pumping, testing, storage and eventual discharge/disposal of contaminated groundwater encountered during construction activities. Please clarify.

Response: Add bid schedule option to account for the potential pumping, testing, storage, and eventual discharge/disposal of contaminated groundwater encountered during construction activities. Pre-priced CLIN in the amount of $100,000. The amount paid will be actual cost NOT TO EXCEED THE PREPRICED AMOUNT.

DRAWINGS
SPECIFICATIONS
PROPOSER’S QUESTIONS AND GOVERNMENT REPLY

File details come from the government source that posted it. Updated .