WVA B. 110 Paint Booth D-B RFP - RTA Submission.pdf

PDF 41 MB Posted

Attached to
Replace Paint Booth and Drying Oven at the Watervliet Arsenal, Watervliet, NY
Solicitation number
W912DS23R0006
Issued by

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Department of the Army

New York District

Corps of Engineers

26 Federal Plaza, RM 16-300

New York, NY 10278-0090

Watervliet Arsenal Building 110 New Paint Booth

Watervliet, New York

U.S. Army Engineering Corps of Engineers, New York District

Contract No.: W912DS19D0012

Order No.: W912DS22F0046

RTA Design-Build Request for Proposal March 2023

B. 110 Automated Paint Booth March 2023 Watervliet, NY RTA Submission

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 00 01 COVER SHEET

DIVISION 01 - GENERAL REQUIREMENTS

01 01 00 STATEMENT OF WORK

01 11 00 SUMMARY OF WORK

01 14 00 WORK RESTRICTIONS

01 20 00 PRICE AND PAYMENT PROCEDURES

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 33 16.00 10 DESIGN DATA (DESIGN AFTER AWARD)

01 33 29 SUSTAINABILITY REQUIREMENTS AND REPORTING

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 QUALITY CONTROL

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 45 20.00 18 TESTING FOR MECHANICAL AND ELECTRICAL SYSTEMS

01 45 35 SPECIAL INSPECTIONS

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 58 00 PROJECT IDENTIFICATION

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

01 78 24.00 10 FACILITY DATA REQUIREMENTS

01 91 00.15 10 TOTAL BUILDING COMMISSIONING

DIVISION 11 - EQUIPMENT

11 30 01 AUTOMATED PAINT BOOTH

11 40 03 CURING OVENS

APPENDICES (at end of RFP document)

Appendix A, RFP Drawings Appendix B, Geotechnical Report Appendix C, Field Investigative Reports Appendix D, Hazardous Materials Report Appendix E, WVA Reference Drawings Appendix F, WVA Information for Contractors Appendix G, Sustainability Spreadsheet Appendix H, Existing Fire Pump Test Reports

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION 00 00 01

COVER SHEET

01/18

PART 1 GENERAL

NEW YORK DI STRI CT

CORPS OF ENGI NEERS

NEW YORK, NEW YORK 10278- 0090

REQUEST FOR PROPOSAL

FOR

WVA AUTOMATED PAI NT BOOTH

BUI LDI NG 110

WATERVLI ET ARSENAL, NEW YORK

1. Attached is Request for Proposal (RFP) NO. W912DS-23R0006

2. RFP MUST BE SET FORTH full, accurate, and complete information as required by this RFP, including attachments. The penalty for making false statements in bids is prescribed under Title 18, United States Code, Section 1001.

3. SUBMISSION OF PROPOSAL: Complete details concerning proper submission of bids are contained in the INSTRUCTIONS TO PROPOSER (Section 00 21 16

4. Note the REQUIREMENT FOR AFFIRMATIVE ACTION of the EQUAL OPPORTUNITY clause as it applies to the contract resulting from this solicitation. (See paragraph NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY in Section 00 70 00 of this IFB).

5. REPRESENTATIONS AND CERTIFICATIONS - SECTION 00 45 00 Bidders and Offerors are required to complete the REPRESENTATIONS AND CERTIFICATIONS and submit them with their bids.

6. CONDITIONS OF CONTRACT - SECTION 00 70 00, note in particular the PROHIBITION SEGREGATED FACILITIES. Failure of a bidder or offeror to agree to the certification will render his bid or offer non-responsive to the terms of solicitations involving awards of contracts exceeding $10,000 which are not exempt from the provisions of the Equal Opportunity Clause

7. Please review all bonds and accompanying documents required to be submitted. Bonds, Powers of Attorney, statements of authenticity and continuing validity, and all related documents MUST NOT bear computer printer-generated signatures and/or seals. Documents bearing signatures and/or seals generated as part of a document, as opposed to being affixed to the document after its generation, will not be accepted. Submission of such documents may render the bid or offer non-responsive and ineligible for award.

8. Sections indicated in the cover sheet are part of the Solicitation Package.

DOCUMENT 00 00 01 Page 1

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

DOCUMENT 00 00 01 Page 2

SECTION 01 10 00 Page 1

SECTION 01 10 00

STATEMENT OF WORK

01/2023

PART 1 GENERAL

1.1 SECTION ORGANIZATION

This specification section is divided into three distinct parts as follows:

Part 1 General includes an overview, design considerations, project schedule and phasing considerations, and project bidding requirements and general information affecting the entire project.

Part 2 Equipment Systems focuses on the paint booth and oven, providing general information on the system.

Part 3 Building Systems focuses on the site and building systems that support the paint booth and oven. It provides general design information and technical criteria for each design discipline.

Drawings and other reference material are provided in the Appendices.

1.2 OVERVIEW

This Request for Proposal (RFP) as issued by the U.S. Army Corps of Engineers (USACE) – New York District sets forth instructions and requirements for proposals for a Design/Build (D/B) supply project to replace the existing paint booth and oven in Building 110 at Watervliet Arsenal in Watervliet, New York. Watervliet Arsenal’s address is:

1 Buffington Street Watervliet, NY 12189-4050

This project includes the complete design, documentation and construction of a replacement paint booth and cure oven, as well as necessary and required modifications to, or replacements of, the HVAC and supporting utility systems.

1.2.1 Background Information

Building 110 at WVA houses an existing paint booth used to paint components used in military equipment. The current operations are manual and the size of the facility limits the number and size of components that can be painted or coated. The current facility also does not meet current code requirements and this project will address current deficiencies and install a modern and code compliant system.

Building 110 is of Historic nature and thereby, all work conducted on the building must be coordinated with the Cultural Resources Offices (SHPO) to ensure all Historic requirements are being met and no adverse effects occur.

SECTION 01 10 00 Page 2

The existing paint booth and oven system is a linear arrangement with two major components:

a. Paint Booth

b. Curing Oven

The overall project requirement is to provide a new paint booth and oven which is automated with robotic tooling, programmable controls, and climate control for heating and cooling. The paint booth and oven would also be designed to accommodate the largest components with flexibility for anticipated future sizes and capacity requirements.

The project would include all infrastructure in support of the paint booth, cure oven, and equipment including electrical, communications, gas, steam, and other services as required. The project will also require modifications to the existing building to accommodate new equipment in support of the paint booth and cure oven.

1.2.2 Key Project Requirements

The project requirements include the installation of a new paint booth with spray painting automation and a new oven to be located in line with the paint booth. The addition of Automated Paint application will improve efficiency, throughput, and quality control to reduce rework of paint systems. The project includes all work required to decommission and demolish the existing paint booth and oven. The new paint booth and oven will be automated with robotic tooling, programmable controls, and automatic adjustment for ambient/climate conditions. The new paint booth and oven shall be integrated to the existing building’s utilities, systems, and structure. Planning and execution of work in areas outside the existing paint booth and oven will help to minimize the downtime to current paint booth operations.

The painting operations will be performed at another location during the demolition of the existing paint booth and oven and construction of the new paint booth and oven. No access and/or work will be allowed within the Building until all approved equipment is on site and ready to be installed. The location of Contractor laydown, storage, and impacts to parking will need to be coordinated during the design and as part of construction for different areas of work. It is anticipated a laydown space would be available adjacent to Building 110 and areas within Building 110 on the South side during the construction phase.

This approach will support minimizing the overall downtime of the painting operations. The project will provide for HVAC, power, fire protection, gas connections, compressed air, and all structural repairs and/or modifications required to properly install the new paint booth and cure oven units.

1.2.3 Project Scope Summary

The D/B Contractor must provide a complete, turnkey project that includes:

a. Decommission and remove the existing Paint Booth and Oven system

SECTION 01 10 00 Page 3

b. Hazardous materials remediation of areas affected by the work of the Paint Booth and Oven System Replacement Project, as indicated in the Hazardous Materials Report attached in Appendix D. The Contractor shall develop plans and specifications to address remediation and conduct additional sampling as necessary.

c. Design, construction, installation and commissioning of the new paint booth and oven system

d. Design, modification and commissioning of supporting building systems, including HVAC and electrical systems.

e. Commissioning of and training on the replacement paint booth, oven and supporting building systems

f. The work listed above must conform to the requirements stated under Part 1, Project Site/Area of Work of this specification section to minimize existing Paint Booth and Curing Oven production interruption.

1.2.4 Available Documentation

Field investigation of the existing paint booth and oven system, the surrounding concrete floor, architectural, structural, and supporting building systems was conducted over several days in June, July and August of 2022. The findings from this investigation are provided as reference in the Field Investigation Report located in the Appendix C of this RFP. The requirements stated in the body of this RFP take precedence over the goals and objectives stated in the Field Investigation Report.

The Government has provided additional reference material (drawings, reports, etc.) describing the conditions in and around the existing paint booth and curing oven system.

Topics covered include:

a. Hazardous Materials Reports, Appendix D

b. Existing Drawings of Building 110, Appendix E

c. Drawings of the Electrical System in and around Building 110, Appendix E

1.2.5 Planned Projects

The Government has ongoing and planned projects within and around Building 110. The Contractor must coordinate with the Government to ensure that the work of the Paint Booth and Oven System Replacement Project does not interfere with the work of these other projects. One such project currently planned is the Building 110 Electrical Substation Relocation Project. Construction completion is scheduled for 21 September 2024. Thus, it is anticipated that the Building 110 Electrical Substation Relocation Project will be closed out after the Paint Booth and Oven Replacement Project is awarded, but before all long lead time equipment arrives on-site and mobilization takes place.

SECTION 01 10 00 Page 4

The scope of work for the Building 110 Electrical Substation Relocation Project includes:

a. Preparation of the future location of the Electrical Substation on the southeast of Building 110

b. Trenching across the building to extend wiring from the southwest side of Building 110 to the southeast side.

c. Demolition of the existing electrical substation on the southwest side of Building 110

d. Installation of the new 480V Electrical Substation.

1.2.6 Site Access and Deliveries

There are two routes for access to Building 110 at Watervliet Arsenal as indicated on G-101, BUILDING 110 LAYDOWN AND ACCESS PLAN within the Appendix. The access route is through the South Gate, proceeding northwest to Building 110. The contractor laydown areas indicated on G-101 are shown as possible locations for the storage of equipment and material. Final location of laydown and storage areas must be coordinated with Watervliet Arsenal Logistical personnel during the design phase. Small deliveries must be made through the South Gate.

The Contractor must notify the Security Office at the South Gate prior to the arrival of all deliveries. Oversize deliveries are taken through Gillespie gate, proceeding south to Building 110. The Contractor must coordinate oversize deliveries with Watervliet Arsenal. Contractor personnel must accept deliveries. Materials delivered to the site are the responsibility of the Contractor.

Storage and all special conditions must be coordinated with the Contracting Officer’s Technical Representative (COR). Refer to GA-101, CONCEPT GENERAL ARRANGEMENT within Appendix A for entry points into and routes within Building 110. Deliveries will be through one of two overhead doors at the south end of Building 110. Trucks must be unloaded outside the door. From there, the Contractor must carry or cart small equipment and items to the project site/area of work. For delivery of large equipment, the Contractor will be permitted to use fork trucks to bring material and equipment into Building 110 at the southwest corner of the building.

1.2.7 Project Site/Area of Work

The project site/area of work in Building 110 is in bays 60 through 69 and within column lines C, D and E as indicated on GA-101, CONCEPT GENERAL ARRANGEMENT within Appendix A. Watervliet Arsenal will cease paint booth operations only after all long lead time items have been procured and delivered to the site, and the contractor is prepared to commence replacement of the paint booth and curing oven uninterrupted.

This area will be made available once all materials necessary for completion of the project have arrived on site. All efforts must be made to minimize the downtime of the paint booth and curing oven system.

SECTION 01 10 00 Page 5

1.2.8 Occupancy of Premises

Building 110 is an occupied building. The buildings surrounding Building 110 are occupied. The work is in an existing, occupied building and around other existing buildings which are occupied.

Contractor personnel must not enter the buildings without prior approval of the COR. Furthermore, there are other operations taking place in Building 110 in addition to the paint booth. The Contractor must not interfere with these other operations and activities.

1.2.9 Protection of Existing Building, Equipment and Property

The existing buildings and their contents must always be kept secure.

Provide temporary enclosures as required to maintain security. Leave attached equipment in place, and protect it against damage, or temporarily disconnect, relocate, protect, and reinstall it as the completion of the work. The Government will remove and relocate other Government property in the area of work within Building 110. The existing building and all existing Government owned equipment and property within the work area must be protected by the Contractor from damage caused by construction operations. At a minimum, the Contractor must cover all furniture, equipment and property in the work area with dust barriers or protective enclosures. Protect such items from damage due to dust, vibration, water, heat or other conditions resulting from construction activities. Existing work damaged by construction operations must be promptly repaired by the Contractor at his own expense. In addition to FAR 52.236-9 "Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:"

a. Remove/alter existing work to prevent injury or damage to portions of the existing work which are to remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of construction work, existing work must be in equal to or better condition than that which existed before new work started.

c. At Contractor's expense, immediately restore to service and repair damage caused by contractor/subcontractors to existing piping, conduits, wires, cables, etc., of utility services, fire protection systems or communications systems which are marked and are not scheduled for discontinuance or abandonment.

d. Repair damage to those facilities, including those owned by a third party, resulting from failure to comply with the requirements of this Contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

SECTION 01 10 00 Page 6

1.3 DESIGN CONSIDERATIONS

The replacement paint booth and curing oven system must meet all requirements as described herein and all applicable requirements for building egress and life safety as required by NFPA 101 as modified by Unified Facilities Criteria (UFC) 1-200-01 and UFC 3-600-01. The paint booth and curing oven system concept diagram and associated building system concept diagrams included in Appendix A. Concept Diagrams should not be considered the required design solution. The design solution of the entire scope is the responsibility of the D/B Contractor’s Designer of Record. The RFP includes requirements that require evaluation to determine if they are applicable to the design solution. The Contractor must address these requirements in their design solution after careful study, due diligence and evaluation of all applicable information.

1.3.1 Standards and Codes

Primarily, Army engineering manuals, regulations and standards must govern the design and preparation of plans, specifications, cost estimates and design analysis. In addition, other design standards and codes must be implemented, as required. The Contractor must obtain, review and utilize all applicable technical criteria, standards and codes in the design and construction of the replacement paint booth and curing oven system and associated building modifications. Special attention is given, but is not limited to, the current edition, at time of award, of the following publications:

a. International Building Code (IBC), New York State Edition

b. International Fire Code, New York State Edition

c. International Plumbing Code, New York State Edition

d. International Mechanical Code, New York State Edition

e. American Concrete Institute (ACI)

1. ACI 318, Building Code Requirements for Structural Concrete

2. ACI 530, Building Code Requirements and Specification for

Masonry Structures

f. American Institute of Steel Construction (AISC) 360-10

Specification for Structural Steel Buildings

g. AMS 2750, Pyrometry

h. AMS 2759, Heat Treatment of Carbon and Low-Alloy Steel Parts

i. Air Force and Army Engineering Technical Letters (ETLs)

j. American National Standards Institute (ANSI) Standards

k. American Society of Civil Engineers (ASCE) 7-10, Minimum Design

Loads for Buildings and Other Structures

l. American Society of Heating, Refrigeration and Air Conditioning

Engineers (ASHRAE) Handbooks

m. American Society for Testing and Materials (ASTM) Standards

n. Institute of Electrical and Electronic Engineers (IEEE) Standards

o. National Electrical Safety Code (NESC)

p. National Standard Plumbing Code

q. National Fire Protection Association (NFPA) Codes and Standards

SECTION 01 10 00 Page 7

1. NFPA 1, Fire Code

2. NFPA 10, Standard for Portable Fire Extinguishers

3. NFPA 13, Standard for the Installation of Sprinkler Systems

4. NFPA 14, Standard for the Installation of Standpipe and

Hose Systems

5. NFPA 20, Standard for the Installation of Stationary Pumps for Fire Protection

6. NFPA 25, Standard for the Inspection, Testing, and

Maintenance of Water-Based Fire Protection Systems

7. NFPA 30, Flammable and Combustible Liquids Code

8. NFPA 33, Standard for Spray application Using Flammable or

Combustible Materials

9. NFPA 54, Fuel Gas Code

10. NFPA 70, National Electrical Code

11. NFPA 70E, Electrical Safety in the Workplace

12. NFPA 72, National Fire Alarm Code

13. NFPA 86, Standard for Ovens and Furnaces

14. NFPA 90A, Standard for the Installation of Air-

Conditioning and Ventilating Systems

15. NFPA 91: Standard for Exhaust Systems for Air

Conveying of Vapors, Gases, Mists, and Particulate Solids

16. NFPA 101, Life Safety Code

17. NFPA 241, Standard for Safeguarding Construction, Alteration, and Demolition Operations

18. NFPA 291, Recommended Practice for Fire Flow Testing and Marking of Hydrants

r. National Institute of Occupational Safety and Health (NIOSH)

Standards

s. Occupational Safety and Health Administration (OSHA) Standards

t. Sheet Metal and Air Conditioning Contractors National Association

(SMACNA): Design, Construction Standards, Fire Smoke, Seismic, Indoor Air Quality Guidelines for Occupied Buildings Under Construction Standards

u. Standard Specifications for Subsurface Exploration and Field Testing

v. Unified Facilities Criteria (UFC)

1. UFC 1-200-01, General Building Requirements

2. UFC 1-300-07A, Design Build Technical Requirements

3. UFC 1-300-08, Criteria for Transfer and Acceptance of DoD

Real Property

4. UFC 1-300-09N, Design Procedures

5. UFC 3-101-01, Architecture

6. UFC 3-110-03, Roofing

7. UFC 3-301-01, Structural Engineering

8. UFC 3-320-06A, Concrete Floor Slabs On Grade Subjected To

Heavy Loads

9. UFC 3-401-01, Mechanical Engineering

10. UFC 3-400-02, Design: Engineering Weather Data

11. UFC 3-410-01, Heating, Ventilating, and Air

Conditioning Systems

SECTION 01 10 00 Page 8

12. UFC 3-410-02, Direct Digital Control For HVAC And Other Building Control Systems

13. UFC 3-420-01, Plumbing Systems

14. UFC 3-501-01, Electrical Engineering

15. UFC 3-520-01, Interior Electrical Systems

16. UFC 3-530-01, Design: Interior and Exterior Lighting and Controls

17. UFC 3-560-01, Electrical Safety

18. UFC 3-600-01, Fire Protection Engineering for

Facilities

19. UFC 3-810-10N, Environmental Engineering for Facility

Construction

20. UFC 4-010-06, Cybersecurity of Facility-Related

Control Systems

w. Unified Facilities Guide Specifications (UFGS)

x. Underwriters Laboratories, Inc. (UL) Standards

y. US Army Corps of Engineers, Engineering Regulations, Manuals, Engineering Technical Letters (ETL) and Pamphlets

1. TI 800-01, Design Criteria (Chg 29 - 16 September 2005

(partially superseded by UFS's))

2. EM 385-1-1, U.S. Army COE Safety and Health Requirements

Manual

3. ER 414-1-10, Contractor Submittal Procedures

4. ER 415-345-42, Construction Costs, Cost Estimating and

Reserves for Contingencies

5. ER-1110-1-263, Chemical Data Quality Management for HTW

Remedial Activities

6. ER 1110-345-700, Design Analysis

7. ER 11100-345-710, Drawings, Military Construction

8. ER 1110-345-720, Specifications, Military Construction

9. ER 1110-3-1300, Military Programs Cost Engineering

10. Installation Information Infrastructure Architecture

(I3A) Implementation Guide

11. Tri-Service A/E/C CAD Standard, The CAD/BIM Technology

Center for Facilities, Infrastructure, and Environment

12. Tri-Service Spatial Data Standards (TSSDS)

z. Watervliet Arsenal specifications as referenced in this document

– A reference copy of these specifications is located in the Appendix.

aa. New York State Department of Environmental Conservation

(NYSDEC)

1. New York State Standards and Specifications for Erosion and Sediment Control (Blue Book)

Codes and standards listed in the specification sections may be supplemented, but not supplanted, by applicable criteria contained in nationally recognized codes, standards, and specifications. When UFC criteria reference IBC, the editions of codes and standards referenced in the IBC must be used, unless noted otherwise. Where codes and standards are not referenced in the UFC or IBC, or where no

SECTION 01 10 00 Page 9 version is specified, the latest available version at the time of award must be used. Where UFCs, Federal standards, State standards, local standards, codes, and other requirements conflict, the most stringent must govern.

1.3.2 Government Furnished/Government Installed Equipment

There is no GF/GI equipment identified for this project.

1.4 PROJECT SCHEDULE AND PHASING CONSIDERATIONS

The work of this specification section will take place in a single phase. Upon award of the contract, the Design-Build Contractor shall provide the submittals required to begin design and initiate the procurement process for the necessary paint booth, curing oven and supporting equipment. The Contractor will coordinate with the Contracting Officer’s Representative (COR) to establish an area for storage of equipment prior to mobilization. Once all long lead time items have been delivered to the site and the Design-Build Contractor is prepared to commence the work of replacing the paint booth and oven system, the Design-Build Contractor will notify the COR. Watervliet Arsenal will then begin the process of diverting materials to an alternate site, and cease painting operations. Once painting operations have concluded and the government has released the project work area to the contractor, dismantling of the existing paint booth, curing oven and associated building systems will take place. Once this work has been completed, assembly of the new paint booth, curing oven and associated building systems will take place. This approach will minimize disturbance and the impact to ongoing operations and production at Watervliet Arsenal.

1.5 PROJECT BIDDING REQUIREMENTS

1.5.1 Bid Schedule

The scope of the project will include all costs in connection to the design, manufacturing and delivery of the replacement paint booth and curing oven system in accordance with this RFP. Scope includes the design and installation of building systems that support the paint booth and curing oven. Also included will be the dismantling and disposal of the existing paint booth, curing oven and supporting building systems.

PART 2 PRODUCTS

2.1 EQUIPMENT SYSTEMS

2.1.1 General

SECTION 01 10 00 Page 10

Drawings depicting the proposed concept are located in Appendix A. The proposed concept requirements are as follows:

Overall Paint booth size will be 22’-9” x 49’-0”, with inside working dimensions of 21’-9” x 40’-0” ( additional 8’ of length accommodates spray paint robotics).

Overall Oven size will be 21’-0” x 41’-0”, with inside working dimensions of 20’-0” x 40’-0”.

NFPA 33 Ventilation requirements for 100 percent conditioned outside air for summer and winter conditions.

The Paint Booth will be designed with environmental controls for temperature and summer humidity.

The Paint Booth will be specified with an X:Y lightweight gantry to support and translate painting automation robotics into position.

Access existing subgrade exhaust air filter housing system, pressure drop and general condition for continued use.

Coordinate existing and new building openings for outside air, exhaust air for paint booth and mixing room and Waste Storage Room

The project intent is to replace the existing Paint booth and Cure Oven within its current footprint. The system must meet the daily production rate of 8-12 barrels per 8 hour shift.

Commissioning will be provided by the Design-Build Contractor. All contractors and subcontractors must cooperate and participate in the commissioning work. The Contractor must ensure participation of major equipment manufacturers or their representatives.

2.1.2 Manufacturing Standards

The proposed Paint Booth and Cure Oven Systems system must conform to the latest revision, at time of award, of each of the following standards: NFPA 33 and NFPA 86.

2.1.3 Startup, Testing and Commissioning

Provide startup and testing service for the new Paint Booth and Cure Oven Systems. Verify the design criteria specified throughout in this document.

Upon completion of work and tests and at a time mutually agreeable to the Contractor and Government, operate all systems installed.

Provide commissioning of the new paint booth, curing oven, and supporting systems installed as part of this project to ensure that design criteria are met.

Provide four weeks of additional start up services, once design criteria have been verified. This time will be to assist Watervliet Arsenal with product testing/verification.

SECTION 01 10 00 Page 11

2.2 INDUSTRIAL EQUIPMENT

2.2.1 Design Criteria

Provide Paint Booth and Cure Oven Systems and associated equipment satisfy the criteria as detailed throughout this specification section and specification 11 30 01, Specification for Automated Paint Booth and specification 11 40 03 Specification for Cure Ovens.

2.2.1.1 Product Size Ranges to process through the Paint Booth and Oven

Refer to the table below for product size ranges for components to be painted and cured.

Item Minimum Maximum Length 13’ – 6” 40’ Outside Diameter 6” 18” Wall Thickness 2” 8” Weight n/a 10,000 pounds

Provide manufacturer’s standard warranty of not less than one year from the date of acceptance of the work. Refer to Section 01 78 00 Closeout Submittals for warranty management requirements.

2.2.2 Sound Levels

The Design-Build Contract must ensure that any equipment installed on the exterior of Building 110 does not produce noise that could be considered nuisance to abutting residents, in accordance with local ordinances. Sound attenuation must be included in the design.

2.3 MATERIALS STORAGE AND HANDLING

2.3.1 Responsibility of Watervliet Arsenal

Watervliet Arsenal will cease painting operations prior to Mobilization and after all equipment has been delivered to the project site. Painting operations will take place at an alternate facility to allow the Contractor to demolish the existing paint booth and oven, and construct the new paint booth and oven.

2.3.2 Delivery

Refer to Part 1, Site Access and Deliveries of this specification section for access routes both to and within Building 110.

2.3.3 Site Preparation

SECTION 01 10 00 Page 12

Site preparation must include demolition of the existing paint booth and oven system and placement of it in Watervliet Arsenal’s scrap contractor’s trucks. Refer to Part 3, Equipment Turnover of this specification section for equipment turnover requirements. Refer to 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS and 01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT for requirements regarding hazardous wastes. Multiple sections in this specification section describe the requirements associated with utilities, pits, foundations/pads and trenches. These sections include, but are not limited to:

a. Bringing utilities to the new paint booth and curing oven system

– Part 3, Utilities; Part 3, Plumbing; and Part 3, Electrical

b. Repair existing exhaust plenum pits and pouring concrete foundations/pads as required – Part 3, Structural

2.3.4 Manufacturing and Installation

The manufacturer(s) must allow the Government to inspect the equipment during its manufacture. This inspection will be a visual inspection.

Installation must include a complete system with all components described herein.

PART 3 EXECUTION

3.1 GENERAL

3.1.1 Summary of Site and Building Work

This part provides the requirements for the site work and building systems supporting the paint booth and curing oven system described in Part 2, Equipment Systems of this specification section.

3.2 CIVIL

3.2.1 Summary of Civil Work

Site work associated with the paint booth and curing oven system is expected to be limited to:

a. Site and building access

b. Staging, storage and transport of new and demolished materials

c. Installation of a construction trailer

d. Security of materials and equipment

3.2.2 Design Criteria

Design and construction must be in accordance with UFC current requirements. Applicable sections for the anticipated exterior improvements include, but are not limited to, UFC 3-201-01 Civil Engineering.

SECTION 01 10 00 Page 13

3.2.3 Site and Building Access

Refer to Part 1, Site Access and Deliveries of this specification section for a description of access both to and within Building 110.

The truck access route and staging area is depicted on G-101, BUILDING 110 LAYDOWN AND ACCESS PLAN in the Appendix.

3.2.4 Pre-Construction Staging and Storage

An area approximately 0.19 acres (86’ x 100’ +/-), located in the vicinity of the intersection of Baker Road and Parker Road will be provided for storage of materials and equipment during the period prior to the commencement of construction activities. Coordinate the exact location with the Government. The area consists of a gravel surface, is currently utilized for material storage, and is located approximately 500 feet from Building 110. The Contractor must provide temporary fencing with locks and gates for security. The area must be maintained to the satisfaction of the Contracting Officer. Precautions must be implemented to prevent damage to the existing pavement and other surrounding improvements. The truck access route and staging area is depicted on G-101, BUILDING 110 LAYDOWN AND ACCESS PLAN in the Appendix.

3.2.5 Construction Staging and Storage

An area approximately 0.23 acres, located along Parker Road, directly across the street from the south entrance of Building 110 will be provided for contractor trailer, equipment and storage of material during construction activities. Coordinate the exact location with the Government. The area consists of a paved surface and is currently utilized as short term storage for material prior to shipment. The staging area is depicted on G-101, BUILDING 110 LAYDOWN AND ACCESS PLAN in the Appendix

3.2.6 Utilities

Existing utilities servicing Building 110 are sufficient to support the Paint Booth and Oven replacement. The Contractor must provide a temporary generator to provide power for the construction trailer(s).

Coordinate with the Government for construction trailer and temporary generator location.

3.2.7 Equipment Turnover

The existing paint booth, curing oven and associated parts that are being removed remain the property of the Government. The Contractor is responsible for dismantling the paint booth and curing oven, and loading the material onto the Government’s scrap metal contractor’s vehicles. Once loaded, the scrap metal contractor will haul the dismantled paint booth and curing oven away.

SECTION 01 10 00 Page 14

3.2.8 Erosion and Sedimentation Control

The Contractor must provide erosion and sedimentation controls at Pre- Construction and Construction equipment staging and storage areas.

These controls must be constructed and maintained in accordance with New York State Standards and Specifications for Erosion and Sedimentation Control, dated November 2016.

3.3 ARCHITECTURE

3.3.1 Summary of Architectural Work

The paint booth and curing oven replacement project requires no significant architectural design of new elements. This building is of Historic nature and thereby, all work conducted on the building must be coordinated with the Cultural Resources Offices to ensure all Historic requirements are being met and no adverse effects occur.

However, it does require design and detailing of the penetrations for rooftop mounted equipment, flooring repairs, in conjunction with structural, repair of roofing materials, repair of wall penetrations and an equipment enclosure as described in Part 3, Structural and Part 3, Mechanical of this specification section. Sound level requirements must be coordinated to ensure no adverse effects occur prior to detail work of equipment enclosure. Locate and support equipment as required by technical requirements determined by the Contractor’s engineering team and the manufacturer based on equipment size and allowable space.

3.3.2 Design Criteria

In all locations where finishes are being repaired and new materials are added, the new material must match the existing in material type, style and finish. This must be coordinated with Cultural Resources Offices and will require samples (coordinate with Watervliet Arsenal).

Complete installation of repair materials after positioning new equipment in a manner which completely seals the exterior envelope of Building 110.

3.3.3 Coordination

Coordinate the work under Architecture with the design and work of projects in or around Building 110. Refer to Part 1, Planned Projects of this specification section for a summary of the work of the Building 110 Renovation Project. The Contractor must maintain all warranties for all products in place at the time of construction.

3.3.4 Architectural Systems and Materials (As required)

3.3.4.1 Division 5 – Metals

a. Surface mounted steel guard rail to be provided and installed around the perimeter of the paint booth and oven. Guardrails must

SECTION 01 10 00 Page 15 protect against impact from fork trucks and materials handling carts. Guardrails must have 4”x4x¼” structural steel tube posts with 10”x10”x5/8” welded base plates that are pre-punched for anchoring. Rails to be corrugated (3 rib)11 gauge high strength steel rails 14” tall x 2 ½” deep with a 3-bolt connection on each rail end. Finish to be durable powder coat safety yellow.

b. Existing bollards are to be removed and replaced. Bollards are to be located to protect equipment and structure. Bollards are to be surface mounted, steel sleeve encased concrete, and painted or powder coated safety yellow.

c. Anchorage to be (4) ¾” expansion anchors that are embedded 6”.

3.3.4.2 Division 6 – Wood

d. Use fire-retardant treated wood, exterior type in exterior applications where not prohibited by UFC 3-110-03 and other applicable codes.

3.3.4.3 Division 7 – Thermal and Moisture Protection

a. Roofing Insulation: Deck insulation must have high compressive strength of sufficient thickness to match the existing roof depth. Provide saddles and crickets of the same material.

b. Roofing: Roof materials, coverings and procedures must comply with the requirements of UFC 3-110-03 as the primary roofing criteria. Determine the required wind uplift resistance criteria using the wind speed information in accordance with Part 3, Structural of this specification section. Install roof materials in accordance with manufacturer’s instructions and performed by certified installers. Roofing materials must be approved by the Government, prior to purchase.

c. Single Source: Low slope membrane roof system must be from a single source manufacturer.

1. Repairs to the existing roof system must match exactly the materials used in the existing roof construction. The repairs must not void the existing roof warranty.

d. Low slope roof membrane systems must be fully compatible with the existing roof system.

e. Roof Components: Roofing must consist of all components above the roof deck and waterproof layer including, but not limited to, the following items:

1. Insulation: Provide insulation to match existing, where required to infill openings.

2. Provide positive roof drainage by sloping the roof structure. Provide a factory tapered roof insulation system, including saddles and crickets, to provide positive drainage of the roof system around curbs, penetrations and projections through the roof plane.

3. Provide glass mat gypsum roof board meeting the latest revision of ASTM C 1177 for use as a thermal barrier (underlayment) on steel decks.

SECTION 01 10 00 Page 16

4. Vapor Retarder: Repair, if the barrier is existing, using like materials. Otherwise, use ANSI/ASHRAE/IES Standard

90.1 for the determination.

5. Penetration Boots and Accessories: Provide all penetrations boots and accessories, in accordance with the final design, for a complete roofing system. Boots and accessories must be compatible with roofing material. Boots and accessories must be part of the roof assembly and must be from the same manufacturer as the roof assembly.

6. Prefabricated Curbs and Equipment Support: Roof assembly must be provided as a complete system including flashing, curbs, membranes and expansion joints. Prefabricated curbs and equipment supports must be of structural quality, hot dipped galvanized sheet steel, factory primed and prepared for painting with mitered and welded joints. Prefabricated curbs must be insulated and provided with a vapor retarder integrated with the roof vapor retarder, if present.

Provide integral base plates and water diverter crickets.

Minimum height for equipment curbs is 8 inches above finished roof surface.

7. Roof Hatches with Ladder: Hatch must be insulated to meet

UFC.

8. Fasteners: Fasteners must meet all requirements of the National Roofing Contractors Association (NRCA) and Factory Mutual.

9. Flashing and Sheet Metal: Provide flashing and sheet metal work as necessary for roof equipment bases and penetrations in accordance with roof manufacturer’s printed installation instructions and in compliance with NRCA and SMACNA recommendations. Fabricate flashing and sheet metal components from copper, stainless steel – ASTM A 167, Type 302 or 304, 2D finish, or pre-finished aluminum.

10. Roof Openings and Supports: Provide flashings for roof openings and supports as recommended by the NRCA. Ensure all penetration flashings extend a minimum 8 inches above the finished roof surface.

f. Joint Sealants: Provide in accordance with the latest revision of ASTM C1193 and the criteria listed below.

1. Exterior Sealants: Low modulus, non-sag silicone sealants, with controlled oil content to eliminate oil migration into substrates as recommended by the sealant manufacturer for the specific substrate. Provide compressible polyethylene foam backer rods. Preconstruction compatibility and adhesion testing required for all exterior wall sealants.

a) All sealants must be GreenGuard, SCS Global Services (SCS), or Collaborative for High Performance Schools (CHPS) certified to be low volatile organic compounds (VOC), meet South Coast Air Quality Management District (SCAQMD) 1168, have no added UF, and be asbestos free.

SECTION 01 10 00 Page 17

3.3.4.4 Division 9 – Finishes

a. Interior Flooring Repair

1. When new concrete has cured, at the discretion of the COR:

a) Provide concrete finish to match existing finish of exposed concrete in Building 110.

3.4 STRUCTURAL

3.4.1 Summary of Structural Work

Structural work associated with the paint booth and curing oven system includes, but is not limited to:

a. Support of new paint booth equipment

b. Support for new mechanical equipment

c. Support for sound attenuation panels at exterior equipment

d. Providing new concrete wear surface

e. Remedial measures as a result of the removal of the existing system

3.4.2 Design Criteria

The project must be designed in accordance with the codes and standards referenced in Part 1, Standards and Codes of this specification section.

3.4.3 Project Phasing

The Contractor’s bid proposal must consider and make allowances for phasing of work as outlined in Part 1, Project Schedule and Phasing Considerations of this specification section, if applicable.

3.4.4 Coordination

Coordinate the work under Structural with the work of projects in or around Building 110. Refer to Part 1, Planned Projects of this specification section for a brief summary of the work of the Building 110 Renovation Project. Coordinate with fire protection and structural engineers for water-filled ducting supports due to sprinkler discharge.

3.4.5 Existing Conditions

The existing building is a steel and wood framed structure originally constructed in the mid 1850’s. Refer to the Field Investigation Report in Appendix B for more information regarding the structural systems for both the existing building and the existing paint booth and curing oven system.

3.4.6 Geotechnical Investigation

SECTION 01 10 00 Page 18

Atlantic Testing Laboratories performed concrete borings at Watervliet Arsenal Building 110 in the vicinity of the existing paint booth and curing oven as part of development of this RFP. Refer to the Field Investigation Report in the Appendix for the findings of the investigation. The Contractor is solely responsible for foundation design based on independent testing conducted.

3.4.7 Serviceability Considerations

The support for platforms and new equipment must meet the serviceability requirements of the UFC along with the referenced IBC code.

3.4.8 Structural Loads

The Contractor must determine all loads in accordance with the governing building code and standards. Dead Loads for structural design must be the actual weight of construction materials, fixed equipment, and must not be less than the uniform dead loads prescribed by UFC 3-301-01.

a. Building Risk Category = II

b. Live Load Criteria:

1. Manufacturing – Heavy 250 psf

2. Equipment Access platform 60 psf

c. Snow Load Criteria

1. Per UFC 3-301-01

d. Wind Load Criteria

1. Per UFC 3-301-01

e. Seismic Loads

1. Per UFC 3-301-01

2. Soil Site Class to be verified by the Contractor’s geotechnical engineer.

3.4.9 Foundation Systems

The geotechnical investigation by the contractor will determine foundation design criteria and subgrade properties.

Design foundations to support the new condenser unit support frames.

Foundations may be shallow concrete spread-type or other systems approved by the government. Provide a minimum 12 inches of compacted fill under new foundations, unless a soils analysis shows the existing fill material is of adequate compaction.

New foundations shall be clear of, and not rely on, existing foundations for support.

The contractor shall anticipate rock removal for the condenser unit foundations. Normal excavating techniques will not necessarily be feasible for work inside the building. The Contractor's means and methods must account for the work being interior to the existing building; and provide equipment appropriate for the environment and physical constraints.

SECTION 01 10 00 Page 19

The final location of foundations must be coordinated with and approved by the Government. If the required bearing capacity cannot be met with excavated, then compacted soil, provide select fill material from offsite to achieve proper compaction and bearing for foundations.

3.4.9.1 Settlement

Foundation bearing must be consistent throughout the project to limit differential settlement. Coordinate with and confirm differential settlement limitations with the equipment manufacturer of the final equipment purchased and confirm that the equipment has adjustability to make-up for movement due to settlement.

3.4.9.2 Earthwork – Compactions

Provide an Earthwork specification based on the recommendations provided in the Contractor’s geotechnical report for excavation, fill, backfill and compaction.

3.4.10 Equipment Support Structures

Based on findings during the field investigation, the building structural framing is in satisfactory condition and does not require repairs as related to the proposed project. However, framing impacted by construction of new equipment, platforms, supports, or other elements must be strengthened as necessary to maintain structural integrity.

Welding of new steel to existing is acceptable but the contractor must perform testing to determine compatibility with the existing steel.

Design and provide structural support for the new condenser units located above the roof. The frame must be independent of the existing building structural system, that is, self-supporting. The frame shall be stiff enough to keep movement at the roof flashing within tolerable limits. If vertical bracing is used it shall allow access below the frame for storage.The framing shall also provide support for grated access platforms (with guardrail) around the units and sound attenuation walls. The walls and platforms must not be supported by the existing roof or building structure. Access to the platform shall be provided via a new ladder and roof hatch. Design and provide support for the ladder and roof hatch as needed. A built-up curb must be developed at the roof surface to accept the hatch up at the grated platform level. Provide framed openings for roof penetrations for the frame columns and ladder to pass through. The contractor should anticipate that the roof decking and purlins are water-damaged in the area of the framed opening and will require replacement from roof truss to roof truss.

Design and provide support for the interior air handler units. Provide an elevated access platform around each unit as required by the equipment vendor. Provide access to the platforms via a fixed ladder.

The platform layout and design shall account for any clearances required by the vendor. The platform can be partially supported by the

SECTION 01 10 00 Page 20 existing structure and partially supported by steel posts down to the existing concrete floor. The contractor shall assess the existing structure’s suitability for use as partial support of the framing and if decided to be used shall be strengthened, if needed, to support the new equipment platform loads. The existing concrete shall also be checked for the ability to support concentrated loading from the new steel posts. If needed, new isolated concrete pad footings shall be designed and provided.

Design and provide supplemental support steel for new air handler ductwork and condenser lines running from the outside units. It is anticipated that new steel supports can be supported from existing steel columns and roof trusses. The contractor is responsible for determining if the existing steel is adequate and shall design and provide any reinforcing to existing steel required.

3.4.11 Floor Slab Requirements

Perform investigative testing on the existing concrete slab near the condenser units and near the new air handler units to determine the thickness and strength of the concrete for use with design tasks.

Provide a new concrete topping in the booth and oven as well as in the area of the existing extents of the trolley loop. The topping material must be designed to withstand temperatures expected in the oven. The topping shall be highly wear-resistant, with a minimum compressive strength (fc’) of 7,000 psi. The total thickness of new topping is two inches. The concrete surface shall be removed to two inches below the existing finished floor level and replaced with the new topping.